This document is a Forest Service Supplemental Specification for the San Juan Williams Creek Road and Spur Resurfacing project. The specifications provide detailed technical requirements and modifications to standard construction practices for road reconstruction, including specific guidelines for aggregate courses, road reconditioning, weed prevention, and temporary traffic control.
Key technical requirements include reshaping roadbeds, cleaning ditches, preparing surfaces, and placing commercially purchased aggregate (CDOT class 6 1"-minus road base material) with specific placement and compaction methods. The project involves reconstructing 2.2 miles of road within the Williams Creek Campground, with specifications for maintaining road crown, width, and surface quality. Contractors must follow strict requirements for equipment washing to prevent weed spread, install temporary traffic control signs, and prepare a traffic control plan certified by the American Traffic Safety Services Association (ATSSA).
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 1240LT25R0024_A0001.pdf | ||
| Attachment 04_StandardSpecList.pdf | ||
| Attachment 02_Schedule of Items.xlsx | XLSX spreadsheet | |
| Attachment 01_Statement of Work.pdf | ||
| Attachment 03_Williams Creek CG Roads - Signed.pdf | ||
| Attachment 06_WD_CO20250012.pdf | ||
| 1240LT25R0024_Final.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
FSSS – San Juan Williams Creek Road and Spur Resurfacing
Table of Contents
Table of Contents
Preface
101 - Terms, Format, and Definitions
102 - Bid, Award, and Execution of Contract
103 - Scope of Work
104 - Control of Work
105 - Control of Material
106 - Acceptance of Work
107 - Legal Relations and Responsibility to the Public
108 - Prosecution and Progress
109 - Measurement and Payment
153 - Contractor Quality Control
155 - Schedules for Construction Contracts
156 - Public Traffic
171 - Weed and Disease Prevention
301 - Untreated Aggregate Courses
303 - Road Reconditioning
635 - Temporary Traffic Control
NOTE: Refer to https://highways.dot.gov/federal-lands/specs FOR
THE FULL VERSION OF THE FP-14. ALL CHANGES, ADDITIONS, AND
MODIFICATIONS ARE NOTED HEREIN.
Preface
Preface_wo_03_15_2004_m
Delete all but the first paragraph and add the following:
The Forest Service, US Department of Agriculture has adopted FP-03 for construction of
National Forest System Roads.
101 - Terms, Format, and Definitions
101.00_nat_us_07_25_2005
101.01_nat_us_01_22_2009
101.01 Meaning of Terms
Delete all references to the TAR (Transportation Acquisition Regulations) in the specifications.
101.03_nat_us_06_16_2006
101.03 Abbreviations.
Add the following to (a) Acronyms:
AFPA
MSHA
NIST
NESC
WCLIB
American Forest and Paper Association
Mine Safety and Health Administration
National Institute of Standards and Technology
National Electrical Safety Code
West Coast Lumber Inspection Bureau
Add the following to (b) SI symbols:
mp Milepost ppm Part Per Million https://highways.dot.gov/federal-lands/specs http://www.nist.gov/
101.04_nat_us_03_29_2007
101.04 Definitions.
Delete the following definitions and substitute the following:
Bid Schedule--The Schedule of Items.
Bridge--No definition.
Contractor--The individual or legal entity contracting with the Government for performance of prescribed work. In a timber sale contract, the contractor is the “purchaser”.
Culvert--No definition.
Right-of-Way--A general term denoting (1) the privilege to pass over land in some particular line (including easement, lease, permit, or license to occupy, use, or traverse public or private lands), or (2) Real property necessary for the project, including roadway, buffer areas, access, and drainage areas.
Add the following:
Adjustment in Contract Price--“Equitable adjustment,” as used in the Federal Acquisition
Regulations, or “construction cost adjustment,” as used in the Timber Sale Contract, as applicable.
Change--“Change” means “change order” as used in the Federal Acquisition Regulations, or
“design change” as used in the Timber Sale Contract.
Design Quantity--“Design quantity” is a Forest Service method of measurement from the FS-96
Forest Service Specifications for the Construction of Roads and Bridges. Under these FP specifications this term is replaced by the term “Contract Quantities”.
Forest Service--The United States of America, acting through the Forest Service, U.S.
Department of Agriculture.
Neat Line--A line defining the proposed or specified limits of an excavation or structure.
Pioneer Road--Temporary construction access built along the route of the project.
Purchaser--The individual, partnership, joint venture, or corporation contracting with the
Government under the terms of a Timber Sale Contract and acting independently or through agents, employees, or subcontractors.
Protected Streamcourse--A drainage shown on the plans or timber sale area map that requires designated mitigation measures.
Road Order--An order affecting and controlling traffic on roads under Forest Service jurisdiction. Road Orders are issued by a designated Forest Officer under the authorities of 36
CFR, part 260.
Schedule of Items--A schedule in the contract that contains a listing and description of construction items, quantities, units of measure, unit price, and amount.
Utilization Standards--The minimum size and percent soundness of trees described in the specifications to determine merchantable timber.
Add Figure 101-1—Illustration of road structure terms:
Figure 101-1—Illustration of road structure terms.
102 - Bid, Award, and Execution of Contract
102.00_nat_us_02_16_2005
102 Bid, Award, and Execution of Contract
Delete Section 102 in its entirety.
103 - Scope of Work
103.00_nat_us_02_16_2005
Deletions
Delete all but subsection 103.01 Intent of Contract.
104 - Control of Work
104.00_nat_us_06_16_2006
Deletions
Delete Sections 104.01, 104.02, and 104.04.
104.06_nat_us_02_17_2005
Add the following subsection:
104.06 Use of Roads by Contractor
The Contractor is authorized to use roads under the jurisdiction of the Forest Service for all activities necessary to complete this contract, subject to the limitations and authorizations designated in the Road Order(s) or described in the contract, when such use will not damage the roads or national forest resources, and when traffic can be accommodated safely.
105 - Control of Material
105.02_nat_us_01_18_2007
105.02 Material Sources.
105.02(a) Government-provided sources.
Add the following:
Comply with the requirements of 30 CFR 56, subparts B and H. Use all suitable material for aggregate regardless of size unless otherwise designated. When required, re-establish vegetation in disturbed areas according to section 625.
105.05_nat_us_05_12_2004
105.05 Use of Material Found in the Work.
Delete 105.05 (a) and (b) and the last sentence of the second paragraph and substitute the following:
Materials produced or processed from Government lands in excess of the quantities required for performance of this contract are the property of the Government. The Government is not obligated to make reimbursement for the cost of producing these materials.
106 - Acceptance of Work
106.01_nat_us_07_31_2007
106.01 Conformity with Contract Requirements.
Delete Subsection 106.01 and substitute the following:
Follow the requirements of FAR Clause 52.246-12 Inspection of Construction.
References to standard test methods of AASHTO, ASTM, GSA, and other recognized standard authorities refer to the methods in effect on the date of solicitation for bids.
Perform all work to the lines, grades, cross-sections, dimensions, and processes or material requirements shown on the plans or specified in the contract.
Incorporate manufactured materials into the work according to the manufacturer’s recommendations or to these specifications, whichever is more strict.
Plan dimensions and contract specification values are the values to be strived for and complied with as the design values from which any deviations are allowed. Perform work and provide material that is uniform in character and reasonably close to the prescribed value or within the specified tolerance range. The purpose of a tolerance range is to accommodate occasional minor variations from the median zone that are unavoidable for practical reasons.
When standard manufactured items are specified (such as fence, wire, plates, rolled shapes, pipe conduits, etc., that are identified by gauge, unit mass, section dimensions, etc.), the identification will be considered to be nominal masses or dimensions. Unless specific contract tolerances are noted, established manufacturing tolerances will be accepted.
The Government may inspect, sample, or test all work at any time before final acceptance of the project. When the Government tests work, copies of test reports are furnished to the Contractor upon request. Government tests may or may not be performed at the work site. If Contractor testing and inspection is verified by the Government, the Contractor’s results may be used by the Government to evaluate work for acceptance. Do not rely on the availability of Government test results for process control.
Acceptable work conforming to the contract will be paid for at the contract unit bid price. Four methods of determining conformity and accepting work are described in Subsections 106.02 to
106.05 inclusive. The primary method of acceptance is specified in each Section of work. However, work may be rejected at any time it is found by any of the methods not to comply with the contract.
Remove and replace work that does not conform to the contract, or to prevailing industry standards where no specific contract requirements are noted, at no cost to the Government.
(a) Disputing Government test results. If the accuracy of Government test results is disputed, promptly inform the CO. If the dispute is unresolved after reasonable steps are taken to resolve the dispute, further evaluation may be obtained by written request. Include a narrative describing the dispute and a proposed resolution protocol that addresses the following:
Sampling method;
1. Number of samples;
2. Sample transport;
3. Test procedures;
4. Testing laboratories;
5. Reporting;
6. Estimated time and costs; and
7. Validation process.
If the evaluation requires additional sampling or testing be performed, mutually agree with the Government on witnessing procedures and on sampling and testing by a third party laboratory. Use a third party laboratory accredited by the AASHTO accreditation program.
Provide proof of the laboratory’s accreditation for the test procedures to be used. Do not use the same laboratory that produced the disputed Government test results or that produced the test results used as a basis for the dispute.
The CO will review the proposed resolution protocol and may modify it before final approval and execution.
The Government will use the approved resolution protocol test results to determine the validity of the disputed testing. If the Government test results are validated, the Contractor will be responsible for all costs associated with developing and performing the resolution protocol. If the Government test results are not validated, the Government will be responsible for all costs associated with developing and performing the resolution protocol.
If the validity of the Government test results cannot be determined, the Contractor and
Government will equally share all costs associated with developing and carrying out the resolution protocol.
(b) Alternatives to removing and replacing non-conforming work. As an alternative to removal and replacement, the Contractor may submit a written request to:
(1) Have the work accepted at a reduced price; or
(2) Be given permission to perform corrective measures to bring the work into conformity.
The request must contain supporting rationale and documentation. Include references or data justifying the proposal based on an evaluation of test results, effect on service life, value of material or work, quality, aesthetics, and other tangible engineering basis. The CO will determine disposition of the nonconforming work.
106.07_nat_us_05_11_2004
106.07 Delete
Delete subsection 106.07.
107 - Legal Relations and Responsibility to the Public
107.05_nat_us_05_11_2004
107.05 Responsibility for Damage Claims.
Delete the entire subsection.
107.06_nat_us_06_16_2006
107.06 Contractor’s Responsibility for Work.
Delete the following from the first paragraph.
“except as provided in Subsection 106.07”.
107.09_nat_us_06_16_2006
107.09 Legal Relationship of the Parties.
107.10_nat_us_06_16_2006
107.10 Environmental Protection.
Add the following:
Design and locate equipment repair shops, stationary refueling sites, or other facilities to minimize the potential and impacts of hazardous material spills on Government land.
Before beginning any work, submit a Hazardous Spill Plan. List actions to be taken in the event of a spill. Incorporate preventive measures to be taken, such as the location of mobile refueling facilities, storage and handling of hazardous materials, and similar information. Immediately notify the CO of all hazardous material spills. Provide a written narrative report form no later than 24 hours after the initial report and include the following:
• Description of the item spilled (including identity, quantity, manifest number, and other identifying information).
• Whether amount spilled is EPA or state reportable, and if so whether it was reported, and to whom.
• Exact time and location of spill including a description of the area involved.
• Containment procedures.
• Summary of any communications the Contractor had with news media, Federal, state and local regulatory agencies and officials, or Forest Service officials.
• Description of clean-up procedures employed or to be employed at the site including final disposition and disposal location of spill residue.
When available provide copies of all spill related clean up and closure documentation and correspondence from regulatory agencies.
The Contractor is solely responsible for all spills or leaks that occur during the performance of this contract. Clean up spills or leaks to the satisfaction of the CO and in a manner that complies with Federal, state, and local laws and regulations.
108 - Prosecution and Progress
108.00_nat_us_02_16_2005
108 Delete.
Delete Section 108 in its entirety.
109 - Measurement and Payment
109.00_nat_us_02_17_2005
109 Deletions
Delete the following entire subsections:
109.06 Pricing of Adjustments.
109.07 Eliminated Work.
109.08 Progress Payments.
109.09 Final Payment.
109.02_nat_us_06_16_2006
109.02 Measurement Terms and Definitions.
(b) Contract quantity.
Contract quantities will be adjusted only when there are errors in the original design of 15% or more.
Change the following:
“(b) Cubic yard” to “(c) Cubic yard”.
153 - Contractor Quality Control
153.04_nat_us_10_24_2007
153.04 Records.
Delete all but the first sentence
155 - Schedules for Construction Contracts
155.00_nat_us_05_11_2004
155 Delete.
Delete Section 155 in its entirety.
156 - Public Traffic
156.03_nat_us_02_24_2005
156.03 Accommodating Traffic During Work.
Delete the following from the last paragraph:
according to Subsection 106.07(b)
156.08_nat_us_02_24_2005
156.08 Traffic and Safety Supervisor.
Delete this subsection in its entirety.
171 - Weed and Disease Prevention
171.00_nat_us_03_30_2005
Description
171.01 This work consists of washing and treating construction equipment to remove seeds, plants, and plant fragments from the equipment before the equipment is used on National Forest
System lands.
Construction Requirements
171.03 General. Notify the CO in writing at least 15 days before moving any construction equipment onto National Forest System lands. Construction equipment does not include cars, pickup trucks, and other vehicles that regularly travel between the construction site and areas outside of National Forest System lands.
Provide the CO with an opportunity to monitor the washing and inspection.
Equipment. Use a high pressure washing system.
171.05 Washing. Wash the sides, tops, and undercarriages of all construction equipment.
Remove all seeds, plants, plant fragments, dirt, and debris from the construction equipment.
171.06 Inspection. Inspect the washed construction equipment, including the undercarriage, to ensure that the washing removed the dirt, debris, and seeds from the construction equipment.
Rewash the construction equipment as necessary or as directed.
171.07 Acceptance. Weed prevention will be evaluated under Subsection 106.02.
Measurement
171.08 Do not measure weed prevention for payment.
Payment
171.09 Include all costs associated with the Section 171-Weed Prevention in the unit price for
Section 151-Mobilization.
301 - Untreated Aggregate Courses
301.00_nat_us_03_03_2005
301 Title Change.
Change the title to: Section 301 Aggregate Courses
301.01_nat_us_03_03_2005
301.03 General.
Add the following:
Written approval of the roadbed is required before placing aggregate.
After processing on the road, remove all oversize material from the road and dispose of it as directed by the CO.
Provide additives or binder, if required, at the proportions specified.
Develop and use Government furnished sources according to Section 105.
301.04_nat_us_03_03_2005
301.04 Mixing and Spreading.
Delete the first sentence of the first paragraph and add the following:
Ensure that aggregate and any required additives, water, mineral filler, and binder are mixed by the specified method except, if crushed aggregate products are being produced and mineral filler, binder, or additives are required, uniformly blend following crushing. Control additive proportions to 0.5 percent dry weight.
(a) Road Mix Method. After placing the aggregate for each layer, mix it with other required materials at the required moisture content until the mixture is uniform throughout. Mix aggregate, water, and all other materials until a uniform distribution is obtained.
Spread the aggregate in a uniform layer, with no segregation of size, and to a loose depth that will provide the required compacted thickness.
Route and distribute hauling and leveling equipment over the width and length of each layer.
(b) Road Mix Method. Before placing the commercially supplied aggregate, the existing surfacing course is to be windrowed. Place commercially supplied aggregate in a second windrow. The windrows will then be blended at the required moisture content until the mixture is uninform throughout.
Spread the aggregate in a uniform layer, with no segregation of size, and to a loose depth that will provide the required compacted thickness.
Route and distribute hauling and leveling equipment over the width and length of each layer.
301.05_nat_us_05_17_2005
301.06_nat_us_03_03_2005
301.06 Surface Tolerance.
Add the following:
Thickness and Width requirements:
The maximum variation from the compacted specified thickness is 1 inch. The compacted thickness is not consistently above or below the specified thickness and the average thickness of
4 random measurements for any ½ mile of road segment is within +OR- 1 inch of the specified thickness.
301.10_nat_us_03_03_2005
301.10 Payment
Delete the following:
Adjusted according to Subsection 106.05
303 - Road Reconditioning
303.00_0213_us_04_05_2006
303.01 Work.
Delete and replace with the following:
This work consists of reconditioning ditches, shoulders, roadbeds, parking areas, and turnouts.
303.03 Ditch Reconditioning.
Remove all slide material, sediment, vegetation, and other debris from the existing ditches and culvert inlets and outlets. Reshape ditches and culvert inlets and outlets to achieve positive drainage and a uniform ditch width, depth, and grade.
303.04 Shoulder Reconditioning.
Remove all slide material, vegetation, and other debris from existing shoulders including shoulders of parking areas, turnouts, and other widened areas. Reshape shoulders.
303.05 Roadbed Reconditioning.
Remove all organic, deleterious, or oversize material larger than 6 inches from the top 6 inches of subgrade. Remove surface irregularities, and shape to provide a uniform surface. Compact according to Subsection 204.11.
303.06_nat_us_08_05_2008
303.06 Aggregate Surface Reconditioning.
Delete and replace with the following:
Repair soft and unstable areas to the full depth of the aggregate surface and according to Subsection
204.07. Scarify to the depth of the aggregate surface or to a depth of 6 inches, whichever is less, and remove surface irregularities. Reshape, finish, and compact the entire aggregate surface according to Subsection 301.05, Subsection 321.05, or Subsection 322.05 as applicable.
303.07 Roadway Reconditioning.
Perform all the applicable work described in Subsections 303.03 through 303.05. Maintain existing cross slope or crown.
303.08 Pulverizing.
303.09 Acceptance.
303.10 Measurement
Modify the second paragraph as follows:
Measure ditch reconditioning and shoulder reconditioning by the mile horizontally along the centerline of the roadway for each side of the roadway.
303.11 Payment.
Delete Table 303-1 and replace with the following:
303.11_nat_us_03_29_2005
T a b le
-1
S m p li n g a n d
T es ti n g R eq u ir e m en ts
R e p o r ti n g im e
B ef o re u si n g i w o rk
B ef o re p la ci ex t la y er
(1
M in im u m o f p o in ts p er p ro ct r.
p li t
S a m le
Y es w h en re q u es te d
P in t o f
S a m p li
P ro ce ss ed m at er ia l b ef in co rp o ra ti n g i rk
In -p la ce m p li
F r e q u e n c y er e ac ix tu re o r ch an g in at er ia l er y st
M e th o d s
S p e c if ic a ti o n s
A A
S H
T O
T
(1
R -1
M ar sh al l
A A
S H
T O
(1
R -1
M ar sh al l
A A
S H
T O
T o th er a p p ro v ro ce d u re s
C a te g ry
C a ra c te r is ti c
M o is tu re -d en si ty
M et h o
D is tu re -d en h o
E is tu re -d en h o
F is tu re -d en h o
G
In -p la ce d en o is tu co te n t
T y p e o f
A c c e p ta n c e
(S u b se c ti o n
M ea su re d a te st fo co n fo rm an ce
(1 .0
M a te ri a l o r
P ro d u c t
E x is ti n g R o ad ay
635 - Temporary Traffic Control
635.03_nat_us_05_13_2004
635.03 General.
Install temporary traffic control signs to temporary posts or approved temporary sign mounts.
635.03_0213_us_04_21_2005
635.03 General.
Add the following paragraph:
Supply a traffic control plan. The proposed plan shall be prepared by an American Traffic
Safety Services Association (ATSSA) certified company and shall be submitted at the pre-work conference. The traffic control plan and all signs used shall be in compliance with the Manual of
Uniform Traffic Control Devices (MUTCD). The Contracting Officer’s Representative (C.O.R.)
shall approve the traffic control plans in writing before any work begins. Payment for traffic control is incidental to and included under the pay item.