TECHNICAL EXHIBIT 2

DELIVERABLES SCHEDULE

Deliverable
Frequency
# of Copies
Medium/Format
Submit To

Contractor shall provide a quality assurance plan.

Paragraph C.1.5.1 of the PWS

1, Within 15 calendar days after award of contract
1
Word document

emailed

COR

Contractor shall provide a document showing the proposed project schedule for creation of the exhibit design package.

Paragraph C.5.1.1 of the PWS

Within 30 days of kick off meeting.
1
Word document

emailed

COR

Contractor shall supply Status reports Paragraph C.5.5.2 of the PWS

The contractor shall provide the COR with a monthly status update appraising the COR of the projects progress beginning with the first day of the second full month of the project. Monthly
1
Word document emailed

COR

50% Concept Design Package Paragraph C.5.1.9 the PWS The completion date to be established in the project schedule being developed by the contractor. (C.5.1.1)

1
PDF emailed
COR

100% Concept Design Package Paragraph C.5.1.10 of the PWS

The completion date to be established in the project schedule being developed by the contractor. (C.5.1.1)
1
PDF emailed
COR

35% Design Development Package Paragraph C.5.1.11 of the PWS

The completion date to be established in the project schedule being developed by the contractor. (C.5.1.1)
1
PDF emailed
COR

100% Design Development Paragraph C.5.1.12 of the PWS

The completion date to be established in the project schedule being developed by the contractor. (C.5.1.1)
1
PDF emailed
COR

50% final design Paragraph C.5.1.13 of the PWS

The completion date to be established in the project schedule being developed by the contractor. (C.5.1.1)
1
PDF emailed
COR

Graphic PDF Proof Package Paragraph C.5.1.14 of the PWS

The completion date to be established in the project schedule being developed by the contractor. (C.5.1.1)
1
PDF emailed or large file transfer
COR

100% Final Design Package Paragraph C.5.1.15 of the PWS

The completion date to be established in the project schedule being developed by the contractor. (C.5.1.1)
1
One (1) Digital file supplied as (PDF). One (1) hardcopy

COR

100% Final Design Package cost element Paragraph C.5.1.16 of the PWS

The completion date to be established in the project schedule being developed by the contractor. (C.5.1.1)
1
PDF and Native file format

Emailed

COR

100% Final Digital Artwork

Paragraph C.5.1.17 of the PWS

The completion date to be established in the project schedule being developed by the contractor. (C.5.1.1)
1
Production ready files including CAD construction.

Files on hard disk or CDs

COR

File details come from the government source that posted it. Updated .