This document provides details for a federal contract opportunity to procure an Integrated Commercial Intrusion Detection System (ICIDS-VI). The solicitation seeks to award a production type contract to manage the follow-on effort for ICIDS. Interested offerors must submit final proposals by January 16, 2023 to be considered for the contract. The opportunity involves planning, scheduling, and executing installations of ICIDS at 4 to 6 concurrent locations across separate geographic areas. Offerors must demonstrate their ability to design, install, test, support and manage the system to protect installations outside the contiguous United States. The proposal submission requirements include information on the offeror's system design, installation approach, testing methodology, supportability processes and program management controls. Questions from potential offerors must be submitted by December 16, 2022 for agency response. The Department of the Army Materiel Command Army Contracting Command in Aberdeen Proving Ground will administer the contract award.
View the file
Other files
Show all 23
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Technical Factor
| Subfactor 1.1 System Design | ||
| Doc | Requirement | Proposal Section and Page Number |
| Section L | The Offeror shall demonstrate a complete design that meets the Governments Performance Specification for an individual ICIDS Installation that is able to report and be controlled by a centralized regional monitoring center. | |
| SPS | Systems Performance Specification Requirements | |
| SPS | Section 4 GENERAL REQUIREMENTS, page 8 | |
| SPS | Section 4.1 General, page 8 | |
| SPS | Section 4.2 Systems of Systems, page 8 | |
| SPS | Section 4.2.1 Central Monitoring Station (CMS) System, page 9 | |
| SPS | Section 4.2.2 Local Control Station (LCS) System, page 9 | |
| SPS | Section 4.3 Integrated Functional Requirements, page 9 | |
| SPS | Section 4.3.1 Security Command Center System, page 9 | |
| SPS | Section 4.3.2 Intrusion Detection System (IDS), page 9 | |
| SPS | Section 4.3.3 Physical Access Control System (PACS), page 9 | |
| SPS | Section 4.3.4 Close Circuit Television (CCTV) System, page 9 | |
| SPS | Section 4.3.5 Communication System, page 10 | |
| SPS | Section 4.3.6 Back-up Power System, page 10 | |
| SPS | Section 4.4 Growth Capability, page 10 | |
| SPS | Section 4.5 Hazardous Locations, page 10 | |
| SPS | Section 4.6 System Configuration, page 13 | |
| SPS | Section 4.7 System Installation, page 13 | |
| SPS | Section 4.8 Performance Requirements, page 13 | |
| SPS | Section 4.8.1 Reliability, page 13 | |
| SPS | Section 4.8.2 Availability, page 14 | |
| SPS | Section 4.8.2.1 Operational Availability, page 14 | |
| SPS | Section 4.8.3 Maintainability, page 14 | |
| SPS | Section 4.8.4 Fail Safe Capability, page 14 | |
| SPS | Section 4.8.5 Preventive Maintenance, page 14 | |
| SPS | Section 4.8.6 Line Supervision, page 14 | |
| SPS | Section 4.8.7 Power Loss Detection, page 14 | |
| SPS | Section 4.8.8 Controls and Designation, page 14 | |
| SPS | Section 4.8.9 Interchangeability, page 15 | |
| SPS | Section 5 SUBSYSTEM REQUIREMENTS, page 15 | |
| SPS | Section 5.1 Performance Characteristics, page 15 | |
| SPS | Section 5.1.1 Security Command Center (SCC) System, page 15 | |
| SPS | Section 5.1.1.1 ICIDS Software, page 15 | |
| SPS | Section 5.1.1.2 Alarm Call Up, page 16 | |
| SPS | Section 5.1.1.3 System Timing, page 16 | |
| SPS | Section 5.1.1.4 Programming, page 16 | |
| SPS | Section 5.1.1.5 ICIDS Monitor Display Software, page 16 | |
| SPS | Section 5.1.1.6 Graphical Map Software, page 16 | |
| SPS | Section 5.1.1.7 Printers, page 16 | |
| SPS | Section 5.1.1.8 Control and Display Integration, page 16 | |
| SPS | Section 5.1.1.9 Enrollment Center Equipment and Software, page 16 | |
| SPS | Section 5.1.1.9.1 Enrollment Center Equipment, page 16 | |
| SPS | Section 5.1.1.9.2 Enrollment Center Software, page 16 | |
| SPS | Section 5.1.1.9.3 Data Storage, page 17 | |
| SPS | Section 5.1.1.9.4 Application Interface and Encryption, page 17 | |
| SPS | Section 5.1.2 Intrusion Detection System (IDS), page 17 | |
| SPS | Section 5.1.2.1 IDS Components, page 17 | |
| SPS | Section 5.1.2.2 Detection Sensitivity, page 18 | |
| SPS | Section 5.1.2.3 Detection Alarm and Reporting Capacity, page 18 | |
| SPS | Section 5.1.2.4 Probability of Detection, page 18 | |
| SPS | Section 5.1.2.5 False Alarm Rate, page 18 | |
| SPS | Section 5.1.2.6 Nuisance Alarm Rate, page 18 | |
| SPS | Section 5.1.2.7 Premise Control Unit (PCU), page 18 | |
| SPS | Section 5.1.2.7.1 Overcurrent Protection Indication, page 19 | |
| SPS | Section 5.1.2.7.2 Manual and Self-Test, page 19 | |
| SPS | Section 5.1.2.7.3 Backup Battery Capacity Calculations, page 19 | |
| SPS | Section 5.1.2.7.4 Backup Battery Monitoring and Detection, page 19 | |
| SPS | Section 5.1.2.8 Detection Sensors, page 19 | |
| SPS | Section 5.1.2.8.1 High Security Switch (HSS), page 19 | |
| SPS | Section 5.1.2.8.2 Passive Infra-Red Sensors (Interior and Exterior), page 20 | |
| SPS | Section 5.1.2.8.3 Microwave Sensors, page 20 | |
| SPS | Section 5.1.2.8.4 Dual Technology Sensors, page 20 | |
| SPS | Section 5.1.2.8.5 Fence Mounted Sensors, page 20 | |
| SPS | Section 5.1.2.8.6 Duress Alarms, page 20 | |
| SPS | Section 5.1.3 Physical Access Control System (PACS), page 20 | |
| SPS | Section 5.1.3.1 Functional Requirements, page 20 | |
| SPS | Section 5.1.3.2 PACS Badging Requirements, page 21 | |
| SPS | Section 5.1.3.3 PACS Programming, page 21 | |
| SPS | Section 5.1.3.4 Error and Throughput Rates, page 21 | |
| SPS | Section 5.1.3.5 Access Control Processing, page 21 | |
| SPS | Section 5.1.3.6 Access Control Unit (ACU) , page 22 | |
| SPS | Section 5.1.3.7 Access Control Devices , page 22 | |
| SPS | Section 5.1.3.8 Access Control Keypads, page 22 | |
| SPS | Section 5.1.3.9 Access Control Cards, page 22 | |
| SPS | Section 5.1.3.10 Personal Identity Verification Equipment, page 22 | |
| SPS | Section 5.1.3.11 Portal Control Devices, page 22 | |
| SPS | Section 5.1.4 Closed-Circuit Television (CCTV) System, page 22 | |
| SPS | Section 5.1.4.1 Cameras, page 22 | |
| SPS | Section 5.1.4.2 Video Analytics, page 23 | |
| SPS | Section 5.1.4.3 Color Video Monitors, page 23 | |
| SPS | Section 5.1.4.4 Ancillary Equipment, page 23 | |
| SPS | Section 5.1.4.5 CCTV Enclosure, page 23 | |
| SPS | Section 5.1.4.6 Camera Mounting Structures, page 23 | |
| SPS | Section 5.1.5 Communication System, page 23 | |
| SPS | Section 5.1.5.1 Link Supervision, page 23 | |
| SPS | Section 5.1.5.2 Hardwire, page 23 | |
| SPS | Section 5.1.5.3 Radio Frequency Link, page 24 | |
| SPS | Section 5.1.5.4 Data Encryption, page 24 | |
| SPS | Section 5.1.5.5 Network Switch, page 24 | |
| SPS | Section 5.1.5.6 Video and ICIDS Transmission, page 24 | |
| SPS | Section 5.1.5.7 Wire and Cable, page 24 | |
| SPS | Section 5.1.5.8 Digital Data Interconnection Wiring, page 24 | |
| SPS | Section 5.1.5.9 Above Ground and Direct Sensor Wiring, page 24 | |
| SPS | Section 5.1.5.10 Local Area Network (LAN) Cabling, page 24 | |
| SPS | Section 5.1.5.11 Cable Construction, page 24 | |
| SPS | Section 5.1.6 Back-Up Power System, page 24 | |
| SPS | Section 5.1.6.1 Uninterruptible Power Supply, page 25 | |
| SPS | Section 5.1.6.2 Batteries, page 25 | |
| SPS | Section 5.1.6.3 Surge Suppression Devices, page 25 | |
| SPS | Section 5.1.7 Component Enclosures, page 25 | |
| SPS | Section 5.1.7.1 Interior and Exterior Sensors, page 25 | |
| SPS | Section 5.1.7.2 Interior Enclosures, page 25 | |
| SPS | Section 5.1.7.3 Exterior Enclosures, page 26 | |
| SPS | Section 5.1.7.4 Metal Thickness, page 26 | |
| SPS | Section 5.1.7.5 Doors and Covers, page 26 | |
| SPS | Section 5.1.7.6 Ventilation, page 26 | |
| SPS | Section 5.1.7.7 Labels, page 26 | |
| SPS | Section 5.1.7.8 Test Points, page 26 | |
| SPS | Section 5.1.8 Equipment Rack, page 26 | |
| SPS | Section 6 CYBERSECURITY, page 26 | |
| Section L | The proposed approach shall address, at a minimum: | |
| Section L | - Identification, description, and features of application software, operating system, and support software | |
| Section L | - Configuration Management (CM) Process | |
| Section L | - Systems Engineering process to executing Engineering Change Proposals | |
| Section L | - Communications media testing and system communication regulations and requirements | |
| Section L | - Method for achieving Risk Management Framework (RMF) system accreditation and Network connection approvals IAW the Department of Defense (DOD) system security requirements | |
| Section L | - Method for managing obsolescence of equipment and software throughout the contract | |
| Section L | - Detailed complete design package to include drawings identifying system architecture, interfaces, design, communications and components, component locations and all interconnecting, network systems for pseudo-site Fort FPS (Section J, Attachment 0009). The Offeror developed interconnecting systems drawings are included in the Fort FPS design package. The 32-page design package is not included in the volume page count. | |
| Subfactor 1.2 System Installation | ||
| Doc | Requirement | Proposal Section and Page Number |
| Section L | The Offeror shall provide an approach to system installation. This approach shall demonstrate the following at a minimum: | |
| Section L | - Comprehensive plan with timeline to completion of installation on how ICIDS will be installed outside the Contiguous United States (OCONUS) on individual Installations that are able to report and be controlled by a centralized regional monitoring center. | |
| Section L | - Quality Assurance techniques and procedures to be used to ensure consistent quality site to site | |
| Section L | - Process for Material Tracking of all equipment and parts | |
| Section L | -Proposed OCONUS Logistics support | |
| Subfactor 1.3 System Testing | ||
| Doc | Requirement | Proposal Section and Page Number |
| Section L | The Offeror shall provide an approach to system testing. This test approach shall demonstrate at a minimum: | |
| Section L | - Approach to system testing IAW the Statement of Work (SOW) section 3.3, ESTL, and 3.16, Test and Evaluation | |
| Section L | - Location of Engineering Support Test Laboratory (ESTL) for Performance Verification Test - 1 (PVT-1) | |
| Section L | - Approach to supporting and maintaining ESTL operation throughout the life of the contract | |
| Section L | - Performance Verification Test - 2 (PVT-2) and Endurance Test (ET) approach for the first Installation | |
| Section L | - System Acceptance Test (SAT) approach composed of System Performance Verification (SPV) and ET for follow-on Installations | |
| Section L | - Methods of documenting test and evaluation data | |
| Section L | - Regression analysis and test approach | |
| Subfactor 1.4 System Supportability | ||
| Doc | Requirement | Proposal Section and Page Number |
| Section L | The Offeror shall demonstrate its System Supportability. | |
| Section L | The Offerors System Supportability information shall provide system software and hardware management and validation that, at a minimum, addresses the following: | |
| Section L | - Procedures for warranty processing and maintenance planning | |
| Section L | - Continuity Of Operations Plan (COOP) for system backup, recovery, documentation, and procedures | |
| Section L | - Management approach of software licenses for installed systems | |
| Subfactor 1.5 Program Management | ||
| Doc | Requirement | Proposal Section and Page Number |
| Section L | The Offeror shall submit its proposed organization and procedures for management of ICIDS-VI. | |
| Section L | The Offeror's discussion of their Program Management shall address the following: | |
| Section L | - Approach to planning, scheduling and executing at 4 to 6 concurrent installations at separate geographic locations | |
| Section L | - System for monitoring, controlling, and reporting progress, including subcontractors |