This is a construction specifications document for the Palmetto Trail Enoree Passage Rehabilitation Design project at the USFS Enoree Ranger District in South Carolina, with project number 0812-FY23-8CO. The specifications detail requirements for trail construction, bridges, boardwalks, and related structures, including material standards, engineering requirements, and construction methods.

The document includes detailed specifications for constructing boardwalks (standard, elevated, and step-and-run types), trail bridges (including prefabricated steel and fiberglass truss designs), and bridge substructures. Key requirements include construction of bridges designed for 90 psf pedestrian live load, with additional vehicle load requirements ranging from 10,000 lbs (H-5 truck) to 20,000 lbs (H-10 truck) depending on bridge width. Materials specifications cover FRP composites, treated timber, hardware, and connections. The document includes two appendices specifically addressing Indian Creek 3.0 bridge components - one for an existing fiberglass truss bridge and another for AASHTO-based prefabricated bridge specifications. All work must meet AASHTO standards and includes requirements for quality assurance, measurement methods, and a 15-year warranty on structural components.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

PALMETTO TRAIL ENOREE PASSAGE

REHABILITATION DESIGN

Atriax, pllc, 703 Main Avenue, SW (28602), PO Box 1629, Hickory, NC 28603, Telephone: (828) 315-9962

INTEGRITY SERVICE EXCELLENCE

BID DOCUMENTS

SPECIFICATIONS FOR CONSTRUCTION

Project # 0812-FY23-8CO

SEPTEMBER 2024

Prepared For:

US Forest Service (USFS)

Submitted by:

Bid Documents September 2024 Palmetto Trail Enoree Passage Rehabilitation Design Project # 0812-FY23-8CO

Palmetto Trail Specifications-1

Table of Contents

Section

900. General Requirements

901. Terms, Format, Abbreviations, and Definitions

902. Intent of Contract

903. Control of Work

904. Control of Materials

905. Quality Assurance and Quantity of Measurement

906. Measurement and Payment

907. Mobilization

908. Construction Survey, Staking, Flagging and Cleanup

909. Maintenance for Traffic and Temporary Construction Access

909.10 Maintenance for Traffic

909.20 Temporary Construction Access

Construction Specifications

930. Trail Structures

938.00. Boardwalks

938.10. Standard Boardwalk

938.20. Elevated Boardwalk

938.30. Step and Run

938.40. Boardwalk Maintenance

939. Reserved for Trail Structures Special Project Specifications

960. Trail Bridges

962.00. Sawn Timber Trail Bridge

962.10. Sawn Timber Stringer Trail Bridge

966.00. Trail Bridge Maintenance

969. Reserved for Trail Bridge Special Project Specifications

970. Specialty Structures

Palmetto Trail Specifications-2

980. Incidentals

981.00. Seeding, Fertilizing and Mulching

982.00. Erosion Control Blankets

983.00. Removal of Structures and Obstructions

989.00. Reserved for Incidentals Special Project Specifications

990. Material

991.00. Rock, Grid Pavement Unit, Aggregate and Asphalt

991.01 Rock

991.05 Screened Aggregate

991.08 Cement

994.00. Geosynthetic Material

994.01 Geotextile

995.00. Material for Timber Structures

Appendices

Appendix A: Indian Creek 3.0 Existing Bridge - Fiberglass Truss Bridge Drawings Basis of Design and Bid

Appendix B: Indian Creek 3.0 Prefabricated Bridge Specifications-AASHTO Basis of Design and Bid

Palmetto Trail Specifications-3

Section 900 General Specifications

Palmetto Trail Specifications-4

Section 901 Terms, Format, Abbreviations and Definitions

901.01 Meaning of Terms. These specifications are generally written in the similar words or phrases. In material specifications, the subject may also be the supplier, fabricator, or manufacturer supplying material, products, or equipment for use on the project.

Wherever or similar words are used, the or of the Contracting Officer is intended.

Similarly, wherever or similar words are used, they mean or the Contracting Officer.

The word generally pertains to decisions or actions of the Contracting Officer.

Whenever in these specifications, or in other contract documents, the following terms (or pronouns in place of them) are used, the intent and meaning shall be interpreted as follows: reference to a specific standard, test, testing method, or specification shall mean the latest published edition or amendment that is in effect at the solicitation issue date for the public works contracts.

901.02 Specification Format These specifications are divided into Sections.

Sections 900 through 906, 908 and 909 consist of general contract requirements for which no direct payment is made. The requirements contained in Sections 900 through 906 are applicable to all contracts.

Sections 907, 908, 909 and 910 through 989 consist of construction contract requirements for specific items of work. Work under these Sections is paid for directly or indirectly according to Subsection 906.04 and the Section ordering the work. When there is no pay item in the bid schedule, no direct payment is made.

Sections 990 through 999 contain the material requirements for Sections 910 through 989. No direct payment is made in Sections 990 through 999. Payment for material is included as part of the work required in Sections 910 through 989.

The first three digits of the pay item number identify the Section under which the work is performed.

901.03 Abbreviations. Whenever these abbreviations are used in the specifications, they represent the following:

(a) Acronyms

AASHTO American Association Of State Highway And Transportation Officials ABS Acrylonitrile-Butadiene-Styrene

Palmetto Trail Specifications-5

AITC American Institute of Timber Construction ANSI American National Standards Institute AQ Actual Quantities APA American Plywood Association ASTM American Society For Testing And Material AWPA American Wood Protection Association CO Contracting Officer C.F. Cubic Feet C.Y. Cubic Yard DQ Design Quantities EA Each FAR Federal Acquisition Regulation g Grams HDPE High-Density Polyethylene hr Hour kg Kilogram kN Kilonewtons lb Pound L.F. Linear Feet LS Lump Sum LSQ Lump Sum Quantities m Meter m2 Square Meter m3 Cubic Meter mi Mile mm Millimeter MPa Megapascals MSE Mechanically Stabilized Earth N Newton NBS National Bureau Of Standards NCMA National Concrete Masonry Association OSHA Occupational Safety & Health Administration Pa Pascal PE Polyethylene PS Product Standard Issued By The U.S. Department Of Commerce psi Pounds Per Square Inch PVC Polyvinyl Chloride S.F. Square Feet SQ Staked Quantities S.Y. Square Yard WCLIB West Coast Lumber Inspection Bureau WWPA Western Wood Products Association WWPI Western Wood Preservers Institute

Palmetto Trail Specifications-6

Additional abbreviations may be found in Section 101.03 of the Standard Specifications for Construction of Roads and Bridges on Federal Highway Projects

(FP-03).

(b) Slope notation (vertical: horizontal). For slopes flatter than 1:1, express the slope as the ratio of one unit vertical to a number of units horizontal. For slopes steeper than 1:1, express the slope as the ratio of a number of units vertical to one unit horizontal.

901.04 Definitions The following terms, or pronouns in place of them, are used in these specifications or in other contract documents, the intent and meaning are as follows:

Barriers. A fence or other obstacle that prevents movement or access.

Base Course. The layer or layers of specified material of designed thickness placed on a trailbed to support surfacing.

Batter. A backward and upward slope of the face of a wall.

Berm. The ridge of material formed on the outer edge of the trail that projects higher than the tread.

Borrow. Suitable materials taken from approved sources designated on the plans or on the ground, to be used for embankments and backfilling.

Bridge. A trail structure, including supports, erected over a depression or obstruction such as a body of water, a road, a trail, or a railroad that provides a continuous pathway and that has a deck for carrying traffic or other loads.

Cap Rock. Rock placed in the top or uppermost layer in a constructed rock structure, such as a talus or rubble rock section or rock retaining wall.

Catch Point. The outer limits of a trailway where the excavation and/or embankment intersect with the ground line.

Clearing Limit. The area over and beside the trail that is cleared of trees, limbs, and other obstructions.

Climbing Turn. A reverse in direction of trail grade without a level landing used to change elevation on a steep slope.

Compacted. Consolidation that is obtained by tamping or rolling suitable material until no noticeable displacement of material is observed.

Contracting Officer (CO). An official of the Government with the authority to enter into, administer, and/or terminate contracts and make related determinations and findings. The term includes certain authorized representatives of the CO acting within the limits of their authority as delegated by the CO.

Culvert. Any structure with a bottom, regardless of the fill depth, the depth of invert, or the presence of a horizontal driving surface, or any bottomless (natural

Palmetto Trail Specifications-7 channel) structure with footings that does not have wheel loads in direct contact with the top of the structure.

Curb. A border defining the edge of the trail or trail bridge.

Cushion Material. Native or imported material generally placed over rocky section of unsurfaced trail to provide a usable and maintained traveled way.

Designated on the Ground. The location of materials, work areas, and construction items, including lines and grades, marked on the ground with stakes, flagging, tags, or paint.

Drawings. Design sheets or fabrication, erection, or construction details submitted to the Government by the Contractor according to FAR Clause 52.236-21 Specifications and Drawings for Construction. Also refers to submissions and submittals.

Duff. Organic material overlying rock or mineral soil.

Embankment. A structure of suitable material placed on the prepared ground surface and constructed to the trailbed elevation.

Excess Excavation. Material in the trailway in excess of that needed for construction of designed trailways.

Falsework. Temporary construction work on which a main work is wholly or partly built and supported until the main work is strong enough to support itself.

Ford. A water-level stream crossing constructed to provide a level surface for safe traffic passage.

Full Bench. Trailbed constructed entirely on undisturbed material.

Gabion Basket. Rectangular wire baskets filled with rock used as pervious, semiflexible building blocks for slope and foundation stabilization.

Grade. The vertical distance of ascent or descent of the trail expressed as a percentage of the horizontal distance.

Hazard Tree. An unstable tree that is likely to fall across the trail.

Header Rock. Rock laid with the narrow end towards the face of the wall.

Inslope. Where the trails tread is sloped downward toward the backslope.

Leave Tree. Trees designated to be left or to remain undisturbed after trail construction.

Mineral Soil. Soil or aggregate that is free from organic substances and contains no particles larger than 2 inches at their greatest dimension.

Outslope. Where the trail tread is sloped downward toward the embankment or daylight side of the trailway.

Plans. The contract plans furnished by the Government showing the location, type, dimensions, and details of work.

Palmetto Trail Specifications-8

Retainers. Embedded border of wood or rock used to retain fill and/or surface material.

Sideslope. The natural slope of the ground, usually expressed as a percentage.

Slough. That material from the backslope or the area of the backslope that has raveled onto the trailbed.

Slump. Where the trailbed material has moved downward, causing a dip in the trail grade.

Special Contract Requirements. Specifications that detail the conditions and requirements peculiar to an individual project, including additions and revisions to the standard specifications.

Standard Plans. Detailed plans approved for repetitive use and included as part of the plans.

Standard Specifications. The Standard Specifications for Construction of Trails on Federal Projects approved for general application and repetitive use.

Surfacing. Material placed on top of the trailbed or base course that provides the desired tread.

Suitable Material. Rock that can be accommodated in the trail structure, and soil free of duff with a recognizable granular texture.

Switchback. A reverse in direction of trail grade with a level landing used to change elevation on a steep slope, usually involving special treatment of the approaches, barriers, and drainages.

Trailbed. The finished surface on which base course or surfacing may be constructed. For trails without surfacing the trailbed is the tread.

Trailway. The portion of the trail within the limits of the excavation and embankment.

Tread. The surface portion of the trail upon which traffic moves.

Turnout. A short section of extra trail width to provide for passage of trail users.

Waterbar. A structure used for turning water off the trail, usually made of logs or stones.

Water Courses. Any natural or constructed channel where water naturally flows or will collect and flow during spring runoff, rainstorms, etc.

Additional definitions may be found in Section 101.03 of the Standard Specifications for Construction of Roads and Bridges on Federal Highway Projects

(FP-03).

Palmetto Trail Specifications-9

Section 902 Intent of Contract

902.01 Intent of Contract. The intent of the contract is to provide for the construction and completion of the work described. The precise details of performing the work are not stipulated except as considered essential for the successful completion of the work. Furnish all labor, material, equipment, tools, transportation, and supplies necessary to complete the work according to the contract.

Palmetto Trail Specifications-10

Section 903 Control of Work

903.01 Specifications and Drawings. Follow the requirements of FAR Clause 52.236-21 Specifications and Drawings for Construction.

(a) General. Prepare drawings as necessary to construct the work.

Drawings include, but are not limited to, layouts that show the relative position (vertical and horizontal as appropriate) of work to be performed, fabrication details for manufactured items and assemblies, installation and erection procedures, details of post-tensioning and other systems, detailed trench and excavation procedures that conform to OSHA requirements, traffic control implementation drawings, and methods for performing work near existing structures or other areas to be protected. Show all the drawing dimensions in United States customary units.

Drawings shall be a minimum size of 11 by 17 inches and a maximum size of 24 by 36 inches. All text should have a minimum height of 1/8 inch for 24 by 36 inch drawings (D size sheets). Include on each drawing and calculation sheet, the project number, name, and other identification as shown in the contract.

Furnish 5 sets of drawings and supporting calculations for acceptance before performing work covered by the drawings. If drawings are returned for revision, correct and resubmit for acceptance. Allow 40 days per submission for railroad structures and 30 days per submission for all other structures. The review time as specified is applied separately to each drawing submitted. The CO may request additional specific drawings for unique situations in order to clarify layout, construction details, or methodology. If drawings must be resubmitted, the time for acceptance starts over. Obtain written approval before changing or deviating from the accepted drawings.

(b) Specific requirements for concrete and miscellaneous structures.

(1) Furnish drawings for the following:

(a) Site-specific layouts for all wall types and gabion installations;

(b) Gabion and revet mattress details and installation procedures;

(c) Forms and falsework for reinforced concrete box culverts less than or equal to 6 feet in height;

Palmetto Trail Specifications-11

(d) Fabrication drawings for bridge railings and parapets;

(e) Fabrication drawings for prestressed members;

(f) Fabrication and installation drawings for expansion joint assemblies;

(g) Fabrication drawings for bearing assemblies;

(h) Construction joint location and concrete deck placement sequences not shown on the plans;

(i) Erection diagrams for Soil-Corrugated Metal Structure interaction systems (multi-plate structures);

(j) Structural steel fabrication drawings;

(k) Utility hangar details; and

(l) Fabrication and installation drawings for precast items.

(2) Furnish drawings that bear the seal and signature of a professional engineer proficient in the pertinent design field for the following:

(a) Erection plans;

(b) Reinforced soil slopes details;

(c) MSE wall and crib wall details;

(d) Details and installation procedures for proprietary wall systems;

(e) Temporary bridge structures for public use;

(f) All bridge forms except for railings, parapets, and components less than 6 feet in height;

(g) Shoring systems and cofferdams greater than 6 feet in height;

(h) All shoring systems that support traffic loadings;

(i) Forms and falsework for all structures greater than 6 feet in height;

(j) Post-tensioning systems;

(k) Ground anchors, soil nail, and rock bolt assembly details, layout, and installation and testing procedures;

(l) Tie back wall details; and

(m) Alternate retaining wall details.

(3) Furnish drawings that bear the seal and signature of a professional engineer who is proficient in forms and falsework

Palmetto Trail Specifications-12 design and licensed in the state where the project will be constructed for the following:

(a) Falsework for any structure with a span exceeding 16 feet;

(b) Falsework for any structure with a height exceeding 14 feet; and

(c) Falsework for structures where traffic, other than workers involved in constructing the structure, will travel under the structure.

Palmetto Trail Specifications-13

Section 904 Control of Materials

904.01 Handling Materials. Transport and handle all materials to preserve their quality and fitness for the work. Stockpile, load, and transport aggregates in a manner that will preserve specified gradation and avoid contamination.

Store materials to assure the preservation of their quality and fitness for the work.

Locate stored materials to facilitate their prompt inspection. Sites on Government-administered land that are not already designated may be used for storage purposes and for placing of equipment only when approved in advance by the CO. Restore all storage sites in accordance with requirements SHOWN ON THE PLANS or as otherwise specified. Arrangements for storage on other than designated sites are the responsibility of the contractor.

904.02 Material Sources

(a) Designated Sources. Sources for materials such as, but not limited to, soil, rock, or logs that are not available from trailway excavation or clearing operations will be designated. Sources of local materials designated in the SPECIAL CONTRACT REQUIREMENTS or SHOWN ON THE PLANS are guaranteed by the Government for the quality and quantity of material in the source.

Use all needed suitable material from the source. The designation of a source includes the right to use areas SHOWN ON THE PLANS for the purposes designated (such as plant sites, stockpiles, and haul roads). Operations are restricted to the confines of the area(s) designated.

Comply with the requirements of 30 CFR 56, subparts B and H. When required, re-establish vegetation in disturbed areas according to section 981.

(b) Contractor-Furnished Sources. Furnish material that produces an end product equivalent in performance to that specified.

904.03 Restoration. Shape and grade borrow areas on Government-administered land to make them stable and to minimize future erosion. Dispose of debris resulting from development of material sources by scattering, unless otherwise specified. Do not scatter debris within the clearing limits of trails or within roadsides. Cut off stumps to less than 12 inches above the ground as measured on the uphill side of the stump.

Palmetto Trail Specifications-14

Section 905 Quality Assurance and Quantity Measurement

Description

905.01 This work consists of providing certification that the quality and quantity of construction conform to the plans, specifications, and requirements of the contract.

Construction

905.02 Certification and Measurements

(a) Offsite-Produced Materials. Furnish signed certificates executed by the manufacturer, supplier, or vendor, stipulating that all offsite-produced materials incorporated in the work meet applicable requirements SHOWN ON THE PLANS or stated in the specifications. Furnish a certificate for each commodity or invoice.

(b) Quantity Measurements. Submit quantities to the CO for periodic progress payments, and the CO will compute payments. Quantities are subject to verification.

905.03 Records. Maintain a set of contract plans depicting as-built conditions resulting from approved changes. Maintain the plans in a current condition and indicate changes from the original contract plans in red. Give the plans to the CO upon the completion of the contract work.

Measurement

905.04 Method. There will be no separate measurement for this item.

Payment

905.05 Payment will be considered incidental to other pay items in this contract.

Palmetto Trail Specifications-15

Section 906 Measurement and Payment

906.01 General. Measurement and payment for contract work will be made only for and under those pay items included in the SCHEDULE OF ITEMS. All other work and materials will be considered incidental and included in the payment of the PAY ITEMS in the SCHEDULE OF ITEMS.

When more than one class, size, or thickness is specified in the SCHEDULE OF ITEMS for any PAY ITEM, suffixes will be added to the item number to differentiate between the items.

906.02 Determination of Quantities. The following measurements and calculations are to be used to determine contract quantities for payment:

Make measurements for seeding, geotextiles, and erosion control blankets along slope lines.

For retaining walls, measure by the square foot of front wall face.

Measure structures according to neat lines SHOWN ON THE PLANS or as altered by the CO in writing to fit field conditions. Make measurements along the centerline and parallel to the specified grade or foundation or as SHOWN ON THE

PLANS.

Deduct lengths for stairways, turnpike, puncheon, retaining walls, wire baskets, switchbacks, bridges, and bridge approaches from the measurement of excavation in Section 911 unless these items are specified as incidental to excavation in Section 911.

For standard manufactured items, such as fence, wire, plates, rolled shapes, and pipe conduits identified by gage, weight, section dimensions, and the like, such identification shall be considered the nominal weights or dimensions.

cited specifications.

906.03 Units of Measurement. Payment will be made by units defined and determined according to U.S. Customary measure and by the following:

(a) Cubic Yard. A measurement computed by one of the following methods:

(1) Excavation, embankment, or borrow. The measurement computed by the average-end-area method from measurements made longitudinally along a centerline or other reference line.

(2) Material in place or stockpiled. The measurement computed with the dimensions of the in-place material using average-end-area method or prismodial formula.

(3) Material in the Delivery Vehicle. The measurement computed using measurements of material in the hauling vehicles at the point of delivery.

Palmetto Trail Specifications-16

Vehicles shall be loaded to at least their water-level capacity. Leveling of the loads may be required when vehicles arrive at the delivery point.

(b) Each (EA). One complete unit, which may consist of one or more parts.

(c) Lump Sum (LS). The quantities that denote one complete unit of work as required by or described in the contract, including necessary materials, equipment, and labor to complete the job.

906.04 Methods of Measurement. One of the following methods of measurement for determining final payment is DESIGNATED ON THE SCHEDULE OF ITEMS for each PAY ITEM:

(a) Designed Quantities. These quantities denote the final number of units to be paid for under the terms of the contract. They are based upon the original design data available prior to advertising the project. Original design data include the preliminary survey information, design assumptions, calculations, and plans.

Changes in the number of units DESIGNATED IN THE SCHEDULE OF ITEMS may be authorized under the following conditions:

(1) As a result of changes in the work approved by the CO.

(2) As a result of the CO determining that errors exist in the original design that cause a PAY ITEM quantity to change by 15 percent or more.

(3) As a result of the contractor submitting to the CO a written request showing evidence of errors in the original design that cause a PAY ITEM quantity to change by 15 percent or more. The evidence must be verifiable and consist of calculations, plans, or other data that show how the designed quantity is believed to be in error.

(b) Staked Quantities (SQ). These quantities are determined from staked measurements prior to the construction.

(c) Actual Quantities (AQ). These quantities are determined from measurement of completed work.

(d) Vehicle Quantities. These quantities are measured or weighed in hauling vehicles.

(e) Lump Sum Quantities (LSQ). These quantities denote one complete unit of work as required by or described in the contract, including necessary materials, equipment, and labor to complete the job.

906.05 Government-Furnished Materials. When materials are furnished by the description of the PAY ITEM.

Palmetto Trail Specifications-17

Section 907 Mobilization

907.01 This work consists of moving personnel, equipment, material, and incidentals to the project and performing all work necessary before beginning work at the project site. Mobilization includes the costs associated with obtaining permits, insurance, and bonds. Mobilization is not intended to pay for the costs of materials before they are used on the project site.

907.02 The accepted quantity, measured as provided in Subsection 906.02, will be paid at the contract price per unit of measurement for the Section 907 pay item shown in the bid schedule. Payment will be full compensation for the work prescribed in this Section.

Progress payments for mobilization lump sum will be paid as follows:

(a) Bond premiums will be reimbursed according to FAR Clause 52.232-5, Payments Under Fixed-Price Construction Contracts, after receipt of the evidence of payment. Reimburse for bond premiums before issuing the Notice to Proceed if evidence of payment is received.

(b) When 5 percent of the original contract amount is earned from other bid items, 50 percent of the mobilization item, or 5 percent of the original contract amount, whichever is less, will be paid.

(c) When 10 percent of the original contract amount is earned from other bid items, 100 percent of the mobilization item, or 10 percent of the original contract amount, whichever is less, will be paid.

(d) Any portion of the mobilization item in excess of 10 percent of the original contract amount will be paid after final acceptance. Pay any unpaid amount for mobilization upon final acceptance of all work items.

Palmetto Trail Specifications-18

Section 908 Construction Staking, Flagging, and Cleanup

908.01 This work consists of establishing any control points needed in addition to existing staking, and removing and disposing of all construction stakes, tags, flagging, and plastic ribbon from the project area.

Construction

908.02 General. The Government will set initial construction stakes or flagging, and control points, and furnish the contractor with all necessary information relating to lines, slopes, and grades. These stakes and flagging constitute the field control.

Furnish and maintain additional stakes, flagging, templates, batter boards, and other materials and supplies necessary for marking and maintaining points and lines established. Do not perform work in the absence of control points. If any construction control points are destroyed, displaced, or erroneous, notify the CO.

Uniformly contour alignment and construct grade from control point to control point.

Remove all construction stakes, tags, flagging, and plastic ribbon from the project area within 7 days after the final inspection of all other work on the project.

Dispose of all stakes, tags, flagging, and plastic ribbon off Government-administered lands unless otherwise designated.

Measurement

908.03 There will be no separate measurement for this item.

Payment

908.04 Trail staking, flagging, and cleanup will be considered incidental to other pay items in this contract, and additional payment will not be made.

Palmetto Trail Specifications-19

Section 909 Maintenance for Traffic and Temporary Construction Access

909.00.01 This work consists of maintaining existing trails that are undergoing improvements open and maintained in such a condition as to safely accommodate traffic and providing temporary construction access to the site. Maintaining the trail for traffic and temporary access may be covered by subsection:

909.10 Maintenance for Traffic

909.20 Temporary Construction Access

Measurement

909.00.02 There will be no separate measurement for these items.

Payment

909.00.03 Maintaining the trail for public access and providing temporary construction access will be considered incidental to other pay items in this contract, and additional payment will not be made.

909.10 - Maintenance for Traffic

Description

909.10.01 Keep existing trails that are undergoing improvements open and maintained in such a condition as to safely accommodate traffic. Provide and maintain temporary detours, approaches, or crossings and intersections with trails, roads, businesses, parking lots, and campgrounds in a safe and passable condition. Perform no work that interferes or conflicts with traffic until a plan for handling traffic has been submitted and approved. Specific requirements for detours or closures are SHOWN ON THE PLANS or in the SPECIAL CONTRACT REQUIREMENTS.

Before any suspension of work, take precautions necessary to prevent damage to the project, such as temporary detours, approaches, crossings, or intersections, and make provisions for normal drainage and to minimize erosion. Leave all trailways in a condition suitable for traffic unless otherwise specified.

The Government may permit use of portions of the project during periods when operations are shut down. All maintenance attributable to permitted use during periods of work suspension will be provided by the Government.

The contractor is responsible for any maintenance that is not attributable to use or that is necessary during suspensions resulting from fault or negligence of the contractor.

Palmetto Trail Specifications-20

909.20 - Temporary Construction Access

909.20.01 The government may provide temporary access for the contractor from another route or trail other than the trail being constructed. The contractor will be responsible for maintaining the temporary access, removing and rehabilitating the temporary access route and any damaged area after construction is completed.

Palmetto Trail Specifications-21

Section 938 Boardwalks

938.00.01 This work consists of construction and maintenance of boardwalks, including excavation, embankment, backfill, curbs and railing systems.

Construction and maintenance of boardwalks may be covered by one or more of the following subsections:

938.10. Standard Boardwalk

938.20. Elevated Boardwalk

938.30. Step and Run

Materials

938.00.02 Materials. Conform to the following Sections and Subsections:

Material for Timber Structures 995

Construction

938.00.03 General. Construct boardwalks of the type and at locations SHOWN ON THE PLANS or DESIGNATED ON THE GROUND.

938.00.04 Excavation and Embankment. Perform excavation and embankment in accordance with the requirements of Section 911 and as SHOWN ON THE PLANS.

938.00.05 Mud Sills. Bury mud sills to a depth that provides a uniform walking surface as SHOWN ON THE PLANS.

938.00.06 Piers. Construct piers as SHOWN ON THE PLANS.

938.00.06 Approach Fills. Construct the approach fills with compacted suitable material.

Measurement

938.00.07 Measure the Section 938 items listed in the bid schedule according to section 906.

Payment

938.00.08 The accepted quantities will be paid at the contract price per unit of measurement for the Section 938 pay items listed in the bid schedule. Payment will be full compensation for the work prescribed in this Section. See Subsection 906.04.

938.10. Standard Boardwalk

Palmetto Trail Specifications-22

938.10.01 This work consists of construction of standard boardwalks, including excavation, embankment, backfill, curbs and/or railing system.

Construction

938.10.02 Construct standard boardwalks as required under construction section 938.00 and/or as SHOWN ON THE PLANS.

938.10.03 Sawn Timber Stringers. Use sawn timbers that are continuous over 2 or more spans. Fasten each stringer to each mud sill with fasteners as SHOWN ON THE PLANS that penetrate a minimum of 4 inches into the mud sill unless otherwise SHOWN ON THE PLANS. Pre-drill holes for fasteners to prevent splitting and drive spikes flush.

938.10.04 Finished Walkway. Construct abutting ends of sections of boardwalk flush with each other. Do not slope the surface of the completed walkway to either side. Construct the boardwalk with a grade that does not exceed 5 percent and where no change in grade exceeds 5 percent unless otherwise SHOWN ON THE PLANS or DESIGNATED ON THE GROUND. Construct the finished walking surface of the boardwalk flush with the trail grade at each end of the structure.

938.10.05 Decking. Lay sawn deck planks on the stringer to provide bearing for the full width of the plank. Fasten decking evenly at right angles to each stringer. Trim protruding ends of the decking to give a straight-line appearance to the edges of the structure or as SHOWN ON THE PLANS.

938.10.06 Curbs and Railing Systems. Construct curbs and railing systems with sawn timber as SHOWN ON THE PLANS. Use lengths greater than or equal to 10 feet and splice with a 6 inch half-lap joint at a spacer location.

Finish curbs and railing systems smooth and free from splinters and sharp projections.

938.20. Elevated Boardwalk

938.20.01 This work consists of construction of elevated boardwalks, including excavation, embankment, backfill, curbs and/or railing system.

Construction

938.20.02 Construct elevated boardwalks as required under construction section 938.00 and/or as SHOWN ON THE PLANS.

938.20.03 Sawn Timber Stringers. Use sawn timbers that are continuous over 2 or more spans. Fasten each stringer to each mud sill with fasteners as SHOWN ON THE PLANS that penetrate a minimum of 4 inches into the

Palmetto Trail Specifications-23 mud sill unless otherwise SHOWN ON THE PLANS. Pre-drill holes for fasteners to prevent splitting and drive spikes flush.

938.20.04 Finished Walkway. Construct abutting ends of sections of boardwalk flush with each other. Do not slope the surface of the completed walkway to either side. Construct the boardwalk with a grade that does not exceed 5 percent and where no change in grade exceeds 5 percent unless otherwise SHOWN ON THE PLANS or DESIGNATED ON THE GROUND. Construct the finished walking surface of the boardwalk flush with the trail grade at each end of the structure.

938.20.05 Decking. Lay sawn deck planks on the stringer to provide bearing for the full width of the plank. Fasten decking evenly at right angles to each stringer. Trim protruding ends of the decking to give a straight-line appearance to the edges of the structure or as SHOWN ON THE PLANS.

938.20.06 Curbs and Railing Systems. Construct curbs and railing systems with sawn timber as SHOWN ON THE PLANS. Use lengths greater than or equal to 10 feet and splice with a 6 inch half-lap joint at a spacer location.

Finish curbs and railing systems smooth and free from splinters and sharp projections.

938.30. Step and Run

938.30.01 This work consists of construction of step and runs, including excavation, embankment, and backfill.

Construction

938.30.02 Construct standard step and runs as required under construction section 938.00 and/or as SHOWN ON THE PLANS.

938.40.01 This work consists of maintaining boardwalks.

Maintenance

938.40.02 General. Perform maintenance on boardwalks as required under construction section 938.00 and/or as SHOWN ON THE PLANS.

Replace missing, broken or decayed lumber with dimensional lumber as SHOWN ON THE PLANS. Secure loose or dislocated decking, curbing and railing systems.

Palmetto Trail Specifications-24

Clear boardwalk of obstructions, silt, and debris so as to permit the free flow of water away under the boardwalk. Clean decking of all dirt and debris.

Palmetto Trail Specifications-25

960. Trail Bridges

Section 964 - PrefabricatedTrail Bridges

964.00.01 This work consists of designing, furnishing, fabricating, and constructing prefabricated trail bridges, including all required materials, hardware, sills, backwalls, rail systems, curbs, decking, excavation, backfill, and approach fills as SHOWN ON THE PLANS. Work includes all other incidental work necessary to complete the bridge installation. These specifications are for a fully engineered clear span bridge and shall be regarded as minimum standards for design and construction.

Design

964.00.02 Engineering Requirements. Structural design of the bridge structure(s) shall be performed by or under the direct supervision of a licensed professional engineer and done in accordance with recognized engineering practices and principles. The engineer shall be licensed to practice in the State in which the bridge is fabricated. The design shall be in accordance with AASHTO LRFD Bridge Design Specifications, Current Edition and as recommended in LRFD Guide Specifications for Design of Pedestrian Bridges, Current Edition.The design shall meet the following requirements unless otherwise SHOWN ON THE

PLANS:

1. Pedestrian Load Main supporting members shall be designed for a pedestrian live load of 90 psf.

2. Vehicle Load When the clear deck width between railings is greater than 7 ft and less than 10 ft the bridge shall be designed for an occasional single maintenance vehicle of 10,000 lbs (H5 Design Vehicle). When clear deck width is greater than 10 feet, the bridge shall be designed for an occasional single maintenance vehicle of 20,000 lbs (H10 Design Vehicle).

The vehicle load shall not be placed in combination with the pedestrian live load or snow load. A vehicle impact allowance is not required.

3. Other Loads Other loads such as snow, equestrian, wind and fatigue loads and load combinations shall be designed for as specified in AASHTO LRFD and as SHOWN ON THE PLANS. When a snow load greater than the 90 psf pedestrian load is SHOWN ON THE PLANS the bridge shall be analyzed and designed for the controlling load.

4. Deflection Pedestrian live load deflection shall not exceed L/360 for steel or as SHOWN ON THE PLANS.

5. Vibration The fundamental frequency of the pedestrian bridge without live load shall be greater than 3.0 hertz in the vertical direction and 1.3 hertz in the lateral direction for steel bridges. The minimum fundamental

Palmetto Trail Specifications-26 frequency for loads other than pedestrian loads, such as equestrian and mule trains shall be determined by the design engineer.

6. Camber - The bridge shall have a vertical camber dimension at midspan equal to 100% of the full dead load deflection plus 1% of the full length of the bridge or as SHOWN ON THE PLANS.

964.00.03 General Features of Design. The following are the required minimum design features unless otherwise SHOWN ON THE PLANS.

1. Span -The required bridge span shall be as SHOWN ON THE PLANS.

2. Deck Width -The required bridge width between railing elements as

SHOWN ON THE PLANS.

3. Truss Type - Bridge(s) shall be designed as a through (or box) "Pratt" truss with one (1) diagonal per panel and square end vertical members.

4. Through truss bridges will be designed utilizing underhung floor beams.

5. The top of the top chord shall not be less than 42 inches above the deck (measured from the high point of the riding surface) unless otherwise

SHOWN ON THE PLANS.

6. Safety Rails - Horizontal safety rails shall be placed on the structure so as to prevent a 4 inch sphere from passing through the truss or as SHOWN ON THE PLANS. The safety rail system shall be designed for 50 pounds per linear foot transversely and vertically, acting simultaneously on each rail.

964.00.04 Design Drawings and Calculations. Provide design drawings and calculations for the prefabricated bridge including wind, seismic and bearing forces. The Contractor is responsible for preparing all shop drawings necessary for erection of the bridge. All design drawings and calculations shall have the signature and seal of a registered professional engineer.

The Contractor shall submit all design drawings and calculations in accordance with section 903 at least 30 days in advance of the start of fabrication to allow time for review by the CO and correction of any changes. Include plan, elevation, and section views of the pedestrian bridge superstructure, dimensions of all components, connection details, and general and specific notes regarding design and construction.

The Contractor and COR shall be provided with detailed installation instructions.

964.00.05 Materials. Conform to the following Sections:

Steel Structures FP-03, Section 555 Rock, Grid Pavement Units, and Aggregate 991 Material for Timber Structures 995

Palmetto Trail Specifications-27

Furnish materials that meet the following requirements:

1. Unpainted Steel - Bridges which are not to be painted shall be fabricated from high strength, low alloy, atmospheric corrosion resistant ASTM A847 cold-formed welded square and rectangular tubing and/or ASTM A588, or ASTM A242, ASTM A606 plate and structural steel shapes (Fy = 50,000 psi). The minimum corrosion index of atmospheric corrosion resistant steel, as determined in accordance with ASTM G101, shall be 5.8.

2. Minimum Metal Thickness The minimum nominal metal thickness of closed structural tubular metal members shall 0.25 inches.

3. 3/8 inch weep holes are required at all low points for bottom and top chords, verticals, and diagonals for closed structural tubular metal members.

4. Hardware All fasteners and hardware shall be in compliance with FP- 03, Section 717 and as SHOWN ON THE PLANS.

5. Wood Decking - Wood decking shall be West Coast Regional Douglas Fir or Southern Pine as SHOWN ON THE PLANS. Treated wood shall meet the requirements as SHOWN ON THE PLANS.

964.00.06 Welding

1. Welding Process - Welding and weld qualification tests shall conform to the provisions of the ANSI/AWS D1.5 Structural Welding Code.

2. Welders - Welders shall be properly accredited experienced operators, each of whom shall submit certification of satisfactorily passing AWS standard qualification tests for all positions, satisfactory evidence of experience and skill in welding structural steel with the kind of welding to be used in the work, and who has demonstrated the ability to make uniform, sound welds of the type required.

964.00.07 Submittals

1. Welder certifications showing compliance with Section 964.00.06(2)

2. Welding procedures in compliance with Section 964.00.06(1)

3. Steel Certification - All certified mill test reports shall be furnished upon request. Mill test reports shall show the chemical analysis and physical test results for each heat of steel used in the work. All steel shall be produced in the United States of America and be AISC certified.

4. Bolt Certification - All certified mill test reports shall be furnished upon request. Mill test reports shall show the chemical analysis and physical test

Palmetto Trail Specifications-28 results for each heat of steel used in the work. All bolts shall be produced in the United States of America.

5. Wood Certifications - Furnish the following compliance certificates to the CO upon delivery of the wood materials to the jobsite:

(a) Verification of compliance with grading rules and species of timber and lumber. Provide certification by an agency accepted as competent by the American Lumber Standards Committee (ALSC).

(b) Lot certification of each charge for preservative, penetration in inches, and retention in pounds per cubic foot (assay method) by a qualified independent inspection and testing agency. In addition, have the producer of the treated products provide written certification that Best Management Practices (BMP's) in accordance with "Best Management Practices for Treated Wood in Western Aquatic Environments," published by the Western Wood Preservers Institute (WWPI) and Canadian Institute of Treated Wood, were followed, including a description and appropriate documentation of the applicable BMP's used.

(c) Such other certifications as SHOWN ON THE PLANS or called for in the SPECIAL PROJECT SPECIFICATIONS.

Provide shop drawings in accordance with section 903 for all bridges 30 days in advance of fabrication when SHOWN ON THE PLANS or in the SPECIAL PROJECT SPECIFICATIONS. Show all dimensions and fabrication details for all cut, framed, or bored timbers.

Construction

964.00.08 General Construct a prefabricated steel trail bridge as required under construction section 964.00. and as SHOWN ON THE PLANS.

964.00.09 Excavation and Embankment. Perform all excavation and embankment work in accordance with Section 911.

964.00.10 Installation. All construction and installation shall be performed in drawings. Unprotected steel chains shall not be used as a sling for installation.

964.00.11 Performance. Provide 14 day notice prior to delivery and/or installation of prefabricated bridge.

If the prefabricated superstructure is not installed immediately upon delivery to the project site, provide appropriate equipment and labor to unload and stack, support, and store all material at the delivery point designated by the COR. Support and stack all components to prevent damage. Furnish and install blocking such that all components are supported at least 8 inches above the ground.

Measurement

Palmetto Trail Specifications-29

964.00.12 Measure the section 964 items listed in the bid schedule according to section 906.

964.00.13 The accepted quantities will be paid at the contract price per unit of measurement for the Section 964 pay items listed in the bid schedule. Payment will

Palmetto Trail Specifications-30

Section 965 Trail Bridge Substructures

965.00.01 This work consists of furnishing, fabricating, constructing trail bridge substructures, including all required geosynthetics, gabion baskets, concrete, lumber, hardware, excavation, and backfill as SHOWN ON THE PLANS.

Construction of trail bridge substructure may be covered by one or more of the following subsections:

965.40. Concrete Footings

965.00.02 Materials. Conform to the following Sections:

Concrete FP-24, Section 552 Reinforcing Steel FP-24, Section 554 Material for Timber Structures 995

Furnish the following compliance certificates to the CO upon delivery of the materials to the jobsite:

(a) Verification of compliance with grading rules and species of timber and lumber. Provide certification by an agency accepted as competent by the American Lumber Standards Committee (ALSC).

(b) Lot certification of each charge for preservative, penetration in inches, and retention in pounds per cubic foot (assay method) by a qualified independent inspection and testing agency. In addition, have the producer of the treated products provide written certification that Best Management Practices (BMP's) in accordance with "Best Management Practices for Treated Wood in Western Aquatic Environments," published by the Western Wood Preservers Institute (WWPI) and Canadian Institute of Treated Wood, were followed, including a description and appropriate documentation of the applicable BMP's used.

(c) Such other certifications as SHOWN ON THE PLANS or called for in the SPECIAL PROJECT SPECIFICATIONS.

Provide shop drawings in accordance with section 903 for all timber bridge substructures 30 days in advance of fabrication when SHOWN ON THE PLANS or in the SPECIAL PROJECT SPECIFICATIONS. Show all dimensions and fabrication details for all cut, framed, or bored timbers.

965.00.03 General. Construct trail bridge substructure at locations SHOWN ON THE PLANS or DESIGNATED ON THE GROUND.

Furnish structural lumber and timber of the required stress grade as SHOWN ON

THE PLANS.

Palmetto Trail Specifications-31

Clear stacks of weeds, rubbish, or other objectionable material from the ground under and in the vicinity of all stored material. Place the bottom layer of material at least 8 inches above the ground level. Provide sufficient support to prevent sagging.

Open-stack untreated material to shed water. Stack material in layers on spacers (stickers) that extend across the full width of the stack to allow for free air circulation. Align all stickers vertically and space them at regular intervals.

Close-stack treated material to shed water.

Protect material from the weather. If covered, used sheet material such as water-resistant paper or opaque polyethylene film. Do not cover with impervious membranes, such as polyethylene film, during dry weather. Slit individual wrappings full length or puncture on the lower side to permit drainage of water.

Use slings or other devices to protect corners of heavy construction timbers and banded packages of heavy construction timber

965.00.04 Excavation and Embankment. Perform excavation and embankment in accordance with Section 911.

965.00.05 Hardware. Furnish and install hardware as SHOWN ON THE PLANS.

965.00.06 Workmanship. Cut and form all lumber and construction timbers so all joints will have even bearing over the entire contact surface. Do not use shims in making joints. Construct all joints to be closed. Drive nails and spikes to set the heads flush with the wood surface. Use the same end, face, and edge of the timber member for all layout dimensions. Bore all holes from mating faces.

Measurement

965.00.07 Measure the Section 965 items listed in the bid schedule according to section 906.

Payment

965.00.08 The accepted quantities will be paid at the contract price per unit of measurement for the Section 965 pay items listed in the bid schedule. Payment will

965.40 Concrete Footings

965.40.01 This work consists of construction of a concrete footings including rock excavation, embankment excavation and backfilling.

Palmetto Trail Specifications-32

965.40.02 Construct a concrete footing as required under construction section 965.00 and as SHOWN ON THE PLANS.

Palmetto Trail Specifications-33

Section 966 - Trail Bridge Maintenance

966.01 This work consists of maintenance of trail bridges, including replacing or reconstructing rail systems, curbs, decking, sills, stringers and approach fills as

SHOWN ON THE PLANS.

Materials

966.02 Materials. Conform to the following Sections:

Material for Timber Structures 995

Furnish the following compliance certificates to the CO upon delivery of the materials to the jobsite:

(a) Verification of compliance with grading rules and species of timber and lumber. Provide certification by an agency accepted as competent by the American Lumber Standards…

This is the start of the file's text. The full file is on GovTribe.

File details come from the government source that posted it. Updated .