This document contains the project execution requirements for a Design/Build Sprinkler System contract for the New Hampshire Fish and Game (NHFG) Region 3 facility. The project involves replacing the existing fire protection system in its entirety with a new nitrogen generator system. The existing building is approximately 7,500 square feet and has dry heads in the heated occupied spaces and attic/interstitial spaces. The contractor will be required to perform a flow test, enlarge or provide new access points as needed, and include all cutting, coring, patching, painting, and finishing of surfaces. The contractor must comply with all applicable codes, obtain required permits, and coordinate system shutdowns with the State Fire Marshal's Office, fire alarm company, and local fire department. The work must be completed within the specified time frame after the Notice to Proceed is issued.
The contract will be awarded as a lump sum base bid. The contractor will be responsible for providing all materials, labor, tools, equipment, and other services necessary to execute, complete, and deliver the work. The State will occupy the premises during construction, and the contractor must coordinate with the State to minimize conflicts and facilitate their operations. The contractor will also be required to meet quality control and safety requirements, and provide project record documents, operation and maintenance data, warranties, and guarantees upon completion of the work.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| attachment_2_bid_2948_25.pdf | ||
| attachment_3_bid_2948_25.pdf | ||
| bid_2948_25.pdf | ||
| attachment_4_bid_2948_25.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
81351R, Contract A – Design/Build Sprinkler NHFG Region 3 December 15, 2022
Summary
01100 - 1
SECTION 01100
SUMMARY
PART 1 GENERAL
1.1 SECTION INCLUDES
A. Contract description.
B. Contractor's use of site and premises.
C. Work sequence.
D. State occupancy.
E. Specification Conventions.
1.2 CONTRACT DESCRIPTION
A. Design/Build Sprinkler System: All work shall be approved and permitted by the Fire
Marshal’s Office before construction. Submit P.E. stamped plans and specs to the
Contract Administrator. After review by the Contract Administrator, the Contractor shall submit P.E. stamped plans and specifications to the Fire Marshal’s Office for permit and approval. Contractor shall comply with Fire Marshal’s comments of P.E. stamped plans and specifications.
a. The existing fire protection system is to be replaced in its entirety complete with a nitrogen generator system.
b. The entire existing fire protection system is dry with dedicated compressed air. Dry heads are used in the heated occupied spaces of the building, as well at the attic/interstitial spaces. All existing piping is run within the attic/ interstitial spaces. All new piping is to be run in these same spaces.
c. Include performing a flow test in accordance with applicable codes, State
Fire Marshal’s Office and the Local Water Department.
d. The existing square footage of building is approximately 7,500 square feet. This does not include the attic.
e. See Appendices for floor plans, fire protection system plans, attic access hatch locations, and photographs. Note that the plans are not available in
CAD form.
f. Install cages where cages are provided in the existing system.
g. If existing furniture must be moved to facilitate the work, coordinate with the State and the State will remove furniture.
h. The existing attic and interstitial space above the Conference and
Reception areas (see Floor Plans in Appendices) area accessed via 3 existing access hatches (see Appendices for locations). Include, if required, enlarging and/or providing new access points as the work of
81351R, Contract A – Design/Build Sprinkler NHFG Region 3 December 15, 2022
01100 - 2 this contract may require, including any confined space access requirements that may be required.
i. Include any/all cutting, coring, patching, painting and/or finishing of existing surfaces as may be required by the work to match existing. This includes but is not limited to:
1) New sprinkler head locations
2) Abandoned existing head locations
3) Enlarging/new existing attic/interstitial space access points
4) Damage as a result of the work
j. Painting:
1) Paint new piping at exposed to view areas (currently at garage bay & garage mezzanine areas only)
2) Paint disturbed wall/ceiling areas (as a result of new/relocated head locations, coring, patching etc – see Part i above)
1. Paint any walls/ceilings “corner-to-corner”
k. Coordinate all system shutdowns with State Fire Marshal’s Office, fire alarm company and local fire department.
l. Assume the following:
1) The fire alarm system shall be active and maintained during all periods which the sprinkler system is inactive. Daily shutdown of fire alarm system as may be required for the work shall be coordinated.
2) The sprinkler system shall be inactive during construction.
m. Submit and pay for any/all permits as may be required for the scope of work.
n. A Hot Work Permit is required for any operation involving open flame or producing heat and/or sparks.
B. SITE EXAMINATION
1. Examine Project site before submitting a Bid.
2. A visit to Project site has been arranged for Bidders at [________] [AM] [PM] on
C. Perform Work of Contract under stipulated lump sum base bid contract with State in accordance with Conditions of Contract.
D. The Contractor shall, except as otherwise specifically stated in the Contract Documents, provide and pay for all materials, labor, tools, equipment, water, heat, fuel, light, power, transportation, superintendence, temporary construction of every nature, and all other services and facilities of every nature whatsoever necessary to execute, complete, and deliver the work within the specified time.
1.3 CONTRACTOR'S USE OF SITE AND PREMISES
A. Limit use of site and premises to allow:
1. State occupancy.
2. Use of site and premises by the public (limited to parking area, main entrance and reception area)
81351R, Contract A – Design/Build Sprinkler NHFG Region 3 December 15, 2022
01100 - 3
B. Emergency Building Exits During Construction: Shall be maintained and all building entrances and exits shall remain functional.
C. Time Restrictions for Performing Interior Work: Normal working hours of 7:00 am to
3:30 pm Monday through Friday with the following restrictions:
1. No access during the following observed holidays:
a. New Year’s Day.
b. Martin Luther King Jr. Civil Rights Day.
c. President’s Day.
d. Memorial Day.
e. Independence Day.
f. Labor Day.
g. Veterans’ Day.
h. Thanksgiving Day.
i. Day after Thanksgiving.
j. Christmas Day.
2. Access for work outside of normal working hours shall be requested in writing to the Contract Administrator, at least one week in advance. The Contract
Administrator may accept or reject the request.
D. Utility Outages and Shutdown: [Shall be coordinated with the building users to minimize disruption of services, and may require work to take place outside of normal working hours.]
1.4 WORK SEQUENCE
A. Work shall commence within 15 days after issuance of Notice to Proceed. Failure to comply shall constitute Default of Contract.
1.5 STATE OCCUPANCY
A. The State will occupy the premises during the entire period of construction for the conduct of normal operations.
B. Cooperate with State to minimize conflict, and to facilitate State's operations.
C. Schedule the Work to accommodate State occupancy.
1.6 SPECIFICATION CONVENTIONS
A. These specifications are written in imperative mood and streamlined form. This imperative language is directed to the Contractor, unless specifically noted otherwise.
The words “shall be” are included by inference where a colon (:) is used within sentences or phrases.
PART 2 PRODUCTS
Not Used.
81351R, Contract A – Design/Build Sprinkler NHFG Region 3 December 15, 2022
01100 - 4
PART 3 EXECUTION
END OF SECTION
81351R, Contract A – Design/Build Sprinkler NHFG Region 3 December 15, 2022
Quality Requirements
01400 - 1
SECTION 01400
QUALITY REQUIREMENTS
PART 1 GENERAL
1.1 SECTION INCLUDES
A. Quality control and control of installation.
B. Tolerances
C. References.
D. Safety
E. Supervision
F. Examination.
G. Preparation.
1.2 QUALITY CONTROL AND CONTROL OF INSTALLATION
A. Monitor quality control over suppliers, manufacturers, products, services, site conditions, and workmanship, to produce Work of specified quality. Prior to acceptance of approved materials on site, establish & maintain controlled environmental conditions required for proper, sequential installations. Products affected by inadequate environmental control
(in storage or installed) shall be removed, disposed of and replaced in-kind with no adjustment to the contract price or work schedule.
B. Comply with manufacturers' instructions, including each step in sequence.
C. When manufacturers' instructions conflict with Contract Documents, request clarification from the Contract Administrator before proceeding.
D. The Contractor shall notify the Contract Administrator of any discrepancies, ambiguities or obvious omissions found in the Contract Documents before proceeding with the work affected thereby. Such notification shall be made in writing requesting clarification and/or interpretation with reasonable promptness consistent with and reasonably inferable from the Contract Documents. If the Contractor fails to make such request, no excuse will thereafter be entertained for failure to carry out work in a satisfactory manner, and no monies will be paid for correcting of items.
E. The Contractor shall give the Contract Administrator timely notice of any additional drawings, specifications or instructions required to define the work in greater detail or to permit the proper progress of the work.
R ev is ed
F eb
81351R, Contract A – Design/Build Sprinkler NHFG Region 3 December 15, 2022
01400 - 2
F. Comply with specified standards as minimum quality for the Work except where more stringent tolerances, codes, or specified requirements indicate higher standards or more precise workmanship.
G. Where, on any of the Drawings, a portion of the work is drawn out and the remainder is indicated in outline, the parts drawn out shall also apply to all other portions of the work.
H. Perform Work by persons qualified to produce required and specified quality.
I. Verify field measurements are as indicated on Shop Drawings or as instructed by manufacturer.
J. Secure products in place with positive anchorage devices designed and sized to withstand stresses, vibration, physical distortion, or disfigurement.
1.3 TOLERANCES
A. Monitor fabrication and installation tolerance control of products to produce acceptable
Work. Do not permit tolerances to accumulate.
B. Comply with manufacturers' tolerances. When manufacturers' tolerances conflict with
Contract Documents, request clarification from the Contract Administrator before proceeding.
C. Adjust products to appropriate dimensions; position before securing products in place.
1.4 REFERENCES
A. Conform to reference standard by date prior to the date of receiving bids, except where specific date is established by code. The standard referred to, except as modified in the specifications, shall have full force and effect as though printed in the Specifications.
B. Obtain copies of standards where required by product specification sections.
C. When specified reference standards conflict with Contract Documents, request clarification from the Contract Administrator before proceeding.
D. Neither contractual relationships, duties, nor responsibilities of parties in Contract nor those of Architect or Engineer shall be altered from Contract Documents by mention or inference otherwise in reference documents.
E. The Contractor shall comply with all applicable Federal, State, Local laws, ordinances, regulations, and requirements to work hereunder, including building code requirements.
If the Contractor ascertains at any time that any requirement of this Contract is at variance with applicable laws, ordinances, regulations or building code requirements, he/she shall notify the Contract Administrator in writing.
81351R, Contract A – Design/Build Sprinkler NHFG Region 3 December 15, 2022
01400 - 3
1.5 SAFETY
A. The Contractor shall, at all times, safely guard the State’s property and persons from injury or loss in connection with this Contract. The Contractor shall, at all times, safely guard and protect their own work and that of adjacent property from damage. All passageways, guard fences, lights, and other facilities required for protection by Federal, State or Municipal laws and regulations must be provided and maintained.
B. Place upon the work or any part thereof, only such loads as are consistent with the safety of that portion of the work.
1.6 SUPERVISION
A. All work shall be done under the observation and inspection of the Contract
Administrator.
B. The Contract Administrator may observe, examine and test materials and workmanship at any and all times during manufacture and/or construction, and at any and all places where such manufacture and/or construction is carried on.
C. The Contract Administrator shall suspend work that may be subject to damage by climatic conditions.
D. Prior to final acceptance, the Contract Administrator at any time before final acceptance of the entire work to make an examination of work already completed that was not specifically called for to receive an inspection prior to covering over, and shall require removing or tearing out same, the Contractor shall, upon request, promptly furnish all necessary facilities, labor, and materials. If such work is found to be defective in any material respect, due to the fault of the Contractor or his Subcontractors, he shall defray all expenses of such examination and of satisfactory reconstruction. If however, such work is found to meet the requirements of the Contract, the actual cost of labor and material necessarily involved in the examination and replacement, shall be completed per a Time and Material Alteration Order.
PART 2 PRODUCTS
Not Used.
PART 3 EXECUTION
3.1 EXAMINATION
A. Verify existing site conditions, controlled environment, protective measures and substrate surfaces are acceptable for subsequent Work. Beginning new Work means acceptance of existing conditions.
B. Verify existing substrate is capable of structural support or attachment of new Work being applied or attached.
R ev is ed
F eb
81351R, Contract A – Design/Build Sprinkler NHFG Region 3 December 15, 2022
01400 - 4
C. Examine and verify specific conditions described in individual specification sections.
Notify the Contract Administrator and the Clerk of the Works of conditions, which prevent start of work.
D. Verify utility services are available, of correct characteristics, and in correct locations.
3.2 PREPARATION
A. Maintain specific environmental controls required in individual sections.
B. Clean substrate surfaces prior to applying next material or substance.
C. Seal cracks or openings of substrate prior to applying next material or substance.
D. Apply manufacturer required or recommended substrate primer, sealer, or conditioner prior to applying new material or substance in contact or bond.
END OF SECTION
R ev is ed
F eb
81351R, Contract A – Design/Build Sprinkler NHFG Region 3 December 15, 2022
Temporary Facilities And Controls
01500 - 1
SECTION 01500
TEMPORARY FACILITIES AND CONTROLS
A. Temporary Utilities:
1. Temporary electricity.
2. Temporary lighting for construction purposes.
3. Temporary ventilation.
4. Temporary sanitary facilities.
B. Construction Facilities:
1. Field offices and sheds.
2. Parking.
3. Progress cleaning and waste removal.
C. Temporary Controls:
1. Barriers.
D. Removal of utilities, facilities, and controls.
E. All work completed herein must conform to applicable state, federal requirements, and guidelines at the Contractor’s expense as is necessary to complete the Work.
1.2 TEMPORARY ELECTRICITY
A. State will pay cost of energy used. Exercise measures to conserve energy. Utilize State’s existing power service.
B. Complement existing power service capacity and characteristics as required for construction operations.
C. Permanent convenience receptacles may [not] be utilized during construction.
1.3 TEMPORARY LIGHTING FOR CONSTRUCTION PURPOSES
A. Augment existing building lighting as required for construction.
B. Maintain lighting and provide routine repairs.
C. Permanent building lighting may be utilized during construction.
81351R, Contract A – Design/Build Sprinkler NHFG Region 3 December 15, 2022
01500 - 2
1.4 TEMPORARY VENTILATION
A. Ventilate enclosed areas to achieve curing of materials, to dissipate humidity, and to prevent accumulation of dust, fumes, vapors, or gases.
1.5 TEMPORARY SANITARY FACILITIES
A. Provide and maintain required facilities and enclosures. Existing facility use is not permitted. Provide facilities at time of project mobilization.
1.6 FIELD OFFICES AND SHEDS
A. Do not use existing facilities for field offices or for storage.
B. Coordinate directly with Fish & Game for conex box or equal exterior storage requirements, if any.
1.7 PARKING
A. Use of existing parking facilities used by construction personnel is permitted.
B. Do not allow heavy vehicles or construction equipment in parking areas.
1.8 PROGRESS CLEANING AND WASTE REMOVAL
A. Maintain areas free of waste materials, debris, and rubbish. Maintain site in clean and orderly condition.
B. Remove debris and rubbish from pipe chases, plenums, attics, crawl spaces, and other closed or remote spaces, prior to enclosing spaces.
C. Broom and vacuum clean interior areas prior to start of surface finishing, and continue cleaning to eliminate dust.
D. Collect and remove waste materials, debris, and rubbish from site periodically and dispose off-site.
1.9 BARRIERS
A. Provide barriers to prevent unauthorized entry to construction areas to allow for State's use of site, and to protect existing facilities and adjacent properties from damage from construction operations and demolition.
B. Protect non-owned vehicular traffic, stored materials, site, and structures from damage.
1.10 REMOVAL OF UTILITIES, FACILITIES, AND CONTROLS
A. Remove temporary utilities, equipment, facilities, materials, prior to Substantial
Completion inspection.
81351R, Contract A – Design/Build Sprinkler NHFG Region 3 December 15, 2022
01500 - 3
B. Clean and repair damage caused by installation or use of temporary work.
C. Restore existing facilities used during construction to original condition. Restore permanent facilities used during construction to specified condition.
PART 2 PRODUCTS
Not Used.
PART 3 EXECUTION
81351R, Contract A – Design/Build Sprinkler NHFG Region 3 December 15, 2022
Construction Waste Management and Disposal
01505 - 1
SECTION 01505
CONSTRUCTION WASTE MANAGEMENT AND DISPOSAL
1.1 SUMMARY
A. Section Includes:
1. Construction waste management plan.
2. Construction waste recycling.
1.2 PLAN REQUIREMENTS
A. Construction Waste Management Plan shall be developed with the following intent:
1. Divert construction, demolition, and land clearing debris from landfill disposal.
2. Redirect recyclable material back to manufacturing process.
B. Develop and implement a Construction Waste Management plan to be reviewed by the
Contract Administrator for compliance with the following
1. Divert 75 % of Project generated waste from landfills.
1.3 SUBMITTALS
A. Section 01330 - Submittal Procedures: Requirements for submittals.
B. Construction Plan: Submit construction waste management plan describing methods and procedures for implementation and monitoring compliance including the following:
1. Project specific analysis of the projected jobsite waste to be generated. Include materials and estimated quantities (weight/volume) of projected waste.
2. Construction waste materials anticipated for recycling and adaptive reuse.
3. On site sorting and site storage methods.
4. Name and location of landfill(s) to be used.
5. Certification from the landfill of ability to receive the types of waste to be generated and of sufficient capacity to accept the waste.
6. Transportation company hauling construction waste to waste processing facilities.
7. Recycling and adaptive reuse processing facilities and waste type each facility will accept.
C. Submit documentation with each application for payment substantiating that the construction waste management plan goals are being achieved. Include the following information:
1. Material category
2. Trash: Quantity by weight deposited in landfills.
81351R, Contract A – Design/Build Sprinkler NHFG Region 3 December 15, 2022
01505 - 2
3. Salvaged, recovered and recycled material: Quantity by weight with destination for each type of material salvaged or recovered for resale, recycling, or adaptive reuse.
1.4 CLOSEOUT SUBMITTALS
A. Section 01700 - Execution Requirements: Requirements for submittals.
B. Waste Management final report: Prior to Completion, submit a written Waste
Management Final report summarizing the types and quantities of materials recycled and disposed of under the Waste Management Plan. Include the name and location of disposal facilities. Include the following:
1. Material category
2. Total quantity of waste, by weight
3. Quantity of waste salvaged, both estimated and actual, by weight
4. Quantity of waste recycled, both estimated and actual, by weight
5. Total quantity of waste recovered (salvaged plus recycled) as a percentage of total waste. ( Compare to minimum requirement of 75% by weight of waste.)
1.5 CONSTRUCTION WASTE MANAGEMENT PLAN
A. Construction Waste Landfill Diversion: Minimum 75 percent by weight of construction waste materials for duration of Project through resale, recycling, or adaptive reuse.
B. Implement construction waste management plan at start of construction.
C. Review construction waste management plan at pre-construction meeting and progress meetings.
D. Distribute the Construction Waste Management Plan to subcontractors and others affected by Plan Requirements.
E. Oversee plan implementation, instruct construction personnel for plan compliance, and document plan results.
F. Manager: The Contractor shall designate on-site personnel responsible for instructing workers and overseeing and documenting results of the Waste Management Plan for the
Project.
1.6 CONSTRUCTION WASTE RECYCLING
A. Use source separation method or co-mingling method suitable to sorting and processing method of selected recycling center.
B. Source Separation Method: Recyclable materials separated from trash and sorted into separate bins or containers, identified by waste type, prior to transportation to recycling center.
81351R, Contract A – Design/Build Sprinkler NHFG Region 3 December 15, 2022
01505 - 3
C. Co-Mingling Method: Recyclable materials separated from trash and placed in unsorted bins or container for sorting at recycling center.
D. Materials recommended for recycling include:
1. Packing materials including paper, cardboard, foam plastic, and sheeting.
2. Recyclable plastics.
3. Organic plant debris.
4. Earth materials.
5. Native stone and granular fill.
6. Concrete and Asphalt paving.
7. Wood with and without embedded nails and staples.
8. Glass, clear and colored types.
9. Metals.
10. Gypsum products.
11. Acoustical ceiling tile.
12. Carpeting.
13. Equipment oil.
PART 2 PRODUCTS - Not Used
PART 3 EXECUTION
3.1 CONSTRUCTION WASTE COLLECTION
A. Collect construction waste materials in containers identified for specific waste materials and arrange for transportation to recycling centers or adaptive salvage and reuse processing facilities.
B. Maintain recycling and adaptive reuse storage and collection area in orderly arrangement with materials separated to eliminate co-mingling of materials required to be delivered separately to waste processing facility.
C. Store construction waste materials to prevent environmental pollution, fire hazards, hazards to persons and property, and contamination of stored materials.
D. Cover construction waste materials subject to disintegration, evaporation, settling, or runoff to prevent polluting air, water, and soil when not in use.
E. . Recycling and waste bin areas are to be kept neat and clean and clearly marked in order to avoid contamination of materials. Location shall be acceptable to the Contract
Administrator.
3.2 CONSTRUCTION WASTE DISPOSAL
A. Deliver construction waste to waste processing facilities. Obtain receipt for deliveries.
81351R, Contract A – Design/Build Sprinkler NHFG Region 3 December 15, 2022
01505 - 4
B. Dispose of construction waste, not capable of being recycled or adaptively reused, by delivery to landfill, incinerator, or other legal disposal facility. Obtain receipt for deliveries.
81351R, Contract A – Design/Build Sprinkler NHFG Region 3 December 15, 2022
Execution Requirements
01700 - 1
SECTION 01700
EXECUTION REQUIREMENTS
A. Closeout procedures.
B. Final cleaning.
C. Starting of systems.
D. Protecting installed construction.
E. Project record documents.
F. Operation and maintenance data.
G. Manual for materials and finishes.
H. Manual for equipment and systems.
I. Spare parts and maintenance products.
J. Product warranties and product bonds.
K. Clean air certification.
L. Maintenance service.
M. Guarantee of work.
1.2 CLOSEOUT PROCEDURES
A. Submit a signed Substantial Completion Application attesting that the Contract
Documents have been reviewed, Work has been inspected, and that all Work is complete in accordance with Contract Documents and ready for Contract Administrator review.
The Substantial Completion Application for use by the Contractor is attached to the end of this specification section. The Contract Administrator may modify this Agreement to accommodate any changes in Work.
1. Provide submittals to the Contract Administrator as required by the Contract
Documents and as required by authorities having jurisdiction.
B. Only after completion of all Punch List items and submission of all items the Contractor shall submit a Final Application for Payment identifying total adjusted Contract Sum, previous payments, and sum remaining due.
81351R, Contract A – Design/Build Sprinkler NHFG Region 3 December 15, 2022
01700 - 2
C. State will occupy all areas of the existing building during construction as specified in
Section 01100.
1.3 FINAL CLEANING
A. Execute final cleaning prior to final project assessment.
B. Clean interior surfaces exposed to view; remove temporary labels, stains and foreign substances, polish transparent and glossy surfaces, vacuum carpeted and soft surfaces.
C. Clean equipment and fixtures to sanitary condition with cleaning materials appropriate to surface and material being cleaned.
D. Clean site; sweep paved areas, rake clean landscaped surfaces.
E. Remove waste and surplus materials, rubbish, and construction facilities from site.
1.4 STARTING OF SYSTEMS
A. Coordinate schedule for start-up of various equipment and systems.
B. Notify the Contract Administrator prior to start-up of each item.
C. Verify each piece of equipment or system has been checked for proper lubrication, drive rotation, belt tension, control sequence, and for conditions which may cause damage.
D. Verify tests, meter readings, and specified electrical characteristics agree with those required by equipment or system manufacturer.
E. Verify wiring and support components for equipment are complete and tested.
F. Execute start-up under supervision of applicable [manufacturer's representative]
[Contractors' personnel] in accordance with manufacturers' instructions.
1.5 PROTECTING INSTALLED CONSTRUCTION
A. Protect installed Work and provide special protection where specified in individual specification sections.
B. Provide temporary and removable protection for installed products. Control activity in immediate work area to prevent damage.
C. Provide protective coverings at walls, projections, jambs, sills, and soffits of openings.
D. Protect finished floors, stairs, and other surfaces from traffic, dirt, wear, damage, or movement of heavy objects, by protecting with durable sheet materials.
E. Prohibit traffic or storage upon waterproofed or roofed surfaces. When traffic or activity is necessary, obtain recommendations for protection from waterproofing or roofing material manufacturer.
81351R, Contract A – Design/Build Sprinkler NHFG Region 3 December 15, 2022
01700 - 3
F. Prohibit traffic from landscaped areas.
1.6 PROJECT RECORD DOCUMENTS
A. Maintain on site one set of the following record documents; record actual revisions to the
Work:
1. Drawings.
2. Specifications.
3. Addenda.
4. Change Orders and other modifications to the Contract.
5. Reviewed Shop Drawings, Product Data, and Samples.
6. Manufacturer's instruction for assembly, installation, and adjusting.
B. Ensure entries are complete and accurate, enabling future reference by State.
C. Store record documents separate from documents used for construction.
D. Record information concurrent with construction progress, not less than weekly.
E. Specifications: Legibly mark and record at each product section description of actual products installed, including the following:
1. Manufacturer's name and product model and number.
2. Product substitutions or alternates utilized.
3. Changes made by Addenda and modifications.
F. Record Drawings and Shop Drawings: Legibly mark each item to record actual construction including:
1. Measured depths of foundations in relation to finish [first] [main] floor datum.
2. Measured horizontal and vertical locations of underground utilities and appurtenances, referenced to permanent surface improvements.
3. Measured locations of internal utilities and appurtenances concealed in construction, referenced to visible and accessible features of the Work.
4. Field changes of dimension and detail.
5. Details not on original Contract drawings.
G. Submit documents to the Contract Administrator at time of Substantial Completion.
H. In addition to the above requirements, record drawings shall also be submitted in
AutoCAD (.dwg) format.
1.7 OPERATION AND MAINTENANCE DATA
A. Submit data bound in 8-1/2 x 11 inch (A4) text pages, three D side ring binders with durable plastic covers.
B. Prepare binder cover with printed title "OPERATION AND MAINTENANCE
INSTRUCTIONS", title of project, and subject matter of binder when multiple binders are required.
81351R, Contract A – Design/Build Sprinkler NHFG Region 3 December 15, 2022
01700 - 4
C. Internally subdivide binder contents with permanent page dividers, logically organized as described below; with tab titling clearly printed under reinforced laminated plastic tabs.
D. Drawings: Provide with reinforced punched binder tab. Bind in with text; fold larger drawings to size of text pages.
E. Contents: Prepare Table of Contents for each volume, with each product or system description identified, typed on white paper, in three parts as follows:
1. Part 1: Directory, listing names, addresses, and telephone numbers of Architect, Engineer(s), Contractor, Subcontractors, and major equipment suppliers.
2. Part 2: Operation and maintenance instructions. For each category, identify names, addresses, and telephone numbers of Subcontractors and suppliers.
Identify the following:
a. Significant design criteria.
b. List of equipment.
c. Parts list for each component.
d. Operating instructions.
e. Maintenance instructions for equipment and systems.
3. Part 3: Project documents and certificates, including the following:
a. Shop drawings and product data.
b. Air and water balance reports.
c. Certificates.
d. Photocopies of warranties and bonds.
1.8 MANUAL FOR MATERIALS AND FINISHES
A. Submit two copies of preliminary draft or proposed formats and outlines of contents before start of Work. The Contract Administrator will review draft and return one copy with comments.
B. For equipment, or component parts of equipment put into service during construction and operated by State, submit documents within ten days after acceptance.
C. Submit one copy of completed volumes 15 days prior to Substantial Completion. Draft copy be reviewed and returned after Substantial Completion, with Architect/Engineer comments. Revise content of document sets as required prior to final submission.
D. Submit two sets of revised final volumes in final form prior to final inspection.
E. Building Products, Applied Materials, and Finishes: Include product data, with catalog number, size, composition, and color and texture designations. Include information for re-ordering custom manufactured products.
F. Instructions for Care and Maintenance: Include manufacturer's recommendations for cleaning agents and methods, precautions against detrimental agents and methods, and recommended schedule for cleaning and maintenance.
G. Moisture Protection and Weather Exposed Products: Include product data listing applicable reference standards, chemical composition, and details of installation. Include recommendations for inspections, maintenance, and repair.
81351R, Contract A – Design/Build Sprinkler NHFG Region 3 December 15, 2022
01700 - 5
H. Additional Requirements: As specified in individual product specification sections.
I. Include listing in Table of Contents for design data, with tabbed fly sheet and space for insertion of data.
1.9 MANUAL FOR EQUIPMENT AND SYSTEMS
A. Submit two copies of preliminary draft or proposed formats and outlines of contents before start of Work. Contract Administrator will review draft and return one copy with comments.
B. For equipment, or component parts of equipment put into service during construction and operated by State, submit documents within ten days after acceptance.
C. Submit one copy of completed volumes 15 days prior to Substantial Completion. Draft copy be reviewed and returned after Substantial Completion, with Architect/Engineer comments. Revise content of document sets as required prior to final submission.
D. Submit two sets of revised final volumes in final form prior to final inspection.
E. Each Item of Equipment and Each System: Include description of unit or system, and component parts. Identify function, normal operating characteristics, and limiting conditions. Include performance curves, with engineering data and tests, and complete nomenclature and model number of replaceable parts.
F. Operating Procedures: Include start-up, break-in, and routine normal operating instructions and sequences. Include regulation, control, stopping, shut-down, and emergency instructions. Include summer, winter, and special operating instructions.
G. Maintenance Requirements: Include routine procedures and guide for preventative maintenance and trouble shooting; disassembly, repair, and reassembly instructions; and alignment, adjusting, balancing, and checking instructions.
H. Include servicing and lubrication schedule, and list of lubricants required.
I. Include manufacturer's printed operation and maintenance instructions.
J. Include sequence of operation by controls manufacturer.
K. Include original manufacturer's parts list, illustrations, assembly drawings, and diagrams required for maintenance.
L. Include control diagrams by controls manufacturer as installed.
M. Include Contractor's coordination drawings, with color coded piping diagrams as installed.
N. Include charts of valve tag numbers, with location and function of each valve, keyed to flow and control diagrams.
81351R, Contract A – Design/Build Sprinkler NHFG Region 3 December 15, 2022
01700 - 6
R ev is ed
-0
-0
O. Include list of original manufacturer's spare parts, current prices, and recommended quantities to be maintained in storage.
P. Include test and balancing reports as specified in Section 01400.
Q. Additional Requirements: As specified in individual product specification sections.
R. Include listing in Table of Contents for design data, with tabbed dividers and space for insertion of data.
1.10 SPARE PARTS AND MAINTENANCE PRODUCTS
A. Furnish spare parts, maintenance, and extra products in quantities specified in individual specification sections.
B. Deliver to Project site; obtain receipt prior to final payment.
1.11 CLEAN AIR CERTIFICATION
A. The Contractor shall employ the services of a Certified Industrial Hygienist using a laboratory accredited by the American Industrial Hygiene Association to comply with
RSA 10-B, ENV-A 2200 Clean Air in State Buildings Rules (New Hampshire Air
Program Rules).
B. Certification of properly collected and analyzed data that demonstrates compliance with said standards will be made by the Department of Environmental Services, Bureau of
Environmental and Occupational Health, Radon Indoor Air Quality Program, 29 Hazen
Drive, Concord, NH 03302-0095, telephone 603/271-3911) upon receipt of data submitted by the Certified Industrial Hygienist.
C. In accordance with Env-A 2200 & Env-A 2205 Standards, the following must be addressed:
1. Ventilation.
2. Noise.
3. Radon.
4. Carbon Dioxide.
5. Asbestos.
6. Formaldehyde.
7. Carbon Monoxide
D. The Contractor shall furnish the Clean Air Certification to the Contract Administrator prior to project Substantial Completion and before building occupancy.
1.12 MAINTENANCE SERVICE
A. Furnish service and maintenance of components indicated in specification sections during warranty period.
B. Examine system components at frequency consistent with reliable operation. Clean, adjust, and lubricate as required.
81351R, Contract A – Design/Build Sprinkler NHFG Region 3 December 15, 2022
01700 - 7
C. Include systematic examination, adjustment, and lubrication of components. Repair or replace parts whenever required. Use parts produced by manufacturer of original component.
D. Do not assign or transfer maintenance service to agent or Subcontractor without prior written consent of State.
1.13 GUARANTEE OF WORK
A. Except as otherwise specified, all work shall be guaranteed by the Contractor against defects resulting form the use of inferior materials, equipment or workmanship for one
(1) year from the Date of Substantial Completion of the work.
B. If, within any guarantee period, repairs or changes are required in connection with guaranteed work, which in the opinion of the Contract Administrator, is rendered necessary as a result of the use of materials, equipment or workmanship which are inferior, defective, or not in accordance with the terms of the Contract shall, promptly upon receipt of notice from the Commissioner, and at his own expense:
1. Place in satisfactory condition in every particular, all such guaranteed work, correct all defects therein.
2. Make good all damage to the building or site, or equipment or contents thereof, which in the opinion of the Contract Administrator, is the result of the use of materials, equipment or workmanship which are inferior, defective, or not in accordance with the terms of the Contract.
3. Make good any work or material, or the equipment and contents of said building or site disturbed in fulfilling any such guarantee.
C. In any case, wherein fulfilling the requirements of the Contract or of any guarantee, embraced in or required thereby, the Contractor disturbs any work guaranteed under another contract, he shall restore such disturbed work to a condition satisfactory to the
Contract Administrator and guarantee such restored work to the same extent as it was guaranteed under such other contracts.
D. If the Contractor, after notice, fails to proceed promptly to comply with the terms of the guarantee, the Commissioner may have the defects corrected and the Contractor and his/her Surety shall be liable for all expense incurred.
E. All special guarantees applicable to definite parts of the work that may be stipulated in the Specifications or other papers forming a part of the Contract shall be subject to the term of this paragraph during the first year of the life of such special guarantee.
F. Failure to adhere to guarantee terms may result in suspension or barring from the prequalification list, or, alternatively, the requirement of a Letter of Credit or other guaranty equal to a percentage of the Contract amount.
PART 2 PRODUCTS
81351R, Contract A – Design/Build Sprinkler NHFG Region 3 December 15, 2022
01700 - 8
PART 3 EXECUTION
81351R, Contract A – Design/Build Sprinkler NHFG Region 3 December 15, 2022
01700 - 9
Attach Substantial Completion Agreement to the end of this Section
| 01100dpw_02202024.pdf |
| RFB XXXX-25 -- Dry System Fire Protection Design and Build - Attachement 1 - Project Execution Requirements.pdf |