This is a specifications document (Appendix B) for PR #2025-0316, a repair project for chilled water lines connecting Building 108 to Building 114 at a U.S. Army installation. The document establishes administrative requirements, project scheduling standards, submittal procedures, safety requirements, and quality control protocols that the contractor must follow.
Key administrative requirements include: the contractor must provide a project superintendent with minimum 10 years of construction experience and 5 years as a superintendent on similar projects; mobilize to the jobsite within 60 calendar days after contract award; maintain fluent English-speaking personnel on-site at all times; and comply with EM 385-1-1 safety standards and FAR insurance requirements. The project schedule must be developed using Critical Path Method with Precedence Diagram Method, submitted within 15 days (Preliminary) and 42 days (Initial) after Notice to Proceed, and include detailed cost loading, activity coding per SDEF standards, and mandatory activities such as submittals, inspections, and punch list corrections. The contractor must provide weekly progress meetings with the Government and submit updated schedules with earnings reports organized by Contract Line Item Number. Submittals are classified as Government-approved (G) or information-only, with a standard 14-day review period, and must be submitted using ENG Form 4025-R with proper documentation of submittals tracked in a project register. Safety requirements mandate a Level One Site Safety and Health Officer on-site at all times, submission of an Accident Prevention Plan within 30 days of contract award, Activity Hazard Analyses for each work task, monthly exposure reports, and accident reporting within 24 hours for standard incidents or 8 hours for severe accidents. Quality Control requirements, while referenced extensively, are detailed in Section 01 45 00, with the contractor responsible for maintaining an effective QC program at no separate charge.
View the file
Other files
Show all 12
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
PR #2025-0316 Repair Chilled Water - Bldg 108 to 114
SECTION 01 30 00
ADMINISTRATIVE REQUIREMENTS
11/20, CHG 5: 02/25
PART 1 GENERAL
1.1 REFERENCES
The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.
U.S. ARMY CORPS OF ENGINEERS (USACE)
EM 385-1-1 (2024) Safety -- Safety and Occupational Health (SOH) Requirements
1.2 MINIMUM INSURANCE REQUIREMENTS
Provide the minimum insurance coverage required by FAR 28.307-2 Liability, during the entire period of performance under this contract. Provide other insurance coverage as required by State law.
1.3 SUPERVISION
1.3.1 Superintendent Qualifications
Provide project superintendent with a minimum of 10 years experience in construction with at least 5 of those years as a superintendent on projects similar in size and complexity. The individual must be familiar with the requirements of EM 385-1-1 and have experience in the areas of hazard identification and safety compliance. The individual must be capable of interpreting a critical path schedule and construction drawings. The qualification requirements for the alternate superintendent are the same as for the project superintendent. The Contracting Officer may request proof of the superintendent's qualifications at any point in the project if the performance of the superintendent is in question.
For projects where the superintendent is permitted to also serve as the Quality Control (QC) Manager as established in Section01 45 00 QUALITY CONTROL, the superintendent must have qualifications in accordance with that section.
1.3.2 Minimum Communication Requirements
Have at least one qualified superintendent, or competent alternate, capable of reading, writing, and conversing fluently in the English language, on the job-site at all times during the performance of Contract work. In addition, if a Quality Control (QC) representative is required on the Contract, then that individual must also have fluent English communication skills.
1.3.3 Duties
The project superintendent is primarily responsible for managing subcontractors and coordinating day-to-day production and schedule adherence on the project. The superintendent is required to attend Red
SECTION 01 30 00 Page 1
Zone meetings, partnering meetings, and quality control meetings. The superintendent or qualified alternative must be on-site at all times during the performance of this contract until the work is completed and accepted.
1.3.4 Non-Compliance Actions
The Project Superintendent is subject to removal by the Contracting Officer for non-compliance with requirements specified in the contract and for failure to manage the project to ensure timely completion.
Furthermore, the Contracting Officer may issue an order stopping all or part of the work until satisfactory corrective action has been taken. No part of the time lost due to such stop orders is acceptable as the subject of claim for extension of time or excess costs or damages by the Contractor.
1.4 MOBILIZATION
Mobilize to the jobsite within 60 calendar days after contract award.
Mobilize is defined as having equipment AND having a physical presence of at least one person from the contractor's team on the jobsite.
PART 2 PRODUCTS
Not used.
PART 3 EXECUTION
Not used.
-- End of Section --
SECTION 01 30 00 Page 2
SECTION 01 32 01.00 10
PROJECT SCHEDULE
08/23, CHG 1: 08/24
PART 1 GENERAL
1.1 REFERENCES
The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.
AACE INTERNATIONAL (AACE)
AACE 52R-06 (2006) Time Impact Analysis - As Applied in Construction
AACE 84R-13 (2015) Planning and Accounting for Adverse Weather
AMERICAN SOCIETY OF CIVIL ENGINEERS (ASCE)
ASCE 67-17 (2017) Schedule Delay Analysis
U.S. ARMY CORPS OF ENGINEERS (USACE)
ER 1-1-11 (2017) Administration -- Project Schedules
1.2 SUBMITTALS
Government approval is required for submittals with a "G" or "S" classification. Submittals not having a "G" or "S" classification are for information only. Submit the following in accordance with Section
01 33 00 SUBMITTAL PROCEDURES:
SD-01 Preconstruction Submittals
Preliminary Project Schedule; G
Initial Project Schedule; G
PART 2 PRODUCTS
2.1 SOFTWARE
The scheduling software utilized to produce and update the schedules required herein must be capable of meeting all requirements of this specification.
PART 3 EXECUTION
3.1 GENERAL REQUIREMENTS
Prepare for approval a Project Schedule, as specified herein, pursuant to FAR Clause 52.236-15 Schedules for Construction Contracts. Show in the schedule the proposed sequence to perform the work and dates contemplated for starting and completing all schedule activities. The scheduling of
SECTION 01 32 01.00 10 Page 1 the entire project is required. The scheduling of construction is the responsibility of the Contractor. Contractor management personnel must actively participate in its development. Subcontractors, and suppliers working on the project must also contribute in developing and maintaining an accurate Project Schedule. Provide a schedule that is a forward planning as well as a project monitoring tool. Use the Critical Path Method (CPM) of network calculation to generate all Project Schedules.
Prepare each Project Schedule using the Precedence Diagram Method (PDM).
3.2 BASIS FOR PAYMENT AND COST LOADING
The schedule is the basis for determining contract earnings during each update period and therefore the amount of each progress payment. The aggregate value of all activities coded to a contract CLIN must equal the value of the CLIN. Match the progress payment "Pay Period Thru" date in RMS to the schedule data date.
3.2.1 Activity Cost Loading
Activity cost loading must be reasonable and without front-end loading.
Activities with a negative cost loading is not allowed. Provide additional documentation to demonstrate reasonableness if requested by the Contracting Officer.
3.2.2 Cost Loading of Submittals
No costs are to be assigned to activities for the preparation, review, or approval of submittals, except as described under paragraph COST LOADING OF CLOSEOUT ACTIVITIES, paragraph AS-BUILT DRAWINGS, and paragraph O&M
MANUALS.
3.2.3 Withholdings / Payment Rejection
Failure to meet the requirements of this specification may result in the disapproval of the preliminary, initial, or periodic schedule updates and subsequent rejection of payment requests until compliance is met.
In the event that the Contracting Officer directs schedule revisions and those revisions have not been included in subsequent Project Schedule revisions or updates, the Contracting Officer may withhold 10 percent of pay request amount from each payment period until such revisions to the project schedule have been made.
3.3 PROJECT SCHEDULE DETAILED REQUIREMENTS
3.3.1 Level of Detail Required
Develop the Project Schedule to the appropriate level of detail to address major milestones and to allow for satisfactory project planning and execution. Failure to develop the Project Schedule to an appropriate level of detail will result in its disapproval. The Contracting Officer will consider, but is not limited to, the following characteristics and requirements to determine appropriate level of detail:
3.3.2 Activity Durations
Reasonable activity durations are those that allow the progress of ongoing activities to be accurately determined between update periods.
SECTION 01 32 01.00 10 Page 2
Non-procurement activities Original Durations (OD) are not to exceed 20 workdays or 30 calendar days.
3.3.3 Procurement Activities
Include in the schedule activities associated with the critical submittals and their approvals, procurement, fabrication, and delivery of long lead materials, equipment, fabricated assemblies, and supplies. Long lead procurement activities are those with an anticipated procurement sequence of over 90 calendar days.
3.3.4 Mandatory Activities
Include the following activities in the initial project schedule and all updates.
a. Submission, review and acceptance of SD-01 Preconstruction Submittals (individual activity for each).
b. Submission and approval of as-built drawings.
c. Submission and approval of DD1354 data and installed equipment lists.
d. Contractor's pre-final inspection.
e. Correction of punch list from Contractor's pre-final inspection.
f. Government's pre-final inspection.
g. Correction of punch list from Government's pre-final inspection.
h. Final inspection.
3.3.5 Government Activities
Show in schedule, Government and other agency activities that could impact progress. These activities include, but are not limited to approvals, environmental permit approvals by State regulators, inspections, utility tie-in, Government Furnished Equipment (GFE) and Notice to Proceed (NTP) for phasing requirements.
3.3.6 Standard Activity Coding Dictionary
Use the activity coding structure defined in the Standard Data Exchange Format (SDEF) in ER 1-1-11 . This exact structure is mandatory. Develop and assign all Activity Codes to activities as detailed herein.
The SDEF format is as follows:
Field Activity Code Length Description
1 WRKP 3 Workers per day
2 RESP 4 Responsible party
3 AREA 4 Area of work
SECTION 01 32 01.00 10 Page 3
Field Activity Code Length Description
4 MODF 6 Modification Number
5 BIDI 6 Bid Item (CLIN)
6 PHAS 2 Phase of work
7 CATW 1 Category of work
8 FOW 20 Feature of work*
*Some systems require that FEATURE OF WORK values be placed in several activity code fields. The notation shown is for Primavera P6. Refer to the specific software guidelines with respect to the FEATURE OF WORK field requirements.
3.3.6.1 Workers Per Day (WRKP)
Assign Workers per Day for all field construction or direct work activities, if directed by the Contracting Officer. Workers per day is based on the average number of workers expected each day to perform a task for the duration of that activity.
3.3.6.2 Responsible Party Coding (RESP)
Assign responsibility code for all activities to the Prime Contractor, Subcontractor(s) or Government agency(ies) responsible for performing the activity.
a. Activities coded with a Government Responsibility code include, but are not limited to: Government approvals, Government design reviews, environmental permit approvals by State regulators, Government Furnished Property/Equipment (GFP) and Notice to Proceed (NTP) for phasing requirements.
b. Activities cannot have more than one Responsibility Code. Examples of acceptable activity code values are: DOR (for the designer of record);
ELEC (for the electrical subcontractor); MECH (for the mechanical subcontractor); and GOVT (for USACE).
3.3.6.3 Area of Work Coding (AREA)
Assign Work Area code to activities based upon the work area in which the activity occurs. Define work areas based on resource constraints or space constraints that would preclude a resource, such as a particular trade or craft work crew from working in more than one work area at a time due to restraints on resources or space. Examples of Work Area Coding include different areas within a floor of a building, different floors within a building, and different buildings within a complex of buildings.
Activities cannot have more than one Work Area Code.
3.3.6.4 Modification Number (MODF)
Assign a Modification Number Code to any activity or sequence of
SECTION 01 32 01.00 10 Page 4 activities added to the schedule as a result of a Contract Modification, when approved by Contracting Officer. Key all Code values to the Government's modification numbering system. An activity can have only one Modification Number Code.
3.3.6.5 Bid Item Coding (BIDI)
Assign a Bid Item Code to all activities using the Contract Line Item Number (CLIN) to which the activity belongs, even when an activity is not cost loaded. An activity can have only one BIDI Code.
3.3.6.6 Phase of Work Coding (PHAS)
Assign Phase of Work Code to all activities. Examples of phase of work are procurement phase and construction phase. Each activity can have only one Phase of Work code.
a. Code proposed fast track design and construction phases proposed to allow filtering and organizing the schedule by fast track design and construction packages.
b. If the contract specifies phasing with separately defined performance periods, identify a Phase Code to allow filtering and organizing the schedule accordingly.
3.3.6.7 Category of Work Coding (CATW)
Assign a Category of Work Code to all activities. Category of Work Codes include, but are not limited to construction submittal, procurement, fabrication, weather sensitive installation, non-weather sensitive installation, start-up, and testing activities. Each activity can have no more than one Category of Work Code.
3.3.6.8 Feature of Work Coding (FOW)
Assign a Feature of Work Code to appropriate activities based on the Definable Feature of Work to which the activity belongs based on the approved QC plan.
Definable Feature of Work is defined in Section 01 45 00 QUALITY CONTROL.
An activity can have only one Feature of Work Code.
3.3.7 Contract Milestones and Constraints
Milestone activities are to be used for significant project events including, but not limited to, project phasing, project start and end activities, or interim completion dates. The use of artificial float constraints such as "zero free float" or "zero total float" are prohibited.
Mandatory constraints that ignore or affect network logic are prohibited.
No constrained dates are allowed in the schedule other than those specified herein. Submit additional constraints to the Contracting Officer for approval on a case by case basis.
3.3.7.1 Project Start Date Milestone and Constraint
The first activity in the project schedule must be a start milestone titled "NTP Acknowledged," which must have a "Start On" constraint date
SECTION 01 32 01.00 10 Page 5 equal to the date that the NTP is acknowledged.
3.3.7.2 End Project Finish Milestone and Constraint
The last activity in the schedule must be a finish milestone titled "End Project."
Constrain the project schedule to the Contract Completion Date in such a way that if the schedule calculates an early finish, then the float calculation for "End Project" milestone reflects positive float on the longest path. If the project schedule calculates a late finish, then the "End Project" milestone float calculation reflects negative float on the longest path.
3.3.7.3 Interim Completion Dates and Constraints
Constrain contractually specified interim completion dates to show negative float when the calculated late finish date of the last activity in that phase is later than the specified interim completion date.
3.3.7.3.1 Start Phase
Use a start milestone as the first activity for a project phase. Call the start milestone "Start Phase X" where "X" refers to the phase of work.
3.3.7.3.2 End Phase
Use a finish milestone as the last activity for a project phase. Call the finish milestone "End Phase X" where "X" refers to the phase of work.
3.3.8 Adverse Weather
Ensure anticipated adverse weather is accounted for in the Project Schedule. AACE 84R-13 provides methodologies for techniques in planning for adverse weather. The preferred methodology is the use of a weather calendar. If a method other than a weather calendar is proposed, discuss the reason during the SEKO meeting.
3.3.9 Calendars
Schedule activities on a Calendar to which the activity logically belongs. Develop calendars to accommodate any contract defined work period such as a 7-day calendar for Government Acceptance activities, concrete cure times, etc. Develop the default Calendar to match the physical work plan with non-work periods identified including weekends and holidays. Develop Seasonal Calendar(s) and assign to seasonally affected activities as applicable.
If a weather calendar is used its implementation and execution is to be in accordance with AACE 84R-13
3.3.10 Open Ended Logic
Only two open ended activities are allowed: the first activity "NTP Acknowledged" is to have no predecessor logic, and the last activity -"End Project" is to have no successor logic. Except as noted above, each activity must have at least a start-to-start or finish-to-start relationship with its predecessor and a finish-to-finish or finish-to-start relationship with its successor.
SECTION 01 32 01.00 10 Page 6
Predecessor open ended logic may be allowed in a time impact analyses upon the Contracting Officer's approval.
3.3.11 Default Progress Data Disallowed
Actual Start and Finish dates must not automatically update with default mechanisms included in the scheduling software. Updating of the percent complete and the remaining duration of any activity must be independent functions. Disable program features that calculate one of these parameters from the other. Activity Actual Start (AS) and Actual Finish (AF) dates assigned during the updating process must match those dates provided in the Contractor Quality Control Reports. Failure to document the AS and AF dates in the Daily Quality Control report will result in disapproval of the Contractor's schedule.
3.3.12 Out-of-Sequence Progress
Activities that have progressed before all preceding logic has been satisfied (Out-of-Sequence Progress) will be allowed only on a case-by-case basis subject to approval by the Contracting Officer.
Propose logic corrections to eliminate out of sequence progress or justify not changing the sequencing for approval prior to submitting an updated project schedule. Address out of sequence progress or logic changes in the Narrative Report and in the periodic schedule update meetings.
3.3.13 Added and Deleted Activities
Do not delete activities from the project schedule or add new activities to the schedule without approval from the Contracting Officer. Activity ID and description changes are considered new activities and cannot be changed without Contracting Officer approval.
3.3.14 Original Durations
Activity Original Durations (OD) must be reasonable to perform the work item. OD changes are prohibited unless justification is provided and approved by the Contracting Officer.
3.3.15 Leads, Lags, and Start to Finish Relationships
Lags must be reasonable as determined by the Government and not used in place of realistic original durations, must not be in place to artificially absorb or create float, or to replace proper schedule logic.
a. Leads (negative lags) are prohibited.
b. Start to Finish (SF) relationships are prohibited.
3.3.16 Retained Logic
Schedule calculations must retain the logic between predecessors and successors ("retained logic" mode) even when the successor activity(s) starts and the predecessor activity(s) has not finished (out-of-sequence progress). Software features that in effect sever the tie between predecessor and successor activities when the successor has started and the predecessor logic is not satisfied ("progress override") are not be allowed.
SECTION 01 32 01.00 10 Page 7
3.3.17 Percent Complete
Update the percent complete for each activity started, based on the realistic assessment of earned value. Activities which are complete but for remaining minor punch list work and which do not restrain the initiation of successor activities may be declared 100 percent complete to allow for proper schedule management. Budgeted cost of activity is to be reduced by the amount needed to correct deficiency. The activity referenced in paragraph COST LOADING of CLOSEOUT ACTIVITIES must have its budgeted cost increased by this amount.
3.3.18 Remaining Duration
Update the remaining duration for each activity based on the number of estimated workdays it will take to complete the activity. Remaining duration may not mathematically correlate with percentage found under paragraph entitled Percent Complete. The remaining duration for unstarted activities are not to be less than its orginal duration.
3.3.19 Cost Loading of Closeout Activities
Cost load the "Correction of punch list from Government pre-final inspection" activity(ies) not less than 1 percent of the present contract value. Activity(ies) may be declared 100 percent complete upon the Government's verification of completion and correction of all punch list work identified during Government pre-final inspection(s).
3.3.19.1 As-Built Drawings
If there is no separate contract line item (CLIN) for as-built drawings, cost load the "Submission and approval of as-built drawings" activity not less than $35,000 or 1 percent of the present contract value, which ever is greater, up to $200,000. Activity will be declared 100 percent complete upon the Government's approval.
3.3.20 Early Completion Schedule and the Right to Finish Early
An Early Completion Schedule is an Initial Project Schedule (IPS) that indicates all scope of the required contract work will be completed before the contractually required completion date.
a. No IPS indicating an Early Completion will be accepted without being fully resource-loaded (including crew sizes and hours) and the Government agreeing that the schedule is reasonable and achievable.
b. The Government is under no obligation to accelerate work items it is responsible for to ensure that the early completion is met nor is it responsible to modify incremental funding (if applicable) for the project to meet the contractor's accelerated work.
3.4 PROJECT SCHEDULE SUBMISSIONS
Provide the submissions as described below. The data reports and network diagrams required for each submission are contained in paragraph SUBMISSION REQUIREMENTS. If the Contractor fails or refuses to furnish the information and schedule updates as set forth herein, the Contractor will be deemed not to have provided an estimate upon which a progress payment can be made.
SECTION 01 32 01.00 10 Page 8
Review comments made by the Government on the schedule(s) do not relieve the Contractor from compliance with requirements of the Contract Documents.
3.4.1 Preliminary Project Schedule Submission
Within 15 calendar days after the NTP is acknowledged, submit the Preliminary Project Schedule defining the planned operations detailed for the first 90 calendar days for approval. The approved Preliminary Project Schedule will be used for payment purposes not to exceed 90 calendar days after NTP. Completely cost load the Preliminary Project Schedule to balance the contract award CLINS shown on the Price Schedule. The Preliminary Project Schedule may be summary in nature for the remaining performance period. It must be early start and late finish constrained and logically tied as specified. The Preliminary Project Schedule forms the basis for the Initial Project Schedule specified herein and must include all of the required plan and program preparations, submissions and approvals identified in the contract (for example, Quality Control Plan, Safety Plan, and Environmental Protection Plan) as well as design activities, planned submissions of all early design packages, permitting activities, design review conference activities, and other non-construction activities intended to occur within the first 90 calendar days. Government acceptance of the associated design package(s) and all other specified Program and Plan approvals must occur prior to any planned construction activities. Code activities that are summary in nature, after the first 90 calendar days, with the following activity codes: Bid Item (CLIN) code (BIDI), Responsibility Code (RESP), and Feature of Work code (FOW)..
3.4.2 Initial Project Schedule Submission
Submit the Initial Project Schedule for approval within 42 calendar days after notice to proceed is issued. The schedule must demonstrate a reasonable and realistic sequence of activities which represent all work through the entire contract performance period. No payment will be made for work items not fully detailed in the Project Schedule.
3.5 SUBMISSION REQUIREMENTS
Submit the following items for the Preliminary Schedule, Initial Schedule, and every Periodic Schedule Update throughout the life of the project:
3.5.1 Schedule Reports
The format, filtering, organizing, and sorting for each schedule report will be as directed by the Contracting Officer. Typically, reports contain Activity Numbers, Activity Description, Original Duration, Remaining Duration, Early Start Date, Early Finish Date, Late Start Date, Late Finish Date, Total Float, Actual Start Date, Actual Finish Date, and Percent Complete. Provide the reports electronically in .pdf format. The following lists typical reports that will be requested:
3.5.1.1 Earnings Report by CLIN
A compilation of the Total Earnings on the project from the NTP to the data date, which reflects the earnings of activities based on the agreements made in the schedule update meeting defined herein. Provided a complete schedule update has been furnished, this report serves as the basis of determining progress payments. Group activities by CLIN number and sort by activity number. Provide a total CLIN percent earned value, SECTION 01 32 01.00 10 Page 9
CLIN percent complete, and project percent complete. The printed report must contain the following for each activity: the Activity Number, Activity Description, Original Budgeted Amount, Earnings to Date, Earnings this period, Total Quantity, Quantity to Date, and Percent Complete (based on cost).
3.5.2 Network Diagram
The Network Diagram is required for the Preliminary, Initial and Periodic Updates. Depict and display the order and interdependence of activities and the sequence in which the work is to be accomplished. The Contracting Officer will use, but is not limited to, the following conditions to review compliance with this paragraph:
3.5.2.1 Continuous Flow
Show a continuous flow from left to right with no arrows from right to left. Show the activity number, description, duration, and estimated earned value on the diagram.
3.5.2.2 Project Milestone Dates
Show dates on the diagram for start of project, any contract required interim completion dates, and contract completion dates.
3.5.2.3 Critical Path
Show all activities on the critical path. The critical path is defined as the longest path.
3.5.2.4 Grouping and Sorting
Group and sort activities as directed to assist in the understanding of the activity sequence. Typically, this flow will group activities by major elements of work, category of work, work area and/or responsibility.
3.6 WEEKLY PROGRESS MEETINGS
Conduct a weekly meeting with the Government for the purpose of jointly reviewing the actual progress of the project as compared to the as planned progress and to review planned activities for the upcoming two weeks. Use the current approved schedule update for the purposes of this meeting and for the production and review of reports. At the weekly progress meeting, address the status of RFIs, RFPs and Submittals.
3.7 REQUESTS FOR TIME EXTENSIONS
ASCE 67-17 provides delay analysis guidelines. If there is a conflict between the contract and guidance provided in ASCE 67-17 , the contract will govern. Provide justification of delay to the Contracting Officer in accordance with the contract provisions and clauses for approval, within 10 days of a delay occuring. Also prepare a time impact analysis for each Government request for proposal (RFP).
3.7.1 Justification of Delay
Provide a description of the event(s) that caused the delay and/or impact to the work. As part of the description, identify all schedule activities impacted. Show that the event that caused the delay/impact was the
SECTION 01 32 01.00 10 Page 10 responsibility of the Government. Provide a time impact analysis that demonstrates the effects of the delay or impact on the project completion date, or interim completion date(s). Evaluate multiple impacts chronologically; each with its own justification of delay. With multiple impacts consider any concurrency of delay. A time extension and the schedule fragnet becomes part of the project schedule and all future schedule updates upon approval by the Contracting Officer.
3.7.2 Changes That Do Not Cause Delay
If it is determined that a change does not constitute a schedule time extension, a fragnet as described in paragraph FRAGMENTARY NETWORK, is to be created and inserted into the Project schedule.
3.7.3 Time Impact Analysis (Prospective Analysis)
Submit requests for time extensions based on a prospective analysis if the work involved or the impact identified has not already occurred. Where the impact is ongoing a prospective analysis may be considered. However, the Government reserves the right to require a retrospective analysis be prepared after the impact has ended.
Prepare a time impact analysis for approval by the Contracting Officer based on industry recommended practice AACE 52R-06 . Utilize a copy of the last approved schedule prior to the first day of the impact or delay for the time impact analysis. If Contracting Officer determines the time frame between the last approved schedule and the first day of impact is too great, prepare an interim updated schedule to perform the time impact analysis. Unless approved by the Contracting Officer, no other changes may be incorporated into the schedule being used to justify the time impact.
3.7.4 Time Extension
The Contracting Officer must approve the Justification of Delay including the time impact analysis before a time extension will be granted. No time extension will be granted unless the delay consumes all available Project Float and extends the projected finish date ("End Project" milestone) beyond the Contract Completion Date. The time extension will be in calendar days.
Actual delays that are found to be caused by the Contractor's own actions, which result in a calculated schedule delay, are not a cause for an extension to the performance period, completion date, or any interim milestone date.
3.7.5 Impact to Early Completion Schedule
No extended overhead will be paid for delay prior to the original Contract Completion Date for an Early Completion IPS unless the Contractor actually performed work in accordance with that Early Completion Schedule. The Contractor must show that an early completion was achievable had it not been for the impact.
3.8 FAILURE TO ACHIEVE PROGRESS
Should the progress fall behind the approved project schedule for reasons other than those that are excusable within the terms of the contract, the Contracting Officer may require provision of a written recovery plan for
SECTION 01 32 01.00 10 Page 11 approval. The plan must detail how progress will be made-up to include which activities will be accelerated by adding additional crews, longer work hours, extra workdays, etc.
3.8.1 Artificially Improving Progress
Artificially improving progress by means such as, but not limited to, revising the schedule logic, modifying, or adding constraints, shortening activity durations, or changing calendars in the project schedule is prohibited. Indicate assumptions made and the basis for any logic, constraint, duration, and calendar changes used in the creation of the recovery plan. Any additional resources, manpower, or daily and weekly work hour changes proposed in the recovery plan must be evident at the work site and documented in the daily report along with the Schedule Narrative Report.
3.8.2 Failure to Perform
Failure to perform work and maintain progress in accordance with the supplemental recovery plan may result in an interim and final unsatisfactory performance rating and may result in corrective action directed by the Contracting Officer pursuant to FAR 52.236-15 Schedules for Construction Contracts, FAR 52.249-10 Default (Fixed-Price Construction), and other contract provisions.
3.8.3 Recovery Schedule
Should the Contracting Officer find it necessary, submit a recovery schedule pursuant to FAR 52.236-15 Schedules for Construction Contracts.
3.9 OWNERSHIP OF FLOAT
Except for the provision given in the paragraph IMPACT TO EARLY COMPLETION SCHEDULE, float available in the schedule, at any time, belongs to the Project and is available for Contractor and Government use. This includes activity and project float. Activity float is the number of workdays that an activity can be delayed without causing a delay to the "End Project" finish milestone. Project float (if applicable) is the number of work days between the projected early finish and the "End Project" finish.
SECTION 01 32 01.00 10 Page 12
SECTION 01 33 00
SUBMITTAL PROCEDURES
08/18, CHG 4: 02/21
PART 1 GENERAL
1.1 SUMMARY
1.1.1 Submittal Information
The Contracting Officer may request submittals in addition to those specified when deemed necessary to adequately describe the work covered in the respective sections. Each submittal is to be complete and in sufficient detail to allow ready determination of compliance with contract requirements.
Units of weights and measures used on all submittals are to be the same as those used in the contract drawings.
1.1.2 Project Type
The Contractor's Quality Control (CQC) System Manager are to check and approve all items before submittal and stamp, sign, and date indicating action taken. Proposed deviations from the contract requirements are to be clearly identified. Include within submittals items such as:
Contractor's, manufacturer's, or fabricator's drawings; descriptive literature including (but not limited to) catalog cuts, diagrams, operating charts or curves; test reports; test cylinders; samples; O&M manuals (including parts list); certifications; warranties; and other such required submittals.
1.1.3 Submission of Submittals
Schedule and provide submittals requiring Government approval before acquiring the material or equipment covered thereby. Pick up and dispose of samples not incorporated into the work in accordance with manufacturer's Safety Data Sheets (SDS) and in compliance with existing laws and regulations.
1.2 DEFINITIONS
1.2.1 Submittal Descriptions (SD)
Submittal requirements are specified in the technical sections. Examples and descriptions of submittals identified by the Submittal Description (SD) numbers and titles follow:
SD-01 Preconstruction Submittals
Submittals that are required prior to or at the start of construction (work) or the next major phase of the construction on a multiphase contract.
Government approved Division 01 preconstruction submittals that are required prior to or commencing with the start of work must be submitted within 30 calendar days of contract award unless specified elsewhere in the specifications.
SECTION 01 33 00 Page 1
Preconstruction Submittals include schedules and a tabular list of locations, features, and other pertinent information regarding products, materials, equipment, or components to be used in the work.
Certificates Of Insurance
Surety Bonds
List Of Proposed Subcontractors
List Of Proposed Products
Submittal Register
Schedule Of Prices Or Earned Value Report
Accident Prevention Plan
Work Plan
Quality Control (QC) plan
Environmental Protection Plan
SD-02 Shop Drawings
Drawings, diagrams and schedules specifically prepared to illustrate some portion of the work.
Diagrams and instructions from a manufacturer or fabricator for use in producing the product and as aids to the Contractor for integrating the product or system into the project.
Drawings prepared by or for the Contractor to show how multiple systems and interdisciplinary work will be coordinated.
SD-03 Product Data
Catalog cuts, illustrations, schedules, diagrams, performance charts, instructions and brochures illustrating size, physical appearance and other characteristics of materials, systems or equipment for some portion of the work.
Samples of warranty language when the contract requires extended product warranties.
SD-06 Test Reports
Report signed by authorized official of testing laboratory that a material, product or system identical to the material, product or system to be provided has been tested in accord with specified requirements. Unless specified in another section, testing must have been within three years of date of contract award for the project.
Report that includes findings of a test required to be performed on an actual portion of the work or prototype prepared for the project before shipment to job site.
SECTION 01 33 00 Page 2
Report that includes finding of a test made at the job site or on sample taken from the job site, on portion of work during or after installation.
Investigation reports
Daily logs and checklists
Final acceptance test and operational test procedure
SD-07 Certificates
Statements printed on the manufacturer's letterhead and signed by responsible officials of manufacturer of product, system or material attesting that the product, system, or material meets specification requirements. Must be dated after award of project contract and clearly name the project.
Document required of Contractor, or of a manufacturer, supplier, installer or Subcontractor through Contractor. The document purpose is to further promote the orderly progression of a portion of the work by documenting procedures, acceptability of methods, or personnel qualifications.
Confined space entry permits
Text of posted operating instructions
SD-08 Manufacturer's Instructions
Preprinted material describing installation of a product, system or material, including special notices and Safety Data Sheets(SDS)concerning impedances, hazards and safety precautions.
SD-11 Closeout Submittals
Documentation to record compliance with technical or administrative requirements or to establish an administrative mechanism.
Submittals required for Guiding Principle Validation (GPV) or Third Party Certification (TPC).
Special requirements necessary to properly close out a construction contract. For example, Record Drawings and as-built drawings. Also, submittal requirements necessary to properly close out a major phase of construction on a multi-phase contract.
1.2.2 Approving Authority
Office or designated person authorized to approve the submittal.
1.2.3 Work
As used in this section, on-site and off-site construction required by contract documents, including labor necessary to produce submittals, construction, materials, products, equipment, and systems incorporated or to be incorporated in such construction. In exception, excludes work to produce SD-01 submittals.
SECTION 01 33 00 Page 3
1.3 SUBMITTALS
Government approval is required for submittals with a "G" or "S" classification. Submittals not having a "G" or "S" classification are for information only. Submit the following in accordance with Section
01 33 00 SUBMITTAL PROCEDURES:
SD-01 Preconstruction Submittals
Submittal Register; G
1.4 SUBMITTAL CLASSIFICATION
1.4.1 Government Approved (G)
Government approval is required for extensions of design, critical materials, variations, equipment whose compatibility with the entire system must be checked, and other items as designated by the Government.
Within the terms of the Contract Clause SPECIFICATIONS AND DRAWINGS FOR CONSTRUCTION, submittals are considered to be "shop drawings."
1.4.2 For Information Only
Submittals not requiring Government approval will be for information only. Within the terms of the Contract Clause SPECIFICATIONS AND DRAWINGS FOR CONSTRUCTION, they are not considered to be "shop drawings."
1.5 PREPARATION
1.5.1 Transmittal Form
Use the ENG Form 4025-R transmittal form for submitting both Government-approved and information-only submittals. Submit in accordance with the instructions on the reverse side of the form. These forms or similar forms will be furnished to the Contractor. Properly complete this form by filling out all the heading blank spaces and identifying each item submitted. Exercise special care to ensure proper listing of the specification paragraph and sheet number of the contract drawings pertinent to the data submitted for each item.
1.5.2 Submittal Format
1.5.2.1 Format of SD-01 Preconstruction Submittals
When the submittal includes a document that is to be used in the project, or is to become part of the project record, other than as a submittal, do not apply the Contractor's approval stamp to the document itself, but to a separate sheet accompanying the document.
Provide data in the unit of measure used in the contract documents.
1.5.2.2 Format for SD-02 Shop Drawings
Provide shop drawings not less than 8 1/2 by 11 inches nor more than 30 by 42 inches, except for full-size patterns or templates. Prepare drawings to accurate size, with scale indicated, unless another form is required.
Ensure drawings are suitable for reproduction and of a quality to produce clear, distinct lines and letters, with dark lines on a white background.
SECTION 01 33 00 Page 4
a. Include the nameplate data, size, and capacity on drawings. Also include applicable federal, military, industry, and technical society publication references.
b. Dimension drawings, except diagrams and schematic drawings. Prepare drawings demonstrating interface with other trades to scale. Use the same unit of measure for shop drawings as indicated on the contract drawings. Identify materials and products for work shown.
Submit an electronic copy of drawings in PDF format and native electronic format.
1.5.2.2.1 Drawing Identification
Include on each drawing the drawing title, number, date, and revision numbers and dates, in addition to information required in paragraph
IDENTIFYING SUBMITTALS.
Number drawings in a logical sequence. Each drawing is to bear the number of the submittal in a uniform location next to the title block. Place the Government contract number in the margin, immediately below the title block, for each drawing.
1.5.2.3 Format of SD-03 Product Data
Present product data submittals for each section. Include a table of contents, listing the page and catalog item numbers for product data.
Indicate, by prominent notation, each product that is being submitted;
indicate the specification section number and paragraph number to which it pertains.
1.5.2.3.1 Product Information
Supplement product data with material prepared for the project to satisfy the submittal requirements where product data does not exist. Identify this material as developed specifically for the project, with information and format as required for submission of SD-07 Certificates.
Provide product data in units used in the Contract documents. Where product data are included in preprinted catalogs with another unit, submit the dimensions in contract document units, on a separate sheet.
1.5.2.3.2 Standards
Where equipment or materials are specified to conform to industry or technical-society reference standards of such organizations as the American National Standards Institute (ANSI), ASTM International (ASTM), National Electrical Manufacturer's Association (NEMA), Underwriters Laboratories (UL), or Association of Edison Illuminating Companies (AEIC), submit proof of such compliance. The label or listing by the specified organization will be acceptable evidence of compliance. In lieu of the label or listing, submit a certificate from an independent testing organization, competent to perform testing, and approved by the Contracting Officer. State on the certificate that the item has been tested in accordance with the specified organization's test methods and that the item complies with the specified organization's reference standard.
SECTION 01 33 00 Page 5
1.5.2.3.3 Data Submission
Collect required data submittals for each specific material, product, unit of work, or system into a single submittal that is marked for choices, options, and portions applicable to the submittal. Mark each copy of the product data identically. Partial submittals will not be accepted for expedition of the construction effort.
Submit the manufacturer's instructions before installation.
1.5.2.4 Format of SD-04 Samples
1.5.2.4.1 Sample Characteristics
Furnish samples in the following sizes, unless otherwise specified or unless the manufacturer has prepackaged samples of approximately the same size as specified:
a. Sample of Equipment or Device: Full size.
b. Sample of Materials Less Than 2 by 3 inches: Built up to 8 1/2 by 11 inches.
c. Sample of Materials Exceeding 8 1/2 by 11 inches: Cut down to 8 1/2 by 11 inches and adequate to indicate color, texture, and material variations.
d. Sample of Linear Devices or Materials: 10 inch length or length to be supplied, if less than 10 inches. Examples of linear devices or materials are conduit and handrails.
e. Sample Volume of Nonsolid Materials: Pint. Examples of nonsolid materials are sand and paint.
f. Color Selection Samples: 2 by 4 inches. Where samples are specified for selection of color, finish, pattern, or texture, submit the full set of available choices for the material or product specified. Sizes and quantities of samples are to represent their respective standard unit.
g. Sample Panel: 4 by 4 feet.
h. Sample Installation: 100 square feet.
1.5.2.4.2 Sample Incorporation
Reusable Samples: Incorporate returned samples into work only if so specified or indicated. Incorporated samples are to be in undamaged condition at the time of use.
Recording of Sample Installation: Note and preserve the notation of any area constituting a sample installation, but remove the notation at the final clean-up of the project.
1.5.2.4.3 Comparison Sample
Samples Showing Range of Variation: Where variations in color, finish, pattern, or texture are unavoidable due to nature of the materials, submit
SECTION 01 33 00 Page 6 sets of samples of not less than three units showing extremes and middle of range. Mark each unit to describe its relation to the range of the variation.
When color, texture, or pattern is specified by naming a particular manufacturer and style, include one sample of that manufacturer and style, for comparison.
1.5.2.5 Format of SD-05 Design Data
Provide design data and certificates on 8 1/2 by 11 inch paper.
1.5.2.6 Format of SD-06 Test Reports
By prominent notation, indicate each report in the submittal. Indicate the specification number and paragraph number to which each report pertains.
1.5.2.7 Format of SD-07 Certificates
Provide design data and certificates on 8 1/2 by 11 inch paper.
1.5.2.8 Format of SD-08 Manufacturer's Instructions
Present manufacturer's instructions submittals for each section. Include the manufacturer's name, trade name, place of manufacture, and catalog model or number on product data. Also include applicable federal, military, industry, and technical-society publication references. If supplemental information is needed to clarify the manufacturer's data, submit it as specified for SD-07 Certificates.
Submit the manufacturer's instructions before installation.
1.5.2.8.1 Standards
Where equipment or materials are specified to conform to industry or technical-society reference standards of such organizations as the American National Standards Institute (ANSI), ASTM International (ASTM), National Electrical Manufacturer's Association (NEMA), Underwriters Laboratories (UL), or Association of Edison Illuminating Companies (AEIC), submit proof of such compliance. The label or listing by the specified organization will be acceptable evidence of compliance. In lieu of the label or listing, submit a certificate from an independent testing organization, competent to perform testing, and approved by the Contracting Officer. State on the certificate that the item has been tested in accordance with the specified organization's test methods and that the item complies with the specified organization's reference standard.
1.5.2.9 Format of SD-09 Manufacturer's Field Reports
By prominent notation, indicate each report in the submittal. Indicate the specification number and paragraph number to which each report pertains.
1.5.2.10 Format of SD-10 Operation and Maintenance Data (O&M)
Comply with the requirements specified in Section 01 78 23 OPERATION AND MAINTENANCE DATA for O&M Data format.
SECTION 01 33 00 Page 7
1.5.2.11 Format of SD-11 Closeout Submittals
When the submittal includes a document that is to be used in the project or is to become part of the project record, other than as a submittal, do not apply the Contractor's approval stamp to the document itself, but to a separate sheet accompanying the document.
Provide data in the unit of measure used in the contract documents.
1.5.3 Source Drawings for Shop Drawings
1.5.3.1 Source Drawings
The entire set of source drawing files (DWG) will not be provided to the Contractor. Request the specific Drawing Number for the preparation of shop drawings. Only those drawings requested to prepare shop drawings will be provided. These drawings are provided only after award.
1.5.3.2 Terms and Conditions
Data contained on these electronic files must not be used for any purpose other than as a convenience in the preparation of construction data for the referenced project. Any other use or reuse is at the sole risk of the Contractor and without liability or legal exposure to the Government. The Contractor must make no claim, and waives to the fullest extent permitted by law any claim or cause of action of any nature against the Government, its agents, or its subconsultants that may arise out of or in connection with the use of these electronic files. The Contractor must, to the fullest extent permitted by law, indemnify and hold the Government harmless against all damages, liabilities, or costs, including reasonable attorney's fees and defense costs, arising out of or resulting from the use of these electronic files.
These electronic source drawing files are not construction documents.
Differences may exist between the source drawing files and the corresponding construction documents. The Government makes no representation regarding the accuracy or completeness of the electronic source drawing files, nor does it make representation to the compatibility of these files with the Contractor hardware or software. The Contractor is responsible for determining if any conflict exists. In the event that a conflict arises between the signed and sealed construction documents prepared by the Government and the furnished source drawing files, the signed and sealed construction documents govern.