This document is a technical specification for a quarters housing roof replacement project at the Trapper Creek Job Corps Civilian Conservation Center in Montana. The project involves replacing roofs on Buildings 29 and 30 with standing seam metal roofs, including removal of existing asphalt shingles, installation of new underlayment, drip edges, flashing, and metal roofing panels. An optional sheathing replacement item allows for replacement of one 4'x8' sheet if identified during inspection. The specifications include detailed requirements for metal roof panels (24-gauge metallic-coated steel with fluoropolymer finish), underlayment materials, fasteners, and accessories, with colors to be selected by the Contracting Officer.

The project requires compliance with International Code Council codes, NFPA standards, and manufacturer installation instructions. Key schedule requirements include a pre-construction conference within 10 days of award, bonds within 10 days, submittals within 12 days of Notice to Proceed, and various warranty provisions including a 20-year No Dollar Limit roofing system warranty. Work hours are restricted to 8:00 AM-4:30 PM Monday through Friday, with the government occupying the site during construction. The contractor must provide all labor, materials, equipment, and proper disposal of removed materials, while coordinating with the Center Point of Contact to minimize disruption to ongoing Job Corps operations.

View the file

Other files

File Type Posted
Answers 1.docx DOCX document
12441925Q0025 0001.pdf PDF
Attachment 3 12441925Q0025 SOI.xlsx XLSX spreadsheet
12441925Q0025.pdf PDF
Attachment 2 12441925Q0025 TPR Drawings.pdf PDF
Attachment 4 12441925Q0025 Wage Rates.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

QUARTERS HOUSING ROOF REPLACEMENT 010150 – 1

TRAPPER CREEK JOB CORPS CCC GENERAL REQUIREMENTS

QUARTERS HOUSING ROOFING REPLACEMENT PROJECT

TRAPPER CREEK JOB CORP CIVILIAN CONSERVATION CENTER

SECTION 010150

GENERAL REQUIREMENTS

PART 1 – SUMMARY OF WORK

3.1 DESCRIPTION

A. Work for this project requires the contractor to be responsible for supplying all labor, materials, equipment, utilities, miscellaneous items, freight and delivery and all necessary valid licenses for the work summarized as follows:

1. Building 29 Quarters, roof replacement

2. Building 30 Quarters, roof replacement

3. Optional Item #1, Sheathing Replacement

3.2 LOCATION

A. This project is located at the Trapper Creek Job Corps Civilian Conservation Center located 26.5 of miles from Darby, Montana in Ravalli County. The address is 5139 West Fork Road, Darby, Montana 59829. Driving instructions can be obtained from the Center by calling 406-821-3286.

3.3 WORK HOURS

A. Work hours for this project are between 8:00 AM-4:30 PM Monday through Friday.

3.4 USE OF PREMISES

A. Confine constructions operations to immediate area of work. Do not disturb portions of Project site beyond areas in which the Work is indicated.

B. Government will occupy site and buildings during entire construction period. Cooperate with Government during construction operations to minimize conflicts and facilitate Government usage. Perform the work so as not to interfere with Government's day-to-day operations.

C. Keep driveways, parking areas, loading areas and entrances to buildings clear and available to Government, Government's employees, and emergency vehicles at all times.

Do not use these areas for parking or storage of materials. Do not close or obstruct walkways, corridors, or other occupied or used facilities without written permission from Government.

3.5 DEFINITIONS

QUARTERS HOUSING ROOF REPLACEMENT 010150 – 2

A. The following terms in any combination relating to the installation of products/materials:

install, furnish, provide, or similar statements; mean that the contractor is responsible for the procurement and installation of the products unless it is specifically designated as either a government furnished item, supply only product, or spare.

3.6 STANDARDS AND CODES

A. All contract work shall adhere to the most recent version of:

1. All the International Code Council Family of codes (ICC) e.g. International

Building Code (IBC), International Fire Code (IFC), and International Mechanical Code (IMC).

2. All National Fire Protection Association (NFPA) codes and Standards e.g. , NFPA 70: National Electrical Code (NEC), NFPA 1: Fire Code, and NFPA 101- Life Safety Code.

3. Architectural Barriers Act Standards (ABA or ABAAS).

4. Product Manufacturer’s installation instructions.

3.7 QUALIFICATIONS

A. When applicable to specific contract work items:

1. Electrical work shall be performed by journey level electricians licensed in the

State of contract performance or trainees/apprentices working under the direct supervision of State-licensed electrical supervisors (or State equivalent).

2. Plumbing work shall be performed by journey level plumbers licensed in the State of contract performance or trainees/apprentices working under the direct supervision of State-licensed plumbing supervisors (or State equivalent).

3. Fire Alarm work shall be performed by NICET certified fire alarm technicians.

3.8 ELECTRICAL INSPECTIONS

A. This Federal contract is exempt from State permitting requirements. However, electrical work must be inspected by a third-party Inspector who is either State-licensed or ICC-certified. The Contractor will arrange for the inspection and pay any fees required for the inspection and associated report; arrangement may include completion and submission of load calculations, permit applications, and any other required coordination. The Inspector does not have any jurisdictional authority on Federal projects. The USFS is the jurisdiction having authority. The inspection will be based on the most recent version of the NFPA 70 National Electric Code (NEC) and currently adopted State codes. A list of deficiencies with corresponding code reference is to be provided in a report signed by the inspector. The addressee in the report is to be the Job Corps Center. The Inspector will provide a copy of their current inspection credentials with the inspection report. The Contractor will submit the report to the COR. The CO will determine which deficiency/violations will be enforced for the Contractor to fix.

QUARTERS HOUSING ROOF REPLACEMENT 010150 – 3

3.9 WORK RESTRICTIONS

A. Smoking is permitted on campus only in the designated smoking area.

3.10 SCHEDULE OF ITEMS

A. Schedule of Items:

1. Provide pricing for all items listed in the Schedule of Items.

2. Contract award will be made for all Base Items.

3. Optional Items may or may not be awarded, depending on funding availability.

B. Base Items (BI):

1. Base Item No. 1 – Building 29

a. Measurement: This item is measured as a Lump Sum quantity.

b. Payment: The contract lump sum price as shown in the Schedule of Items includes all materials, equipment, labor and incidentals to reroof building with a metal roof.

1) Remove existing asphalt shingles, underlayment, drip edge, flashing/boots, accessories, and properly dispose of off-site.

2) Contractor to inspect soundness of all existing materials prior to installing new materials.

3) Install new underlayment and continuous drip-edge. Drip-edge color shall be selected by the Contracting Officer (CO), from the manufacturer’s full color palette.

4) Install all trim, roof penetration flashing/boots, accessories, and fasteners per manufacturer’s recommendations.

5) Install standing seam metal roof. Color shall be selected by the CO, from the manufacturer’s full color palette.

6) Seal all penetrations with butyl based caulking.

2. Base Item No. 2 – Building 30

a. Measurement: This item is measured as a Lump Sum quantity.

b. Payment: The contract lump sum price as shown in the Schedule of Items includes all materials, equipment, labor and incidentals to reroof building with a metal roof.

1) Remove existing asphalt shingles, underlayment, drip edge, flashing/boots, accessories, and properly dispose of off-site.

2) Contractor to inspect soundness of all existing materials prior to installing new materials.

QUARTERS HOUSING ROOF REPLACEMENT 010150 – 4

3) Install new underlayment and continuous drip-edge. Drip-edge color shall be selected by the Contracting Officer (CO), from the manufacturer’s full color palette.

4) Install all trim, roof penetration flashing/boots, accessories, and fasteners per manufacturer’s recommendations.

5) Install standing seam metal roof. Color shall be selected by the CO, from the manufacturer’s full color palette.

6) Seal all penetrations with butyl based caulking.

C. Optional Items (OI):

1. Optional Item No. 1 - Sheathing

2. Payment: The contract lump sum price as shown in the Schedule of Items includes all materials, equipment, labor and incidentals to Description of work included in this bid item.

a. Replacement of 1 each 4 FT by 8 FT sheathing identified by the contractor and the Center POC after inspection.

PART 2 – PROJECT SCHEDULE

4.1 PROJECT SCHEDULE

ITEM* REQUIRED DUE DATE (calendar days)

Pre-Construction Conference

Within 10 days of Award (virtually)

Notice To Proceed (NTP)

Issued first weekday after Pre-Construction Conference

Bonds 10 days after Award

Action and Informational Submittals

12 days after NTP (CORs have 12 days to return)

Closeout Submittals

Prior to CO acceptance of project

QUARTERS HOUSING ROOF REPLACEMENT 010150 – 5

Contract Release form and final pay request

10 days after CO acceptance of project

* All items above must be included in Contractor’s construction schedule

PART 3 – SUBMITTAL PROCEDURES

5.1 DEFINITIONS

A. Action Submittals: Written and graphic information that requires Government approval.

B. Informational Submittals: Written information that does not require Government approval. Submittals may be rejected for not complying with requirements.

5.2 PROCEDURES

A. Contractor Responsibilities

1. Review each submittal and check for compliance with the Contract Documents.

2. Highlight, encircle, or otherwise identify deviations from the Contract Documents on submittals.

3. Include the following information on label or cover sheet for processing and recording action taken:

a. Project name.

b. Date.

c. Name and address of Contractor.

d. Name of manufacturer.

e. Unique identifier, including revision number.

f. Number and title of appropriate Specification Section.

g. Drawing number and detail references, as appropriate.

h. Date of Contractor’s approval.

i. Statement certifying that submittal has been reviewed, checked, and approved by the Contractor for compliance with the Contract Documents.

4. The Government will not review submittals that do not bear Contractor's approval and will return them without action.

5. Unless additional copies are required for final submittal, and unless the

Contracting Officer (CO) observes noncompliance with provisions of the Contract Documents, initial submittal may serve as final submittal.

6. Submittals must be submitted in electronic PDF format. Submit to CO via email or electronic file transfer site.

7. Only final submittals with mark indicating action taken by Government are to be used for construction.

QUARTERS HOUSING ROOF REPLACEMENT 010150 – 6

8. Submittals not required by the Contract Documents will not be reviewed and may be discarded.

B. Processing Time: Time for review shall commence on CO's receipt of submittal.

1. Initial Review: Government will review initial submittal within 12 calendar days.

Additional time may be needed if processing must be delayed to permit coordination with subsequent submittals. CO will advise Contractor when a submittal being processed must be delayed for coordination.

2. Resubmittals: If resubmittal is necessary, it will be resubmitted within 3 calendar days, and reviewed by the Government within 3 calendar days.

5.3 ACTION SUBMITTALS

A. Prepare and submit Action Submittals required in the Technical Specifications in this contract, if applicable, and as indicated at the end of this subsection.

B. Collect information into a single submittal for each element of construction and type of product or equipment.

1. Mark up each submittal to show which products and options are applicable.

2. Include the following information, as applicable:

a. Manufacturer's written recommendations.

b. Manufacturer's product specifications.

c. Manufacturer's installation instructions.

d. Manufacturer's catalog cuts.

e. Wiring diagrams showing factory-installed wiring.

f. Compliance with recognized trade association standards.

g. Compliance with recognized testing agency standards.

C. Required Action Submittals

1. Product Data: See Technical Specification Sections

OR

LIST REQUIRED PRODUCT DATA SUBMITTALS (if not identified in separate technical specifications)

5.4 INFORMATIONAL SUBMITTALS

A. Prepare and submit Informational Submittals required in the Technical Specifications in this contract, if applicable, and as indicated below:

B. Required Informational Submittals:

1. Accident Prevention Plan.

2. Construction Schedule.

3. Current licensure and/or certifications for individuals indicated in QUALIFICATIONS paragraph above or as required in individual technical sections.

QUARTERS HOUSING ROOF REPLACEMENT 010150 – 7

5.5 CLOSEOUT SUBMITTALS

A. Prepare and submit Closeout Submittals, as follows:

1. One-Year Warranty on Entire Project as required by FAR 52.246–21

2. Project Record Documents.

PART 4 – TEMPORARY FACILITIES AND CONTROLS

6.1 USE OF UTILITIES

A. Utilities: Use of Government existing facilities will be permitted without metering and without payment of use charges, as long as facilities are cleaned and maintained in an acceptable condition. At Substantial Completion, restore these facilities to condition existing before initial use. The following are available for use by the contractor: water, and electrical power services. The following are not available: telephone service. The contractor is expected to provide whatever phone service he deems necessary for the duration of the project.

6.2 SANITARY FACILITIES

A. Sanitary facilities are not available for use by the Contractor. Facilities must be cleaned and maintained daily.

6.3 STAGING AND STORAGE

A. Coordinate on-site staging and storage requirements with the Center Point of Contact or the Contracting Officer Representative (COR).

6.4 CONSTRUCTION WASTE DISPOSAL FACILITIES

A. Provide waste-collection containers in sizes adequate to handle waste from construction operations. Containerize and clearly label hazardous, dangerous, or unsanitary waste materials separately from other waste. Use of Government waste containers will not be permitted.

6.5 SAFETY AND ENVIRONMENTAL PROTECTION

A. Environmental Protection: Contractor shall provide protection, operate temporary facilities, and conduct construction in ways and by methods that comply with environmental regulations and that minimize possible air, waterway, and subsoil contamination or pollution or other undesirable effects.

QUARTERS HOUSING ROOF REPLACEMENT 010150 – 8

B. Barricades, Warning Signs, and Lights: Comply with the national or state Manual on Uniform Traffic Control Devices (MUTCD) for erecting structurally adequate barricades, paint with appropriate colors, graphics, and warning signs/lights to inform personnel, students, and the public of possible hazards.

C. Fire Protection.

1. Store combustible materials in containers in fire-safe locations.

2. Maintain unobstructed access to fire extinguishers, fire hydrants, fire-protection facilities, stairways, and other access routes for firefighting. Prohibit smoking in hazardous fire-exposure areas.

3. Supervise welding operations, combustion-type temporary heating units, and similar sources of fire ignition.

PART 5 – EXECUTION REQUIREMENTS

7.1 EXAMINATION

A. Before beginning work, examine areas and document existing conditions. Proceed with installation only after unsatisfactory conditions have been corrected. Proceeding with the Work indicates acceptance of surfaces and conditions.

B. Field verify all new and existing dimensions affecting the work of this contract before ordering products.

C. Immediately on discovery of the need for clarification of the Contract Documents, submit a request for information to CO. Include a detailed description of problem encountered, together with recommendations for changing the Contract Documents.

7.2 INSTALLATION

A. Locate the Work and components of the Work accurately, in correct alignment and elevation to fit with existing construction.

B. Make vertical work plumb and make horizontal work level.

C. Install per manufacturer's written instructions and recommendations.

7.3 PROGRESS CLEANING

A. Clean Project site and work areas daily, including common areas. Dispose of materials lawfully.

1. Comply with NFPA 241 requirements for removal of combustible waste materials and debris.

2. Do not hold materials more than 7 days during normal weather or 3 days if the temperature is expected to rise above 80 deg F (27 deg C).

QUARTERS HOUSING ROOF REPLACEMENT 010150 – 9

B. Burying or burning waste materials on-site will not be permitted. Washing waste materials down sewers or into waterways will not be permitted.

7.4 PROTECTION OF INSTALLED CONSTRUCTION

A. Provide protection and maintain conditions that ensure installed Work does not get damaged or deteriorated prior to Substantial Completion.

7.5 CORRECTION OF THE WORK

A. Repair or remove and replace defective construction. Restore damaged substrates and finishes.

1. Repairing includes replacing defective parts, refinishing damaged surfaces, touching up with matching materials, and properly adjusting operating equipment.

PART 6 – CLOSEOUT PROCEDURES

8.1 SUBSTANTIAL COMPLETION

A. Definition of Substantial Completion: The Date certified by the CO when construction is sufficiently complete, in accordance with the Contract Documents, so the Government can occupy or utilize the Work or designated portion thereof for the use for which it is intended, as expressed in the Contract Documents.

B. Preliminary Procedures: Before requesting inspection for determining date of Substantial Completion, complete the following. List items below that are incomplete in request.

1. Prepare a list of items to be completed and corrected (punch list), the value of items on the list, and reasons why the Work is not complete.

2. Advise the CO of pending insurance changeover requirements.

3. Submit specific warranties, workmanship bonds, final certifications, and similar documents.

4. Obtain and submit releases permitting Government unrestricted use of the Work and access to services and utilities.

5. Deliver tools, spare parts, extra materials, and similar items to location designated by Government. Label with manufacturer's name and model number where applicable.

6. Complete startup testing of systems.

7. Submit changeover information related to Government occupancy, use, operation, and maintenance.

8. Complete final cleaning requirements, including touchup painting.

9. Touch up and otherwise repair and restore marred exposed finishes to eliminate visual defects.

QUARTERS HOUSING ROOF REPLACEMENT 010150 – 10

C. Inspection: Submit a written request for inspection for Substantial Completion. On receipt of request, CO will either proceed with inspection or notify Contractor of unfulfilled requirements. CO will prepare the Certificate of Substantial Completion after inspection or will notify Contractor of items, either on Contractor's list or additional items identified by CO, that must be completed or corrected before certificate will be issued.

1. Reinspection: Request reinspection when the Work identified in previous inspections as incomplete is completed or corrected.

2. Results of completed inspection will form the basis of requirements for Final Completion.

8.2 FINAL COMPLETION

A. Preliminary Procedures: Before requesting final inspection for determining date of Final Completion, complete the following:

1. Submit certified copy of CO’s Substantial Completion inspection list of items to be completed or corrected (punch list), endorsed and dated by CO. The certified copy of the list shall state that each item has been completed or otherwise resolved for acceptance.

2. Submit evidence of final, continuing insurance coverage complying with insurance requirements.

3. Instruct Government personnel in operation, adjustment, and maintenance of products, equipment, and systems.

B. Inspections: Submit a written request for final inspection for acceptance. On receipt of request, CO will either proceed with inspection or notify Contractor of unfulfilled requirements. CO will prepare a final Certificate for Payment after inspection or will notify Contractor of construction that must be completed or corrected before certificate will be issued.

1. Reinspection: Request reinspection when the Work identified in previous inspections as incomplete is completed or corrected.

8.3 LIST OF INCOMPLETE ITEMS (PUNCH LIST)

A. Preparation: Submit two copies of list. Include name and identification of each space and area affected by construction operations for incomplete items and items needing correction including, if necessary, areas disturbed by Contractor that are outside the limits of construction.

8.4 PROJECT RECORD DOCUMENTS

A. General: Do not use Project Record Documents for construction purposes. Protect Project Record Documents from deterioration and loss. Provide access to Project Record Documents for CO's reference during normal working hours.

QUARTERS HOUSING ROOF REPLACEMENT 010150 – 11

B. Provide Draft of Project Record Drawings at Substantial Completion. CO will return reviewed copy. Provide Final Project Record Drawings at Final Completion.

C. Record Drawings: Maintain and submit one set of blue- or black-line white prints of Contract Drawings and Shop Drawings.

1. Mark Record Prints to show the actual installation where installation varies from that shown originally. Require individual or entity who obtained record data, whether individual or entity is Installer, subcontractor, or similar entity, to prepare the marked-up Record Prints.

a. Give particular attention to information on concealed elements that cannot be readily identified and recorded later.

b. Record data as soon as possible after obtaining it. Record and check the markup before enclosing concealed installations.

2. Mark record sets with erasable, red-colored pencil. Use other colors to distinguish between changes for different categories of the Work at the same location.

3. Note Construction Change Directive numbers, Change Order numbers, alternate numbers, and similar identification where applicable.

4. Identify and date each Record Drawing; include the designation "PROJECT RECORD DRAWING" in a prominent location. Organize into manageable sets;

bind each set with durable paper cover sheets. Include identification on cover sheets.

8.5 FINAL CLEANING

A. General: Provide final cleaning. Conduct cleaning and waste-removal operations to comply with local laws and ordinances and Federal and local environmental and antipollution regulations.

B. Cleaning Agents: Use cleaning materials and agents recommended by manufacturer or fabricator of the surface to be cleaned. Do not use cleaning agents that are potentially hazardous to health or property or that might damage finished surfaces.

C. Complete the following cleaning operations before requesting inspection for certification of Substantial Completion for entire Project or for a portion of Project:

1. Clean Project site, yard, and grounds, in areas disturbed by construction activities, including landscape development areas, of rubbish, waste material, litter, and other foreign substances.

2. Remove tools, construction equipment, machinery, and surplus material from Project site.

3. Touch up and otherwise repair and restore marred, exposed finishes and surfaces.

Replace finishes and surfaces that cannot be satisfactorily repaired or restored or that already show evidence of repair or restoration.

QUARTERS HOUSING ROOF REPLACEMENT 010150 – 12

D. Remove waste materials from Project site and dispose of lawfully.

END OF SECTION 010150

QUARTERS ROOF REPLACEMENT 061600-1

TRAPPER CREEK JOB CORPS CCC SHEATHING

SECTION 061600

SHEATHING

PART 1 – GENERAL

1.1 SUMMARY

A. Section Includes:

1. Roof Sheathing.

1.2 SUBMITTALS

A. Product Data: For each type of process and factory-fabricated product. Indicate com-ponent materials and dimensions and include construction and application details.

1. Include data for wood-preservative treatment from chemical treatment manufac-turer and certification by treating plant that treated plywood complies with re-quirements.

B. Research/Evaluation Reports: For the following:

1. Preservative-treated plywood.

1.3 DELIVERY, STORAGE, AND HANDLING

A. Stack plywood and other panels flat with spacers between each bundle to provide air circulation. Provide for air circulation around stacks and under coverings.

PART 2 – PRODUCTS

2.1 WOOD PANEL PRODUCTS, GENERAL

A. Plywood: Either DOC PS 1 or DOC PS 2, unless otherwise indicated.

2.2 PRESERVATIVE-TREATED PLYWOOD

A. Preservative Treatment by Pressure Process: AWPA C9.

B. Mark plywood with appropriate classification marking of an inspection agency ac-ceptable to the CO.

C. Application: Treat items indicated on Drawings and plywood in contact with con-crete.

2.3 ROOF SHEATHING

A. Plywood Roof Sheathing: Structural I, Exposure 1 sheathing.

2.4 FASTENERS

QUARTERS ROOF REPLACEMENT 061600-2

TRAPPER CREEK JOB CORPS CCC SHEATHING

A. General: Sizes to comply with Table 2304.9 of the International Building Code.

1. For wall panels, provide fasteners with corrosion-protective coating having a salt-spray resistance of more than 800 hours according to ASTM B 117.

2.5 MISCELLANEOUS MATERIALS

A. Adhesives for Field Gluing Panels to Framing: Formulation complying with ASTM D 3498 that is approved for use indicated by manufacturers of both adhesives and panels.

1. Use adhesives that have a VOC content of 70g/L or less when calculated accord-ing to 40 CFR 59, Subpart D (EPA Method 24).

PART 3 – EXECUTION

3.1 INSTALLATION, GENERAL

A. Securely attach to substrate by fastening as indicated, complying with the following:

1. NES NER-272 for power-driven fasteners.

2. Table 2304.9.1, "Fastening Schedule," in ICC's "International Building Code."

B. Coordinate sheathing installation with flashing and joint-sealant installation so these materials are installed in sequence and manner that exclude exterior moisture.

C. Do not bridge building expansion joints; cut and space edges of panels to match spac-ing of structural support elements.

3.2 WOOD STRUCTURAL PANEL INSTALLATION

A. General: Comply with applicable recommendations in APA Form No. E30K, "APA Design/Construction Guide: Residential & Commercial."

1. Comply with "Code Plus" installation provisions in guide referenced in para-graph above.

B. Fastening Methods: Fasten roof sheathing to existing framing with nails.

END OF SECTION 061600

QUARTERS ROOF REPLACEMENT 074113 - 1

TRAPER CREEK

JOB CORPS CCC METAL ROOF PANELS

SECTION 074113

METAL ROOF PANELS

PART 1 - GENERAL

1.1 SUMMARY

A. This Section includes factory-formed and field-assembled, metal roof panels and ac-cessories.

B. See Division 7 Section "Sheet Metal Flashing and Trim".

1.2 PERFORMANCE REQUIREMENTS

A. Wind-Uplift Resistance: Comply with UL 580 for wind-uplift resistance class.

B. Structural Performance: Capable of withstanding the effects of gravity loads and the wind and snow loads for the location in accordance with the International Building Code and the state of Oregon amendments based on testing according to ASTM E 1592. Comply with the following loads and stresses unless code requirements are greater:

1. Wind Loads: follow ASCE 7, latest version, for project location.

2. Snow Loads: follow ASCE 7, latest version, for project location.

3. Deflection Limits: Vertical deflections no greater than 1/240 of the span.

C. Seismic Performance: Provide metal roof panel assemblies capable of withstanding the effects of earthquake motions determined according to ASCE 7, "Minimum De-sign Loads for Buildings and Other Structures": Section 9, "Earthquake Loads.”

D. Energy Performance: Provide roof panels with solar reflectance index not less than 29 when calculated according to ASTM E 1980 based on testing identical products by a qualified testing agency.

E. Energy Performance: Provide roof panels that are listed on the U.S. Department of Energy's ENERGY STAR Roof Products Qualified Product List for steep-slope roof products.

F. Energy Performance: Provide roof panels with initial solar reflectance not less than

0.25 and emissivity not less than 0.75 when tested according to CRRC-1.

1.3 QUALITY ASSURANCE

A. Roof Installer Qualifications: The roofing installer shall be approved and authorized by Roofing System Manufacturer to install manufacturer’s product.

1.4 SUBMITTALS

QUARTERS ROOF REPLACEMENT 074113 - 2

A. As specified in “Submittal Procedures” paragraph in Division 1 Section “General Requirements”. Submit manufacturer's literature for each type of roof panel and accessory.

1. Include details of edge conditions, joints, panel profiles, corners, anchorages, trim, flashings, closures, and accessories.

B. Shop Drawings:

1. Provide shop drawings drawn to scale and coordinating metal roof panel instal-lation with penetrations, flashing, and roof-mounted items. Include manufac-turer’s details addressing each type of trim and flashing condition encountered for the project.

2. Provide layout and standard detail drawing showing locations of all snow guard components including clamps and clamp spacing.

3. Include all pertinent design information such as wind load value, snow load value, etc.

C. Samples: Provide color samples for each exposed finish.

D. Sample Warranty.

1.5 CLOSEOUT SUBMITTALS

A. As specified in “Closeout Procedures” paragraph of Division 1 Section “General Re-quirements”.

1. Operation and Maintenance Data.

2. Material certificates

3. Warranty:

a. Special Warranty on Panels: Manufacturer's standard form in which man-ufacturer agrees to repair or replace components of metal roof panel as-semblies that fail in materials or workmanship within five (5) years from date of Substantial Completion.

1) Failures include, but are not limited to, the following:

a) Structural failures, including rupturing, cracking, or puncturing.

b) Deterioration of metals, metal finishes, and other materials be-yond normal weathering.

b. Special Warranty on Panel Finishes: Manufacturer's standard form in which manufacturer agrees to repair finish or replace metal roof panels that show evidence of deterioration of factory-applied finishes within 20 years from date of Substantial Completion.

QUARTERS ROOF REPLACEMENT 074113 - 3

c. Special Warranty on Roofing System: A 20-year Roofing System NDL warranty is required from the roofing system manufacturer. System is de-fined as the complete roof, including substrate, underlayment, flashing, including penetrations, valleys, fasteners, and roofing panels. System warranty shall cover both materials and workmanship and shall be No Dollar Limit (NDL) on warranty repairs for duration of 20-year warranty period. The Contractor will be responsible to accommodate any removal and reinstallation of incidental materials which must be removed and rein-stalled due to the construction of the new roofs. All work shall be accom-plished in accordance with the Metal Construction Association (MCA) recommendations.

1) Substantial Completion documentation shall include:

a) Center Name / Building Name(s)

b) Date of Substantial Completion (warranty commencement date) & Warranty Expiration Date

c) Roofing system manufacturer’s “Quality Assurance Program” representatives written inspection reports.

d) Roofing system manufacturer’s “Quality Assurance Program” representatives written acceptance inspection report clearly stating that the roofing system has been installed in accordance with the manufacturer’s warranty requirements.

PART 2 - PRODUCTS

2.1 PANEL MATERIALS

A. Metallic-Coated Steel Sheet Pre-painted with Coil Coating: Steel sheet metallic coated by the hot-dip process and pre-painted by the coil-coating process to comply with ASTM A 755/A 755M.

1. Aluminum-Zinc Alloy-Coated Steel Sheet: ASTM A 792/A 792M, Class AZ50 coating designation, Grade 40 (Class AZM150 coating designation, Grade 275);

structural quality.

2. Surface: Smooth, flat finish.

3. Exposed Finishes: Two-coat, thermo-cured system with fluoropolymer coats containing not less than 70 percent polyvinylidene fluoride resin by weight;

complying with physical properties and coating performance requirements of AAMA 2604, except as modified below:

1) Humidity Resistance: 1000 hours.

2) Water Resistance: 1000 hours.

QUARTERS ROOF REPLACEMENT 074113 - 4

4. Concealed Finish: White or light-colored acrylic or polyester backer finish.

B. Panel Sealants:

1. Sealant Tape: Pressure-sensitive, gray polyisobutylene compound sealant tape with release-paper backing; 1/2 inch wide and 1/8 inch thick.

2. Joint Sealant: ASTM C 920; as recommended in writing by metal roof panel manufacturer.

3. Butyl-Rubber-Based, Solvent-Release Sealant: ASTM C 1311.

2.2 UNDERLAYMENT MATERIALS

A. Felts: ASTM D 226, Type II (No 30), asphalt-saturated organic felts.

B. Self-Adhering, High-Temperature Sheet: 40 mils (1.0 mm) thick minimum, consisting of slip-resisting polyethylene-film top surface laminated to layer of butyl or SBS-modified asphalt adhesive, with release-paper backing; cold applied. Provide primer when recommended by underlayment manufacturer.

C. Slip Sheet: Building paper, minimum 5 lb./100 sq. ft., rosin sized.

2.3 MISCELLANEOUS MATERIALS

A. Fasteners: Self-tapping screws, bolts, nuts, self-locking rivets and bolts, end-welded studs, and other suitable fasteners designed to withstand design loads. Provide ex-posed fasteners with heads matching color of metal roof panels by means of plastic caps or factory-applied coating.

1. Fasteners for Flashing and Trim: Blind fasteners or self-drilling screws with hex washer head.

2. Blind Fasteners: High-strength aluminum or stainless-steel rivets.

B. Bituminous Coating: Cold-applied asphalt mastic, SSPC-Paint 12, compounded for 15-mil (0.4-mm) dry film thickness per coat. Provide inert-type noncorrosive com-pound free of asbestos fibers, sulfur components, and other deleterious impurities.

2.4 METAL ROOF PANELS

A. Standing-Seam Metal Roof Panels: Factory-formed, designed to be field assembled by lapping and interconnecting raised side edges of adjacent panels with joint type in-dicated and mechanically attaching panels to supports using concealed clips inside laps. Include clips, cleats, pressure plates, and accessories required for weathertight installation.

1. Steel Panel Systems: Comply with ASTM E 1514.

QUARTERS ROOF REPLACEMENT 074113 - 5

B. Basis-of-Design Product: Subject to compliance with requirements, provide McElroy Maxima, or a comparable product that meets the following specifications.

1. Type: Vertical rib, mechanically seamed, or snap joint.

2. Material: Metallic-coated steel sheet, 24 gauge.

a. Exterior Finish: Fluoropolymer.

b. Color: As selected by Contracting Officer from manufacturer's full range

3. Clips: Metallic-coated-steel sheet. Floating type to accommodate thermal movement.

4. Panel Coverage: 12”.

5. Seam Height: 1.5” for mechanically seamed, or 1.75” for snap joint.

6. Uplift Rating: UL 90.

2.5 ACCESSORIES

A. Roof Panel Accessories: Provide components required for a complete metal roof panel assembly including trim, copings, fascia, corner units, ridge closures, clips, flashings, sealants, gaskets, fillers, closure strips, and similar items. Match material and finish of metal roof panels, unless otherwise indicated.

1. Closures: Provide closures at eaves and ridges, fabricated of same metal as metal roof panels.

2. Clips: Minimum 0.0625-inch-thick, stainless steel panel clips designed to with-stand negative-load requirements.

3. Cleats: Mechanically seamed cleats formed from minimum 0.0250-inch-thick, stainless steel or nylon-coated aluminum sheet.

4. Closure Strips: Closed-cell, expanded, cellular, rubber or crosslinked, polyole-fin-foam or closed-cell laminated polyethylene; minimum 1-inch- (25-mm-) thick, flexible closure strips; cut or pre-molded to match metal roof panel pro-file. Provide closure strips where indicated or necessary to ensure weathertight construction.

B. Flashing and Trim: Formed from 0.0179-inch-thick, metallic-coated steel sheet. Pro-vide flashing and trim as required to seal against weather and to provide finished ap-pearance. Locations include eaves, rakes, corners, bases, framed openings, ridges, fas-cia, and fillers. Finish flashing and trim with the same finishes as adjacent metal roof panel.

2.6 FABRICATION

A. General: Fabricate and finish metal roof panels and accessories at the factory to great-est extent possible, by manufacturer's standard procedures and processes, as necessary to fulfill indicated performance requirements demonstrated by laboratory testing.

Comply with indicated profiles and with dimensional and structural requirements.

QUARTERS ROOF REPLACEMENT 074113 - 6

B. Provide panel profile, including major ribs and intermediate stiffening ribs, if any, for full length of panel.

C. Where indicated, fabricate metal roof panel joints with factory-installed captive gas-kets or separator strips that provide a tight seal and prevent metal-to-metal contact, in a manner that will minimize noise from movements within panel assembly.

D. Sheet Metal Accessories: Fabricate flashing and trim to comply with recommenda-tions in SMACNA's "Architectural Sheet Metal Manual" that apply to the design, di-mensions, metal, and other characteristics of item indicated.

E. Protect mechanical and painted finishes on exposed surfaces from damage by applying a strippable, temporary protective covering before shipping.

PART 3 - EXECUTION

3.1 PREPARATION

A. Install flashings and other sheet metal to comply with requirements specified in Divi-sion 7 Section "Sheet Metal Flashing and Trim."

3.2 UNDERLAYMENT INSTALLATION

A. Self-Adhering Sheet Underlayment: Install self-adhering sheet underlayment, wrinkle free, to roof substrate. Comply with temperature restrictions of underlayment manu-facturer for installation; use primer rather than nails for installing underlayment at low temperatures. Apply in shingle fashion to shed water, with end laps of not less than 6 inches staggered 24 inches between courses. Overlap side edges not less than 3-1/2 inches. Extend underlayment into gutter trough. Roll laps with roller.

B. Felt Underlayment: Install felt underlayment over entire roof deck including self-ad-hering sheet underlayment. Use adhesive for temporary anchorage. Apply in shingle fashion to shed water, with lapped joints of not less than 2 inches.

C. Slip-Sheet: Apply slip-sheet over felt underlayment and on top of self-adhering un-derlayment before installing metal roof panels.

D. Cover underlayment within 14 days.

3.3 METAL ROOF PANEL INSTALLATION, GENERAL

A. General: Provide metal roof panels of full length from eave to ridge, unless otherwise indicated or restricted by shipping limitations. Anchor metal roof panels and other components of the Work securely in place, with provisions for thermal and structural movement.

1. Field cutting of metal roof panels by torch is not permitted.

QUARTERS ROOF REPLACEMENT 074113 - 7

2. Rigidly fasten eave end of metal roof panels and allow ridge end free movement due to thermal expansion and contraction. Predrill panels.

3. Provide metal closures at peaks, rake edges, rake walls and each side of ridge and hip caps.

4. Flash and seal metal roof panels with weather closures at eaves, rakes, and at pe-rimeter of all openings. Fasten with self-tapping screws.

5. Locate panel splices over, but not attached to, structural supports. Stagger panel splices and end laps to avoid a four-panel lap splice condition.

6. Lap metal flashing over metal roof panels to allow moisture to run over and off the material.

7. Install roof panels such that the wind blows over the lap side joints and not into the side lap joints.

B. Fasteners: Use stainless-steel fasteners for surfaces exposed to the exterior and galva-nized steel fasteners for surfaces exposed to the interior.

C. Metal Protection: Where dissimilar metals will contact each other or corrosive sub-strates, protect against galvanic action by painting contact surfaces with bituminous coating, by applying rubberized-asphalt underlayment to each contact surface, or by other permanent separation as recommended by metal roof panel manufacturer.

1. Coat back side of aluminum roof panels with bituminous coating where roof panels will contact wood, ferrous metal, or cementitious construction.

D. Joint Sealers: Install gaskets, joint fillers, and sealants where required for weather-proof performance of metal roof panel assemblies.

1. Seal metal roof panel end laps with double beads of tape or sealant, full width of panel. Seal side joints where recommended by metal roof panel manufacturer.

3.4 FIELD-ASSEMBLED METAL ROOF PANEL INSTALLATION

A. Standing-Seam Metal Roof Panels: Fasten metal roof panels to supports with con-cealed clips at each standing-seam joint at location, spacing, and with fasteners recom-mended by manufacturer.

1. Install clips to supports with self-tapping fasteners.

2. Mechanically Seamed: Comply with manufacturer’s product data, recommen-dations, and installation instructions.

3. Snap Joint: Nest standing seams and fastens together by interlocking and com-pletely engaging factory-applied sealant.

3.5 ACCESSORY INSTALLATION

A. General: Install accessories with positive anchorage to building and weathertight mounting and provide for thermal expansion. Coordinate installation with flashings and other components.

QUARTERS ROOF REPLACEMENT 074113 - 8

1. Install components required for a complete metal roof panel assembly including trim, copings, ridge closures, seam covers, flashings, sealants, gaskets, fillers, closure strips, and similar items.

2. Comply with performance requirements, manufacturer's written installation in-structions, and SMACNA's "Architectural Sheet Metal Manual." Provide con-cealed fasteners where possible and set units true to line and level. Install work with laps, joints, and seams that will be permanently watertight and weather re-sistant.

3.6 CLEANING AND PROTECTION

A. Remove temporary protective coverings and strippable films, if any, as metal roof panels are installed, unless otherwise indicated in manufacturer's written installation instructions. On completion of metal roof panel installation, clean finished surfaces as recommended by metal roof panel manufacturer.

END OF SECTION 074113

QUARTERS ROOF REPLACEMENT

TRAPPER CREEK JOB CORPS CCC

076200 - 1

SHEET METAL

FLASHING AND

TRIM

SECTION 076200

SHEET METAL FLASHING AND TRIM

1.1 SUMMARY

A. Section Includes:

1. Formed roof-drainage sheet metal fabrications.

2. Formed wall sheet metal fabrications.

3. Vent pipe flashing.

1.2 ACTION SUBMITTALS

A Product Data: For each type of product.

B. Shop Drawings: For sheet metal flashing and trim.

1. Include plans, elevations, sections, and attachment details.

2. Distinguish between shop- and field-assembled work.

3. Include identification of finish for each item.

4. Include pattern of seams and details of termination points, expansion joints and expansion-joint covers, direction of expansion, roof-penetration flashing, and connections to adjoining work.

1.3 INFORMATIONAL SUBMITTALS

A. Product certificates.

B. Product test reports.

C. Sample warranty.

1.4 CLOSEOUT SUBMITTALS

A. Maintenance data.

B. Warranties.

1.5 QUALITY ASSURANCE

A. Fabricator Qualifications: Employs skilled workers who custom fabricate sheet metal flashing and trim similar to that required for this Project and whose products have a record of successful in-service performance.

076200 - 2

SHEET METAL

FLASHING AND

TRIM

1. For copings and roof edge flashings that are SPRI ES-1 tested, shop shall be listed as able to fabricate required details as tested and approved.

1.6 WARRANTY

A. Special Warranty on Finishes: Manufacturer agrees to repair finish or replace sheet metal flashing and trim that shows evidence of deterioration of factory-applied finishes within specified warranty period.

1. Finish Warranty Period: 20 years from date of Substantial Completion.

PART 2 - PRODUCTS

2.1 PERFORMANCE REQUIREMENTS

A. General: Sheet metal flashing and trim assemblies shall withstand wind loads, structural movement, thermally induced movement, and exposure to weather without failure due to defective manufacture, fabrication, installation, or other defects in construction.

Completed sheet metal flashing and trim shall not rattle, leak, or loosen, and shall remain watertight.

B. Sheet Metal Standard for Flashing and Trim: Comply with NRCA's "The NRCA Roofing Manual" and SMACNA's "Architectural Sheet Metal Manual" requirements for dimensions and profiles shown unless more stringent requirements are indicated.

C. Recycled Content of Steel-Sheet Flashing and Trim: Postconsumer recycled content plus one-half of pre-consumer recycled content not less than 25 percent.

D. Thermal Movements: Allow for thermal movements from ambient and surface temperature changes.

1. Temperature Change: 120 deg F (67 deg C), ambient; 180 deg F (100 deg C), material surfaces.

2.2 SHEET METALS

A. General: Protect mechanical and other finishes on exposed surfaces from damage by applying strippable, temporary protective film before shipping.

B. Aluminum Sheet: ASTM B 209 (ASTM B 209M), alloy as standard with manufacturer for finish required, with temper as required to suit forming operations and performance required.

1. Exposed Coil-Coated Finish:

076200 - 3

SHEET METAL

FLASHING AND

TRIM

a. Two-Coat Fluoropolymer: AAMA 620. Fluoropolymer finish containing not less than 70 percent PVDF resin by weight in color coat. Prepare, pretreat, and apply coating to exposed metal surfaces to comply with coating and resin manufacturers' written instructions.

2. Colors: As selected by CO from Manufacturer’s full range.

C. Stainless-Steel Sheet: ASTM A 240/A 240M, Type 304, dead soft, fully annealed; 2D (dull, cold rolled) finish.

D. Metallic-Coated Steel Sheet: Provide zinc-coated (galvanized) steel sheet according to ASTM A 653/A 653M, G90 (Z275) coating designation; prepainted by coil-coating process to comply with ASTM A 755/A 755M.

1. Exposed Coil-Coated Finish:

a. Two-Coat Fluoropolymer: AAMA 621. Fluoropolymer finish containing not less than 70 percent PVDF resin by weight in color coat. Prepare, pretreat, and apply coating to exposed metal surfaces to comply with coating and resin manufacturers' written instructions.

2. Colors: As selected by CO from Manufacturer’s full range.

2.3 UNDERLAYMENT MATERIALS

A. Felt: ASTM D 226/D 226M, Type II (No. 30), asphalt-saturated organic felt;

nonperforated.

B. Self-Adhering, High-Temperature Sheet: Minimum 30 mils (0.76 mm) thick, consisting of a slip-resistant polyethylene- or polypropylene-film top surface laminated to a layer of butyl- or SBS-modified asphalt adhesive, with release-paper backing; specifically designed to withstand high metal temperatures beneath metal roofing. Provide primer according to written recommendations of underlayment manufacturer.

1. Products: Subject to compliance with requirements, available products that may be incorporated into the Work include, but are not limited to, the following:

a. Carlisle Residential, a division of Carlisle Construction Materials;

WIP 300HT.

b. Grace Construction Products, a unit of W. R. Grace & Co.-Conn.; Grace Ice and Water Shield HT.

c. Henry Company; Blueskin PE200 HT.

d. Kirsch Building Products, LLC; Sharkskin Ultra SA.

e. Metal-Fab Manufacturing, LLC; MetShield.

f. Owens Corning; WeatherLock Specialty Tile & Metal Underlayment.

g. Polyguard Products, Inc.; Deck Guard HT.

076200 - 4

SHEET METAL

FLASHING AND

TRIM

h. Protecto Wrap Company; Protecto Jiffy Seal Ice & Water Guard HT.

i. SDP Advanced Polymer Products Inc; Palisade SA-HT.

2. Thermal Stability: ASTM D 1970; stable after testing at 240 deg F (116 deg C) or higher.

3. Low-Temperature Flexibility: ASTM D 1970; passes after testing at minus 20 deg F (29 deg C) or lower.

C. Slip Sheet: Rosin-sized building paper, 3 lb/100 sq. ft. (0.16 kg/sq. m) minimum.

2.4 MISCELLANEOUS MATERIALS

A. General: Provide materials and types of fasteners, solder, protective coatings, sealants, and other miscellaneous items as required for complete sheet metal flashing and trim installation and as recommended by manufacturer of primary sheet metal or manufactured item unless otherwise indicated.

B. Fasteners: Wood screws, annular threaded nails, self-tapping screws, self-locking rivets and bolts, and other suitable fasteners designed to withstand design loads and recommended by manufacturer of primary sheet metal or manufactured item.

1. General: Blind fasteners or self-drilling screws, gasketed, with hex-washer head.

a. Exposed Fasteners: Heads matching color of sheet metal using plastic caps or factory-applied coating. Provide metal-backed EPDM or PVC sealing washers under heads of exposed fasteners bearing on weather side of metal.

b. Blind Fasteners: High-strength aluminum or stainless-steel rivets suitable for metal being fastened.

c. Spikes and Ferrules: Same material as gutter; with spike with ferrule matching internal gutter width.

2. Fasteners for Aluminum Sheet: Aluminum or Series 300 stainless steel.

3. Fasteners for Stainless-Steel Sheet: Series 300 stainless steel.

4. Fasteners for Zinc-Coated (Galvanized) Steel Sheet: Series 300 stainless steel or hot-dip galvanized steel according to ASTM A 153/A 153M or ASTM F 2329.

C. Solder:

1. For Stainless Steel: ASTM B 32, Grade Sn60, with acid flux of type recommended by stainless-steel sheet manufacturer.

2. For Zinc-Coated (Galvanized) Steel: ASTM B 32, Grade Sn50, 50 percent tin and

50 percent lead or Grade Sn60, 60 percent tin and 40 percent lead.

D. Sealant Tape: Pressure-sensitive, 100 percent solids, polyisobutylene compound sealant tape with release-paper backing. Provide permanently elastic, nonsag, nontoxic, nonstaining tape 1/2 inch (13 mm) wide and 1/8 inch (3 mm) thick.

076200 - 5

SHEET METAL

FLASHING AND

TRIM

E. Elastomeric Sealant: ASTM C 920, elastomeric silicone polymer sealant; of type, grade, class, and use classifications required to seal joints in sheet metal flashing and trim and remain watertight.

2.5 FABRICATION, GENERAL

A. General: Custom fabricate sheet metal flashing and trim to comply with details shown and recommendations in cited sheet metal standard that apply to design, dimensions, geometry, metal thickness, and other characteristics of item required. Fabricate sheet metal flashing and trim in shop to greatest extent possible.

1. Obtain field measurements for accurate fit before shop fabrication.

2. Form sheet metal flashing and trim to fit substrates without excessive oil canning, buckling, and tool marks; true to line, levels, and slopes; and with exposed edges folded back to form hems.

3. Conceal fasteners and expansion provisions where possible. Do not use exposed fasteners on faces exposed to view.

B. Expansion Provisions: Form metal for thermal expansion of exposed flashing and trim.

1. Form expansion joints of intermeshing hooked flanges, not less than 1 inch (25

mm) deep, filled with butyl sealant concealed within joints.

2. Use lapped expansion joints only where indicated on Drawings.

C. Sealant Joints: Where movable, nonexpansion-type joints are required, form metal to provide for proper installation of elastomeric sealant according to cited sheet metal standard.

D. Fabricate cleats and attachment devices from same material as accessory being anchored or from compatible, noncorrosive metal.

E. Fabricate cleats and attachment devices of sizes as recommended by cited sheet metal standard for application, but not less than thickness of metal being secured.

F. Seams: Fabricate nonmoving seams with flat-lock seams. Form seams and seal with elastomeric sealant unless otherwise recommended by sealant…