Attachment 1 - 765-24-700_SPECS_BID - Final_GL CMOP.pdf

PDF 10 MB Posted

Attached to
Y1BG--EHRM Infrastructure Upgrades Construction Project 765-24-700 Great Lakes Consolidated Mail Outpatient Pharmacy (CMOP) Hines, IL 60141
Solicitation number
36C77626R0039
Issued by

About this file

This document is a comprehensive specifications manual and bid document for the EHRM Infrastructure Upgrades Construction Project at the Great Lakes Consolidated Mail Outpatient Pharmacy (CMOP) in Hines, Illinois (Project 765-24-700). The specifications establish detailed requirements for a complex renovation project encompassing electrical infrastructure upgrades, server room reconstruction, telecommunications infrastructure improvements, fire suppression integration, and hazardous materials assessment and abatement.

Key project requirements include: provision of two new UPS units for redundant power systems, installation of redundant power busway systems, upgrade of electrical distribution infrastructure, complete server room renovation including HVAC, lighting, power devices, and electrostatic dissipative flooring, relocation of servers from existing Room C1080 to new Room C1060A, upgrade of communications infrastructure to Cat 6A cabling with fiber backbone improvements, implementation of NEPA and hazardous materials assessments, provision of commissioning agent services, life safety and fire protection design modifications, and development of infection control risk assessment (ICRA) plans. The project is structured in four phased construction sequences designed to maintain CMOP operations (24/7) throughout execution. Critical requirements address security procedures, occupant notification, utility service interruption coordination, asbestos roofing abatement (estimated 500-750 square feet), lead-based paint removal, structural steel framing with welded connections, thermal insulation, firestopping, joint sealants, hollow metal doors and frames, door hardware with master keying systems, gypsum board installation, resilient tile flooring (ESD tiles specified), painting, and comprehensive quality control and commissioning protocols. The contractor must comply with all OSHA construction standards, maintain a certified Site Safety and Health Officer on-site, perform continuous air and personnel monitoring for hazardous materials abatement, and provide detailed warranty management including four and nine-month post-occupancy inspections. This SDVOSB set-aside project is estimated at $10,000,000 to $20,000,000 with NAICS Code 236220 and PSC Code Y1BG.

View the file

Other files

Show all 19

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Final Bid Documents Submission

EHRM Infrastructure Upgrades – Great Lakes CMOP, Hines, IL

Project Number: 765-24-700

Specifications

Great Lakes Consolidated Mail Outpatient Pharmacy 5000 S 5th Avenue, Building 37NW

Hines, Illinois

October 09, 2025

EHRM Infrastructure Upgrades

Project 765-24-700

SEALS AND CERTIFICATIONS

Final Bid Document

Specification divisions and sections bound herein are listed below under the name of the Designer-of-Record responsible for their preparation, under whose seal and/or authority each document so listed is issued for the purpose(s) stated above. Seals and signatures do not apply to documents not listed below, nor to documents prepared by the government or others, including (except as otherwise indicated) sections in

Division 00 Procurement and Contracting Requirements and Division 01 General Requirements, Geotechnical Reports, etc.

Engineer-of-Record: Structural:

E. Brian Turner, PE #044583/North Carolina

Britt, Peters and Associates

Divisions 05

Professional Seal

10/9/2025

SEALS AND CERTIFICATIONS

Final Bid Document

Specification divisions and sections bound herein are listed below under the name of the Designer-of-Record responsible for their preparation, under whose seal and/or authority each document so listed is issued for the purpose(s) stated above. Seals and signatures do not apply to documents not listed below, nor to documents prepared by the government or others, including (except as otherwise indicated) sections in

Division 00 Procurement and Contracting Requirements and Division 01 General Requirements, Geotechnical Reports, etc.

Architect-of-Record:

Todd Ginder, AIA, 11300/North Carolina

Atriax, PLLC

Divisions 01, 02, 06, 07, 08, 09, 10

10/9/25

SEALS AND CERTIFICATIONS

Final Bid Document

Specification divisions and sections bound herein are listed below under the name of the Designer-of-Record responsible for their preparation, under whose seal and/or authority each document so listed is issued for the purpose(s) stated above. Seals and signatures do not apply to documents not listed below, nor to documents prepared by the government or others, including (except as otherwise indicated) sections in

Division 00 Procurement and Contracting Requirements and Division 01 General Requirements, Geotechnical Reports, etc.

Engineer-of-Record: Fire Protection:

John Callahan, PE #062071566/Illinois

Charlotte Engineers

Divisions 21

SEALS AND CERTIFICATIONS

Final Bid Document

Specification divisions and sections bound herein are listed below under the name of the Designer-of-Record responsible for their preparation, under whose seal and/or authority each document so listed is issued for the purpose(s) stated above. Seals and signatures do not apply to documents not listed below, nor to documents prepared by the government or others, including (except as otherwise indicated) sections in

Division 00 Procurement and Contracting Requirements and Division 01 General Requirements, Geotechnical Reports, etc.

Engineer-of-Record: Mechanical & Plumbing:

Elizabeth K. Elliott, PE 062-075120/IL

Professional Engineering Consultants

Divisions 22, 23

ELIZABETH K.

ELLIOTT

062-075120 10/02/2025

SEALS AND CERTIFICATIONS

Final Bid Document

Specification divisions and sections bound herein are listed below under the name of the Designer-of-Record responsible for their preparation, under whose seal and/or authority each document so listed is issued for the purpose(s) stated above. Seals and signatures do not apply to documents not listed below, nor to documents prepared by the government or others, including (except as otherwise indicated) sections in

Division 00 Procurement and Contracting Requirements and Division 01 General Requirements, Geotechnical Reports, etc.

Engineer-of-Record: Electrical:

Robert Biby, PE 062-062268/IL

Professional Engineering Consultants

Division 26

10-02-2025

License Expires: 11/30/2025

SEALS AND CERTIFICATIONS

Final Bid Document

Specification divisions and sections bound herein are listed below under the name of the Designer-of-Record responsible for their preparation, under whose seal and/or authority each document so listed is issued for the purpose(s) stated above. Seals and signatures do not apply to documents not listed below, nor to documents prepared by the government or others, including (except as otherwise indicated) sections in

Division 00 Procurement and Contracting Requirements and Division 01 General Requirements, Geotechnical Reports, etc.

Engineer-of-Record: Telecommunications:

Jared McCoig, RCDD 219554

Wiley Wilson

Divisions 27, 28

10/09/2025

06-01-24

00 01 10-1

DEPARTMENT OF VETERANS AFFAIRS

VHA MASTER SPECIFICATIONS

TABLE OF CONTENTS

Section 00 01 10

SECTION NO DIVISION AND SECTION TITLES DATE

DIVISION 00 - SPECIAL SECTIONS

00 01 15 List of Drawing Sheets 05-20

DIVISION 01 - GENERAL REQUIREMENTS

01 00 00 General Requirements (REQUIRED) 11-21

01 32 16.15 Project Schedules (Small Projects – Design/Bid/Build

(REQUIRED)

01-24

01 33 23 Shop Drawings, Product Data, and Samples (REQUIRED) 11-23

01 35 26 Safety Requirements for Major Projects (REQUIRED) 05-24

01 42 19 Reference Standards (REQUIRED) 11-20

01 45 00 Quality Control (REQUIRED) 02-21

01 45 29 Testing Laboratory Services (REQUIRED) 11-18

01 57 19 Temporary Environmental Controls (REQUIRED) 01-21

01 74 19 Construction Waste Management (REQUIRED) 04-22

01 81 13 Sustainable Construction Requirements (REQUIRED) 10-17

01 91 00 General Commissioning Requirements (REQUIRED) 04-22

DIVISION 02 – EXISTING CONDITIONS

02 41 00 Demolition 08-17

02 82 13.21 Asbestos Roofing Abatement 01-21

02 83 33.13 Lead-Based Paint Removal and Disposal 01-21

DIVISION 03 – CONCRETE (NOT USED)

DIVISION 04 – MASONRY (NOT USED)

DIVISION 05 – METALS

05 12 00 Structural Steel Framing 11-18

DIVISION 06 – WOOD, PLASTICS AND COMPOSITES

06 10 00 Rough Carpentry 10-17

DIVISION 07 - THERMAL AND MOISTURE PROTECTION

07 21 13 Thermal Insulation 01-21

07 72 00 Roof Accessories 01-21

07 81 00 Applied Fireproofing 07-23

07 84 00 Firestopping 01-21

00 01 10-2

07 92 00 Joint Sealants 04-22

DIVISION 08 - OPENINGS

08 11 13 Hollow Metal Doors and Frames 01-21

08 71 00 Door Hardware 03-24

DIVISION 09 – FINISHES

09 05 16 Subsurface Preparation for Floor Finishes 01-21

09 06 00 Schedule for Finishes 01-21

09 22 16 Non-Structural Metal Framing 06-18

09 29 00 Gypsum Board 04-20

09 65 13 Resilient Base and Accessories 01-21

09 65 19 Resilient Tile Flooring 05-18

09 65 33 Conductive Resilient Flooring 04-19

09 91 00 Painting 01-21

DIVISION 10 – SPECIALTIES

10 14 00 Signage 01-21

10 26 00 Wall and Door Protection 01-21

DIVISION 11 – EQUIPMENT (NOT USED)

DIVISION 12 – FURNISHINGS (NOT USED)

DIVISION 13 - SPECIAL CONSTRUCTION (NOT USED)

DIVISION 14– CONVEYING EQUIPEMENT (NOT USED)

DIVISION 21- FIRE SUPPRESSION

21 08 00 Commissioning of Fire Suppression System 11-16

21 13 13 Wet-Pipe Sprinkler Systems 06-15

21 22 00 Clean Agent Fire Suppression Systems 05-15

DIVISION 22 – PLUMBING

22 05 11 Common Work Results for Plumbing 01-23

22 05 23 General-Duty Valves for Plumbing Piping 09-20

22 07 11 Plumbing Insulation 09-19

22 11 00 Facility Water Distribution 05-21

DIVISION 23 – HEATING, VENTILATING, AND AIR

CONDITIONING (HVAC)

23 05 11 Common Work Results for HVAC 03-23

23 05 12 General Motor Requirements for HVAC and Steam

Generation Equipment

03-23

00 01 10-3

SECTION NO DIVISION AND SECTION TITLES DATE

23 05 41 Noise and Vibration Control for HVAC Piping and

Equipment

03-23

23 05 93 Testing, Adjusting, and Balancing for HVAC 03-23

23 07 11 HVAC and Boiler Plant Insulation 02-20

23 08 00 Commissioning of HVAC Systems 03-23

23 09 23 Direct-Digital Control System for HVAC 03-23

23 23 00 Refrigerant Piping 03-24

23 31 00 HVAC Ducts and Casings 03-23

23 34 00 HVAC Fans 03-23

23 37 00 Air Outlets and Inlets 03-23

23 81 00 Decentralized Unitary HVAC Equipment 03-24

23 81 23 Computer-Room Air-Conditioners 03-24

DIVISION 25 – INTEGRATED AUTOMATION (NOT USED)

DIVISION 26 – ELECTRICAL

26 05 11 Requirements for Electrical Installations 11-22

26 05 19 Low-Voltage Electrical Power Conductors and Cables 11-22

26 05 26 Grounding and Bonding for Electrical Systems 11-22

26 05 33 Raceway and Boxes for Electrical Systems 11-22

26 08 00 Commissioning of Electrical Systems 11-16

26 24 16 Panelboards 11-22

26 25 11 Busways 11-22

26 27 26 Wiring Devices 11-22

26 29 11 Motor Controllers 11-22

26 29 21 Enclosed Switches and Circuit Breakers 11-22

26 33 53 Static Uninterruptible Power Supply 11-22

26 43 13 Surge Protective Devices 11-22

26 51 00 Interior Lighting 03-24

DIVISION 27 – COMMUNICATIONS

27 05 26 Grounding and Bonding for Communications Systems 12-22

27 05 33 Conduits and Backboxes for Communications Systems 12-22

27 05 36 Cable Trays for Communications Systems 12-22

27 05 53 Identification for Communications Systems 12-22

27 08 00 Commissioning of Communications Systems 11-16

27 10 00 Structured Cabling 12-22

27 11 16 Communications Cabinets, Racks, Frames, and Enclosures 12-22

27 11 19 Communications Termination Blocks and Patch Panels 12-22

27 11 26 Communications Rack Mounted Power Protection and Power

Strips

12-22

27 13 13 Communications Copper Backbone Cabling 12-22

27 13 13.13 Communications Copper Cable Splicing and Terminations 12-22

27 13 23 Communications Optical Fiber Backbone Cabling 12-22

27 13 23.13 Communications Optical Fiber Splicing and Terminations 12-22

27 15 13 Communications Copper Horizontal Cabling 12-22

27 16 19 Communications Patch Cords, Station Cords, and Cross-

Connect Wire

12-22

00 01 10-4

DIVISION 28 – ELECTRONIC SAFETY AND SECURITY

28 05 00 Common Work Results for Electronic Safety and Security 04-18

28 05 13 Conductors and Cables for Electronic Safety and

Security

10-18

28 05 26 Grounding and Bonding for Electronic Safety and

Security

09-11

28 05 28.33 Conduits and Backboxes for Electronic Safety and

Security

09-11

28 08 00 Commissioning of Electronic Safety and Security Systems 11-16

28 13 00 Physical Access Control System 10-11

28 16 00 Intrusion Detection System 10-11

28 23 00 Video Surveillance 09-11

28 31 00 Fire Detection and Alarm 10-11

DIVISION 31 – EARTHWORK (NOT USED)

DIVISION 32 – EXTERIOR IMPROVEMENTS (NOT USED)

DIVISION 33 – UTILITIES (NOT USED)

DIVISION 34 – TRANSPORTATION (NOT USED)

DIVISION 48 – Electrical Power Generation (NOT USED)

05-01-20

00 01 15 - 1

SECTION 00 01 15

LIST OF DRAWING SHEETS

Reference Drawing G-001, Cover Sheet for the complete List of Drawings.

- - - E N D - - -

11-01-21

01 00 00 -1

SECTION 01 00 00

GENERAL REQUIREMENTS

GENERAL

1.1 SAFETY REQUIREMENTS

A. Refer to section 01 35 26, SAFETY REQUIREMENTS for safety and infection control requirements.

1.2 GENERAL INTENTION

A. Contractor shall completely prepare site for building operations, including demolition and removal of existing structures, and furnish labor and materials and perform work for EHRM Infrastructure Upgrades – Great Lakes CMOP, Hines, IL as required by drawings and specifications.

B. Visits to the site by Bidders may be made in accordance with what is listed in the solicitation and at the discretion of the Contracting Officer.

C. Offices of Atriax, PLLC, as Architect-Engineers, will render certain technical services during construction. Such services shall be considered as advisory to the Government and shall not be construed as expressing or implying a contractual act of the Government without affirmations by

Contracting Officer or his duly authorized representative.

D. Testing activities and inspection services required during project construction shall be provided by a Testing

Laboratory retained by the General Contractor. Before placement and installation of work subject to tests by testing laboratory, the Contractor shall notify the COR in sufficient time to enable testing laboratory personnel to be present at the site in time for proper taking and testing of specimens and field inspection. Such prior notice shall be not less than three workdays unless otherwise designated by the COR.

01 00 00 -2

E. All employees of general contractor and subcontractors shall comply with VA security management program and obtain permission of the VA police, be identified by project and employer, and restricted from unauthorized access.

F. Normal working hours for this contract will be from 7:00AM to 4:30PM (local time) Monday through Friday except for weekends and established Federal Holidays.

G. Performing on-site work outside normal working hours will require approval from the Contracting Officer and the COR.

Requests shall be submitted via email at least 72 hours prior to the requested date and at no additional cost to the Government. Approvals are subject to the availability of on-site staff.

1.3 STATEMENT OF BID ITEM(S)

A. ITEM I, EHRM Infrastructure Upgrades – Great Lakes CMOP:

BASE BID: Work includes facility infrastructure upgrade to support the new Electronic Health Record Modernization

(EHRM) system in accordance with VA OEHRM Site

Infrastructure Requirements (provided by VHA).

Infrastructure improvements as part of this scope include, but are not limited to the following:

• Electrical infrastructure upgrades o Provide two new UPS units for 2N redundant system.

o Provide redundant power busway system installed over telecom cabinets.

o Provide power distribution panelboards within the server room.

o Provide power to each remote TE location for UPS outlet.

o Upgrade power in the two remote TR’s per ISTS requirements for a 2-rack room.

• Server Room work:

o Remove and replace HVAC, lighting, and power devices.

01 00 00 -3 o Remove existing ACT ceiling and all related appurtenances.

o Remove existing floor finishes, base, doors, frames, and existing walls between existing Hardware Storage C1061, existing Server Room C1060A, and existing UPS Room

C1060B.

o New firewall separating existing Hardware Storage C1061 and new Server Room C1060A.

o New in-fill walls, doors, frames, and hardware sets.

o Repairing and finishing all walls in Server Room C1060A to match existing finishes and follow facility standard.

o Install new electro-static dissipative (ESD) floor tiles.

o New painted fire-rated plywood backing for mounting equipment.

• Provide new telecommunications server racks and cable management

• Relocation of servers from room C1080 to 1060A

• Communications Infrastructure o Patch panels o Upgrade to Cat 6A o Upgrade fiber infrastructure backbone to

Telecommunications rooms and enclosures from the DEMARC room.

• Assist with NEPA and assess hazardous materials

• Provide commissioning agent services to include participating in design reviews and development of commissioning specifications

• Life Safety/Fire Protection

• Design modifications as needed to accommodate the new

Server Room

• ICRA plans

01 00 00 -4

• Phasing Plans

• Upgrade cabling, patch panel and fiber to Room C1060. Room

C1060 will remain a Telecommunications Room (TR). Existing video surveillance equipment will remain in this room.

1.4 SPECIFICATIONS AND DRAWINGS FOR CONTRACTOR

A. Drawings and contract documents may be obtained from the website where the solicitation is posted. Additional copies will be at Contractor's expense.

1.5 CONSTRUCTION SECURITY REQUIREMENTS

A. Security Plan:

1. The security plan defines both physical and administrative security procedures that will remain effective for the entire duration of the project.

2. The General Contractor is responsible for assuring that all sub-contractors working on the project and their employees also comply with these regulations.

B. Security Procedures:

1. General Contractor’s employees shall not enter the project site without appropriate badge. They may also be subject to inspection of their personal effects when entering or leaving the project site.

2. Before starting work the General Contractor shall give one week’s notice to the Contracting Officer so that security arrangements can be provided for the employees.

This notice is separate from any notices required for utility shutdown described later in this section.

3. No photography of VA premises is allowed without written permission of the Contracting Officer. Staff shall not to be photographed at any time.

4. VA reserves the right to close down or shut down the project site and order General Contractor’s employees off the premises in the event of a national emergency. The

01 00 00 -5

General Contractor may return to the site only with the written approval of the Contracting Officer.

C. Guards: (NOT USED)

D. Key Control:

1. The General Contractor shall provide duplicate keys and lock combinations to the Contracting officers representative (COR) for the purpose of security inspections of every area of project including tool boxes and parked machines and take any emergency action.

2. The General Contractor shall install all permanent cores at completion of the work. See Section 08 71 00, DOOR

HARDWARE and coordinate.

E. Document Control:

1. Before starting any work, the General Contractor/Sub

Contractors shall submit an electronic security memorandum describing the approach to following goals and maintaining confidentiality of “sensitive information”.

2. The General Contractor is responsible for safekeeping of all drawings, project manual and other project information. This information shall be shared only with those with a specific need to accomplish the project.

3. Certain documents, sketches, videos or photographs and drawings may be marked “Law Enforcement Sensitive” or

“Sensitive Unclassified”. Secure such information in separate containers and limit the access to only those who will need it for the project. Return the information to the Contracting Officer upon request.

4. These security documents shall not be removed or transmitted from the project site without the written approval of Contracting Officer.

01 00 00 -6

5. All paper waste or electronic media such as CD’s and diskettes shall be shredded and destroyed in a manner acceptable to the VA.

6. Notify Contracting Officer and Site Security Officer immediately when there is a loss or compromise of

“sensitive information”.

7. All electronic information shall be stored in specified location following VA standards and procedures using an

Engineering Document Management Software (EDMS).

Security, access and maintenance of all project drawings, both scanned and electronic shall be performed and tracked through the EDMS system.

“Sensitive information” including drawings and other documents may be attached to e-mail provided all VA encryption procedures are followed.

F. Motor Vehicle Restrictions

1. Vehicle authorization request shall be required for any vehicle entering the site and such request shall be submitted 24 hours before the date and time of access.

Access shall be restricted to picking up and dropping off materials and supplies.

2. A limited number of (2 to 5) permits shall be issued for

General Contractor and its employees for parking in designated areas only. Contractor to coordinate with VA

Medical Center Facility Manager.

1.6 OPERATIONS AND STORAGE AREAS (FAR 52.236-10)

A. The Contractor shall confine all operations (including storage of materials) on Government premises to areas authorized or approved by the Contracting Officer. The

Contractor shall hold and save the Government, its officers and agents, free and harmless from liability of any nature occasioned by the Contractor's performance.

01 00 00 -7

B. Temporary buildings (e.g., storage sheds, shops, offices) and utilities may be erected by the Contractor only with the approval of the Contracting Officer and shall be built with labor and materials furnished by the Contractor without expense to the Government. The temporary buildings and utilities shall remain the property of the Contractor and shall be removed by the Contractor at its expense upon completion of the work. With the written consent of the

Contracting Officer, the buildings and utilities may be abandoned and need not be removed.

C. The Contractor shall, under regulations prescribed by the

Contracting Officer, use only established roadways, or use temporary roadways constructed by the Contractor when and as authorized by the Contracting Officer. When materials are transported in prosecuting the work, vehicles shall not be loaded beyond the loading capacity recommended by the manufacturer of the vehicle or prescribed by any Federal, State, or local law or regulation. When it is necessary to cross curbs or sidewalks, the Contractor shall protect them from damage. The Contractor shall repair or pay for the repair of any damaged curbs, sidewalks, or roads.

D. Working space and space available for storing materials shall be as determined by the COR.

E. Workers are subject to rules of CMOP applicable to their conduct.

F. NOT USED

G. Execute work so as to interfere as little as possible with normal functioning of CMOP as a whole, including operations of utility services, fire protection systems and any existing equipment, and with work being done by others.

Use of equipment and tools that transmit vibrations and noises through the building structure, are not permitted in

01 00 00 -8 buildings that are occupied, during construction, and

Contractor's personnel, except as permitted by COR where required by limited working space.

1. Do not store materials and equipment in other than assigned areas.

2. Schedule delivery of materials and equipment to immediate construction working areas within buildings in use by

Department of Veterans Affairs in quantities sufficient for not more than two work days. Provide unobstructed access to CMOP areas required to remain in operation.

3. Where access by CMOP personnel to vacated portions of buildings is not required, storage of Contractor's materials and equipment will be permitted subject to fire and safety requirements.

H. Utilities Services: Where necessary to cut existing pipes, electrical wires, conduits, cables, etc., of utility services, or of fire protection systems or communications systems (except telephone), they shall be cut and capped at suitable places where shown; or, in absence of such indication, where directed by COR. All such actions shall be coordinated with the COR or Utility Company involved:

1. Whenever it is required that a connection fee be paid to a public utility provider for new permanent service to the construction project, for such items as water, sewer, electricity, gas or steam, payment of such fee shall be the responsibility of the Government and not the

Contractor.

I. Phasing:

1. CMOP must maintain its operation 24 hours a day 7 days a week. Therefore, any interruption in service must be scheduled and coordinated with the COR to ensure that no lapses in operation occur. It is the CONTRACTOR'S

01 00 00 -9 responsibility to develop a work plan and schedule detailing, at a minimum, the procedures to be employed, the equipment and materials to be used, the interim life safety measure to be used during the work, and a schedule defining the duration of the work with milestone subtasks.

2. To ensure such executions, Contractor shall furnish the

COR with a schedule of approximate phasing dates on which the Contractor intends to accomplish work in each specific area of site, building or portion thereof. In addition, Contractor shall notify the COR two weeks in advance of the proposed date of starting work in each specific area of site, building or portion thereof.

Arrange such phasing dates to ensure accomplishment of this work in successive phases mutually agreeable to COR and Contractor, as follows:

Phase 1A:

• CMOP to remove all equipment and furniture from the area of work in Hardware Storage (C1061), including but not limited to, the storage racks on the plan west side of the wall scheduled for demolition.

• Install ICRA barriers according to the ICRA plan and matrix for Phase 1A on sheet G-602.

• Construct new demising firewall between Hardware Storage

(C1061) and new Server Room (C1060A). Complete all work in

Hardware Storage (C1061), as shown on drawings, to provide finished space for CMOP use.

• After COR approval, reposition ICRA barrier according to the ICRA plan and matrix for phases 1B through 4 on sheet

G-602. Release Hardware Storage (C1061) for CMOP use.

Phase 1B:

Demolition:

01 00 00 -10

• Concurrently, existing Rooms C1060A and C1060B and their appurtenances, as indicated in the construction documents, shall be demolished, including but not limited to removal of existing ACT ceiling, light fixtures, electrical panels, existing UPS components, CRAC units, diffusers, and all related equipment, floor finishes and base, doors, frames, hardware sets, sills and jambs, and removal of existing demising wall between Hardware Storage (C1061) and existing rooms C1060A and C1060B. (See demolition sheets for all disciplines).

New Work:

• After the demolition of existing rooms C1060A and C1060B and their appurtenances, as indicated in the construction documents, they shall be combined as Server Room (C1060A) and the new data center shall be constructed within Server

Room (C1060A).

• Finish construction of new firewall separating Hardware

Storage (C1061) and new Server Room (C1060A).

• Construct new metal stud in-fill walls as indicated on new work plans.

• Install new doors, frames, hardware sets, sills and jambs

(see door schedule).

• Repair and finish new and existing walls to match existing finishes.

• Patch/fill any holes in floor slab as required prior to installing new ESD floor tile, and base.

• Install and paint fire-rated plywood backboard for service provider/security/video equipment around new Server Room

(C1060A) walls as needed to accommodate new equipment mounted on them.

01 00 00 -11

• Install all new electrical, mechanical, and telecommunications equipment per drawings.

• During this phase, the new telecommunications primary and redundant backbone pathways shall be installed from the new data center (C1060A) to the new Telecommunications

Enclosures (TE), existing Telecommunications Rooms (TR), and existing DEMARC rooms (RM. 137 & RM. 138).

Phase 1C:

• Once the new Server Room (C1060A) is completed as per Phase

1B, a temporary fiber backbone connection is required between the new Server Room (C1060A) and the existing

Server Room (C1085).

• (1) Primary 72-strand OM4 multi-mode fiber optic cable and

(1) 24-strand OS1a single-mode fiber optic cable shall be routed from the new data center (C1060A) to the existing server room (C1085). (1) Redundant 72-strand OM4 multi-mode fiber optic cable and (1) 24-strand OS1a single-mode fiber optic cable shall be routed from the new data center

(C1060A) to the existing server room (C1085). The primary and redundant fiber optic cables shall be in separate and diverse pathways (the new telecommunications primary and redundant backbone pathways provided as part of phase 1B shall be utilized and added to as required to support the temporary fiber backbone cabling). This temporary backbone connection shall remain in place until all the following are completed:

o All new backbone cabling is installed.

o New TE & existing TRs are installed and operational.

o The existing Server Room (C1085) equipment is migrated to the new Server Room (C1060A).

o The existing Server Room (C1085) is decommissioned.

01 00 00 -12

• Upon completion of Phase 1C the contractor shall coordinate with local OIT personnel, local CMOP personnel, and

National OIT team to migrate the core switch from the existing server room (C1085) to the new data center

(C1060A). It should be noted that this coordination with

National OIT team may take from 90 to 120 days to schedule.

Phase 2:

• The contractor shall coordinate:

o The replacement of existing TEs with new TEs.

o The renovation of existing TRs.

o Installation of primary and redundant backbone fiber cabling.

o Replacement of the entire horizontal cabling infrastructure throughout the CMOP area of the building.

• This shall be completed in a manner that does not provide any telecommunications infrastructure/LAN downtime and/or outage to the CMOP operations.

• New power circuits to be provided at each proposed TE location per the electrical drawings.

Phase 3:

• Upon the completion of Phase 2 the contractor shall coordinate with local OIT personnel, local CMOP personnel, and National VA OIT to migrate the equipment from the existing Server Room (C1085) to the new Server Room

(C1060A).

• It should be noted that this coordination with National VA

OIT may take from 90 to 120 days to schedule.

• Upon completion of Phase 3 the new Server Room (C1060A) will be online and operational.

01 00 00 -13

Phase 4:

• Once Phase 3 has been completed, the existing Server Room

(C1085) is no longer operational and the temporary primary and redundant fiber optic backbone cabling provided in

Phase 1C can be taken offline and demolished.

• The existing Server Room (C1085) can now be decommissioned and turned over to local OIT and CMOP personnel.

J. NOT USED

K. Building(s) No.(s) __37_____ will be occupied during performance of work; but immediate areas of alterations will be vacated.

1. Contractor shall take all measures and provide all material necessary for protecting existing equipment and property in affected areas of construction against dust and debris, so that equipment and affected areas to be used in CMOP operations will not be hindered. Contractor shall permit access to CMOP personnel through other construction areas which serve as routes of access to such affected areas and equipment. These routes whether access or egress shall be isolated from the construction area by temporary partitions and have walking surfaces, lighting etc. to facilitate staff access. Coordinate alteration work in areas occupied by CMOP so that operations will continue during the construction period.

2. Immediate areas of alterations not mentioned in preceding

Subparagraph 1 will be temporarily vacated while alterations are performed.

L. Construction Fence: Before construction operations begin, Contractor shall provide a chain link construction fence, 2.1m (seven feet) minimum height, around the construction

01 00 00 -14 area indicated on the drawings. Provide gates as required for access with necessary hardware, including hasps and padlocks. Fasten fence fabric to terminal posts with tension bands and to line posts and top and bottom rails with tie wires spaced at maximum 375mm (15 inches). Bottom of fences shall extend to 25mm (one inch) above grade.

Remove the fence when directed by COR.

M. When a building and/or construction site is turned over to

Contractor, Contractor shall accept entire responsibility including upkeep and maintenance therefore:

1. Contractor shall maintain a minimum temperature of 4 degrees C (40 degrees F) at all times, except as otherwise specified.

2. Contractor shall maintain in operating condition existing fire protection and alarm equipment. In connection with fire alarm equipment, Contractor shall make arrangements for pre-inspection of site with Fire Department or

Company (Department of Veterans Affairs or municipal) whichever will be required to respond to an alarm from

Contractor's employee or watchman.

N. Utilities Services: Maintain existing utility services for

CMOP at all times. Provide temporary facilities, labor, materials, equipment, connections, and utilities to assure uninterrupted services. Where necessary to cut existing water, steam, gases, sewer or air pipes, or conduits, wires, cables, etc. of utility services or of fire protection systems and communications systems (including telephone), they shall be cut and capped at suitable places where shown; or, in absence of such indication, where directed by COR.

1. No utility service such as water, gas, steam, sewers or electricity, or fire protection systems and

01 00 00 -15 communications systems may be interrupted without prior approval of COR. Electrical work shall be accomplished with all affected circuits or equipment de-energized.

When an electrical outage cannot be accomplished, work on any energized circuits or equipment shall not commence without a detailed work plan, the Medical Center

Director’s prior knowledge and written approval. Refer to specification Sections 26 05 11, REQUIREMENTS FOR

ELECTRICAL INSTALLATIONS and 28 05 00, COMMON WORK

RESULTS FOR ELECTRONIC SAFETY AND SECURITY for additional requirements.

2. Contractor shall submit a request to interrupt any such services to COR, in writing, 7 days in advance of proposed interruption. Request shall state reason, date, exact time of, and approximate duration of such interruption.

3. Contractor will be advised (in writing) of approval of request, or of which other date and/or time such interruption will cause least inconvenience to operations of CMOP. Interruption time approved by CMOP may occur at other than Contractor's normal working hours.

4. Major interruptions of any system must be requested, in writing, at least 15 calendar days prior to the desired time and shall be performed as directed by the COR.

5. In case of a contract construction emergency, service will be interrupted on approval of COR. Such approval will be confirmed in writing as soon as practical.

6. Whenever it is required that a connection fee be paid to a public utility provider for new permanent service to the construction project, for such items as water, sewer, electricity, gas or steam, payment of such fee shall be

01 00 00 -16 the responsibility of the Government and not the

Contractor.

O. Abandoned Lines: All service lines such as wires, cables, conduits, ducts, pipes and the like, and their hangers or supports, shall be removed back to their source. Those which are indicated to be abandoned but are not required to be entirely removed, shall be sealed, capped or plugged at the main, branch or panel they originate from. The lines shall not be capped in finished areas, but shall be removed and sealed, capped or plugged in ceilings, within furred spaces, in unfinished areas, or within walls or partitions;

so that they are completely behind the finished surfaces.

P. To minimize interference of construction activities with flow of CMOP traffic, comply with the following:

1. Keep roads, walks and entrances to grounds, to parking and to occupied areas of buildings clear of construction materials, debris and standing construction equipment and vehicles.

2. Method and scheduling of required cutting, altering and removal of existing roads, walks and entrances must be approved by the COR.

Q. Coordinate the work for this contract with other construction operations as directed by COR. This includes the scheduling of traffic and the use of roadways, as specified in Article, USE OF ROADWAYS.

R. NOT USED

1.7 ALTERATIONS

A. Survey: Before any work is started, the Contractor shall make a thorough survey with the COR, of areas of buildings in which alterations occur and areas which are anticipated routes of access, and furnish a report, signed by both, to

01 00 00 -17 the Contracting Officer. This report shall list by rooms and spaces:

1. Existing condition and types of resilient flooring, doors, windows, walls and other surfaces not required to be altered throughout affected areas of building.

2. Existence and conditions of items such as plumbing fixtures and accessories, electrical fixtures, equipment, venetian blinds, shades, etc., required by drawings to be either reused or relocated, or both.

3. Shall note any discrepancies between drawings and existing conditions at site.

4. Shall designate areas for working space, materials storage and routes of access to areas within buildings where alterations occur and which have been agreed upon by Contractor and COR.

B. Any items required by drawings to be either reused or relocated or both, found during this survey to be nonexistent, or in opinion of COR, to be in such condition that their use is impossible or impractical, shall be furnished and/or replaced by Contractor with new items in accordance with specifications which will be furnished by

Government. Provided the contract work is changed by reason of this subparagraph B, the contract will be modified accordingly, under provisions of clause entitled "DIFFERING

SITE CONDITIONS" (FAR 52.236-2) and "CHANGES" (FAR 52.243-

4).

C. Re-Survey: Thirty days before expected partial or final inspection date, the Contractor and COR together shall make a thorough re-survey of the areas of buildings involved.

They shall furnish a report on conditions then existing, of resilient flooring, doors, windows, walls and other

01 00 00 -18 surfaces as compared with conditions of same as noted in first condition survey report:

1. Re-survey report shall also list any damage caused by

Contractor to such flooring and other surfaces, despite protection measures; and, will form basis for determining extent of repair work required of Contractor to restore damage caused by Contractor's workers in executing work of this contract.

D. Protection: Provide the following protective measures:

1. Wherever existing roof surfaces are disturbed they shall be protected against water infiltration. In case of leaks, they shall be repaired immediately upon discovery.

2. Temporary protection against damage for portions of existing structures and grounds where work is to be done, materials handled and equipment moved and/or relocated.

3. Protection of interior of existing structures at all times, from damage, dust and weather inclemency. Wherever work is performed, floor surfaces that are to remain in place shall be adequately protected prior to starting work, and this protection shall be maintained intact until all work in the area is completed.

1.8 DISPOSAL AND RETENTION

A. Materials and equipment accruing from work removed and from demolition of buildings or structures, or parts thereof, shall be disposed of as follows:

1. Reserved items which are to remain property of the

Government are identified by attached tags, noted on drawings or in specifications as items to be stored.

Items that remain property of the Government shall be removed or dislodged from present locations in such a manner as to prevent damage which would be detrimental to

01 00 00 -19 re-installation and reuse. Store such items where directed by COR.

2. Items not reserved shall become property of the

Contractor and be removed by Contractor from CMOP.

3. Items of portable equipment and furnishings located in rooms and spaces in which work is to be done under this contract shall remain the property of the Government.

When rooms and spaces are vacated by the Department of

Veterans Affairs during the alteration period, such items which are NOT required by drawings and specifications to be either relocated or reused will be removed by the

Government in advance of work to avoid interfering with

Contractor's operation.

4. NOT USED

1.9 PROTECTION OF EXISTING VEGETATION, STRUCTURES, EQUIPMENT,

UTILITIES, AND IMPROVEMENTS (FAR 52.236-9) NOT USED

1.10 RESTORATION

A. Remove, cut, alter, replace, patch and repair existing work as necessary to install new work. Except as otherwise shown or specified, do not cut, alter or remove any structural work, and do not disturb any ducts, plumbing, steam, gas, or electric work without approval of the COR. Existing work to be altered or extended and that is found to be defective in any way, shall be reported to the COR before it is disturbed. Materials and workmanship used in restoring work, shall conform in type and quality to that of original existing construction, except as otherwise shown or specified.

B. Upon completion of contract, deliver work complete and undamaged. Existing work (walls, ceilings, partitions, floors, mechanical and electrical work, lawns, paving, roads, walks, etc.) disturbed or removed as a result of

01 00 00 -20 performing required new work, shall be patched, repaired, reinstalled, or replaced with new work, and refinished and left in as good condition as existed before commencing work.

C. At Contractor's own expense, Contractor shall immediately restore to service and repair any damage caused by

Contractor's workers to existing piping and conduits, wires, cables, etc., of utility services or of fire protection systems and communications systems (including telephone) which are not scheduled for discontinuance or abandonment.

D. Expense of repairs to such utilities and systems not shown on drawings or locations of which are unknown will be covered by adjustment to contract time and price in accordance with clause entitled "CHANGES" (FAR 52.243-4) and "DIFFERING SITE CONDITIONS" (FAR 52.236-2).

1.11 PHYSICAL DATA – SOIL CONDITIONS NOT USED

1.12 PROFESSIONAL SURVEYING SERVICES NOT USED

1.13 LAYOUT OF WORK NOT USED

1.14 AS-BUILT DRAWINGS

A. The contractor shall maintain two full size sets of as-built drawings which will be kept current during construction of the project, to include all contract changes, modifications and clarifications.

B. All variations shall be shown in the same general detail as used in the contract drawings. To ensure compliance, as-built drawings shall be made available for the COR review, as often as requested.

C. Contractor shall deliver two approved completed sets of as-built drawings in the electronic version (scanned PDF) to the COR within 15 calendar days after each completed phase and after the acceptance of the project by the COR.

01 00 00 -21

D. Paragraphs A, B, & C shall also apply to all shop drawings.

1.15 WARRANTY MANAGEMENT

A. Warranty Management Plan: Develop a warranty management plan which contains information relevant to FAR 52.246-21

Warranty of Construction in at least 30 days before the planned pre-warranty conference, submit one set of the warranty management plan. Include within the warranty management plan all required actions and documents to assure that the Government receives all warranties to which it is entitled. The plan must be in narrative form and contain sufficient detail to render it suitable for use by future maintenance and repair personnel, whether tradesman, or of engineering background, not necessarily familiar with this contract. The term “status” as indicated below must include due date and whether item has been submitted or was approved. Warranty information made available during the construction phase must be submitted to the Contracting

Officer for approval prior to each monthly invoice for payment. Assemble approved information in a binder and turn over to the Government upon acceptance of the work. The construction warranty period will begin on the date of the project acceptance and continue for the product warranty period. A joint 4 month and 9-month warranty inspection will be conducted, measured from time of acceptance, by the

Contactor and the Contracting Officer. Include in the warranty management plan, but not limited to, the following:

1. Roles and responsibilities of all personnel associated with the warranty process, including points of contact and telephone numbers within the company of the

Contractor, subcontractors, manufacturers or suppliers involved.

01 00 00 -22

2. Furnish with each warranty the name, address and telephone number of each of the guarantor’s representatives nearest project location.

3. Listing and status of delivery of all Certificates of

Warranty for extended warranty items, to include roofs, HVAC balancing, pumps, motors, transformers and for all commissioned systems such as fire protection and alarm systems, sprinkler systems and lightning protection systems, etc.

4. A list for each warranted equipment item, feature of construction or system indicating:

a. Name of item.

b. Model and serial numbers.

c. Location where installed.

d. Name and phone numbers of manufacturers and suppliers.

e. Name and phone numbers of manufacturers or suppliers.

f. Names, addresses and phone numbers of sources of spare parts.

g. Warranties and terms of warranty. Include one-year overall warranty of construction, including the starting date of warranty of construction. Items which have extended warranties must be indicated with separate warranty expiration dates.

h. Starting point and duration of warranty period.

i. Summary of maintenance procedures required to continue the warranty in force.

j. Cross-reference to specific pertinent Operation and

Maintenance manuals.

k. Organizations, names and phone numbers of persons to call for warranty service.

l. Typical response time and repair time expected for various warranted equipment.

01 00 00 -23

5. The plans for attendance at the 4 and 9-month post construction warranty inspections conducted by the government.

6. Procedure and status of tagging of all equipment covered by extended warranties.

7. Copies of instructions to be posted near selected pieces of equipment where operation is critical for warranty and/or safety reasons.

B. Performance & Payment Bonds: The Performance & Payment

Bonds must remain effective throughout the construction period.

1. In the event the Contractor fails to commence and diligently pursue any construction warranty work required, the Contracting Officer will have the work performed by others, and after completion of the work, will charge the remaining construction warranty funds of expenses incurred by the Government while performing the work, including, but not limited to administrative expenses.

2. In the event sufficient funds are not available to cover the construction warranty work performed by the

Government at the contractor’s expenses, the Contracting

Officer will have the right to recoup expenses from the bonding company.

3. Following oral or written notification of required construction warranty repair work, the Contractor shall respond in a timely manner. Written verification will follow oral instructions. Failure to respond will be cause for the Contracting Officer to proceed against the

Contractor.

C. Pre-Warranty Conference: Prior to contract completion, and at a time designated by the Contracting Officer, the

01 00 00 -24

Contractor shall meet with the Contracting Officer to develop a mutual understanding with respect to the requirements of this section. Communication procedures for

Contractor notification of construction warranty defects, priorities with respect to the type of defect, reasonable time required for Contractor response, and other details deemed necessary by the Contracting Officer for the execution of the construction warranty will be established/ reviewed at this meeting. In connection with these requirements and at the time of the Contractor’s quality control completion inspection, furnish the name, telephone number and address of a licensed and bonded company which is authorized to initiate and pursue construction warranty work action on behalf of the Contractor. This point of contract will be located within the local service area of the warranted construction, be continuously available and be responsive to Government inquiry on warranty work action and status. This requirement does not relieve the

Contractor of any of its responsibilities in conjunction with other portions of this provision.

D. Contractor’s Response to Construction Warranty Service

Requirements:

E. Following oral or written notification by the Contracting

Officer, the Contractor shall respond to construction warranty service requirements in accordance with the

“Construction Warranty Service Priority List” and the three categories of priorities listed below. Submit a report on any warranty item that has been repaired during the warranty period. Include within the report the cause of the problem, date reported, corrective action taken, and when the repair was completed. If the Contractor does not perform the construction warranty within the timeframe

01 00 00 -25 specified, the Government will perform the work and back charge the construction warranty payment item established.

1. First Priority Code 1. Perform onsite inspection to evaluate situation, and determine course of action within

4 hours, initiate work within 6 hours and work continuously to completion or relief.

2. Second Priority Code 2. Perform onsite inspection to evaluate situation, and determine course of action within

8 hours, initiate work within 24 hours and work continuously to completion or relief.

3. Third Priority Code 3. All other work to be initiated within 3 work days and work continuously to completion or relief.

4. The “Construction Warranty Service Priority List” is as follows:

a) Code 1-Life Safety Systems

Fire suppression systems.

Fire alarm system(s).

b) Code 1-Air Conditioning Systems

Air conditioning leak in part of the building, if causing damage.

Air conditioning system not cooling properly.

c) Code 1 Doors

Overhead doors not operational, causing a security, fire or safety problem.

1) Interior, exterior personnel doors or hardware, not functioning properly, causing security, fire or safety problem.

d) Code 3-Doors

Overhead doors not operational.

Interior/exterior personnel doors or hardware not functioning properly.

01 00 00 -26

e) Code 1-Electrical

Power failure (entire area or any building operational after 1600 hours).

Security lights.

Smoke detectors.

f) Code 2-Electrical

Power failure (no power to a room or part of building). Receptacle and lights not operational (in a room or part of building).

g) Code 3-Electrical

Exterior lights not operational.

h) Code 1-Gas

Leaks and pipeline breaks.

i) Code 1-Heat

Power failure affecting heat.

j) Code 1-Plumbing

Hot water heater failure.

2) Leaking water supply pipes

k) Code 2-Plumbing

Flush valves not operating properly

Fixture drain, supply line or any water pipe leaking.

Toilet leaking at base.

l) Code 3- Plumbing

Leaky faucets.

m) Code 3-Interior

Floors damaged.

Paint chipping or peeling.

Casework damaged.

n) Code 1-Roof Leaks

Damage to property is occurring.

o) Code 2-Water (Exterior)

01 00 00 -27

No water to facility.

p) Code 2-Water (Hot)

No hot water in portion of building listed.

q) Code 3

All work not listed above.

F. Warranty Tags: At the time of installation, tag each warranted item with a durable, oil and water-resistant tag approved by the Contracting Officer. Attach each tag with a copper wire and spray with a silicone waterproof coating.

Also submit two record copies of the warranty tags showing the layout and design. The date of acceptance and the QC signature must remain blank until the project is accepted for beneficial occupancy. Show the following information on the tag.

Warranty Tags

Type of product/material

Model number

Serial number

Contract number

Warranty period from/to

Inspector’s signature

Construction Contractor

Address

Telephone number

Warr…