GOGA 212511A 01 11 00 - 1
012721 SUMMARY OF WORK
Cleanup of Lead-Related Dust, East Wing of FM-201, Park Headquarters, Golden Gate National Recreation Area
SECTION 01 11 00 - SUMMARY OF WORK
PART 1 - GENERAL
1.1 SUMMARY
A. Section includes the following:
1. Work Covered by Contract Documents
2. Work Phases
3. Work Under Other Contracts
4. Government-Furnished Materials
5. Contractor Use of Site
6. Public Use of Site
7. Occupancy Requirements for Buildings
8. Conduct of Operations
9. Work Restrictions
10. Special Construction Requirements
11. Additional Reports
1.2 WORK COVERED BY CONTRACT DOCUMENTS
A. Project Location: The project location is in the Golden Gate National Recreation Area (GGNRA), San Francisco, California. From Highway 101/Lombard Street travel north onto Franklin Street.
Cross Bay Street and continue north on Fort Mason Road until reaching Franklin W. Street. Fort
Mason Building 201 will be on the left.
B. The Work consists of:
1. The scope of work for this project is focused on the east wing of the Fort Mason Building 201, Park Headquarters and will include: the cleaning and disposal of lead-containing dusts and paint chips including but not limited to regulatory requirements; project submittals; personal protective measures; execution of work; inspections; and waste handling. The goal of the dust removal is to clean all horizontal surfaces within the scope of work areas sufficiently to less than the clearance levels noted within this workplan.
C. Project will be constructed under a single prime contract.
1.3 WORK PHASES
A. The Work shall be conducted in one phase.
GOGA 212511A 01 11 00 - 2
1.4 WORK UNDER OTHER CONTRACTS
A. General: Cooperate with separate contractors so work on those contracts may be carried out smoothly, without interfering with or delaying work under this Contract. Coordinate Work of this
Contract with work performed under separate contracts.
B. Concurrent Work: Government will award a separate contract to provide inspections, testing and monitoring services related to this contract at Project site. Those operations will be conducted simultaneously with work under this Contract.
1. See Paragraph 1.7 of specification section 02 83 33 Lead-Related Dust Cleaning for further information.
1.5 GOVERNMENT-FURNISHED MATERIALS (NOT USED)
1.6 CONTRACTOR USE OF SITE
A. The Contractor’s use of the premises is restricted to the first, second and third floors of the east wing of FM201 Park Headquarters for cleaning operations. Materials and equipment must be stored inside the work area. Contractor shall maintain control of the work area. The contractor's use of the site is limited only by the Government's right to access room 116 and the east wing basement as needed to maintain continuity of operations or to provide access to other contractors on portions of Project.
B. Parking: The government will provide 2 parking spaces during working hours for the duration of the contract. Any other parking needs will be subject to the applicable parking restrictions on public parking on the site.
C. Driveways and Entrances: Keep driveways and entrances serving premises clear and available to
Government employees, and emergency vehicles at all times. Do not use for parking or storage of materials.
1. Schedule deliveries to minimize use of driveways and entrances.
2. Schedule deliveries to minimize space and time requirements for storage of materials and equipment on-site.
D. Construction Camp: Establishment of a camp within park will not be permitted.
E. Hauling Restrictions: Comply with legal load restrictions in hauling of materials. Load restrictions on park roads are identical to state load restrictions with such additional regulations as may be imposed by the Park Superintendent. Information regarding rules and regulations for vehicular traffic on park roads may be obtained from the Office of the Park Superintendent. A special permit will not relieve Contractor of liability for damage which may result from moving of equipment.
F. Bridge Restrictions: Identify jurisdictions, load restrictions, permit requirements, time and calendar restrictions as outlined.
GOGA 212511A 01 11 00 - 3
1.7 PUBLIC USE OF SITE
A. The east wing of FM201 Park Headquarters will be closed to the public during construction. The east wing is also closed to general park staff except for project monitors and staff conducting critical maintenance operations.
B. Contractor shall conduct his operations to ensure the least inconvenience to public.
1.8 OCCUPANCY REQUIRMENTS FOR BUILIDINGS
A. Existing Buildings
1. Full Government Occupancy: Government will occupy west wing of FM201 Park
Headquarters during the entire contract period. Cooperate with Government during cleaning operations to minimize conflicts and facilitate Government usage. Perform Work so as not to interfere with Government's day-to-day operations. Maintain existing exits, unless otherwise indicated.
a. Maintain access to existing walkways, corridors, and other adjacent occupied or used facilities. Do not close or obstruct walkways, corridors, or other occupied or used facilities without written permission from Contracting Officer.
b. Maintain existing building in weather tight condition throughout construction period. Protect building and occupants during contract period. Maintain seals at all critical barriers to ensure lead dust does not migrate from the project site to the west wing.
1.9 CONDUCT OF OPERATIONS
A. Contractor personnel shall comply with all Federal and State law and regulations, including the
Golden Gate National Recreation Area Superintendent’s Compendium. Any exception must be specifically justified and approved in writing by the Contracting Officer.
1. The Superintendent’s Compendium can be found at this internet address:
https://home.nps.gov/goga/learn/management/lawsandpolicies.htm
B. Work on Saturdays, Sundays, Federal holidays or at night may not be performed unless stated in the Work Restrictions below or without prior consent from the Contracting Officer. Submit requests 3 business days in advance of the work to the Contracting Officer for approval.
C. No signs or advertisements (except those specified herein) shall be displayed on the construction site or within the park unless approved by the Contracting Officer.
1.10 WORK RESTRICTIONS
A. On-Site Work Hours: Work shall be generally performed during normal business working hours of 8:30 a.m. to 5:00 p.m., Monday through Friday, except when otherwise indicated.
1. Weekend Hours: Weekend work is not permitted unless approved in advance by the
Contracting Officer.
GOGA 212511A 01 11 00 - 4
2. Early Morning Hours: Early morning work is not permitted unless approved in advance by the Contracting Officer, B. Existing Utilities
1. Contractor shall be responsible for locating and preventing damage to known utilities. If damage occurs, repair utility at no additional expense to the Government.
2. If damage occurs to an unknown utility, repair utility. An equitable adjustment will be made in accordance with the Changes clause of the contract.
C. Existing Utility Interruptions: Not Anticipated under this Scope of Work.
D. Nonsmoking Building/Tobacco Use/Vaping: Smoking is not permitted within building or within
25 feet of entrances, operable windows, or outdoor air intakes. Tobacco use and vaping is restricted to the bus shelter across the street from the building,
1.11 INCLUDED SPECIFICATION SECTIONS
A. Section 01 11 00 Summary of Work
B. Section 01 35 23 Safety Requirements
C. Section 02 83 33 Lead-Related Dust Cleaning
1.12 ADDITIONAL REPORTS
A. The report Draft Result Summary for Fort Mason Building 201 Lead-Dust Sampling, November 17th, 2021, prepared by Millennium Consulting Associates is appendix with this package.
B. “Guidance on Site Specific Safety Plans” dated January 1, 2016.
C. Reference Floor Plans
D. In case of conflict between report and drawings or specifications, drawings and specifications govern.
PART 2 - PRODUCTS (Not Used)
PART 3 - EXECUTION (Not Used)
END OF SECTION 01 11 00