Attachment 07 - Deliverables.xlsx

XLSX spreadsheet 27 KB Posted

Attached to
High Energy Rail (HE-Rail) Large-Scale Fixed Systems
Solicitation number
12012025
Issued by

About this file

This file is a Deliverables Attachment (Attachment 07) for a High Energy Rail (HE-Rail) Large-Scale Fixed Systems contract with U.S. Customs and Border Protection (CBP), detailing comprehensive submission requirements across multiple project phases. The deliverables are organized into six primary sections: System Deliverables (S-series), Design/Construction Deliverables (D-series), Training Requirements (TR-series), Testing Requirements (TE-series), and Lifecycle Sustainment Requirements (L-series), with specific deadlines ranging from 14 days to 120 days after contract award.

Key deliverables include a Contract Kick-Off Meeting within 30 days of award, monthly progress reports due on the 10th of each month, weekly status reports, multiple design review submissions, safety plans, equipment installation data, site survey reports, training design plans, instructor and student guides, system user manuals, acceptance test plans, radiological survey reports, preventative maintenance schedules, technical documentation packages, and warranty certificates. Most deliverables are to be submitted to the Contracting Officer's Representative (COR) or specific CBP divisions, with review periods typically ranging from 30 to 90 days, emphasizing a structured approach to project documentation and compliance.

View the file

Other files

Show all 12

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Sheet1 Deliverable Identification Number (DIN): Deliverable Section Due Date Due to Template tc={0BB54775-5E88-49A0-8162-ED4F83AD4676}: [Threaded comment]

Your version of Excel allows you to read this threaded comment; however, any edits to it will get removed if the file is opened in a newer version of Excel. Learn more: https://go.microsoft.com/fwlink/?linkid=870924

Comment:

Consider additional column indicating format requirements - hardcopy, electronic, word, pdf, laminated etc

Statement of Work
S001Contract Kick-Off MeetingAllNo more 30 days after contract award.

tc={9B63E2D4-A5BB-485C-A86E-CD501A434691}: [Threaded comment]

Your version of Excel allows you to read this threaded comment; however, any edits to it will get removed if the file is opened in a newer version of Excel. Learn more: https://go.microsoft.com/fwlink/?linkid=870924

Comment:

The SOW suggests that the kick-off meeting has to be scheduled within 30 days but not necessarily held within that time. This implies that it must be held within 30 days (it should be sooner to avoid losing a whole month before the contract gets under way). Are there related documents and reports due for/ from this meeting?

October 29, 2025 at 9:18 AM

CORNO
S002Delivery ScheduleAllNo more 30 days after contract award.

tc={7EC65899-2D07-491D-BBBF-D07B785D05EE}: [Threaded comment]

Your version of Excel allows you to read this threaded comment; however, any edits to it will get removed if the file is opened in a newer version of Excel. Learn more: https://go.microsoft.com/fwlink/?linkid=870924

Comment:

What would the contract say about delivery of systems if the Delivery Schedule isn't due until 30 days after contract award?NIID/CORNO
S003System DeliveryAllNo more 60 days from the date of delivery order execution.NIID/CORNO
S004Project Management PlanAllNo more 14 days after contract award.

tc={1EA36FEE-A0D9-45D8-A1C2-DF031B294BC0}: [Threaded comment]

Your version of Excel allows you to read this threaded comment; however, any edits to it will get removed if the file is opened in a newer version of Excel. Learn more: https://go.microsoft.com/fwlink/?linkid=870924

Comment:

Will a draft of the PMP be required to be submitted with the Phase II proposal to facilitate evaluation of the Management Approach factor??NIID/CORNO
S005Monthly Progress ReportsAllOn the 10th of each month. If the 10th is a weekend or holiday, it is due the next working day.NIID/CORYes - Appendix C

tc={3083EC9B-425C-4EC7-8443-79E65049FB43}: [Threaded comment]

Your version of Excel allows you to read this threaded comment; however, any edits to it will get removed if the file is opened in a newer version of Excel. Learn more: https://go.microsoft.com/fwlink/?linkid=870924

[Tasks]

There is a task anchored to this comment that cannot be viewed in your client.

Comment:

@GRUEBELE, DONOVAN M. or @LAO, DALMACIO (CTR) any update on this? I think this is the only thing we need to finalize for this. If we know the title of it we can probably close this out and make it Appendix A.

Reply:

I think we can call it Appendix A.

Reply:

Dan is still working on the report template.

Reply:

There should be a separate HE Rail Appendix unrelated to MEP/LEP.

S006 Integrated Master Schedule Reporting 3 Weekly (day to be determined) Business Operations Division/NIID/COR YES - CBP IMS (to be provided after award)

S007Instance Progress Reports, Inspection Reports, Test Results, Burn-in period Daily Logs4.2.2Daily during the burn-in period.NIID/CORNO
Attachment 03, Design, Construction and Installation
D001Safety Plan2First submission – 90 days after award

Review - Government has 30 days to review and comment.

Updates – as necessary.NIID/CORNO
D002Equipment Installation Data2.1.First submission due 30 days after award.

Government has 45 days to review and comment from time of award.

Final due 45 days after Government review.NIID/CORNO
D003Site Survey Report2.2.1.120 days prior to Site Acceptance TestNIID/CORNO
D004Design Reviews

System and Conceptual Design Review 50% Design Review 95% Desgin Review IFC Design Review Factory Test Design Review 2.3, 2.4 2.3, 2.5 2.3, 2.6 2.3, 2.6 2.3 60 days after contract award Dependent on conceptual acceptance Dependent on 50% acceptance 120 days after contract award

150 days after contract awardNIID/CORNO
D005Engineering Assessment and Construction Drawings Package2.2.2.Prelimary due 90 days prior to Site Acceptance Test
Final due 60 days prior to Site Acceptance TestNIID/CORNO
D006Installation Plan and Checklist2.2.3.Preliminary due at time of Construction Kick-Off
Final due 45 days prior to Site Acceptance TestNIID/CORNO
D007Construction Schedule

High-level Key Milestone Timeline

Detailed and Phased Construction Schedule3.1Prelimiary due 30 days prior to Construction kick-off meeting
Final due at time of CKOMNIID/CORNO
D008Construction Kick-Off Meeting3.230 days prior to breaking groundNIID/CORNO
D009Certified (As-Built) Construction Drawings6.230 days after Site AcceptanceCORNO
Attachment 04, Training Requirements
TR001Weekly Status Report2.2WeeklyOTD/NIID/CORNO
TR002Training Design Plan2.3No more than 14 days after contract award.OTD/NIID/CORNO
TR003Instructor Guide2.4No more than 60 days after contract award.OTD/NIID/CORNO
TR004Student Guide2.5No more than 60 days after contract award.OTD/NIID/CORNO
TR004System User's Manual4.1First submission - 120 days prior to first site acceptance test.

Review - Government has 60 days to review and comment.

Final - Due 30 days after receipt of comments.

Updates - shall be provided as changes are made to the design/configuration affecting system operation.OTD/NIID/CORNO
TR005Operational/Storage Checklist4.2No more than 60 days after contract awardOTD/NIID/CORNO
TR006Operator Service and Maintenance Manual4.3First submission - 120 days prior to expiration of first system warranty.

Review - Government has 90 days to review and comment.

Final - Due 30 days after receipt of comments.

Updates - shall be provided as changes are made to the design/configuration affecting system maintenance.OTD/NIID/CORNO
TR007Image Analysis Exercises/Manual1No more than 60 days after contract awardOTD/NIID/CORNO
TR008Image Interpretation Software1No more than 60 days after contract awardOTD/NIID/CORNO
TR009Contractor Supplied Laptops with images and software loaded for Image Exercises1No more than 60 days after contract awardOTD/NIID/CORNO
TR009Operator Training Video1No more than 60 days after contract awardOTD/NIID/CORNO
Attachment 05, Testing Requirements
TE001Acceptance Test Plan2.2Preliminary due 90 days prior to first testing.

Subsequent draft ATPs due 30 days prior to test.

Final due 15 days prior to any testing.

NIID/CORNO
TE002Radiological Survey Report3.2Upon delivery of each system and then annually thereafter.Accompanied with the system;
Copies to CORNO
TE003Radiation Survey/Leak Test Report2.4, 3.2, 3.3Final reports of initial surveys or tests are due at site acceptance of system.
Subsequent Radiation Survey Reports are due annually.ILD Operations Center/CORNO
Attachment 06, Lifecycle Sustainment and Support Requirements
L001Reports (Sustainment Report, After-Action Report1.1MonthyILD MDC/CORNO
L002Preventative Maintenance Schedule1.6MonthlyILD Maintenance Management /NIID/CORNO
L003As-Built Configuration Baseline Report6With the delivery of each systemILD Maintenance Management /NIID/CORNO
L005Hazardous Materials List and Safety Data Sheets5First submission included with proposal. Government has 120 days to review and comment from time of award. Final due 60 days after Government review.NIID/CORNO
L006Technical Documentation Package7First submission - 90 days prior to first site acceptance testing.

Review - CBP has 30 days to review and comment.

Final - 5 working days prior to start of testing.

Updates - Required whenever changes are necessary.ILD Maintenance Management /CORNO
L007Warranty Certificates and Documentation9First submission - 30 days prior to site acceptance of the first system.

Review - Government has 30 days to review and comment.

Updates - provided monthly until all warranties have expired. ILD Maintenance Management /NIID/COR NO tc={DE6135BA-A550-476A-8A3F-8C7F7539275F}: [Threaded comment]

Your version of Excel allows you to read this threaded comment; however, any edits to it will get removed if the file is opened in a newer version of Excel. Learn more: https://go.microsoft.com/fwlink/?linkid=870924

Comment:

Check for Deliverables in all Attachments of the SOW. For instance, in Attachment 9 Section 7 there is a requirement for the Contractor to deliver a QA Assessment Report after each PMR. This is not included in Attachment 7.

Consider additional column indicating format requirements - hardcopy, electronic, word, pdf, laminated etc

The SOW suggests that the kick-off meeting has to be scheduled within 30 days but not necessarily held within that time. This implies that it must be held within 30 days (it should be sooner to avoid losing a whole month before the contract gets under way). Are there related documents and reports due for/ from this meeting?

October 29, 2025 at 9:18 AM

What would the contract say about delivery of systems if the Delivery Schedule isn't due until 30 days after contract award?

Will a draft of the PMP be required to be submitted with the Phase II proposal to facilitate evaluation of the Management Approach factor??

@GRUEBELE, DONOVAN M. or @LAO, DALMACIO (CTR) any update on this? I think this is the only thing we need to finalize for this. If we know the title of it we can probably close this out and make it Appendix A.

I think we can call it Appendix A.

Dan is still working on the report template.

There should be a separate HE Rail Appendix unrelated to MEP/LEP.

Check for Deliverables in all Attachments of the SOW. For instance, in Attachment 9 Section 7 there is a requirement for the Contractor to deliver a QA Assessment Report after each PMR. This is not included in Attachment 7.