This document is a Performance Work Statement (PWS) for the provision of annual preventative maintenance services on three laboratory instruments owned by the Cereal Crops Research Unit, Hard Red Spring & Durum Wheat Quality Laboratory (WQL) at North Dakota State University (NDSU).
The PWS requires a contractor to perform annual preventative maintenance on a PerkinElmer Single Kernel Characterization System (SKCS), an Aquamatic 5200 moisture meter, and a Lab Mill 3100. The services are to be provided on an annual basis, scheduled each year by the USDA Agricultural Research Service (ARS) director or technicians, generally by the end of April. The contractor must provide OEM-certified engineers or technicians to complete the maintenance. This is a firm fixed-price requirement, with all travel costs assumed by the contractor. The PWS is associated with a solicitation issued by the USDA ARS for these preventative maintenance services, solicitation number 12805B25Q0007. The solicitation is set-aside for small businesses, with quotes due by the date specified.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Attachment 002 Wage Determination.pdf | ||
| Attachment 003 Pricing Schedule.docx | DOCX document | |
| RFQ 12805B25Q0007 Clauses and Provisions.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Performance Work Statement (PWS)
Project: Preventive Maintenance Service on PerkinElmer Single Kernel Characterization System
(SKCS), Aquamatic 5200 moisture meter, and Lab Mill 3100.
GENERAL INFORMATION
1.0 Background and Purpose: The Cereal Crops Research Unit, Hard Red Spring & Durum Wheat
Quality Laboratory (WQL) owns a PerkinElmer Single Kernel Characterization System 4100
(SKCS), Aquamatic 5200 moisture meter, and Lab Mill 3100, which were purchased in 2017, 2019, and 2023, respectively. On-site preventive maintenance (PM) on all three instruments are needed to be performed on an annual basis.
2.0 Definitions:
ARS: Agricultural Research Service
PM: Preventive maintenance
SKCS: Single Kernel Characterization System 4100
WQL: Wheat Quality Laboratory
CONTRACTOR REQUIREMENTS
3.0 Technical Requirements/Tasks:
Contractor will come to NDSU, Peltier Complex where all 3 instruments are housed. Contractor will perform annual PMs on the SKCS, Aquamatic 5200 moisture meter, and Lab Mill 3100.
4.0 Deliverable / Schedule:
• USDA-ARS will contact contractor and schedule annual service visit at a mutually agreed upon date, generally no later than by the end of April of each year.
• Contractor will perform the PMs on the SKCS (S/N 5179), Aquamatic 5200 moisture meter (S/N
1954220), and Lab Mill 3100 (S/N 221159).
5.0 Site Information:
• ARS will provide the contractor access to the laboratories where the instruments are housed at
NDSU Peltier Complex (1300 18th Street North, Fargo, ND) in cooperation with WQL director or
ARS-technicians. Access can generally be gained from 6:00 a.m. to 6:00 p.m., Monday through
Friday, excepting federal holidays.
6.0 Travel:
This is a firm fixed price requirement. All travel costs are assumed by the contractor. Only one on site visit per year is necessary if all annual PMs are completed at the same time.
7.0 Contractor’s Key Personnel:
Contractor shall provide OEM certified engineers and/or technicians qualified to perform annual PMs on
PerkinElmer SKCS, Aquamatic 5200 moisture meter, and Lab Mill 3100.
8.0 Performance Requirement Measures:
Contractor shall provide PMs on PerkinElmer SKCS, Aquamatic 5200 moisture meter, and Lab Mill
3100 to meet performance specifications as scheduled with USDA ARS director or technicians.
9.0 Invoicing:
The clause at FAR 52.212-4(i)(1) indicates payment after delivery only. Invoicing is in arrears. Any invoicing submitted prior to delivery will be rejected.