Attachment_1_Davie_Ditch_Specifications.pdf
PDF 6 MB Posted
- Attached to
- DAVIE DITCH PIPELINE PROJECT Federal contract opportunity
- Solicitation number
- 140R4022R0029
About this file
This solicitation is for the Davie Ditch Pipeline Project to be performed on Bureau of Reclamation land in Colorado. Key requirements include furnishing and installing approximately 4,400 linear feet of 36-inch and 24-inch diameter PVC, HDPE, or polypropylene pipe. Additional work comprises concrete structures, miscellaneous metalwork, earthwork, clearing and grubbing, and seeding disturbed areas.
The solicitation includes three price schedules—the base schedule for segments 1 and 2, and optional schedules 2 and 3 for additional segments. Offerors must complete all schedules. The project is to be completed by April 2024 with final seeding from September to November 2023. The pre-bid site visit will be held on the specified date and time. Safety standards are in accordance with Reclamation Safety and Health Standards.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Davie_Ditch_Site_Visit_Sign-In_Sheet_8_10_23_0003.pdf | ||
| Sol_140R4022R0029_Amd_0003.pdf | ||
| Sol_140R4022R0029_Amd_0002.pdf | ||
| Attachment_6_Davie_Ditch_Questions___Answers_0002.pdf | ||
| Attachment_7_Davie_Ditch_Revised_Specifications_16Aug2023_0002.pdf | ||
| Sol_140R4022R0029_Amd_0001.pdf | ||
| Attachment_2_Davie_Ditch_Drawings.pdf | ||
| 140R4022R0029_Davie_Ditch_Solicitation.pdf | ||
| Attachment_5_Davie_Ditch_Section_B_Price_Schedules.xlsx | XLSX spreadsheet | |
| Sol_140R4022R0029.pdf | ||
| Attachment_4_Wage_Determination_CO20230003.pdf | ||
| Attachment_3_Past_Performance_Questionnaire.pdf |
Show all 12
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
U.S. Department of the Interior SPECIFICATIONS Bureau of Reclamation Technical Service Center Denver, Colorado July 2022
DAVIE DITCH PIPELINE
Silt Project - Colorado
Volume II of II
DAVIE DITCH PIPELINE – SILT PROJECT, COLORADO
FOREWORD
This solicitation involves placing several sections of an existing open-channel water conveyance system into a pipeline system.
The system is the Davie Ditch up to the Silt Project located North of Rifle, Colorado. This project includes furnishing and installing approximately 4,400 linear feet of 36-inch and 24-inch diameter pipe. The project will also include furnishing and placing concrete for inlet and outlet structures, fabrication, and installation of miscellaneous metalwork.
PRE-BID SITE VISIT: SEE VOLUME I, SECTION L, SOLICITATION CLAUSE
52.236-27 FOR DATE AND TIME. THE SITE VISIT WILL BE HELD AT (LOCATION,
DATE AND TIME TO BE ANNOUNCED)
PROSPECTIVE BIDDERS SHOULD MAKE ARRANGEMENTS BY CONTACTING:
Joshua Dunham, USBR Telephone: 970-248-0613
FOR INFORMATION REGARDING BUREAU OF RECLAMATION'S PUBLICATION
"RECLAMATION SAFETY AND HEALTH STANDARDS" (2009 EDITION AS
REVISED, WITH REVISIONS AT http://www.usbr.gov/ssle/safety/RSHS/rshs.html)
WHICH IS APPLICABLE TO WORK UNDER THIS CONTRACT, SEE CLAUSE AT
"WBR 1452.223-81 SAFETY AND HEALTH."
http://www.usbr.gov/ssle/safety/RSHS/rshs.htm
Davie Ditch Pipeline
Price Schedule
B - 1
CONTINUATION OF
SECTION B – SUPPLIES OR SERVICES AND PRICES COSTS
DAVIE DITCH PIPELINE – SILT PROJECT, COLORADO
B.1 PRICE SCHEDULES
(a) Offers will be considered for award on the following Price Schedules, but no offer will be considered for award on only a part of the Price Schedules.
(1) Offerors shall complete Price Schedule 1 and Optional Price Schedules 2 and 3.
Offers that do not include the Optional Price Schedules 2 and 3 will be considered nonresponsive and will not be evaluated for award.
(2) Offers will be evaluated based on the total of Price Schedule 1 and Optional Price Schedules 2 and 3.
(3) The Government intends to award Price Schedule 1 and may also award one or both Optional Price Schedules 2 and 3. Award of Optional Price Schedules 2 and 3 will depend on available funds.
(4) Details of the Price Schedules are as follow:
PRICE SCHEDULES AND SEGMENTS OF DAVIE DITCH
Price Schedules Segment(s) to be Completed
Stations Plan and Profile Drawing Numbers
Price Schedule 1 Segment 1 Segment 2
Station 100+00 to 115+85 Station 200+00 to 206+16
514-417-490 514-417-494
Price Schedule 2 Segment 4 Station 400+00 to 409+00 514-417-501 Price Schedule 3 Segment 3 Station 300+00 to 312+68 514-417-497
(b) Offers are subject to the terms and conditions of this solicitation.
(c) Quantities in the Price Schedules are estimated quantities for comparison of offers only.
Except as provided in the contract clause at FAR 52.211-18, Variation in Estimated Quantity, no claim shall be made against the Government for overruns or underruns.
The contract clause at FAR 52.211-18, Variation in Estimated Quantity does not apply to lump sum items.
(d) See the contract clause at WBR 1452.232-81 and Specifications Section 01 71 13, Payment for Mobilization and Preparatory Work, CLIN 1 of the Price Schedules.
(e) Definitions:
(1) CLIN – Contract Line-Item Number
B - 2
PRICE SCHEDULE 1
CLIN Section Supplies or Services Quantity and Unit
Unit Price
Amount
1 WBR
1452.232 -81 and 01 71 13
Mobilization and Preparatory Work For the lump sum of $
2 02 41 07 Removal and Disposal of Existing Features For the lump sum of $
3 03 30 00 Concrete for Structures 25 yd3 $ $
4 05 50 00 Miscellaneous Metalwork for Structures For the lump sum of $
5 05 50 00 Miscellaneous Metalwork for Manhole Tees 2 Ea. $ $
6 31 23 02 Select Material Refill for Unsuitable Material 100 yd3 $ $
7 31 23 11 Earthwork for Concrete Structures For the lump sum of $
8 31 23 22 Excavation of Unsuitable Material 100 yd3 $ $
31 35 00 Geocell Erosion Protection 140 yd2 $ $
10 31 35 00 6-inch Cobble 30 yd2 $ $
11 32 92 20 Seeding Disturbed Areas 4 ac $ $
12 33 11 10 Furnish and Install 36-inch Pipe 2201 lin ft $ $
TOTAL FOR PRICE SCHEDULE 1 $_________________
B - 3
OPTIONAL PRICE SCHEDULE 2
CLIN Section Supplies or Services Quantity and Unit
Unit Price
Amount
1 WBR
1452.232 -81 and 01 71 13
Mobilization and Preparatory Work (Incremental Increase) For the lump sum of $
2 02 41 07 Removal and Disposal of Existing Features For the lump sum of $
3 03 30 00 Concrete for Structures 25 yd3 $ $
4 05 50 00 Miscellaneous Metalwork for Structures For the lump sum of $
5 31 23 02 Select Material Refill for Unsuitable Material 40 yd3 $
6 31 23 11 Earthwork for Concrete Structures For the lump sum of $
7 31 23 22 Excavation of Unsuitable Material 40 yd3 $ $
8 31 35 00 6-inch Cobble 5 yd2 $ $
9 32 92 20 Seeding Disturbed Areas 3 ac $ $
10 33 11 10 Furnish and Install 24-inch Pipe 900 lin ft $ $
33 11 10 Furnish and Install 4-inch Pipe 200 lin ft $ $
33 11 10 Furnish and Install 10-inch Pipe 25 lin ft $ $
35 22 10 Furnish and Install Canal Gates For the lump sum of $
TOTAL FOR OPTIONAL PRICE SCHEDULE 2: $_________________
TOTAL FOR PRICE SCHEDULE 1
AND OPTIONAL PRICE SCHEDULE 2: $_________________
B - 4
OPTIONAL PRICE SCHEDULE 3
CLIN Section Supplies or Services Quantity and Unit
Unit Price
Amount
1 WBR
1452.232 -81 and 01 71 13
Mobilization and Preparatory Work (Incremental Increase) For the lump sum of $
2 03 30 00 Concrete for Structures 25 yd3 $ $
3 05 50 00 Miscellaneous Metalwork for Structures For the lump sum of $
4 05 50 00 Miscellaneous Metalwork for Manhole Tees 2 Ea. $ $
5 31 23 02 Select Material Refill for Unsuitable Material 60 yd3 $
6 31 23 11 Earthwork for Concrete Structures For the lump sum of $
7 31 23 22 Excavation of Unsuitable Material 60 yd3 $ $
8 31 35 00 Geocell Erosion Protection 400 yd2 $ $
9 31 35 00 6-inch Cobble 55 yd2 $ $
10 32 92 20 Seeding Disturbed Areas 4 ac $ $
33 11 10 Furnish and Install 36-inch
Pipe 1268 lin ft $ $
TOTAL FOR OPTIONAL PRICE SCHEDULE 3: $_________________
TOTAL FOR PRICE SCHEDULE 1
AND OPTIONAL PRICE SCHEDULE 3: $_________________
TOTAL FOR PRICE SCHEDULE 1, PRICE SCHEDULE 2, AND
PRICE SCHEDULE 3: $_________________
END OF PRICE SCHEDULES
Table of Contents
00 01 10 - 1
SECTION C - DESCRIPTION / SPECIFICATIONS
TABLE OF CONTENTS
DIVISION 01 - GENERAL REQUIREMENTS
01 11 00 Summary of Work 01 14 10 Use of Site 01 31 19 Project Management and Coordination 01 33 00 Submittals 01 35 10 Safety Data Sheets 01 35 20 Safety and Health 01 35 21 Removal from Work 01 42 10 Reference Standards 01 46 00 Quality Procedures 01 51 00 Temporary Utilities 01 55 00 Vehicular Access and Parking 01 55 20 Traffic Control 01 56 10 Protection of Existing Installations 01 56 15 Protection of Existing Utilities 01 56 20 Existing Fences 01 56 32 Temporary Safety Fence 01 57 20 Environmental Controls 01 57 30 Water Pollution Control 01 57 60 Protected Species 01 57 90 Preservation of Historical and Archeological Data 01 60 00 Product Requirements 01 71 13 Mobilization and Preparatory Work 01 71 20 Surveying 01 74 00 Cleaning and Waste Management 01 78 30 Project Record Documents
DIVISION 02 - EXISTING CONDITIONS
02 41 07 Removal and Disposal of Existing Features
DIVISION 03 - CONCRETE
03 11 10 Concrete Forming 03 20 00 Concrete Reinforcing 03 20 30 Grouted Anchor Bars 03 30 00 Cast-In-Place Concrete 03 62 20 Nonshrink Grout for Equipment and Metalwork
Table of Contents
00 01 10 - 2
DIVISION 05 - METALS
05 50 00 Metal Fabrications
DIVISION 31 - EARTHWORK
31 02 10 Water for Dust Abatement 31 03 33 Removal and Control of Water 31 11 00 Clearing and Grubbing 31 23 02 Compacting Earth Materials 31 23 11 Earthwork for Structures 31 23 18 Excavation from Borrow 31 23 22 Pipe Trench Earthwork 31 23 39 Disposal of Excavated Materials 31 35 00 Erosion Protection
DIVISION 32 - EXTERIOR IMPROVEMENTS
32 92 20 Seeding and Soil Supplements
DIVISION 33 - UTILITIES
33 11 10 Pipeline General Requirements 33 11 16 PVC Pressure Pipe 33 11 18 HDPE Pressure Pipe 33 44 20 Polypropylene Profile Wall Pipe
DIVISION 35 - WATERWAY AND MARINE CONSTRUCTION
35 22 10 Hydraulic Gates
DIVISION 51 - INFORMATION AVAILABLE TO OFFERORS
51 00 00 Information Available to Offerors
DIVISION 52 - DRAWINGS
52 00 00 Drawings
END OF CONTENTS
Summary of Work
01 11 00 - 1
SECTION 01 11 00
SUMMARY OF WORK
PART 1 GENERAL
1.01 LOCATION
A. The work on the Davie Ditch is located approximately 5.5 miles north of Rifle, Colorado in Garfield County. The Davie Ditch conveys irrigation water to farms and pastures along the entire length.
1.02 PRINCIPAL COMPONENTS OF WORK
A. Work on the Davie Ditch Pipeline shall consist of:
1. Mobilization and Preparation
2. Removing and disposal of existing features
3. Constructing reinforced concrete structures
4. Fabricating and installing miscellaneous metal work, including covers for manhole tees on 36-inch and 24-inch Pipe
5. Earthwork for structures
6. Clearing and grubbing existing canal alignment
7. Installing 36-inch and 24-inch diameter pipe and associated fittings of selected pipe type
Table 01 11 00 - PRICE SCHEDULES AND SEGMENTS OF DAVIE DITCH Price
Schedules Segment(s) to be
Completed Stations Plan and Profile
Drawing Numbers
Price Schedule 1
Segment 1 Segment 2
Station 100+00 to 115+85 Station 200+00 to 206+16
514-417-490 514-417-494
Optional Price
Schedule 2
Segment 4 Station 400+00 to 409+00 514-417-501
Optional Price
Schedule 3
Segment 3 Station 300+00 to 312+68 514-417-497
01 11 00 - 2
1.01 WORK RESTRICTIONS AND LIMITATIONS
A. Do not interfere with SWCD’s maintenance operations on other portions of the Silt Project.
B. All work shall be completed by April 1, 2024, with the exception of seeding stated below.
C. Final seeding in those areas on disturbance, shall take place between September 1st and November 1st of the same year the work is completed. Work shall take place during non-irrigation season.
1.02 SPECIFICATIONS REQUIREMENTS
A. Requirements in Division 1 General Requirements, apply to Divisions 2 through 5.
B. Imperative statements in these specifications are Contractor requirements, unless otherwise stated.
C. Where specifications are written in streamlined form, words “shall be” are included by inference where a colon (:) is used within sentence or phrase.
1.03 ACRONYMS
A. The following acronyms apply to specifications Divisions 1 through 52:
1. BLM: Bureau of Land Management
2. BOP: Beginning of Project
3. CMP: Corrugated Metal Pipe
4. CO: Contracting Officer.
5. COR: Contracting Officer’s Representative.
6. CY: Cubic yard
7. EOP: End of Project
8. HDPE: High Density Polyethylene
9. LF: Linear Foot
10. PDF: Portable Document Form
11. SWCD: Silt Water Conservancy District
1.04 DEFINITIONS
A. When specifications use a word or term defined in Federal Acquisition Regulations (FAR), definition of the word or term shall be in accordance with FAR sections in effect at the time solicitation was issued.
01 11 00 - 3
1.05 PIPELINE MATERIALS
A. The Government has included three different types of “Pipe” in these specifications to permit the greatest flexibility with potential offerors’ experience, procurement and delivery from suppliers and the construction schedule. The Pipe materials that are included in the following specifications include PVC, HDPE, and Polypropylene Profile Wall Pipe.
B. The contractor will not be permitted to change material type through a specified segment.
Segments are defined in Specification Section 33 11 10, article 1.03, and Table 01 11 00
– Price Schedules and Segments of Davie Ditch.
PART 2 PRODUCTS
Not Used
PART 3 EXECUTION
Not Used
END OF SECTION
01 11 00 - 4
This page intentionally left blank.
Use of Site 01 14 10 - 1
SECTION 01 14 10
USE OF SITE
PART 1 GENERAL
1.01 MEASUREMENT AND PAYMENT
A. Cost:
1. Include in prices offered in the Price Schedules for other items of work.
1.02 REFERENCE STANDARDS
A. Bureau of Reclamation (USBR)
1. Cleaning Manual-2012 Inspection and Cleaning Manual for
Equipment and Vehicles to Prevent the Spread of Invasive Species (Technical Memorandum No. 86-68220-07-05) 2012 Edition Available online at:
http://www.usbr.gov/mussels/prevention
1.03 SUBMITTALS
A. Submit the following in accordance with Section 01 33 00 - Submittals.
B. RSN 01 14 10-1, Land Use and Landscape Rehabilitation Plan for Davie Ditch:
1. For each Contractor use site on Government land:
a. Show use location and extent of impact. Uses include but are not limited to the following:
1) Buildings and service areas including offices, shops, warehouses, storage areas, fuel and oil storage areas, and fabrication yards.
2) Parking areas, temporary roads, and haul routes.
3) Areas for processing, storing, and disposing of waste materials from construction operations.
b. Describe methods to preserve, protect, and repair vegetation (such as trees, shrubs, and grass) and other landscape features on or adjacent to jobsite, which are not to be removed and which do not interfere with work required under this contract. Include methods to mark work area limits, protect disturbed areas, and prevent erosion.
c. Describe methods to protect, and repair if damaged, existing improvements and utilities at or near jobsite.
http://www.usbr.gov/mussels/prevention
01 14 10 - 2
d. Describe methods for removing temporary structures and facilities, cleanup, and rehabilitating site after completion of construction activities.
2. Submit revised drawings of changes in use of Government land made during design and erection stages or after use of Government land is in operation.
1.04 PROJECT CONDITIONS
A. Government land as shown on drawings within the Right-of-Way (ROW) limits shown on the drawings and may be used for required construction facilities. The ROW limits include four permanent easements from private landowners for use as construction staging. The staging areas are shown on Drawing No. 514-417-508.
1. These areas may be used for borrow materials and disposal of excavated materials.
B. In these specifications and the contract, the term “Government land” shall also include the private land authorized for use under the temporary construction easement that is used by the contractor(s).
C. When additional private land is used for construction facilities or other construction purposes, make necessary arrangements associated with use of private land. The use of additional land shall be in accordance with Section 01 57 90, Preservation of Historical and Archeological Data.
D. Location, construction, operation, maintenance, and removal of construction facilities on Government land will be subject to approval of COR.
E. Do not interfere with work of other contractors or the Government in the vicinity, or with reservations made by the Government for use of such land.
F. Housing for construction personnel will not be permitted on Government land.
PART 2 EXECUTION
2.01 CLEANING
A. Construction equipment:
1. Before bringing on site, clean construction equipment to remove dirt, vegetation, and other organic material to prevent introduction of noxious weeds, and invasive plant and animal species.
2. Contractor cleaning procedures shall result in equipment being cleaned as well or better than the procedures described in Cleaning Manual.
3. COR will inspect construction equipment following procedures described in Cleaning Manual before allowing equipment onsite.
01 14 10 - 3
2.02 RESTORATION
A. Restore Contractor staging areas to pre-construction condition with regard to grades and contours.
B. After completion of work, regrade and scarify Government land used for construction purposes and not required for completed installation so that surfaces blend with natural terrain and are in a condition that will facilitate revegetation, provide proper drainage, and prevent erosion.
C. Seed disturbed areas of Government land used for construction purposes and not required for completed installation in accordance with Section 32 92 20 - Seeding and Soil Supplements.
01 14 10 - 4
Project Management and Coordination
01 31 19 - 1
SECTION 01 31 19
PROJECT MANAGEMENT AND COORDINATION
PART 1 GENERAL
1.01 MEASUREMENT AND PAYMENT
A. Cost:
1. Include project management in prices offered in the Price Schedules for other items of work.
1.02 REFERENCE STANDARDS
A. Bureau of Reclamation (USBR)
1. RSHS-2009 Reclamation Safety and Health Standards
PART 2 PRODUCTS
Not Used
PART 3 EXECUTION
3.01 PROJECT COORDINATION
A. The following meetings are considered significant, but do not relieve the Contractor from the responsibility of other meetings required by the specifications.
3.02 PRECONSTRUCTION MEETING
A. Meet with COR at Reclamation’s Western Colorado Area Office in Grand Junction, CO prior to the start of construction. The Contractor shall provide as a minimum the Project Manager or Project Superintendent for the Preconstruction Meeting. Review will include, but may not be limited to:
1. Use of premises by Contractor, Government and SWCD.
2. Construction facilities and controls.
3. Access to the work and haul routes.
4. Temporary utilities.
5. Survey layout.
6. Housekeeping procedures.
7. Schedules and sequence of work.
8. Work restrictions.
Project Management and Coordination
01 31 19 - 2
9. Procedures for testing including quality assurance and quality control.
10. Procedures for maintaining record documents.
11. Roles and responsibilities:
a. Bureau of Reclamation organization and personnel.
b. Contractor organization and personnel.
c. Subcontractors.
d. Proposed work schedule.
12. Contract requirements:
a. Progress payments.
b. Invoices.
c. Differing site conditions.
d. Changes.
e. Superintendence by the Contractor.
f. Payment for mobilization and preparatory work.
g. Submittal procedures.
3.03 SAFETY PROGRAM REVIEW MEETING
A. Meet with COR at Reclamation’s Western Colorado Area Office in Grand Junction, CO prior to the start of construction. Review will include but may not be limited to:
1. Safety requirements.
2. Monthly joint safety policy meetings.
3. Weekly toolbox safety meetings.
4. Contractor’s safety program.
5. Job hazard analysis.
6. Required safety inspections.
7. Government will monitor Contractor’s operations for compliance with RSHS.
3.04 PROGRESS MEETINGS
A. Meet weekly with COR project office to review work, progress made, difficulties in performing work, and resolution necessary to meet specifications requirements.
B. Meetings will include review of construction schedule.
Submittals
01 33 00 - 1
SECTION 01 33 00
SUBMITTALS
PART 1 GENERAL
1.01 MEASUREMENT AND PAYMENT
A. Cost:
1. Include in prices offered in the Price Schedules for other items of work.
1.02 REFERENCE STANDARDS
A. American Society of Mechanical Engineers (ASME)
1. ASME Y14.1-2005(2010) Decimal Inch Drawing Sheet Size and
Format
B. National Institute of Building Sciences (NIBS)
1. NIBS NCS-2011 United States National CAD Standards, Version 5
1.03 DEFINITIONS
A. Days: Calendar days.
B. Required Submittal Number (RSN): Identifies items to be submitted together as part of a complete submittal.
C. Submittal Types, as listed in Table 01 33 00A – List of Submittals:
1. A – Approval:
a. Government will approve or disapprove these submittals.
b. Approval submittals are considered to be “shop drawings” within the terms of the clause at FAR 52.236-21, Specifications and Drawings for Construction.
2. I – Informational:
a. The Government will acknowledge receipt of these submittals.
b. The Government may reject an Informational submittal when the submittal does not comply with the contract. The Contractor shall correct mistakes or deficiencies in rejected Informational submittals and resubmit.
c. Informational submittals are considered to be “shop drawings” within the terms of the clause at FAR 52.236-21, Specifications and Drawings for Construction, except that approval by the Government is not required.
01 33 00 - 2
1.04 SUBMITTAL REQUIREMENTS
A. In case of conflict between requirements of this section and requirements included elsewhere in these specifications, requirements included elsewhere take precedence.
B. General:
1. Prepare in English.
2. Label with contract number, contract title, and RSN.
3. Measurement units: US Customary Units.
C. Drawings:
1. Minimum identification in title block:
a. Contract number and title.
b. Contractor’s or supplier’s title and drawing number.
c. Date.
2. Reserve 3- by 3-inch space next to title block for review stamps.
3. Size: D size (22 inches by 34 inches) as defined by ASME Y14.1.
4. Draw to scale using computer drafting or drafting equipment, unless otherwise specified.
a. Lettering shall be neat when drawing preparation with drafting equipment is allowed.
5. Government Format drawings:
a. Prepare drawings designated as “Government Format” in the specifications as follows:
1) Title block and sheet format:
a) As shown on Drawing 40-D-7102.
b) Government will provide specific title block information to be used.
2) Drawing format:
a) AutoCAD, Version 2018 or later.
b) In accordance with NIBS NCS.
3) Government will provide an electronic AutoCAD template.
6. Final drawings:
a. Drawing format: AutoCAD, Version 2018 or later.
b. Show as-built changes, including revision dates, made during installation.
Indicate changes by clouding.
c. Electronic files: On flash drives.
01 33 00 - 3
d. Government will provide an electronic AutoCAD template.
D. Product Data:
1. Mark manufacturer's data for commercial products or equipment, such as catalog cut sheets.
a. Identify manufacturer's name, type, model, size, and characteristics.
b. Illustrate that product or equipment meets requirements of specifications.
c. Mark items to be furnished in a manner that will photocopy (no highlighter).
d. Strike through items that do not apply.
E. Certifications:
1. Certifications by a registered professional: Signed and sealed by registered professional.
2. Manufacturer’s certifications: Signed by authorized representative of manufacturer.
F. Manuals:
1. Copies:
a. Printed copies: Bound and indexed.
b. Electronic copies: pdf files or flash drives.
1) Bookmark longer files to assist in navigating file.
2. Contents:
a. Parts identification lists, lists of special tools, and accessories.
b. Schematics and wiring diagrams.
c. Detailed instructions for installing, operating, lubricating, and maintaining equipment.
G. As-built drawings, photographs, and test records or reports if required by the specifications.
H. Sample Submittals:
1. Label with complete manufacturer's product and color identification.
2. Include type and quantity of materials specified in the referenced section in each
“set” of samples.
3. Samples: Representative of product to be installed.
4. Label each sample or sample kit with contract number and title.
01 33 00 - 4
1.05 SUBMITTALS PROCEDURES
A. Submit only checked submittals. Submittals without evidence of Contractor's approval will be returned for resubmission.
B. Submit sets specified in Table 01 33 00A - List of Submittals. A complete set includes all listed items for RSNs with multiple parts.
1. Electronic submittals:
a. In pdf form.
b. Include RSN transmittal letter.
c. Do not include Personally Identifiable Information (PII) in electronic submittals.
C. Include the following information in transmittal letters:
1. Contract number and title.
2. RSN for each attached submittal.
3. Responsible code.
4. Number of sets for each RSN.
5. Identify submittal as initial or resubmittal.
D. Resubmittal of submittals not approved:
1. Mark changes such that they are readily identifiable and show revision date.
2. Describe reasons for significant changes in transmittal letter.
3. Resubmit returned submittals within 14 days after receiving the comments, unless otherwise directed.
4. Requirements for initial submittals apply to resubmittals.
E. Each RSN shall be submitted under a separate transmittal letter. Multiple RSNs submitted under a single letter will be returned to the Contractor for resubmittal.
01 33 00 - 5
1.06 REVIEW OF SUBMITTALS
A. Time Required:
1. Submittal review will require up to 21 days for review of each submittal or resubmittal, unless otherwise specified.
2. Time required for review of each submittal or resubmittal begins when complete sets of paper copy materials required for a particular RSN are received and extends through return mailing postmark date.
B. Time in Excess of Specified:
1. The CO may extend the contract completion date to allow additional time for completing work affected by excess review time.
a. The time extension will be to the extent that excess review time caused delay to the contract completion date.
b. The time extension will not exceed the time used in excess of the specified number of days for review of submittals or resubmittals.
c. Concurrent days of excess review time resulting from review of two or more separate submittals or resubmittals will be counted only once in extending the contract completion date.
2. No time extension will be allowed if the Contractor fails to make complete action submittals in sequence and within time periods specified.
3. Adjustment for delay will be made only to the extent that:
a. Approval was required under the contract and,
b. Requests for approval were properly and timely submitted and were approved.
4. Adjustment will be subject to terms of paragraphs (b) and (c) of the clause at FAR
52.242-14, Suspension of Work, however, no such delay shall be deemed to be a “suspension order” as the term is used in that clause.
C. Submittal Response:
1. A response letter from the COR for each submittal will be sent to the Contractor indicating whether the submittal is approved, approved subject to identified changes, or not approved.
a. Revise and resubmit submittals not approved.
b. Do not change designs without approval of the COR after drawings, documentation, and technical data have been approved.
1.07 TRANSMITTAL
A. Addresses for codes listed in Table 01 33 00A - List of Submittals:
01 33 00 - 6
1. Where the recipient is the Contracting Officer, address the transmittal letter to Bureau of Reclamation, 125 South State Street, Salt Lake City, UT, 84137-1148, Attn.: Dwane Esplin
2. Where the recipient is the Contracting Officer’s Representative, address the transmittal letter to Bureau of Reclamation, Attention: Joshua Dunham, Suite 221, 445 West Gunnison Avenue, Suite 221 Grand Junction, CO 81501.
a. In addition to the paper copy submissions mailed to the above referenced address, electronic pdf submittals shall be e-mailed to the following address: jdunham@usbr.gov.
PART 2 PRODUCTS
Not Used
PART 3 EXECUTION
01 33 00 - 7
Table 01 33 00A. - List of Submittals
* CO indicates Contracting Officer, and COR indicates Contracting Officer’s Representative.
** Submit types: A – Approval, I – Information
RSN
Clause or
Section Title
Submittals required
Due date or delivery time
Type
Respon-sible code
No. of sets to be sent to: *
CO COR
1 Bonds 52.228-15
Performance and Payment Bonds
Within 10 calendar days after award
A CO 1
electronic
2 Insurance-work on a Government Installation 1452.228-70
1) Written certification that the required insurance has been obtained
2) Current certification of insurance for each subcontractor
Before commencing onsite work A CO 1 electronic
3 Liability Insurance 1452.228-70
Acceptable Certificate of Liability Insurance
Prior to commencement of work under the contract
A CO 1
electronic
4 Equal Opportunity 52.222-26
Information required by Executive Order
112246 (SF-100)
Within 30 days following award A CO 1 electronic
6 Release of Claims 1452.204-70
Release of Claims (DI-137) against the Government
After completion of the work and prior to final payment
A CO 1
electronic
7 Labor Standards Data 52.222-11
1) List of subcontractors
2) Statement and acknowledgement Form (SF-1413) for each subcontract
Within 14 days after award of contract
A COR 1
8 Payrolls 52.222-08
Copies of all payrolls
Statement of Compliance
Weekly for each week of contract performance
Weekly for each week of contract performance
A COR 1
9 Schedules for
Construction Contracts (52.236-15)
Practicable schedule:
Blackline prints
Within 7 days after work commences on the contract or another period of time as determined by the COR
A COR 1
electronic electronic
11 Schedules for Construction Contracts (52.236-15)
Supplementary schedule or schedules:
Blackline prints
As deemed necessary by the
COR
A COR 1
electronic electronic
01 14 10-1 Use of Site Land Use and Landscape Rehabilitation Plan for Davie Ditch
At least 14 days before use of Government land
A COR 1
electronic electronic
01 35 10-1 Safety Data Sheets
Complete LHM and
SDS
At least 7 days before jobsite delivery of hazardous material
I COR 1
electronic
01 33 00 - 8
Table 01 33 00A. - List of Submittals
* CO indicates Contracting Officer, and COR indicates Contracting Officer’s Representative.
** Submit types: A – Approval, I – Information
RSN
Clause or
Section Title
Submittals required
Respon-sible code
No. of sets to be sent to: *
CO COR
01 35 10-2 Safety Data Sheets
Updated LHM and
SDS
At least 7 days before jobsite delivery of hazardous material not previously listed
I COR 1
electronic electronic
01 35 20-1 Safety and Health
Safety Program Submitted and accepted before commencing onsite work. See Section 3 of RSHS
A COR 1
electronic electronic
01 35 20-2 Safety and Health
Certificates At least 14 days before beginning onsite work
A COR 1
electronic electronic
01 35 20-3 Safety and Health
Monthly Reports At start of each month I COR 1 electronic electronic
01 55 20-1 Traffic Control Traffic control plan (when applicable)
At least 30 days before affecting public traffic
A COR 1
electronic electronic
01 57 30-1 Water Pollution Control
Pollution Prevention Plan – Copies of 402 Wastewater Discharge Permit for Davie Ditch
At least 14 days before start of onsite construction work
I COR 1
electronic electronic
01 57 30-2 Water Pollution Control
Spill Prevention Control and Countermeasure Plan (SPCC) for Davie Ditch
At least 14 days before delivery or storage of oil – if required
I COR 1
electronic electronic
01 57 30-3 Water Pollution Control
Notice of Intent (NOI) and Storm Water Discharge Permit Associated with a Construction Site – Davie Ditch
Within 2 days after time of signature
I COR 1
electronic electronic
01 57 30-4 Water Pollution Control
Monitoring Results – Davie Ditch (when applicable)
Within 2 days after each monitoring
I COR 1
electronic electronic
01 57 90-1 Preservation of Historical and Archeological Data
Maps showing locations of alternate staging areas, off-site borrow areas
Submitted and approved at least 45 days prior to use of staging areas, and off-site borrow areas not from commercial sources
A COR 1
electronic electronic
01 71 20-1 Surveying Resumes At least 14 days before beginning survey work; At least 14 days before personnel change
A COR 1
electronic electronic
01 71 20-2 Surveying Accuracy Check Results for Davie Ditch
At least 14 days before beginning construction activities
A COR 1
electronic electronic
01 74 00-1 Cleaning and Waste Management
Waste Production and Disposal Records
Within 7 days of waste disposal I COR 1 electronic
01 33 00 - 9
Table 01 33 00A. - List of Submittals
* CO indicates Contracting Officer, and COR indicates Contracting Officer’s Representative.
** Submit types: A – Approval, I – Information
RSN
Clause or
Section Title
Submittals required
Respon-sible code
No. of sets to be sent to: *
CO COR
01 74 00-2 Cleaning and Waste Management
Environmental Consultant Resume (when applicable)
At least 21 days before beginning environmental assessment
A COR 1
electronic electronic
01 74 00-3 Cleaning and Waste Management
Environmental Site Assessment (when applicable)
Within 14 days of completion of work
I COR 1
electronic electronic
01 78 30-1 Project Record Documents
Final As-Built Drawings for Davie Ditch
Within 14 days of completion of work
A COR 1
electronic electronic
03 20 00-1 Concrete Reinforcing
Reinforcement Diagrams and Lists
At least 14 days before fabricating reinforcing bars
I COR 1
electronic electronic
03 20 30-1 Grouted Anchor Bars
Approval Data At least 14 days before using grout
I COR 1
electronic electronic
03 20 30-2 Grouted Anchor Bars
Instructions At least 14 days before using grout
I COR 1
electronic electronic
03 30 00-1 Cast-In-Place Concrete
Approval Data for Each Concrete Mix and Supplier
At least 14 days before placing concrete
I COR 1
electronic electronic
03 30 00-2 Cast-In-Place Concrete
Concrete Repair Methods
At least 14 days before placing concrete
I COR 1
electronic electronic
03 62 20-1 Nonshrink Grout for Equipment and Metalwork
Packaged Nonshrink Grout Data
At least 14 days before placing packaged nonshrink grout
I COR 1
electronic electronic
31 35 00-1 Erosion Protection
Approval Data for Geocell Manufacturer’s Product Data
At least 14 days before placing geocell
A COR 1
electronic electronic
31 35 00-2 Erosion Protection
Approval Data for Geotextile Manufacturer’s Product Data
At least 14 days before placing geotextile
A COR 1
electronic electronic
32 92 20-1 Seeding and Soil Supplements
Seeding Plan for Davie Ditch
At least 14 days before seeding A COR 1 electronic electronic
32 92 20-2 Seeding and Soil Supplements
Certifications for Davie Ditch
At least 14 days before furnishing seed
A COR 1
electronic electronic
33 11 10-1 Pipeline General Requirements
Installation Plan At least 14 days before procuring pipe
I COR 1
electronic electronic
*33 11 16-1 PVC Pressure Pipe
Approval Data At least 14 days before procuring PVC pipe
I COR 1
electronic electronic
*33 11 16-2 PVC Pressure Pipe
Saddle taps At least 14 days before procuring fittings
I COR 1
electronic
01 33 00 - 10
Table 01 33 00A. - List of Submittals
* CO indicates Contracting Officer, and COR indicates Contracting Officer’s Representative.
** Submit types: A – Approval, I – Information
RSN
Clause or
Section Title
Submittals required
Respon-sible code
No. of sets to be sent to: *
CO COR
*33 11 18-1 HDPE
Pressure Pipe
Shop Drawings At least 14 days before procuring HDPE pipe fittings
I COR 1
electronic electronic
*33 11 18-2 HDPE
Pressure Pipe
Pipe manufacturer’s certifications
At least 14 days before procuring HDPE pipe
I COR 1
electronic electronic
*33 11 18-3 HDPE
Pressure Pipe
Pipe Fusion Procedures
At least 14 days before beginning fusion welding HDPE pipe
A COR 1
electronic electronic
*33 11 18-4 HDPE
Pressure Pipe
Daily Fusion Data Logger Record
End of shift for pipe fusion welding crew
A COR 0 1
electronic
*33 11 18-5 HDPE
Pressure Pipe
Project Fusion Data Logger Record
Within 14 days of completing all pipe fusions
A COR 1
electronic electronic
*33 44 20-1 Polypropylene Profile Wall Pipe
Pipe manufacturer’s certifications
At least 14 days before procuring PE Profile wall pipe
I COR 1
electronic electronic
*33 44 20-2 Polypropylene Profile Wall Pipe
Pipe Fitting manufacturer’s certifications
At least 14 days before procuring PE Profile wall pipe
I COR 1
electronic electronic
*33 44 20-3 Polypropylene Profile Wall Pipe
Pipe manufacturer’s Pipeline Lay drawings
At least 14 days before procuring PE Profile wall pipe
I COR 1
electronic electronic
35 22 10-1 Hydraulic Gates
Approval data for Canal Gates
At least 14 days before procuring gate
A COR 1
electronic electronic
35 22 10-2 Hydraulic Gates
Final data for Canal Gates
At least 14 days after procuring gate
A COR 1
electronic electronic
* Denotes submittals that are only required if pipe type is selected by for the project.
Safety Data Sheets
01 35 10 - 1
SECTION 01 35 10
SAFETY DATA SHEETS
PART 1 GENERAL
1.01 MEASUREMENT AND PAYMENT
A. Cost:
1. Include in prices offered in the Price Schedules for other items of work.
1.02 DEFINITIONS
A. LHM: List of Hazardous Materials.
B. SDS: Safety Data Sheet.
1. Referred to as Material Safety Data Sheets in the clause at 52.223-3, Hazardous
Material Identifications and Material Safety Data - Alternate 1.
1.03 APPLICATION
A. For the purposes of this contract, “delivered under this contract” in paragraph (b) of the clause at FAR 52.223-3, Hazardous Material Identification and Material Safety Data - Alternate 1, includes:
1. Materials delivered to Government.
2. Materials incorporated into work.
3. Materials used by the Contractor during contract performance at the jobsite.
1.04 SUBMITTALS
A. Submit the following in accordance with Section 01 33 00 - Submittals.
B. RSN 01 35 10-1, Complete LHM and SDS.
C. RSN 01 35 10-2, Updated LHM and SDS:
1. Comply with paragraph (e) of clause at FAR 52.223-3, Hazardous Material
Identification and Material Safety Data - Alternate 1.
1.05 DELIVERY
A. Do not deliver hazardous materials to jobsite which are not included on original or previously updated LHM and SDS before receipt of updated LHM and SDS by COR.
Safety Data Sheets
01 35 10 - 2
PART 2 PRODUCTS
Not Used
PART 3 EXECUTION
Safety and Health
01 35 20 - 1
SECTION 01 35 20
SAFETY AND HEALTH
PART 1 GENERAL
1.01 MEASUREMENT AND PAYMENT
A. Cost:
1. Include in prices offered in the Price Schedules for other items of work.
1.02 REFERENCE STANDARDS
A. Bureau of Reclamation (USBR)
1. RSHS-2009 Reclamation Safety and Health Standards, including revisions posted at http://www.usbr.gov/ssle/safety/RSHS/rshs.
html
1.03 SUBMITTALS
A. Submit the following in accordance with Section 01 33 00 - Submittals.
B. RSN 01 35 20-1, Safety Program:
1. Prepared in accordance with RSHS Section 3 and RSHS Appendix B.
2. Job specific. Generic company safety program will not be accepted.
3. Comprehensive, detailed information on safe work practices, training, engineering controls and personal protective equipment that will be used for this job.
C. RSN 01 35 20-2, Certificates:
1. CPR and First Aid training certificates for on-site supervisors and foremen.
D. RSN 01 35 20-3, Monthly reports:
1. Safety Inspection Reports:
a. List noted deficiencies, their abatement dates, and follow-up action for jobsite activities.
b. Base inspection report on findings of jobsite walk-through with Government personnel.
2. Monthly summary: Form 7-2218 or other acceptable form in accordance with paragraph 3.8 of RSHS.
1.04 QUALIFICATIONS
A. Contractor’s Onsite Safety Representative(s):
http://www.usbr.gov/ssle/safety/RSHS/rshs.html
01 35 20 - 2
1. Competent supervisory employee with appropriate level of safety related training and experience.
2. Holds current certificates for first aid and adult CPR.
1.05 CONTRACTOR’S ONSITE SAFETY PERSONNEL
A. Designate employee(s) as Contractor’s Onsite Safety Representative(s) prior to start of construction.
B. Contractor’s Onsite Safety Representative(s) authorities, duties, and responsibilities:
1. Review and approve Safety Program prior to submittal.
2. Implement Safety Program.
3. Full authorization to correct unsafe activity on the spot.
4. Prepare safety inspection reports.
5. At least one Contractor Onsite Safety Representative shall be onsite during construction activities.
1.06 SAFETY AND HEALTH
A. Onsite work, including mobilization, shall not begin until the COR has reviewed the Safety Program and replied that the Safety Program is adequate for proceeding with onsite work.
B. Comply with the clause at FAR 52.236-13 - Accident Prevention, the clause at WBR 1452.223-81- Safety and Health, RSHS, local safety programs, referenced safety and health standards, and Safety Program.
1. In the event there is a conflict between requirements contained in these documents, the more stringent requirement shall prevail.
1.07 MEDICAL SERVICES AND FIRST AID
A. Provide medical services and first aid in accordance with RSHS Section 5.
B. Make facilities and services available for emergency aid to employees, subcontractor employees, and Government employees.
1. Provide services free of charge to Government employees injured on job.
2. Government employees not injured on job may be charged fees for rendered services based on reasonable and established fee rates.
01 35 20 - 3
C. Ambulance service:
1. Arrange for dependable ambulance service in accordance with RSHS, paragraph
5.4.
2. On site ambulance is not required.
3. Ambulance operators: Certified to render first aid/CPR and competent to operate vehicle.
1.08 QUALITY ASSURANCE
A. Contractor’s Onsite Safety Representative(s):
1. The effectiveness of Contractor’s Onsite Safety Representative(s) in prosecuting the safety program will be subject to continual review by the CO.
B. Safety Program:
1. The effectiveness of the Safety Program will be subject to continual review by the
CO.
PART 2 PRODUCTS
Not Used
PART 3 EXECUTION
01 35 20 - 4
Removal from Work
01 35 21 - 1
SECTION 01 35 21
REMOVAL FROM WORK
PART 1 GENERAL
1.01 REMOVAL FROM WORK
A. If, in the opinion of the CO, an employee refuses or repeatedly fails to comply with, or supervisors fail to enforce compliance with the safety requirements contained in the "Accident Prevention" clause and the "Safety and Health - Bureau of Reclamation" clause in Section I of this contract, the CO may require, in accordance with paragraph (c) of the "Material and Workmanship" clause in Section E, that the individual be removed from the work, and the site if necessary.
PART 2 PRODUCTS
Not Used
PART 3 EXECUTION
Removal from Work
01 35 21 - 2
Reference Standards
01 42 10 - 1
SECTION 01 42 10
REFERENCE STANDARDS
PART 1 GENERAL
1.01 MEASUREMENT AND PAYMENT
A. Cost:
1. Include in prices offered in the Price Schedules for other items of work.
1.02 REFERENCE STANDARDS
A. Referenced editions of standard specifications, codes, and manuals form a part of this specification to the extent referenced.
B. These specifications take precedence when conflicting requirements occur between specifications and referenced standard.
1.03 JOBSITE REFERENCE STANDARDS
A. Maintain at fabrication site, access to referenced standard specifications, codes, and manuals required for work in progress at fabrication site. Make available for use by the Government.
B. Maintain onsite, access to referenced standard specifications, codes, and manuals required for onsite work in progress. Make available for use by the Government.
1.04 AVAILABILITY
A. Code of Federal Regulations (CFR):
1. Available online, authorized by the National Archives and Records
Administration (NARA) and the Government Printing Office (GPO), at http://www.gpo.gov/fdsys/search/home.action
B. Bureau of Reclamation Documents:
1. Reclamation Safety and Health Standards (RSHS) may be downloaded at www.usbr.gov/ssle/safety/RSHS/rshs.html.
a. Hard copies of RSHS, stock number 024-003-00204-6, may be purchased from The Superintendent of Documents at the U.S. Government Printing Office (GPO), phone number 202-512-1800. Hard copies of RSHS are subject to revisions posted on the site shown above.
1) GPO online bookstore:
http://bookstore.gpo.gov/actions/GetPublication.do?stocknumber= 024-003-00204-6.
http://www.gpo.gov/fdsys/search/home.action http://www.usbr.gov/ssle/safety/RSHS/rshs.html http://bookstore.gpo.gov/actions/GetPublication.do?stocknumber=024-003-00204-6 http://bookstore.gpo.gov/actions/GetPublication.do?stocknumber=024-003-00204-6
01 42 10 - 2
2. Bureau of Reclamation Standard Specifications are designated with an M-number. Copies of individual standards may be obtained from Bureau of Reclamation, Attn: 86-68510, P.O. Box 25007, Denver CO 80225-0007. Specify standard(s) needed when requesting a copy.
3. Bureau of Reclamation manuals and other publications including significant scientific, technical, and engineering works are available from the National Technical Information Service (NTIS). Information regarding availability and pricing may be obtained by contacting NTIS at the following address:
United States Department of Commerce National Technical Information Service 5285 Port Royal Road Springfield, VA 22161 Telephone: 703-487-4650 or 1-800-553-6847
C. Industrial and Governmental Documents:
1. When a reference has a joint designation (e.g. ANSI/IEEE) these specifications generally cite the proponent organization (e.g. IEEE).
2. Addresses for obtaining industrial and governmental (other than Federal and
Bureau of Reclamation specifications and standards) specifications, standards, and codes are listed in Table 01 42 10A - Addresses for Specifications, Standards, and Codes.
Table 01 42 10A - Addresses for Specifications, Standards, and Codes
Acronym Name and Address Telephone
AASHTO American Association of State Highway and Transportation Officials 444 North Capitol Street, NW., Suite 249 Washington, DC 20001 www.aashto.org
202-624-5800 800-231-3475
ACI American Concrete Institute 38800 Country Club Dr.
Farmington Hills, MI 48331-3439 https://www.concrete.org/home.aspx”
248-848-3700
AGC Associated General Contractors of America 333 John Carlyle Street, Suite 200 Alexandria, VA 22314 www.agc.org
703-548-3118 http://www.aashto.org/ https://www.concrete.org/home.aspx http://www.agc.org/
01 42 10 - 3
Table 01 42 10A - Addresses for Specifications, Standards, and Codes
Acronym Name and Address Telephone
AISC American Institute of Steel Construction One East Wacker Drive, Suite 3100 Chicago, IL 60601-2001 www.aisc.org
312-670-2400
ANSI American National Standards Institute 1819 L. Street, NW.
Washington, DC 20036 www.ansi.org
202-293-8020
APA/EWA APA-The Engineered Wood Association P.O. Box 11700 Tacoma, WA 98411-0700 www.apawood.org
253-565-6600
ASME American Society of Mechanical Engineers 3 Park Avenue New York, NY 10016-5990 www.asme.org
800-843-2763
ASTM ASTM International P.O. Box C700 100 Barr Harbor Drive West Conshohocken, PA 19428-2959 www.astm.org
610-832-9585
AWS American Welding Society 550 NW LeJeune Road Miami, FL 33126 www.amweld.org
800-443-9353 305-443-9353
ICRI International Concrete Repair Institute 1000 Westgate Drive, Suite 252 | St. Paul, Minnesota 55114 http://www.icri.org/
651-366-6095
IEEE Institute of Electrical and Electronics Engineers 3 Park Avenue,17th Floor New York, NY 10016-5997 www.ieee.org
212-419-7900
NACE NACE International 1440 South Creek Drive Houston, TX 77084 www.nace.org
281-228-6200 http://www.aisc.org/ http://www.ansi.org/ http://www.apawood.org/ http://www.asme.org/ http://www.astm.org/ http://www.amweld.org/ http://www.icri.org/ http://www.ieee.org/ http://www.nace.org/
01 42 10 - 4
Table 01 42 10A - Addresses for Specifications, Standards, and Codes
Acronym Name and Address Telephone
NEMA National Electrical Manufacturers Association 1300 N 17th Street, Suite 1847 Rosslyn, VA 22209 www.nema.org
703-841-3200
NETA International Electrical Testing Association Inc.
3050 Old Centre Ave., Suite 102 Portage, MI 49024 http://www.netaworld.org/
269-488-6382
SSPC SSPC: The Society for Protective Coatings 40 24th Street, 6th Floor Pittsburgh, PA 15222-4656 www.sspc.org
800-837-8303 412-281-2331
TIA/EIA
Telecommunications Industry Association/Electronic Industries Alliance 2500 Wilson Boulevard, Suite 300 Arlington, VA 22201 www.tiaonline.org
703-907-7700
UL Underwriters Laboratories, Inc.
333 Pfingsten Road Northbrook, IL 60062-2096 www.ul.com
847-272-8800
PART 2 PRODUCTS
Not Used
PART 3 EXECUTION
http://www.nema.org/ http://www.netaworld.org/ http://www.sspc.org/ http://www.ul.com/
Quality Procedures
01 46 00 - 1
SECTION 01 46 00
QUALITY PROCEDURES
PART 1 GENERAL
1.01 MEASUREMENT AND PAYMENT
A. Cost:
1. Include in prices offered in the Price Schedules for other items of work.
1.02 DEFINITIONS
A. Government Contract Quality Assurance: (from FAR 46.101) Various functions, including inspection, performed by the Government to determine whether a contractor has fulfilled the contract obligations pertaining to quality and quantity.
B. Contractor Quality Assurance / Quality Control (QA/QC): Activities performed by the Contractor to ensure work conforms to contract requirements.
1. The clause at FAR 52.246-12 - Inspection of Construction, requires the
Contractor to establish an inspection system to ensure quality.
2. Contractor QA/QC includes activities in addition to specified Contractor Quality
Testing to ensure work conforms to contract requirements.
C. Contractor Quality Testing: Specified tests shall be performed by the Contractor.
1. The Government will evaluate results of these tests when determining acceptability of work.
2. The Contractor may use the test results as part of Contractor QA/QC.
a. The Government anticipates that these tests will be part of the Contractor’s QA/QC program, however the tests do not relieve the Contractor of maintaining adequate quality system in accordance with the clause at FAR 52.246-12 - Inspection of Construction.
PART 2 PRODUCTS
Not Used
PART 3 EXECUTION
Quality Procedures
01 46 00 - 2
Temporary Utilities
01 51 00 - 1
SECTION 01 51 00
TEMPORARY UTILITIES
PART 1 GENERAL
1.01 MEASUREMENT AND PAYMENT
A. Cost:
1. Include in prices offered in the Price Schedules for other items of work.
1.02 REFERENCE STANDARDS
A. Institute of Electrical and Electronics Engineers (IEEE)
1. IEEE C2-12 National Electrical Safety Code (NESC)
1.03 TEMPORARY ELECTRICITY
A. Provide electric power required for construction.
B. Provide generators, transmission lines, distribution circuits, transformers, and other electrical equipment and facilities required for obtaining and distributing power to points of use.
C. Comply with IEEE C2 clearances and spacing for temporary communications and supply lines.
1.04 TEMPORARY WATER
A. Provide water required for construction purposes.
B. Use water which meets specified requirements for water used in concrete, grouting, and other permanent work.
C. Provide means of conveying water to points of use.
1.05 SANITARY FACILITIES
A. Contractor shall provide sanitary facilities.
PART 2 PRODUCTS
Temporary Utilities
01 51 00 - 2
PART 3 EXECUTION
3.01 REMOVAL
A. Remove temporary equipment and facilities upon completion of work under this contract.
Vehicular Access and Parking
01 55 00 - 1
SECTION 01 55 00
VEHICULAR ACCESS AND PARKING
PART 1 GENERAL
1.01 MEASUREMENT AND PAYMENT
A. Cost:
1. Include in prices offered in the Price Schedules for other items of work.
1.02 REGULATORY REQUIREMENTS
A. Meet requirements established by jurisdictional authority for use of existing roadways and haul routes; including seasonal or other limitations or restrictions, payment of excess size and weight fees, and posting of bonds conditioned upon repair of damage.
B. Comply with applicable regulations for haul routes over public highways, roads, or bridges.
1.03 SITE CONDITIONS
A. Rights-of-way for access to work from existing roads will be established by Government.
1. In accordance with clause at FAR 52.236-10, Operations and Storage Areas, use only established roadways, parking areas, and haul routes; or temporary roadways, parking areas, or haul routes constructed by Contractor when and as authorized by CO.
2. Subject to clause at FAR 52.249-10, Default (Fixed-Price Construction), unavailability of transportation facilities or limitations thereon shall not become a basis for claims for damages or extension of time for completion of work.
B. The project access road is…
This is the start of the file's text. The full file is on GovTribe.