This Performance Work Statement (PWS) details a herbicide application service contract for the Bureau of Land Management's Upper Snake Field Office to reduce woody vegetation along 22.5 miles of desert roads in Fremont and Clark Counties, Idaho. The project involves applying herbicides to create a 300-foot-wide strategic fuel break (150 feet on each side of designated roads), covering approximately 821 acres of sagebrush steppe habitat previously mowed to reduce vegetation continuity.
The contract specifies a fixed-price, non-personal services agreement with a small business set-aside, to be performed between June 1-30, 2025. The contractor must provide all labor, equipment, and materials to apply 32 ounces/acre of 2,4-D LV6, 3/4 ounces/acre of Escort XP, and other specified chemicals, ensuring 95% uniform coverage. Key requirements include using a differentially corrected GPS system, maintaining safety protocols, properly handling herbicides, and submitting daily application logs and geospatial data to the Contracting Officer's Representative (COR).
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Attachment_2_-_Maps.pdf | ||
| Attachment_3_-_Wage_Determination___2015-5517_rev_24_23_DEC_24.pdf | ||
| Appendix_2-_FAR_52_212-3_(MAY_2024)(DEVIATION_FEB_2025).pdf | ||
| Sol_140L2625Q0037.pdf | ||
| Appendix_1-_PRICING_SCHEDULE.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
BUREAU OF LAND MANAGEMENT – Upper Snake Field Office Performance Work Statement
Sand Creek Desert Fuel Break (SCDFB) Herbicide Application F-1
1. General: This is a non-personal services contract to provide for herbicide application services. The Government shall not exercise any supervision or control over the providers performing these services. Such contract service providers shall be accountable solely to the Contractor who, in turn, is responsible to the Government.
1.1. Description of Services/Introduction: The Upper Snake Field Office (USFO), Bureau of Land Management (BLM) is acquiring services for herbicide application. The Contractor shall furnish all labor, equipment, tools, materials, supervision, supplies, and incidentals; and perform all work necessary to complete applications in accordance with the specifications provided.
1.2. Background: The treatment areas consist of sagebrush steppe habitat that was previously mowed to reduce the vertical and horizontal continuity of the woody vegetation. Vegetation within the treatment area is typical of the Great Basin and consists primarily of bluebunch wheatgrass or Idaho fescue, mountain big sagebrush, and antelope bitterbrush along with other native vegetation. The topography of the project area consists of gently rolling lava plains with associated basalt bluffs and desert playas. Due to recent wildfires within the Sand Creek Desert (SCD), an increased emphasis has been placed on developing a strategic fuel break network along designated roads to protect the remaining intact sagebrush steppe habitat.
1.3. Objectives: The objective of this service is to reduce/eradicate sagebrush and other woody vegetation from within designated roadside fuel breaks.
1.4. Scope: The work under this contract includes the application of herbicides along 22.5 miles of improved and unimproved desert roads resulting in an affected treatment area of 150 feet either side of the designated roads with a total affected area of 821 acres (see Detailed Specifications 4.4.2).
1.5. Period of Performance: Application operations will begin on or after June 1, 2025, as soon as weather and vegetation conditions are favorable. The Contracting Officers Representative (COR) will notify the contractor that favorable conditions have been met, and the contractor shall be prepared to commence application operations within three (3) calendar days of notification. The contractor shall complete operations within three (3) calendar days once the application is initiated. This application may coincide with early snowfall and/or poor weather and site conditions. During the contract and application period, county, state and BLM jurisdiction roads and remote airstrips may not be suitable for staging areas due to muddy, wet, or snow-covered conditions.
Estimated Start Date: June 1, 2025
Estimated End Date: June 30, 2025
1.6. General Information
1.6.1. Designation of Contracting Officer’s Representative: The Contracting Officer (CO) shall designate the COR and Project Inspector (PI). The COR is responsible for administering the performance of work under this contract. In no event, however, will any understanding, agreement, modification, change order, or other matter deviating from the terms of this contract be effective or binding upon the Government unless formalized by proper contractual documentation executed by the CO prior to completion of the contract.
1.6.2. Hours of Operation: Herbicide Application Operations will be permitted only during daylight hours. The Contractor will be allowed to work six days per week including Saturdays. Work will not be permitted on Sundays and holidays, unless authorized by the COR.
1.6.3. Federal Observed Holidays: In addition to any holidays declared by Executive Orders, the following Federal Legal Holidays are observed: New Year’s Day, Martin Luther King Jr. Day, President’s Day, Memorial Day, Juneteenth, Independence Day, Labor Day, Columbus Day, Veterans Day, Thanksgiving Day, Christmas Day.
1.6.4. Place of Performance: The project area is located approximately 16 miles north-northeast of St. Anthony within Fremont and Clark Counties. All work will be performed on land either administered by the Bureau of Land Management or on land (State/Private) where treatment has been authorized and funded by the Idaho Department of Lands (see Location Map). The topography of the project area consists of gently rolling lava plains with associated basalt bluffs and desert playas. Elevations range from 5,000 feet to over 6,300 feet above sea level.
1.6.5. Pre-work Conference: A pre-work conference will be held prior to the commencement of work. The Contractor will be notified in advance of meeting time, date, and place. The purpose will be to review required work, specifications, payment, and administrative provisions of the contract. The Contractor and the persons responsible for coordination for the work (Contractor Representative/Foreman) shall be present at the meeting. The Contractor shall be prepared to summarize and explain procedures planned for the project and provide a schedule to meet the time frames of the project.
1.6.6. Invoicing: Invoices shall be submitted through IPP for payment, after services have been performed with supporting invoice on company letterhead and referenced purchase order number. Unit Costs offered must be “All-Inclusive” for materials, labor, transportation, surcharges, fees, and services necessary and incidental to herbicide application.
Invoices shall reflect only those costs indicated in the Price Schedule. All expenses relating to maintenance and operation of equipment shall be considered in the inclusive pricing. The Contract will be considered completed and payment due when all herbicide has been applied to the standards specified above and when all areas designated under the contract have been treated to the said standards. Measurement for payment for herbicide application will be the actual area, in acres, within the designated boundaries satisfactorily treated in conformance with these specifications. Measurement will be made from the ArcGIS polygons provided by the government. Acreages will be computed from horizontal distances as shown on maps. Payment will be made at the unit price per acre specified in the Pricing Schedule and shall include the cost of all work described in this paragraph and the Detailed Specifications, including any reapplication, if such work is required. Acreages will not be computed from DGPS acreages covered. Contractor must factor in additional application time required for coverage of the polygons, complete application, and any contour application that may be required to properly cover the area.
1.6.7. Project Boundary Marking: The location and access to the unit(s) are shown on the vicinity and unit map(s). The unit boundaries will not be identified by flagging, it will be up to the contractor to identify and verify boundaries in the field using maps and electronic devices to stay within the unit(s).
1.6.8. Notification of Cessation or Restart of Work: The Contractor will have personnel on site prior to commencing daily application, during application, and will notify COR or PI of changing weather conditions. The COR/PI will allow Contractor to continue or stop application if weather factors dictate. The COR/PI will give the permission to start, approximately one (1) hour from notification of conditions, depending on location of project from the USFO.
1.6.9. Personnel Requirements: The Contractor must always maintain an adequate work force to ensure timely completion of the work and is responsible for the crew knowing the requirements of the contract. The crew is also responsible for maintaining a safe working environment following OSHA standards. The Contractor must include a crew manifest during the pre-work conference.
1.6.9.1. Key Personnel: The following personnel are considered key personnel by the Government: A Contractor Representative must be on-site always directing work. This person must be fluent in English and will also serve as an on the ground contact person for the COR/PI. Failure to maintain a Contractor Representative will result in suspension of work until an acceptable on-the-ground Contractor Representative is provided. A maximum of five (5) days will be allowed to produce a qualified Contractor Representative. Failure to do so within five days may result in the CO issuing a Suspend Work Order. CO and COR must be informed of any changes of Contractor Representative. The contractor will furnish a legible list of all contract employees (last name, first name) to the assigned COR. If there are any changes to the list of contract employees during the life of the contract a new list will be provided to the COR.
1.6.9.1.1. Applicators: Shall be furnished by the Contractor and shall be experienced in applying herbicide in rough, rocky, or mountainous terrain, all equipment, labor, supplies, and materials required to complete the job.
1.6.9.1.1.1. The Contractor’s applicators shall hold a current Idaho Professional Applicator License in the Agricultural Pesticide Category. The Government will inspect each applicator for their current Idaho Professional Applicator’s License in the Agricultural Pesticide Category before work on this contract.
1.6.9.1.2. Work Crew: Shall be furnished by the Contractor for handling, mixing, and applying the herbicide.
The Contractor shall furnish the necessary qualified mechanics for maintenance of equipment and shall furnish all fuel, oil, and service required for operation of equipment and vehicles.
1.6.10. Camping: Camping on agency-administered lands will only be allowed on site(s) pre-approved by an authorized officer. Camping areas for crews will be identified and surveyed for cultural resources prior to use of that camp location. Some camp sites including designated camp sites have been identified and cleared for use, ask the COR for details. The Contractor shall maintain all camping areas in an orderly and sanitary manner. The ordering and maintenance of portable toilets and dumpsters is the responsibility of the contractor. All fire regulations and restrictions shall be followed. All garbage and refuse shall be removed from the camp site(s) by the Contractor and disposed of offsite before final payment is made.
1.6.11. Risk and Damages: The Contractor shall assume all risks in connection with performance of the contract and shall be liable for any damages to persons or property in connection with the prosecution of the work, including the applicator or other employees of the Contractor.
1.6.12. Flight Hazards: If Contractor aircraft(s) are utilized, hazards such as the presence of power lines or anemometer towers on the work site are the responsibility of the Contractor to identify. All appropriate precautions shall be taken by the Contractor. Flight hazards which have been identified by the Government in the Specifications or Work Location Map may not be the only hazards present at the work sites, and it is the Contractor's responsibility to check all work sites for flight or other hazards.
1.6.13. Safety
1.6.13.1. Equipment must meet OSHA standards.
1.6.13.2. It is the responsibility of the contractor to ensure for the safety of employees and general public during treatment. The treatment area will remain open to public access and, as such, the contractor shall furnish roadside warning signs to be placed at treatment area access points. Signs shall be high visibility, with minimum dimensions of 3-feet by 3-feet and shall warn of chemical application. Should public safety become a concern, the contractor shall stop all operations and work with the COR/PI to resolve the issue.
1.6.13.3. The Contractor shall comply with all the applicable Idaho State Fire Prevention Laws, Restrictions, Rules, Regulations, and Standards. If a fire is started or discovered, work crews will immediately notify Eastern Idaho Interagency Fire Center (208) 524-7600. See Section 6 for additional information.
1.6.13.4. The Contractor shall comply with all the applicable Federal and State Laws, Restrictions, Rules, and Regulations pertaining to the use of herbicides. See Section 6 for additional information.
F-2
2. Definitions
2.1. Active Ingredient: The chemicals in an herbicide which control the targeted brush species.
2.2. Adjuvant: An inert material added to an herbicide formulation or tank mix to increase the effectiveness of the active ingredient.
2.3. Contractor: A supplier or vendor awarded a contract to provide specific supplies or service to the government. The term used in this contract refers to the prime.
2.4. Contracting Officer (CO): A person with authority to enter into, administer, and or terminate contracts, and make related determinations and findings on behalf of the government. Note: The only individual who can legally bind the government.
2.5. Contracting Officer’s Representative (COR): An employee of the U.S. Government appointed by the contracting officer to administer the contract. Such appointment shall be in writing and shall state the scope of authority and limitations. This individual has authority to provide technical direction to the Contractor as long as that direction is within the scope of the contract, does not constitute a change, and has no funding implications. This individual does NOT have authority to change the terms and conditions of the contract.
2.6. Deliverable: Anything that can be physically delivered but may include non-manufactured things such as meeting minutes or reports.
2.7. Drift: The movement of airborne particles by air motion or wind away from the intended target area.
2.8. Equipment: A tangible item that is functionally complete for its intended purpose, durable, nonexpendable, and needed for the performance of a contract. Equipment is not intended for sale and does not ordinarily lose its identity or become a component part of another article when put into use. Equipment does not include material, real property, special test equipment or special tooling.
2.9. Key Personnel: Contractor personnel that are evaluated in a source selection process and that may be required to be used in the performance of a contract. When key personnel are used as an evaluation factor in best value procurement, an offer can be rejected if it does not have a firm commitment from the persons that are listed in the proposal. The prime contractor is responsible for performance of all subcontractors.
2.10. Quality Control: All necessary measures taken by the Contractor to assure that the quality of an end product or service shall meet contract requirements.
2.11. Subcontractor: One that enters into a contract with a prime contractor. The Government does not have privity of contract with the subcontractor.
2.12. Safety Hazards: Any ground or above ground hazards that would pose a danger to Contractor’s personnel or operating equipment must be identified and mitigated by the Contractor prior to commencing operations.
F-3
3. Government Furnished Property and Services
3.1. The Government will provide the following items to the Contractor:
3.1.1. Provide various USGS 7.5-minute quadrangles (1:24,000 scales) or GIS equivalent with clear cut project area boundaries clearly identified.
3.1.2. Provide GIS shapefiles of the project boundary and treatment strips in WGS84 coordinate system.
3.1.3. An Avenza map file will be provided that delineates the treatment perimeters. The Contractor must have a smart device capable accepting and displaying georeferenced files.
3.1.4. A list of contacts, including emergency contacts, will be provided at the pre-work meeting.
F-4
4. Contractor -Furnished Items and Services
4.1. Equipment Requirements:
4.1.1. Unless otherwise specified, the Contractor shall provide all labor, transportation, materials, supplies, and equipment necessary to perform the work as described herein.
4.1.2. Equipment shall be capable of traveling at moderate speed and close enough to the ground for proper control and distribution of herbicide. The Contractor shall service and repair their equipment as necessary to maintain satisfactory progress on work. Contractor is responsible for all costs incidental to equipment move-in and move-out associated with the project.
4.1.3. The Contractor shall furnish sufficient equipment to have communications with the Government either by using radio frequencies designated by the COR/PI or by providing a radio to the COR/PI. Contract will not commence until radio communication is established.
4.1.4. The Government will have the option to inspect the Contractor's equipment and work before, during, and after completion of this contract.
4.1.5. Application equipment
4.1.5.1. Spray Tanks: Spray solutions of the product shall be mixed, stored, and applied using only stainless steel, aluminum, fiberglass, plastic, or plastic-lined steel containers.
4.1.5.2. Spray Nozzles: Contractor shall furnish a nozzle type that is designated for the intended application. Refer to the Label for proper nozzles to comply with Drift Management Section.
4.1.5.3. Booms: Contractor shall furnish non-rust booms. The distance of the outermost nozzles on the boom must not exceed 3/4 the length of the wingspan or rotor if aircraft is utilized.
4.1.6. Differentially Corrected Global Positioning System (DGPS)
4.1.6.1. Tracking/Guidance: Contractor shall be required to utilize a Differentially Corrected Global Positioning System (DGPS) for electronic Navigation. System must be capable of utilizing ArcGIS shape files created by the government and given to the Contractor on a USB Thumb Drive or by email. Ground flaggers and an auto-flagger system (if aircraft is utilized) can supplement the DGPS system but not substitute for it. DGPS is required for tracking, and data collection. The Contractor shall provide all guidance equipment, materials, computers, printers, personnel, and services required for the system to be used. The system shall be sufficiently sensitive to provide immediate deviation indications (real-time). The DGPS system must be capable of determining a differentially corrected location with an error of no more than one to two meters in the horizontal plane. The guidance system shall be capable of updating current position at a rate of a minimum of one time per second. Differential correction must cover the complete operational area. During operation, differentially corrected signal must be accurately recorded at least 90% of the operational time.
Differential correction may be, provided by a portable differential station, FM radio fixed towers, or satellite.
4.1.6.2. Software: Software provided with DGPS must be designed for parallel offset in increments equal to the assigned swath width of the application equipment
4.1.6.3. Project Log: Must be capable of a minimum rate of one-second logging intervals. Full record includes position, time altitude, speed, track, application system on/off, job name/number, and differential correction status. The computer program must be capable of calculating and show total acres treated during the flight, and capable of downloading to a computer for analysis and review. The project log must show and differentiate between spray-on and spray-off when viewed on a computer monitor or printer. Export files of each project log shall be provided and must be compatible with ArcGIS system on a USB Thumb Drive.
The contractor must, upon request by the COR or PI, be able to supply project log data on a USB Thumb Drive for review at any time during the contract. The Contract will not be considered complete until the data has been reviewed and deemed complete with no skips in the treated areas. The Contractor shall provide a map with project log data at the end of each day’s application. The DGPS system must be capable of zooming in on any portion of the treatment to view a specific area with greater detail.
4.1.6.4. Hardware:
4.1.6.4.1. Visual Display Monitor: (1) Capable of displaying swath width over project path; (2) mounted in a location that will allow the applicator to view the screen; (3) have a method to display nested polygons to indicate sensitive or no-spray areas within or adjacent to treatment blocks; (4) have a feature that allows the applicator to return to the exact location of application shutdown and complete application without omitted or doubled treated areas.
4.1.6.4.2. Control Keypad: The keypad must: (1) be able to input reference waypoints (A-B line): (2) have a feature which alerts the operator when they are about to enter or exit a specific treatment block or an exclusion area within a block: (3) have a method to display nested polygons to indicate sensitive or no-treat areas within or adjacent to treatment blocks: (4) have a feature that allows the operator to return to the exact location of application shutdown and complete application without omitted or doubled treated areas.
4.1.6.4.3. Course Deviation Indicator (CDI): The course deviation indicator or course deviation light must have the capability to display both cross-track error and intercept angle to desired heading. Cross-track error shall be adjustable down to one (1) foot.
4.1.6.4.4. Memory: Must be capable of storing up to 8 hours of continuous project log data.
4.2. Loading Facilities: Use of any loading area, federal, state, or private land, shall be arranged by and at the discretion and risk of the contractor. Contractor shall be responsible for access to the site. Contractor shall have personnel at project site prior to commencing daily application, during application, and shall notify COR or PI of changing weather conditions. The Government shall not be held responsible for any loss, mishap, or accident due to conditions of any site used. The Contractor shall provide appropriate warning signs for traffic if roads are used as loading sites.
4.2.1. Base of Operations: The Contractor shall provide such loading facilities as may be required for competent performance of contract. If loading sites are described in the Detailed Specifications or shown on the Work Location Map, the Government makes no warranty as to their availability or condition. Use of any loading area shall be arranged by and at the discretion and risk of the Contractor, and the Government shall not be held responsible for any loss, mishap, or accident due to conditions of any loading facility used. Any applicable fees for loading facilities are the responsibility of the Contractor. If Contractor wishes to use BLM land, this must be approved in advance by the COR or PI. The Contractor shall provide appropriate warning signs for traffic if roads are used as loading sites.
4.2.2. Dust Abatement: Any material used for dust abatement, other than water, shall be approved by the COR prior to use.
4.2.3. Flight Hazards: If Contractor aircraft(s) are utilized, hazards such as the presence of power lines or anemometer towers on the work site are the responsibility of the Contractor to identify. All appropriate precautions shall be taken by the Contractor. Flight hazards which have been identified by the Government in the Detailed Specifications or Work Location Maps may not be the only hazards present at the work sites, and it is the Contractor's responsibility to check all work sites for flight or other hazards.
4.3. Applicator Logs: One report shall be provided to the Government. The report shall include daily herbicide application records. This log or record shall be signed by the applicator operator and turned into the COR upon completion of the contract via email within 10 business days.
4.4. Service Requirements:
4.4.1. It shall be the responsibility of the Contractor (i.e., knowledge and experience of the crew leader) to determine the quantity of work needed to meet specifications identified in this PWS.
4.4.2. Detailed Specifications: Herbicide Application
4.4.2.1. Application shall be performed in a linear fashion along roadways creating a 300-ft-wide treatment area, 150-ft on both sides from the edge of the road. The contractor will make every effort possible to treat ALL targeted vegetation within the 300-ft-wide treatment area.
4.4.2.2. Rate of Application: 32 ounces/acre of 2,4-D LV6 + 3/4 ounces/acre of Escort XP + 1 quart/acre MSO + 3 ounces per 100 gallons of solution of drift control. Carrier (water) will be at the three (3) gallons per acre rate.
4.4.2.3. The Contractor will supply all herbicide and carrier necessary to complete the specifications of this contract.
The carrier (water) must be clean, free of dirt particles. Ditch water will not be considered clean. Contractor is responsible for the proper disposal of mixed, unused herbicide.
4.4.2.4. Spray Drift Management: The interaction of application equipment and weather-related factors determines the potential for spray drift. The Contractor is responsible for considering all factors when making application decisions. Drift agents WILL be used and supplied by the contractor for all liquid aerial applications. Controlling drift is the responsibility of the Contractor.
4.4.2.5. Coverage: The entire surface within the designated boundaries of the project area(s) shall receive uniform coverage with the specified herbicide except for areas excluded by the Government. Areas excluded from the spraying operation within the designated boundaries, will not be included in the acreage computed for payment. Any areas not properly treated by the Contractor shall be either retreated or compensated by suitable contract adjustment, at the option of and at no additional cost to the Government.
4.4.2.6. Applicator Logs: One report shall be provided to the Government. The report shall include daily herbicide application records as well as daily geospatial data in shapefile format. This log or record shall be signed by the applicator operator and turned into the COR upon completion of the contract via email within 10 business days.
4.4.2.7. Environmental Conditions
4.4.2.7.1. Wind: The Contractor shall follow the Label Section on Spray Drift Management - Wind. Local wind can influence wind patterns. Every applicator should be familiar with local wind patterns and how they affect drift.
4.4.2.7.2. Relative Humidity: Refer to the product label when making applications in low relative humidity conditions. Measurements can be obtained from local National Weather Service.
4.4.2.7.3. Site Conditions: No treatment spraying will be allowed if conditions do not meet the label requirements.
4.4.2.8. Application Paths: Shall be patterned to secure a uniform distribution of herbicide. Contractor must ensure that there will be straight and regular paths of application. The Contractor must keep applications within the perimeter of the Government provided shapefile. Irregular paths or areas sprayed outside of the perimeter will result in immediate stoppage of work. Corrective action shall be taken immediately by the Contractor to insure evenly spaced, straight, and regular application paths and complete coverage of areas included in the spraying job. Overlapping will be avoided.
4.4.2.9. Swath Width: Effective swath width shall not exceed the maximum for adequate coverage of supplied application equipment.
4.4.2.10. Application Height: Herbicide dispenser shall be set at a height to obtain proper distribution and uniform coverage of herbicide on target species. Contractor shall follow Herbicide Label instructions on Spray Drift Management to obtain proper boom height.
4.4.2.11. Land Patterns and Terrain: Contractor shall be capable of treating small irregular shaped areas and avoid lands not owned by the BLM or not authorized to treat under this contract. Contractor shall also be capable of applying herbicide in contour patterns and WILL NOT be allowed to apply herbicide at one fixed elevation over the entire project site.
4.4.2.12. Tests for uniformity and rate of application: The Government representative (COR/PI) will utilize field data to determine uniformity of herbicide application. Randomly spaced water sensitive cards or collection trays will be utilized. Should the Contractor wish to object in any way to the ground sampling done at any particular time by the Government, the Contractor shall be present in person or by authorized representative to voice said objections when said ground samplings are done, and to agree upon new samples at the time, where after the ground sampling is done by the Government shall be final and binding in the settlement of the contract.
4.4.2.13. Sprayer Clean-up: Shall be conducted according to the label instructions. Avoiding contamination of the work site is the responsibility of the Contractor. All empty herbicide containers will be tripled rinsed, labels removed and punctured by the Contractor after mixing. The Contractor shall be responsible for disposal of the empty boxes, labels, empty containers, and lids.
F-5
5. Specific Tasks
5.1. Herbicide Application: The Contractor shall perform the herbicide application in designated areas in conformance with these specifications. Unless otherwise specified, the Contractor shall furnish, equipment, labor, supplies, tools, supervision, materials, incidentals, and perform all work necessary to complete the herbicide application in accordance with the specifications provided (see Detailed Specifications 4.4.2). Services shall be billed in accordance with pricing schedule.
F-6
6. Applicable Technical Orders, Specifications, Regulations, Manuals
6.1. Fire Prevention: Primarily for purposes of fire prevention and control, the Contractor shall comply with the following provisions:
6.1.1. All equipment will have the following:
6.1.1.1. A serviceable chemical “ABC” fire extinguisher of at least 10-pounds minimum capacity. Such fire extinguisher shall be filled and in operating condition.
6.1.1.2. A shovel in good condition with not less than a three (3) foot handle and a blade not less than seven and three-quarters (7 3/4) inches wide. The shovel shall be in good condition, be tight on strong handles, and have sharp cutting edges. There shall be at least one (1) tool for each Contractor employee working on the contract area.
6.1.1.3. The CO may require additional fire tools and fire equipment as the fire danger warrants. This may require the contractor to supply a mechanized fire suppression apparatus (i.e., UTV with water tank and gas or electric pump) that will be always manned during times of high fire danger.
6.1.2. All diesel and/or gasoline operated engines will be equipped with spark arresters.
6.1.3. Remove all concentrations of wood dust and debris from equipment daily.
6.2. Fuel Storage and Transfer: Storage of flammables and combustibles may occur on site. Storage of flammable and combustibles shall follow State and Federal Regulations.
6.2.1. Only approved containers and portable tanks shall be used for storage and handling of flammable liquids. Approved safety cans or Department of Transportation approved containers shall be used for the handling and use of flammable liquids in quantities of 5-gallons or less, except that this shall not apply to those flammable liquid materials which are highly viscid (extremely hard to pour), which may be used and handled in original shipping containers. For quantities of one gallon or less, the original container may be used, for storage, use and handling of flammable liquids.
6.2.2. Safety can shall mean an approved container, of not more than 5-gallons capacity, having a spring-closing lid and spout cover and so designed that it will safely relieve internal pressure when subjected to fire exposure.
6.2.3. Storage areas shall be kept free of weeds, debris, and other combustible material not necessary to the storage.
6.2.4. At least one portable 10-pound (minimum) “ABC” fire extinguisher shall be located not less than 25-feet, nor more than 75-feet, from any flammable liquid storage area located outside.
6.2.5. Areas in which flammable liquids are transferred at one time, in quantities greater than 5-gallons from one tank or container to another tank or container, shall be separated from other operations by 25-feet distance or by construction having a fire resistance of at least 1-hour. Drainage or other means shall be provided to control spills.
Adequate natural or mechanical ventilation shall be provided to maintain the concentration of flammable vapor at or below ten percent of the lower flammable limit.
6.3. Herbicide Transportation, Storage, and Usage:
6.3.1. The Contractor shall be responsible for the storage and transport of herbicides used to fulfill the specifications of this contract. The Contractor shall secure herbicide containers in mixing area to prevent spillage. Contractor is required to have locked storage for herbicide and keep herbicide locked up while unattended. Contractor shall be responsible for the herbicide’s protection from loss or damage due to weather, rodents, insects, theft, or any other hazard. Any herbicide damaged or lost while in the custody of the Contractor will be replaced by the Contractor at the Contractors expense.
6.3.2. The Contractor shall supply protective clothing and equipment to contract workers that guarantee minimal exposure throughout the herbicide application process. The Contractor shall follow all advice on protective clothing and equipment which appears on the herbicide label and/or MSDS documentation. The Contractor shall make available clean-up facilities to contract employees exposed to herbicides or herbicide-contaminated equipment.
6.3.3. The Contractor shall mix herbicides in accordance with the proportions listed on the product labels. The Contractor shall provide adequate protective clothing and equipment for contract employees who engage in herbicide mixing.
6.3.4. By law, the application of an herbicide, either directly or through drift, must not expose workers or other people.
The Contractor shall be very aware and cautious of any environmental hazard present during herbicide application.
Upon completion of herbicide application, the Contractor shall thoroughly clean equipment and dispose of waters, residues, rinses, and unused herbicides only according to EPA and Idaho State regulations. All empty herbicide containers will be tripled rinsed, labels removed and punctured by the Contractor after mixing. The Contractor shall be responsible for disposal of the empty boxes, labels, and lids. The Contractor will be responsible for disposal and recycling of the empty containers.
6.3.5. The Contractor shall be responsible if accidents and chemical spills occur. The Contractor shall report immediately spills and accidents to the BLM authorized officers and appropriate local authorities. The Contractor shall provide immediate treatment of contaminated or injured persons and seek professional medical attention when necessary.
The Contractor shall control chemical spills quickly and shall secure additional help when the Contractor cannot effectively or safely handle the spill clean-up. Spills will be the responsibility of the Contractor and shall be cleaned up to the satisfaction of the local authorities.
Technical Exhibits:
Required services table with AQL:
PERFORMANCE
TASK
PERFORMANCE
STANDARD
ACCEPTABLE QUALITY
LEVEL
METHOD(S) OF
SURVEILLANCE
Herbicide Application (PWS 5.1) Uniform coverage 95%
• Comparing applicator logs/shapefiles to original polygon to confirm uniform coverage over the application area.
• Uniformity tests using randomly spaced water sensitive cards will be utilized.
• Noticeable wilting and/or chlorosis of the target vegetation.
DELIVERABLE FREQUENCY REFERENCE MEDIUM/FORMAT SUBMIT TO
Performance/Work Plan Once 1.6.5 Pre-work conference
By email in PDF format or hard copy COR
Crew Manifest Once, and as needed when crew manifest changes.
1.6.9 Personnel
Requirements
By email in PDF or scanned or hard copy COR
Applicator Log and Geospatial Data
Once, or as needed for updates 4.3 Applicator Logs By email in PDF or scanned or hard copy COR
| BUREAU OF LAND MANAGEMENT – Upper Snake Field Office |
| Performance Work Statement |
| Sand Creek Desert Fuel Break (SCDFB) Herbicide Application |
| F-1 |
| 1. General: This is a non-personal services contract to provide for herbicide application services. The Government shall not exercise any supervision or control over the providers performing these services. Such contract service providers shall be acc... |
| 1.1. Description of Services/Introduction: The Upper Snake Field Office (USFO), Bureau of Land Management (BLM) is acquiring services for herbicide application. The Contractor shall furnish all labor, equipment, tools, materials, supervision, supplies... |