This is a Statement of Work (SOW) for the manufacture and delivery of security hoods for the Bureau of Engraving and Printing (BEP). The security hoods are used to cover Stack and Rack Carts during the drying process after currency printing, allowing printed sheets to cure for a minimum of 72 hours while remaining secure. The hoods must be manufactured from breathable, strength material with adequate open weave to permit airflow, be resistant to rips and tears from normal working conditions, and include perforated security belts and straps for securing to carts without pulling the cloth or strapping. Finished equipment shall be delivered to the Fort Worth, Texas Currency Facility located at 9000 Blue Mound Road, Fort Worth, TX 76131.

The contractor must deliver two security hoods within 60 days of contract award for an initial two-week testing and acceptance period, with subsequent deliveries following an agreed-upon schedule on a lot delivery basis until all hoods are received. The contractor is responsible for providing a comprehensive warranty outlining coverage details and a point of contact for warranty issues. The BEP reserves the right to inspect all deliverables and will evaluate contractor performance through random sampling per Acceptable Quality Limits, customer complaint investigation, and final acceptance after 60 days of use without problems. Any non-conforming hoods shall be returned at contractor expense and replaced at no cost to the government. The contractor must immediately notify the Contracting Officer and Contracting Officer's Representative of any delays, technical deviations requiring prior written approval, or quality audit findings, with corrective action reports due within 30 calendar days of notification. Deliveries are not accepted on Federal Holidays or during the BEP's year-end shutdown (December 25 to January 1) except under extenuating circumstances with advance arrangement.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Statement of Work Security Hoods

SECTION I: Background

The Bureau of Engraving and Printing’s (BEP) mission is to develop and produce United States currency notes, trusted worldwide. BEP’s vision is to be the world standard securities printer providing its customers and the public with superior products through excellence in manufacturing and innovation. As its primary function, the BEP prints billions of dollars, referred to as Federal Reserve notes, each year for delivery to the Federal Reserve System.

As part of the printing and delivery process, Stack and Rack Carts (also referred to as Carts) are used for separating wet work during the drying process after Intaglio printing. These carts are specific to press size and include several accessories including metal rods and security hoods that allow for wet work to breathe while drying.

SECTION II: Purpose

The purpose of this requirement is to establish a single contract for security hoods to be used at the BEP. Contractor shall provide the BEP with hoods for use in the internal production process.

Upon completion of Offset and Intaglio print phase, carts are used to hold sheets for no less than seventy-two (72) hours of drying time. During dry times, each cart will be secured and strapped with a security hood and locking mechanism. Mechanism will be provided by the BEP.

SECTION III: Technical Requirements

The Contractor shall manufacture and deliver security hoods that are compliant with the specified requirements in the Statement of Work (SOW), Technical Requirements Data Sheet (TRDS) and drawings. Finished equipment shall be delivered to the Ft. Worth, TX Currency Facility.

The following outlines the specifications for the security hoods:

1. Security Hoods:

a. Hoods shall be designed to cover the carts.

b. Hoods must have enough open weave to allow adequate airflow to allow printed sheets to cure for seventy-two (72) hours.

c. Hoods shall be of breathable, strength material that does not pull the cloth and/or strapping.

d. Hood shall be resistant to rips and tears from normal working conditions.

e. Hoods shall also include perforated security belt and straps to allow the BEP to secure the hoods to the Carts

SECTION IV: Warranty

The Contractor shall provide a warranty. The Warranty shall outline what is and what is not covered. The Contractor shall also provide a point of contact for warranty issues and concerns.

SECTION V: Inspection and Testing

Responsibility for Inspection and Testing: The BEP reserves the right to perform any inspections on all deliverables under this contract. The security hoods shall meet or exceed the minimum technical requirements as required herein.

Any security hoods that do not meet the specifications shall be returned to the Contractor at Contractor’s expense. If any item is deemed insufficient or damaged, the Contracting Officer Representative (COR) will notify the Contractor. In the event, any piece does not work or is deemed damaged or found to be unacceptable; the Contractor will replace the item at no cost to the Government.

The government will evaluate contractor’s performance utilizing the below methods:

• Random Sampling: The COR will facilitate or conduct random sampling in accordance with the Acceptable Quality Limits outlined in the requirements to ensure equipment meets requirements.

• Customer Complaints: The COR will be responsible for investigating and notifying the CO of customer complaints. The CO will notify the contractor when complaints arise.

• Final Acceptance: The security hoods shall be utilized by the BEP for a minimum of sixty

(60) days without any problems or issues being noted prior to the final acceptance by the BEP.

SECTION VI: Deliverables

SOW # Deliverable Due Date Deliverable Recipient

4.0 Warranty

Completion of full acceptance

PDF/Email/MS Word 2003 (or higher)

4.0 Contact Information

Completion of full acceptance

PDF/Email/MS Word 2003 (or higher)

SECTION VI: Performance/Delivery Period

The Contractor is responsible for the delivery of security hoods that meet the Quality level outlined in the SOW and TRDS. Delivery of two (2) security hoods within sixty (60) days after receipt of contract award for a two (2) week initial testing and acceptance. After testing is completed, the security hoods will follow an agreed upon delivered schedule. The BEP will allow for lot delivery until all hoods have been received.

A. Place of Delivery:

Fort Worth, T.X. Facility (WCF) 9000 Blue Mound Road | Fort Worth, T.X. 76131

B. Warranty: Contractor shall provide a warranty for all equipment. Warranty shall outline what is and what is not covered. Contractor shall also provide a point of contact for warranty issues and concerns.

SECTION VIII: Other Important

Information Federal Holidays and Year-

End Shutdown The Bureau of Engraving and Printing observes all Federal Holidays outlined by the Office of Personnel Management (OPM). For a current list of holidays please visit OPM’s website at www.opm.gov. Additionally, the BEP typically has a year-end shutdown (YES) that runs from 25 December to 1 January. Deliveries are not typically accepted on Federal Holidays or during YES, unless there are extenuating circumstances and arrangements have been made in advance with appropriate BEP personnel.

Notice of Delays

In the event the Contractor encounters difficulty in meeting performance requirements, anticipates difficulty in complying with the contract delivery order schedule or dates, or whenever the Contractor has knowledge that any actual or potential situation is delaying or threatens to delay the timely performance of this contract, the Contractor shall immediately notify the Contracting Officer (CO) and the Contracting Officer’s Representative (COR). This notification must be in writing, giving pertinent details, provided, however, that this data shall be informational only in character and that this shall not be construed as a waiver by the Government of any delivery schedule or date or of any rights or remedies provided by law or under this contract.

Notice of Changes The contractor shall inform the CO and COR in writing of any potential or actual deviations from technical requirements. Any deviations from the technical requirements in this contract require prior written approval from the CO.

Corrective Action Requests The Contractor shall provide written corrective action reports to the CO and the COR for any root cause letters or quality audit findings issued for nonconformance to the contract specifications. A corrective action report shall be submitted within thirty (30) calendar days after receipt of a root cause letter or a quality audit finding by the contractor.

http://www.opm.gov/

Statement of Work
Security Hoods
SECTION II: Purpose
SECTION III: Technical Requirements
SECTION V: Inspection and Testing
SECTION VI: Deliverables
SECTION VI: Performance/Delivery Period
A. Place of Delivery:
SECTION VIII: Other Important Information Federal Holidays and Year-End Shutdown
Notice of Delays