Attachment 03 Schedule of Material Submittal.xlsx

XLSX spreadsheet 21 KB Posted

Attached to
FA468624Q0024 Upgrade Electrical Overhead 940th
Solicitation number
FA468624Q0024
Issued by

About this file

This document is an Attachment 03 Schedule of Material Submittal related to a federal contract opportunity. The contract opportunity, identified by Solicitation Number FA468624Q0024, is for the Upgrade Electrical Overhead 940th project at Beale AFB in California. The project has a range of magnitude between $25,000 and $100,000 and a NAICS code of 238210 with a $19 million size standard. It is 100% set aside for small businesses. Key submittal requirements include a project-specific form, construction schedule, contractor's health/safety/environment and QA/QC plans, work plan documents, demolition work plan, and various electrical components. Submittal deadlines range from NTP+7 days to before final acceptance. A site visit is scheduled on July 18, 2024 and proposals are due on July 26, 2024.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Submittal 1

SCHEDULE OF MATERIAL SUBMITTALSPROJECT NUMBERPROJECT NAMESOLICITATION /CONTRACT NUMBER
BAEY 1136627UPGRADE ELECTRICAL OVERHEAD FOR 940 ARW SQ OPS AMUFA468624Q0024
TO BE COMPLETED BY PROJECT ENGINEERTO BE COMPLETED BY CONTRACT ADMINISTRATOR
LINE NUMBERNote: 3 copies required per submittal. Government will retain all submittals. Provide an electronic copy for each submittal.CERTIF. OF COMPLIANCESHOP DRAWINGSCOLOR SELECTIONMANUFATURUR'S RECOMMENDATIONCATALOG DATAO&M RECOMMENDATIONSCALCULATIONSWARRANTYDRAWINGSREPORTTEST RESULTSREQUIRED SUBMISSION DATEDATE TO CONTRACTINGDATE TO CIVIL ENGINEERINGRETURN SUSPENSE DATESUBMITTAL NUMBERSAPPROVEDDISAPPROVEDCONTRACTOR SUBMITTALFINAL APPROVAL
GENERAL
Project Specific Form 66XNTP + 3
Construction ScheduleXNTP + 7
TCN Schedule (electronic required, hard copy optional)XNTP + 7
Contractor's Health, Safety, and Environment PlanXNTP + 7
Contractor's QA/QC PlanXNTP + 7
Copy of Engineering License(s) of person or consultancy responsible for designXDesign
WORK PLAN
All submissions to be provided in hard copy and electronically unless noted otherwise. 65%, 95%, and 100% Work Plan Documents to include:XNTP + 21 (65%) NTP + 35 (95%) NTP + 45 (100%)
One-Line Diagram
Technical SpecificationsXNTP+45
DEMOLITION
Demolition Work PlanXXXNTP+45
EXTERIOR ELECTRICAL
ConduitsXXNTP+14
Cables(med & low voltage)XXXXNTP+14
SwitchesXXNTP+14
ContactorsXXXNTP+14
PanelsXXNTP+14
BreakersXXNTP+14
ControllerXXXNTP+14
Junction CabinetXXXXXNTP+14
Heating MatXXXXXXXXNTP+14
CLOSEOUT
Factory and Field Test Certificates, Logs and Test ResultsXBefore Acceptance
Inspection LogbookXBefore Acceptance
As Builts (electronic in AutoCAD and hard copies on Mylar)XFinal + 7