Attachment 03 Schedule of Material Submittal.xlsx
XLSX spreadsheet 21 KB Posted
- Attached to
- FA468624Q0024 Upgrade Electrical Overhead 940th
- Solicitation number
- FA468624Q0024
About this file
This document is an Attachment 03 Schedule of Material Submittal related to a federal contract opportunity. The contract opportunity, identified by Solicitation Number FA468624Q0024, is for the Upgrade Electrical Overhead 940th project at Beale AFB in California. The project has a range of magnitude between $25,000 and $100,000 and a NAICS code of 238210 with a $19 million size standard. It is 100% set aside for small businesses. Key submittal requirements include a project-specific form, construction schedule, contractor's health/safety/environment and QA/QC plans, work plan documents, demolition work plan, and various electrical components. Submittal deadlines range from NTP+7 days to before final acceptance. A site visit is scheduled on July 18, 2024 and proposals are due on July 26, 2024.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Solicitation Amendment FA468624Q00240001 SF 30.pdf | ||
| Solicitation Amendment - FA468624Q00240001.pdf | ||
| Attachment 06 RFI - Upgrade Electrical Overhead for 940 ARW SQ Ops AMU.pdf | ||
| Attachment 01 BAEY 1136627 - SON v1.docx | DOCX document | |
| Attachment 02 BAEY 1136627 Electrical Site Plan.pptx | PPTX presentation | |
| Attachment 04 Wage Determination CA20230007.txt | TXT text file | |
| Attachment 05 Contractor Entry Access List Form EAL.xlsx | XLSX spreadsheet |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Submittal 1
| SCHEDULE OF MATERIAL SUBMITTALS | PROJECT NUMBER | PROJECT NAME | SOLICITATION /CONTRACT NUMBER | ||||||||||||||||||
| BAEY 1136627 | UPGRADE ELECTRICAL OVERHEAD FOR 940 ARW SQ OPS AMU | FA468624Q0024 | |||||||||||||||||||
| TO BE COMPLETED BY PROJECT ENGINEER | TO BE COMPLETED BY CONTRACT ADMINISTRATOR | ||||||||||||||||||||
| LINE NUMBER | Note: 3 copies required per submittal. Government will retain all submittals. Provide an electronic copy for each submittal. | CERTIF. OF COMPLIANCE | SHOP DRAWINGS | COLOR SELECTION | MANUFATURUR'S RECOMMENDATION | CATALOG DATA | O&M RECOMMENDATIONS | CALCULATIONS | WARRANTY | DRAWINGS | REPORT | TEST RESULTS | REQUIRED SUBMISSION DATE | DATE TO CONTRACTING | DATE TO CIVIL ENGINEERING | RETURN SUSPENSE DATE | SUBMITTAL NUMBERS | APPROVED | DISAPPROVED | CONTRACTOR SUBMITTAL | FINAL APPROVAL |
| GENERAL | |||||||||||||||||||||
| Project Specific Form 66 | X | NTP + 3 | |||||||||||||||||||
| Construction Schedule | X | NTP + 7 | |||||||||||||||||||
| TCN Schedule (electronic required, hard copy optional) | X | NTP + 7 | |||||||||||||||||||
| Contractor's Health, Safety, and Environment Plan | X | NTP + 7 | |||||||||||||||||||
| Contractor's QA/QC Plan | X | NTP + 7 | |||||||||||||||||||
| Copy of Engineering License(s) of person or consultancy responsible for design | X | Design | |||||||||||||||||||
| WORK PLAN | |||||||||||||||||||||
| All submissions to be provided in hard copy and electronically unless noted otherwise. 65%, 95%, and 100% Work Plan Documents to include: | X | NTP + 21 (65%) NTP + 35 (95%) NTP + 45 (100%) | |||||||||||||||||||
| One-Line Diagram | |||||||||||||||||||||
| Technical Specifications | X | NTP+45 | |||||||||||||||||||
| DEMOLITION | |||||||||||||||||||||
| Demolition Work Plan | X | X | X | NTP+45 | |||||||||||||||||
| EXTERIOR ELECTRICAL | |||||||||||||||||||||
| Conduits | X | X | NTP+14 | ||||||||||||||||||
| Cables(med & low voltage) | X | X | X | X | NTP+14 | ||||||||||||||||
| Switches | X | X | NTP+14 | ||||||||||||||||||
| Contactors | X | X | X | NTP+14 | |||||||||||||||||
| Panels | X | X | NTP+14 | ||||||||||||||||||
| Breakers | X | X | NTP+14 | ||||||||||||||||||
| Controller | X | X | X | NTP+14 | |||||||||||||||||
| Junction Cabinet | X | X | X | X | X | NTP+14 | |||||||||||||||
| Heating Mat | X | X | X | X | X | X | X | X | NTP+14 | ||||||||||||
| CLOSEOUT | |||||||||||||||||||||
| Factory and Field Test Certificates, Logs and Test Results | X | Before Acceptance | |||||||||||||||||||
| Inspection Logbook | X | Before Acceptance | |||||||||||||||||||
| As Builts (electronic in AutoCAD and hard copies on Mylar) | X | Final + 7 |