Attachment 0002 - Repair Beck Avenue SOW PR 2024-0236.pdf
PDF 341 KB Posted
- Solicitation number
- W519TC-25-R-A006
About this file
This document is a Scope of Work (SOW) for a construction project at Rock Island Arsenal in Rock Island, IL. The project involves repairing Beck Avenue from the east side of Sylvan Drive intersection to the east entrance of building 212, spanning stations 115+00.00 to 130+75.00. Key work activities include demolition and removal of existing roadway, regrading Beck Avenue, removing and installing new storm and sanitary sewer, and constructing new pavement.
Specific construction requirements include installing 9-inch Portland Cement Concrete (P.C.C.) pavement with reinforcement, 6-inch curb and gutter, 12-inch modified subbase, and subdrain tile. The parking lot 2G will receive 2-3 inches of hot mix asphalt (HMA). The project will be constructed using the Iowa State Urban Design and Specifications Program (SUDAS) 2024, with a contract duration of 160 working days. The contractor will be responsible for environmental compliance, including managing contaminated soil and groundwater, storm water pollution prevention, and adhering to various environmental regulations and best practices.
View the file
Other files
Show all 13
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Rock Island Arsenal Scope of Work
PR #2024-0236
Repair Beck Avenue Sylvan Drive to Building 212 East Entrance
US Army Garrison‐Rock Island Arsenal
Directorate of Public Works Engineering and Services Division
AMIM‐RIP‐G
1 Rock Island Arsenal
Rock Island, IL 61299‐5000
Project # 2024-0236 Repair Beck Avenue – Sylvan Drive to Building 212 East Entrance
2 | P a g e
PROJECT SUMMARY: The scope of this project consists of furnishing labor, equipment and material to fully grade and repave the Beck Avenue corridor. The project also includes removing existing storm and sanitary sewer. Realigning and installing new storm and sanitary sewer. The project is located along Beck Avenue, starting at the east side of the Sylvan Dive intersection and finishing at the east entrance of building 212 parking lot on the Rock Island Arsenal, Rock Island, IL.
1. PART ONE: SPECIFIC PROJECT
PROJECT DESCRIPTION: US Army Garrison – Rock Island Arsenal (RIA) is seeking a construction project to grade and pave Beck Avenue from the east side of the Sylvan Drive intersection to the east entrance of building 212. Construction shall also include removing and installing new storm and sanitary sewer from the south side of building 212 to building 295. The Contractor shall provide construction services for the project. The premise for this project is to remove the existing pavement outlined in the plans, regrade Beck Avenue from station 115+00.00 to station 130+75.00, remove all storm and sanitary sewer listed in the existing removal (ER) sheets found in Appendix A. Install new storm and sanitary sewer and place new pavement. Beck Avenue along with existing parking lots and parking lot entrances shall be 9-inch Portland Cement Concrete (P.C.C.) with reinforcement at the joints with a standard 6-inch curb and gutter at 30-inch width, placed on a 12-inch modified subbase. The parking lot pavement of lot 2G shall be 2-3” lifts of hot mix asphalt (HMA). Subdrain tile shall be installed along the Beck Avenue gutter line and tied into new storm intakes. All green space areas disturbed during construction shall receive 6” of topsoil and hydro seed, fertilizer and mulch. The project shall be constructed using the Iowa State Urban Design and Specifications Program (SUDAS) 2024. The technical criteria contained and cited in this Scope of Work (SOW) and all accompanying appendices shall establish the minimum construction standards for this project. The Contractor shall make the Government aware in writing of any conflicts within these minimum standards by informing the Contracting Officer’s Representative (COR). The KO/COR reserves the right to determine how conflicting standards shall be resolved. This project will require the following work activities:
1.1.1 Demolition and removal of existing roadway of Beck Avenue from station
115+00.00 to station 130+75.00. The existing dumpster staging area located near the northwest corner of building 230, a small portion of Kingsbury Avenue located in front of building 212 and a small portion of Flagler Street at the entrance of the 2G parking lot.
1.1.2 Demolition and removal of the existing pavement in parking lot 2G and 2Z along the existing and proposed route of the storm and sanitary sewer.
1.1.3 Regrade Beck Avenue.
1.1.4 Install subdrain tile on Beck Avenue, see Appendix A “D sheets” for locations.
1.1.5 Remove and replace the existing storm and sanitary sewer located in and around building 212/230 and tying into the existing storm and sanitary sewer at the southwest corner of building 299 and building 295.
1.1.6 Horizontally drill the proposed sanitary sewer near the southwest corner of building 299.
3 | P a g e
1.1.7 Fill and plug the existing 30” sanitary sewer near the northwest corner of building 299.
1.1.8 Fill and plug the existing 10” sanitary sewer under the existing railroad tracks located along Kingsbury Avenue.
1.1.9 Install 9” P.C.C. pavement with 12” modified subbase, steel reinforcement with a standard 6” curb on Beck Avenue.
1.1.10 Form and pour a 4’X 5’ P.C.C. storm sewer box to be connected to building 295 pump station.
1.1.11 Remove existing perimeter fence along the west side of building 299.
1.1.12 Install signage and pavement markings in the existing parking lots and new road.
1.1.13 Place 6” of topsoil in locations labeled in the plan set found in Appendix A.
1.1.14 Hydro seed fertilize and mulch all disturbed green space areas.
1.2 SPECIAL SERVICES/REQUIREMENTS
1.2.1 Contractor shall provide all services, labor, materials, supervision, equipment, tools, etc. necessary to accomplish the work described in this SOW.
1.2.2 Disruption of the tenants and their missions shall be minimized. Any potential interferences with the tenants or the rest of the Rock Island Arsenal’s (RIA) services, personnel or entities shall be coordinated with the KO/COR in an effort minimize disruption. The contractor shall maintain continued access to all buildings in the area. Detour signs may be required. Fire and emergency service access to all adjacent buildings to the project must be maintained through the entire project.
1.2.3 The contractor shall submit a phasing plan of execution. A 48-hour notice must be given to the Department of Public works prior to any temporary closure or change in plan.
1.2.4 This project shall be constructed in accordance with the 2024 edition of the SUDAS Specifications unless otherwise noted.
1.2.5 It shall be the responsibility of the contractor to protect all existing utilities and paved streets, including any not shown on these drawings. The contractor shall verify all existing utilities prior to construction and notify the engineer of record and department of public works if any conflicts with the drawings occur. Any damage to existing utilities caused by trenching and grading operations shall be repaired at the contractor's expense. Existing utility locations shown on the drawings are approximate. It is possible that there are other utilities whose existence is presently not known or shown. It shall be the contractor's responsibility to determine the type and location of underground utilities and to avoid damage thereto. Minor conflict with underground utilities that are abandoned but not removed by the owner of the utility shall be removed as necessary for the construction of the project by the contractor. Removal shall be incidental to the job.
1.2.6 The contractor shall be responsible for field verifying all existing utility locations including but not limited to storm sewer, sanitary sewer, manholes, gas mains, fiber optic duct banks, water mains, electrical and telecommunications.
1.2.7 The Department of Public Works (DPW) shall have access to the project for construction and to make extensions or adjustments of services.
4 | P a g e
1.2.8 All unsuitable material, construction debris resulting from construction operations shall be properly disposed of off-site in accordance with local, state and federal guidelines.
1.2.9 It shall be the contractor's responsibility to provide waste areas or disposal sites for excess or undesirable material. This material is not to be incorporated in the work involved in this project. Overhaul will not be accepted on this project.
1.2.10 The contractor shall prevent silt and debris from entering storm sewers and culverts and shall remove any such material that enters them. Care shall be taken to prevent storm water from undermining the pavement during construction. If areas become undermined, they shall be repaired in a manner acceptable to the engineer/KO/COR representative. Pressure grouting may be required.
1.2.11 The contractor shall be responsible for keeping adjacent streets free from excessive build-up of soil and/or granular material from the project. The contractor shall clean excess soil and other material from the adjacent streets as required by the engineer/KO/COR representative. Any damage done to existing streets shall be repaired at the contractor's expense.
1.2.12 The contractor shall take measures to prevent the spread of dust from the construction areas and haul routes, which include the application of water as directed by the engineer/KO/COR representative. This work shall be considered incidental to earth excavation.
1.2.13 When not initiated at an existing joint, removal of existing concrete pavement, asphalt or concrete drives and sidewalks shall be initiated with full depth saw cuts, exercising extreme care to avoid surface breaks and spalling. If surface breaks or spalling occur, additional removal and replacement shall be made at the contractor's expense. The cost of saw cuts shall be considered incidental to the cost of construction.
1.2.14 Special care shall be taken forming at intersections so that the profiles and grades obtained are as shown on the plans and grade sheets. Short lengths of forms or flexible forms may be necessary at these locations.
1.2.15 All concrete shall utilize a SUDAS C-4WR-C15 mix design and have a compressive strength of 3,500 psi at 14 days and 4,000 psi at 28 days.
1.2.16 The contractor shall notify the engineer immediately if any discrepancies are encountered between the plans and specifications and the existing filed conditions. Work warranting a change in scope shall be submitted to the KO/COR within 30 days of notice or the contractor will forfeit rights to compensation for the work.
1.2.17 Pumping ground water and/or storm water from open trenches shall be considered incidental to the contract.
1.2.18 Construction staking shall be the responsibility of the contractor. The contractor and survey crew and company shall be considered competent and responsible for reporting any discrepancies or unforeseen project errors before and during construction staking to ensure blunders and misinformation is not constructed in the field. If an apparent error in the design is discovered during construction staking of the project, the contractor and or survey crew and company shall cease construction and report it to KO/COR immediately so the error may be corrected
5 | P a g e as soon as possible. Any lost work time, labor or equipment fee will not be paid during work stoppage due to unforeseen error.
1.2.19 Machine controlled grading is required on this project.
1.2.20 All existing storm and sanitary information shall be considered a reference and is the responsibility of the contractor verify in the field prior to construction.
1.2.21 The contracting authority reserves the right to keep any/all removed material that includes but is not limited to manholes and storm sewer pipe. If the contracting authority elects not to keep removed material, the material becomes the property of the contractor and is responsible for the disposal/removal from the project.
1.2.22 No overhaul on this project.
1.2.23 A pipe laser shall be used on storm and sanitary sewer to verify line and grade.
1.2.24 SUDAS specifications 4060 Cleaning, Inspection and Testing shall be enforced on this project. Video inspectors shall be NASSCO, PACP certified.
1.2.25 Manhole castings shall be 2-piece fixed castings. All castings shall comply with
SUDAS Figures SW-601 and SW-602. Concrete box outs for manholes in P.C.C.
paving shall comply with SUDAS Figure PV-103. Concrete box outs for manholes in hot mix asphalt paving shall comply with figure PV-201. All manholes shall be gasketed.
1.2.26 The contractor shall work/grade around trees not noted for removal. The objective is not to harm any existing tress that do not need to be removed.
1.2.27 The contractor shall submit a Storm Water Pollution Prevention Plan (SWPPP) to the KO/COR or project engineer, prior to the commencing of the project.
1.2.28 The contractor shall provide all labor, equipment and material required to execute the SWPPP.
1.3 BASE BID
The Base Bid consists of providing all labor and materials construct the Beck Avenue roadway corridor from the east side of the intersection of Beck Avenue and Sylvan Drive (station 115+00.00) to the east entrance of building 212 (station 130+75.00). Work includes, but is not limited to, construction of the roadway/parking lot, grading, paving and removing and installing new storm and sanitary sewer as identified in the attached plan set in Appendix A. This project shall be a working day contract. The contractor is allowed 160 working days to complete the project. The definition of a working day is defined in the SUDAS Specifications 1080. Failure in completing the project in the allotted 160 working days will result in a deduction at the liquidated damages rate of $1,000.00 (one thousand dollars) per working day until the project is completed.
1.4 BECK AVENUE - CONSTRUCTION
1.4.1 Mainline paving shall consist of 9” PCC pavement with a 12” modified subbase along with joint reinforcement steel. See “B Sheets” and “D Sheets” for specifics and details in the plan set of Appendix A.
1.4.2 All parking lot entrance and side streets shall be the same mix along with depth of pavement and subbase as the mainline of Beck Avenue.
1.4.3 The curb and gutter shall be a 6” standard curb and gutter see SUDAS Fig.
7010.102 (PV-102). The contracting authority reserves the right to change
6 | P a g e portions of the 6” curb and gutter to “Driveway Drop Curb” if it improves drainage or mobility.
1.4.4 A 4-foot granular shoulder, 6-inch thickness, shall be placed from station 115+00.00 to approximate station 125+62.36.
1.4.5 All disturbed areas shall be hydraulic seeded, fertilized and mulched. A native grass seed mix shall be applied to all green space from station 115+00.00 to station 125+62.35. If construction ceases due to inclement weather, the contractor shall apply a temporary cool seed mix and cover to prevent erosion on exposed areas. The seed window for the native grass mix is from April 1st to June 30th.
Seed windows for a permanent seed type 6 application apply between March 1st and May 31st and between August 10th and September 30th. Any seeding outside of this window requires the approval of the KO/COR or project engineer.
1.4.6 Reinstall existing and new signage and apply traffic striping and symbols.
1.4.7 6-inch corrugated PVC subdrain shall be installed from station 115+00.00 to station 130+75.00. Subdrain shall outlet in proposed storm sewer intakes or subdrain outlets into the proposed ditch area.
1.4.8 Remove all trees note noted in the “ER” sheets of the plan set found in Appendix A.
1.4.9 All proposed and disturbed green space areas shall receive 6 inches of topsoil.
Topsoil shall be free of organic and rock material.
1.4.10 Compaction testing is required.
1.5 STORM SEWER CONSTRUCTION
1.5.1 Remove all existing storm sewer pipe and manholes according to the “ER” sheets found in the plan set of Appendix A. Backfill all removed storm sewer pipes and structures according to the SUDAS specifications.
1.5.2 The contractor shall submit a plan to remove the existing twin 48-inch RCP storm sewer pipe under the existing railroad tracks on the west side of building 299.
1.5.3 The disturbed railroad beds shall receive a minimum 6 inch compacted subballast layer and a compacted minimum 8-inch depth of class 2 railroad ballast under the existing tracks. The gradation of material and typical can be found in the “C” sheets of the plan set in Appendix A.
1.5.4 An existing 6 linear feet of 48-inch RCP going into the existing sluice gate south of building 295 shall remain. A 2-foot section shall be plugged with the intention of being able to hook on to the existing sluice gate in the future.
1.5.5 A 4’ x 5’reinforced P.C.C. storm sewer box shall be formed and connected to the existing pump station at building 295. The connection shall be reinforced, #5 rebar, drilled 12 inches on center.
1.5.6 Proposed storm sewer shall be backfilled according to SUDAS figure 3010-102 Class R-2. Backfilling in around Building 295 and other sturcutres shall be in no more than 8-inch lifts with a plate compactor.
1.5.7 Watermain grade quality pipe is required at locations noted in the “ST” sheets in the plan set of Appendix A.
1.5.8 All locations requiring a pipe material change due to a water main nearby shall be fitted with a fernco connection.
1.5.9 Pipe joints shall be wrapped in engineering fabric.
7 | P a g e
1.6 SANITARY SEWER CONSTRUCTION
1.6.1 Remove all existing sanitary sewer pipe and manholes according to the “ER” sheets found in the plan set of Appendix A. Backfill all removed sanitary sewer pipes and structures according to the SUDAS specifications.
1.6.2 The 30-inch RCP sanitary sewer located at the northwest corner of building 299 shall be abandoned and filled with flowable mortar for approximately 400 linear feet. An additional 20 linear feet shall also be abandoned and filled with flowable mortar, located under the existing flood wall found at the southwest corner of building 299. A 10” vitrified clay pipe located under the existing railroad tracks adjacent to Kingsbury Avenue shall also be abandoned and filled with flowable mortar an approximate distance of 45 linear feet.
1.6.3 The proposed sanitary sewer shall be backfilled according to SUDAS figure
3010.103 Class F-2. Backfilling in around structures shall be in no more than 8-inch lifts with a plate compactor.
1.6.4 Watermain grade quality pipe is required at locations noted in the “SAN” sheets in the plan set of Appendix A.
1.6.5 All locations requiring a pipe material change due to a water main nearby shall be fitted with a fernco connection.
1.6.6 The proposed 12-inch PVC sanitary sewer shall be horizontally drilled with a 24-inch steel casing under the existing railroad tracks and under the existing flood wall located on the west side of building 299.
1.7 KINGSBURY AVENUE
1.7.1 Remove the existing P.C.C. pavement noted in the “ER” sheets in the plan set in
Appendix A.
1.7.2 Place 8-inch P.C.C. pavement, C-4WR-C15 mix on a 6-inch modified subbase.
1.7.3 Place 6-inch P.C.C. standard curb, 30-inch width on a 6-inch modified subbase.
1.7.4 The pavement jointing shall follow the requirements laid out on sheet B.03 in the plan set in Appendix A.
1.7.5 Remove and relocate the existing smoke hut. Place the smoke hut back in the existing location at the end of construction.
1.8 PARKING LOT 2G CONSTRUCITON
1.8.1 Remove the existing HMA pavement and P.C.C. curb and gutter marked for removal in the “ER” sheets of the plan set in Appendix A.
1.8.2 The existing card reader located near the northeast corner of parking lot shall remain undisturbed.
1.8.3 The new final pavement shall be 6 inches of HMA. The base course shall be a 4-inch lift, ¾” mix. The surface course shall be a 2-inch lift, ½” mix. The binder shall be a PG 58-28S. Placed on a compacted 6-inch modified subbase. A tack coat is required between lifts.
1.8.4 All disturbed parking stalls and existing striping shall be restriped in their respective color and size.
1.8.5 The curb and gutter along the north edge of the parking lot shall be a standard 6-inch curb and gutter, 24 inch in width on 6-inch modified subbase.
8 | P a g e
1.9 PARKING LOT 2Z
1.9.1 Remove the existing P.C.C. pavement and P.C.C. curb and gutter marked for removal in the “ER” sheets of the plan set in Appendix A.
1.9.2 Place 9-inch P.C.C. pavement, C-4WR-C15 mix on a 12-inch modified subbase.
1.9.3 Place 6-inch P.C.C. standard curb, 30-inch width on a 12-inch modified subbase.
1.9.4 The pavement jointing shall follow the requirements laid out on sheet B.03 in the plan set in Appendix A or match the existing joints adjacent to construction.
1.9.5 All disturbed parking stalls and existing striping shall be restriped in their respective color and size.
1.9.6 Remove and relocate the existing smoke hut. Place the smoke hut back in the existing location at the end of construction.
1.10 CONTAMINATED SOIL AND GROUND WATER
1.10.1 Contaminated soil and groundwater are present in and around the area of proposed construction. This contamination exceeds the Illinois Environmental Protection Agency (IEPA) Title 35 Illinois Administrative Code (IAC) Part 742 Tiered Approach to Corrective Action Objectives (TACO) Soil Remediation Objectives (SROs) and Groundwater Remediation Objectives (GROs). The contaminants are coal, coal ash, heavy metals, and semi-volatile organic compounds (SVOCs). Contamination is present at four locations along the south side of Beck Avenue, one location near the railroad tracks on the west side of building 299 adjacent to the former coal pile, and along a long section on the north side of Beck Avenue. These areas are highlighted on sheet CONTAM.01 in the plan sheets found in appendix “A”. Excavated soil in these areas cannot be reused and will need to be disposed of as a non-hazardous waste at an approved landfill. The contractor is responsible for the disposal of this material. Method of measurement for disposing of the contaminated soil shall be done by cubic yard (CY) removed. Method of measurement shall be counted by truck load; each truck shall be counted as 8 cubic yards. Truck load counts shall be submitted to the COR at the end of each workday to be counted. Truck load counts not submitted within 24 hours of hauling shall be omitted.
1.10.2 Groundwater contamination has been detected in the form of heavy metals in and around the area of construction for the storm sewer along the west side of building
299. The location of concern regarding ground water contamination is the storm sewer line noted and highlighted in red on sheet CONATM.01 in appendix “A” of the plan sheets. This contamination exceeds the IEPA Title 35 IAC Part 742 TACO GROs. Groundwater likely will not be encountered during the road replacement activities but will be encountered during the storm sewer line installation given the depth that excavation activities will be conducted. Per the IEPA General National Pollutant Discharge Elimination System (NPDES) Permit Number ILR10 that expires on August 31, 2028, any groundwater removed from the excavation must be done in such a manner as to provide pollution prevention measures for the discharging of the non-storm water component. RIA DPW will collect up to two groundwater samples for laboratory analysis in the contaminated areas identified above. The first groundwater sample is to be collected at the
9 | P a g e beginning of trenching activities assuming it will start at the downstream portion of the sewer line at building 295 and work northward. If the trenching activities along the above-mentioned north-south trending sections are still ongoing after one month, a second sample will be collected. The contractor is required to notify the COR in advance of trenching activities required to install the new storm sewer line in question. The groundwater samples will be submitted for laboratory analysis of the 23 Target Analyte List (TAL) metals, lithium, and hexavalent chromium. If the laboratory analytical results do not exceed the IEPA Title 35 IAC Part 302 Water Quality Standards for surface water discharge, then the groundwater can be discharged onto the ground surface. If the laboratory analytical results exceed the surface water standards, the contractor is responsible furnishing all labor material and equipment required for pumping, containerizing and properly disposing of the contaminated non-hazardous water.
1.10.3 Contaminated soil that is encountered during construction activities cannot be reused and must be properly disposed of at an approved landfill. This can be performed by staging it on plastic and covering with plastic for disposal later during construction activities or directly loading into dump trucks to be transported and disposed of at the approved landfill. It will be the contractor’s responsibility to identify a landfill to accept the contaminated soil and determine the landfill’s requirements (i.e. laboratory analytical data/soil sampling and sampling frequency (one sample per X tons) to dispose of the contaminated soil.
All soil sampling and associated costs will be the responsibility of the contractor.
1.11 MUNITIONS AND EXPLOSIVES CONCERN
1.11.1 For both the Beck Avenue replacement construction and the storm sewer line replacement, there are no known Munitions and Explosives of Concern (MEC) in those areas. Historically there were magazines in the grass area north of Beck Avenue, near the intersection of the railroad tracks and the south side of Beck Avenue, and in the parking north of Beck Avenue. These magazines were removed in the mid-1980s. A MEC survey was conducted in 2010 at the grass areas east and west of the railroad tracks north of Beck Avenue resulting in no MEC concerns being reported. No development or changes to the area has occurred since the MEC survey was completed. Excavation of contaminated soils were conducted at the former coal and ash pile area and no MEC or indications of the former magazine there were encountered in the northwest corner of the former coal pile. According to the 2010 MEC survey the two magazines under the parking lot were also removed at the same time as the other magazines.
1.12 ELECTRICAL CONSTRUCTION
1.12.1 The contractor shall relocate the existing handhole located along the south side of
Beck Avenue at the entrance of building 299. Relocation shall include providing new electric wire to feed the relocated 12-foot light poles. The size of the proposed wire shall match the size of the existing wire.
1.12.2 The contractor shall remove and relocate an existing 12-foot light poles. Location information can be found on sheet D.04 in the plan sheets of Appendix A. The contractor shall terminate the proposed electrical wire to the relocated light poles at the new location.
10 | P a g e
1.12.3 The light pole shall be mounted to a 2-foot diameter foundation. The foundation shall sit 6 inches above finished grade.
1.12.4 Final acceptance shall include the commissioning and testing of the relocated light pole per the article 300’s of the NEC code.
1.12.5 The contractor shall remove and relocate an existing 30-foot light pole. The pole can be located at the southeast corner of parking lot 2G.
1.12.6 The contractor shall provide wind load calculations that must be approved by the Department of Public Works electrical engineer.
1.12.7 Relocation of the light pole includes a new foundation proportional to the wind load calculations and the weight of the relocated pole.
1.12.8 Rewire the existing electrical wire to the new location.
1.12.9 Final acceptance shall include commissioning and testing of the relocated light pole per the article 300’s of the NEC code.
1.13 DRAWINGS:
1.13.1 The design plans for this project are attached to this Statement of Work in
Appendix A.
1.14 SPECIFICATIONS
1.14.1 The contractor shall perform all work in accordance with the 2024 version of the Iowa State Urban Design and Specifications Program (SUDAS). The specifications can be found at the following website https://iowasudas.org/manuals/specifications-manual/. The contractor shall also follow the submittal procedures laid out in Appendix B.
1.14.2 All traffic control shall be in accordance with the Federal Highway Administration’s (FHWA) Manual on Uniform Traffic Control Devices (2009 with Rev 1 and 2) (MUTCD).
1.14.3 Notify the KO/COR immediately in writing if there is a discrepancy between the specifications and the referenced codes. If the Contractor fails to notify the KO/COR regarding conflicts within these documents, the more stringent requirements shall apply as determined by the KO/COR.
1.15 EXISTING CONDITIONS:
1.15.1 The existing roadway is a combination of concrete and asphalt that is in failed or failing condition. Existing roadway typicals can be found in the “B Sheets” in the set of plans found in Appendix A.
1.15.2 Soil boring information can be found in the “C sheets” of appendix A.
1.16 SUBMITTALS
1.16.1.1 Copy of On-Site SWPPP Binder
1.16.1.2 Hot mix asphalt mix design
1.16.1.3 Shop Drawings
1.16.1.4 The contractor shall submit all requirements listed in part 2 of each bid item defined in the SUDAS Standard Specifications pertaining to this project.
1.16.1.5 Safety Submittals
https://iowasudas.org/manuals/specifications-manual/
11 | P a g e
1.16.1.6 Form 1354 -Real Property Acceptance
1.16.1.7 Environmental Submittals
1.16.1.8 Construction Schedule
1.16.1.9 Construction Phasing Plan
2. PART TWO: GENERAL INFORMATION
2.1 COMMENCEMENT, PROSECUTION, AND COMPLETION OF WORK:
2.1.1 The Contractor shall be required to (a) commence physical work under this contract within 45 working days after the date the Contractor receives the notice to proceed, (b) prosecute the work diligently, and (c) complete the entire work ready for use not later than 160 days working days after receipt of the notice to proceed. Contractor submission of all closeout documentation is also included within this timeline. The time stated for completion shall include final cleanup of the premises.
2.2 SPECIAL CONDITIONS:
2.2.1 Staging Area: The construction area may be used as a staging area. Any additional staging area requires coordination with the KO/COR.
2.2.2 Construction Schedule and Closure Periods: The Construction Schedule shall be submitted to the KO/COR for approval in accordance with the SOW.
2.2.3 Access and Working Hours: Standard work hours for this project are 5:30 am on
Monday to 5:00 pm on Friday. The contractor’s schedule may deviate from these hours when approved by the KO/COR. The Federal Holidays are: New Year’s Day, January 1; Martin Luther King Day, 3rd Monday in January; President’s Day, 3rd Monday in February, Memorial Day, last Monday in May; Juneteenth, June 19; Independence Day, July 4; Labor Day, 1st Monday in September;
Columbus Day, 2nd Monday in October; Veteran’s Day, November 11, Thanksgiving Day, 4th Thursday in November; Christmas Day, December 25. If a holiday falls on Saturday, the preceding Friday is a holiday. If a holiday falls on Sunday, the following Monday is a holiday.
2.2.4 Miscellaneous: All site condition information provided by the Government shall be field verified by the contractor.
3.1 PART THREE: SECURITY
3.1.1 OPERATIONS SECURITY (OPSEC) REVIEW: In order to perform the project the contractor must do the following:
3.1.2 AT Level I training. This standard language is for contractor employees with an area of performance within an Army controlled installation, facility or area. All contractor employees, to include sub-contractor employees, requiring access to Army installations, facilities and controlled access areas shall complete AT Level I awareness training within 30 calendar days after contract start date or effective date of incorporation of this requirement into the contract, whichever is applicable. The contractor shall submit certificates of completion for each affected contractor employee and sub-contractor employee, to the COR or to the
12 | P a g e contracting officer, if a COR is not assigned, within 5 calendar days after completion of training by all employees and sub-contractor personnel. AT level I awareness training is available at the following website: http://jko.jten.mil
3.1.3 Access and general protection/security policy and procedures. This standard language is for contractor employees with an area of performance within Army controlled installation, facility, or area. Contractor and all associated sub-contractor employees shall provide all information required for background checks to meet installation access requirements to be accomplished by installation Provost Marshal Office, Director of Emergency Services or Security Office.
Contractor workforce must comply with all personal identity verification requirements (FAR clause 52.204-9, Personal Identity Verification of Contractor Personnel) as directed by DoD, HQDA and/or local policy. In addition to the changes otherwise authorized by the changes clause of this contract, should the Force Protection Condition (FPCON) at any individual facility or installation change, the Government may require changes in contractor security matters or processes.
3.1.4 For contractors requiring Common Access Card (CAC). Before CAC issuance, the contractor employee requires, at a minimum, a favorably adjudicated National Agency Check with inquiries (NAC) or an equivalent or higher investigation in accordance with Army Directive 2014-05. The contractor employee will be issued a CAC only if duties involve one of the following: (1) Both physical access to a DoD facility and access, via logon, to DoD networks on-site or remotely; (2) Remote access, via logon, to a DoD network using DoD approved remote access procedures; or (3) Physical access to multiple DoD facilities or multiple non-DoD federally controlled facilities on behalf of the DoD on a recurring basis for a period of 6 months or more. At the discretion of the sponsoring activity, an initial CAC may be issued based on a favorable review of the FBI fingerprint check and a successfully scheduled NACI at the Office of Personnel Management.
3.1.5 For contractors that do not require CAC, but require access to a DoD facility or installation. Contractor and all associated sub-contractor employees shall comply with adjudication standards and procedures using the National Crime Information Center Interstate Identification Index (NCIC-III) and Terrorist Screening Database (TSDB) (Army Directive 2014-05/AR 190-13), applicable installation, facility and area commander installation/facility access and local security policies and procedures (provided by government representative), or, at OCONUS locations, in accordance with status of forces agreements and other theater regulations.
3.1.6 AT Awareness Training for Contractor Personnel Traveling Overseas. This standard language required U.S. based contractor employees and associated sub-contractor employees to make available and to receive government provided area of responsibility (AOR) specific AT awareness training as directed by AR 525-13.
Specific AOR training content is directed by the combatant commander with the unit ATO being the local point of contact.
3.1.7 iWATCH Training. This standard language is for contractor employees with an area of performance within and Army controlled installation, facility or
13 | P a g e area. The contractor and all associated sub-contractors shall brief all employees on the local iWATCH program (training standards provided by the requiring activity ATO). This locally developed training will be used to inform employees of the types of behavior to watch for and instruct employees to report suspicious activity to the COR. This training shall be completed within 30 calendar days of contract award and within 5 calendar days of new employees commencing performance with the results reported to the COR NLT 30 calendar days after contract award.
3.1.8 Army Training Certification Tracking System (ATCTS) registration for contractor employees who require access to government information systems. All contractor employees with access to a government information system must be registered in the ATCTS (Army Training Certification Tracking System) at commencement of services, and must successfully complete the DoD Information Assurance Awareness training prior to access to the IS and then annually thereafter.
3.1.9 For contracts that require a formal OPSEC program. The contractor shall develop an OPSEC Standing Operating Procedure (SOP)/Plan within 90 calendar days of contract award, to be reviewed and approved by the responsible Government OPSEC officer. This plan will include a process to identify critical information, where it is located, who is responsible for it, how to protect it and why it needs to be protected. The contractor shall implement OPSEC measures as ordered by the commander. In addition, the contractor shall have an identified certified Level II OPSEC coordinator per AR 530-1.
3.1.10 For contracts that require OPSEC Training. Per AR 530-1 Operations Security, the contractor employees must complete Level I OPSEC Awareness training. New employees must be trained within 30 calendar days of their reporting for duty and annually thereafter.
3.1.11 For information assurance (IA)/information technology (IT) training. All contractor employees and associated sub-contractor employees must complete the DoD IA training before issuance of network access and annually thereafter. All contractor employees working IA/IT functions must comply with DoD and Army training requirements in DoD 8570.01, DoD 8570.01-M and AR 25-2 within six months of appointment to IA/IT functions.
3.1.12 For information assurance (IA)/information technology (IT) certification. Per DoD 8570.01-M, DFARS 252.239.7001 and AR 25-2, the contractor employees supporting IA/IT functions shall be appropriately certified upon contract award.
The baseline certification as stipulated in DoD 8570-.01-M must be completed upon contract award.
3.1.13 For contractors authorized to accompany the force. DFARS Clause 252.225- 7040, Contractor Personnel Authorized to Accompany U.S. Armed Forces Deployed Outside the United States. The clause shall be used in solicitations and contracts that authorize contractor personnel to accompany U.S. Armed Forces deployed outside the U.S. in contingency operations; humanitarian or peacekeeping operations; or other military operations or exercises, when designated by the combatant commander. The clause discusses the following AT/OPSEC related topics: required compliance with laws and regulations, pre-
14 | P a g e deployment requirements, required training (per combatant command guidance), and personnel data required.
3.1.14 For Contract Requiring Performance or Delivery in a Foreign Country.
DFARS Clause 252.225-7043, Antiterrorism/Force Protection for Defense Contractors Outside the US. The clause shall be used in solicitations and contracts that require performance or delivery in a foreign country. This clause applies to both contingencies and noncontingency support. The key AT requirement is for non-local national contractor personnel to comply with theater clearance requirements and allows the combatant commander to exercise oversight to ensure the contractor's compliance with combatant commander and subordinate task force commander policies and directives.
3.1.15 For contracts that require handling or access to classified information.
Contractor shall comply with FAR 52.204-2, Security Requirements. This clause involves access to information classified "Confidential", "Secret", or "Top Secret" and requires contractors to comply with (1) The Security Agreement (DD Form 441), including the National Industrial Security Program Operating Manual (DoD 5220.22-M); (2) any revisions to DOD 5220.22-M, notice of which has been furnished to the contractor.
3.1.16 Threat Awareness Reporting Program. For all contractors with security clearances. Per AR 381-12 Threat Awareness and Reporting Program (TARP), contractor employees must receive annual TARP training by a CI agent or other trainer as specified in 2-4b of AR 381-12.
3.1.17 For contracts that require delivery of food and water. This standard language is for contractor employees with an area of performance delivering food and water within an Army-controlled installation, facility or area. The supplies delivered under this contract shall be transported in delivery conveyances maintained to prevent tampering with and/or adulteration or contamination of the supplies, and if applicable, equipped to maintain a prescribed temperature. All delivery vehicles will also be subject to inspection at all times and all places by the Contracting Officers Representative, Post Veterinarian, and/or Law Enforcement Officials.
When the sanitary conditions of the delivery conveyance have led, or may lead to product contamination, adulteration, constitute a health hazard, the delivery conveyance is not equipped to maintain prescribed temperatures or the transport results in product "unfit for intended purpose", supplies tendered for acceptance may be rejected without further inspection. As the holder of a contact with the Department of Defense, it is incumbent upon the awardee to ensure that all products and/or packaging have not been tampered with or contaminated.
Delivery conveyances will be locked or sealed at all times, except when actively loading or unloading. Unsecured vehicles will not be left unattended. All incoming truck drivers will provide adequate identification upon request. In the event of an identified threat to an installation, or a heightened force protection/Homeland Security threat Level, the contractor may be required to adjust delivery routes to minimize vulnerability risks and enable direct delivery to DOD facilities.
15 | P a g e
3.1.18 All Training (iWatch/AT/OPSEC) will be face to face, provided by a level II certified ATO and OPSEC officer, conducted on RIA. Any conflicts with training locations/performance will be directed by the project COR.
3.1.19 Contractors, sub-contractors will be escorted by the COR in areas where they may be exposed to classified and/or sensitive materials. All contractor employees, including subcontractor employees who are not in possession of the appropriate security clearance, will be escorted in areas where they may be exposed to classified and/or sensitive materials. The Vendor will coordinate with the COR and/or the facility security office for access when required.
3.1.20 Building Stand-Off: All occupied buildings on Rock Island Arsenal require a 33feet stand-off by all vehicles and equipment. At no time will unoccupied vehicles, equipment or tools/toolboxes be left unattended within 33 feet of installation buildings.
3.1.21 All personnel requesting access to Rock Island Arsenal will only enter through a manned and operational Access Control Point and present a United States National or State issued identification that is capable of being scanned for valid entry. All contractor and contractor employees' vehicles, equipment, and packages are subject to inspection or examination (search) at entry/exit of the Rock Island Arsenal. Only authorized individuals that pass a screening and vetting process will be permitted access. All contractor and subcontractor personnel will be required to submit the required identification credentials and must receive a favorable background check as conducted through the National Crime Information Center (NCIC) Interstate ID Index (III) to gain access and work on the installation.
4 PART FOUR: ROCK ISLAND ARSENAL SUPPLEMENTAL GUIDANCE
4.1 SAFETY REQUIREMENTS:
4.1.1 Contractor shall comply with Engineering Manual EM-385-1-1 “Safety and
Health Requirements Manual”.
4.1.2 Contractor shall designate a Site Safety and Health Officer (SSHO) in accordance with EM 385-1-1, Section 01.A.17. SSHO shall also be responsible to coordinate contract employees in the event of an emergency.
4.1.3 The following safety submittals are required prior to performing work:
4.1.3.1 Accident Prevention Plan (APP) (EM 385-1-1, Section 01.A.12)
4.1.3.2 Activity Hazard Analysis (AHA) (EM 385-1-1, Section 01.A.15)
4.1.3.3 Emergency Plan (EM 385-1-1, Section 01.E)
4.1.3.4 Supplemental plans in accordance with EM 385-1-1 shall be required as dictated by the types of work being performed (e.g. Hazardous Energy Control Program, Hot Work, Hazardous Material Abatement)
4.1.4 The Contractor shall adhere to the most current requirements of NFPA 241, EM 385-1-1 and local Fire Department requirements as supplemented below. If a conflict between requirements occurs the most stringent shall apply.
4.1.4.1 Fires, regardless of size, will be reported to the fire department.
4.1.4.2 Contractor storage areas in RIA buildings shall be inspected and approved by the
RIA Fire Department prior to use.
16 | P a g e
4.1.4.3 Extinguishers for hot work shall be a minimum of 10 lb. ABC Type (UL Rating 4A:80B:C). Building extinguishers shall not be used to meet this requirement.
4.1.4.4 Contractors shall provide flameproof tarps or shields to protect combustible material during hot work.
4.1.4.5 Tar kettles shall not be located any closer than 20 feet to any building or 100 feet to an ammunition/explosive storage area.
4.1.4.6 The Contractor shall make requests in writing to the KO/COR no less than two weeks in advance for approval to connect to a fire hydrant. The contractor is responsible for installing the water meter/back flow preventer and providing their own hose, hose connections, and hydrant wrenches for opening/closing fire hydrants. The Contractor shall not use pipe wrenches, channel locks, etc. for opening/closing of fire hydrants.
4.1.5 Contractor shall comply with all emergency communication instructions provided through official channels to include the outdoor speaker system, building notification systems, direction by emergency service personnel, or the
KO/COR.
4.1.5.1 Upon award, the Government will provide further information regarding building points of contact, areas of refuge, and access restrictions.
4.1.5.2 Contractor vehicles and/or equipment shall not block fire department access, hose connections, alarm panels, access roads, fire hydrants, building safety features, etc. without prior approval. Requests shall be made in writing 30 days prior to the request and shall include proposed length of closure.
4.1.5.3 Contractor shall adhere to and follow safety policy as written in the latest editions of the National Electrical Safety Code and National Electrical Code.
4.2 ENVIRONMENTAL PROTECTION:
The Contractor shall follow all environmental requirements in accordance with this
SOW.
4.2.1 Compliance with Environmental Laws and Regulations: Contractor shall comply with all applicable federal, state, and local environmental laws, statutes, regulations, executive orders, permits, Army regulations (with supplements), as well as Major Subordinate Command (MSC) and installation regulation, policy, Host Tenant Agreement, Interagency Service Support Agreement, or Status-of- Forces Agreement. Contractor shall immediately report any conflicts between applicable federal, state, local environmental laws, statutes, executive orders, and provisions of Army Regulation 200-1, and any specifications within this contract to the Contracting Officer Representative (COR).
4.2.2 Compliance with Green Procurement Requirements: Contractor shall follow Federal EPA Comprehensive Procurement guidelines (www.epa.gov/cpg) and Army Contracting Command Quick Guide (https://acc.aep.army.mil/accapps/ACCMAP/Documents/Quick-Guide-for- Sustainable-Procurement.docx) for acquisition of building materials and products and select materials that have a long life cycle; the least toxic materials;
recyclable materials; materials that are resource-efficient; materials with the maximum recycled content; materials harvested on a sustained yield basis; and products causing the least pollution during their manufacture, use, and reuse.
17 | P a g e
4.2.3 Compliance with License and Certification Requirements: Contractor shall obtain all licenses and certifications required by Federal, State, and Local environmental laws and regulations necessary to adhere to the specifications of this contract. The Contractor shall submit all plans, notifications, reports, submittal documents, and fees required by Federal, State, and Local environmental laws and regulations to the appropriate Federal, State, and Local authority and/or agency as necessary to adhere to the specification of this contract. All required licenses and certifications required by Federal, State, and Local environmental laws and/or regulations shall be considered a contract deliverable upon award.
4.2.4 Notification of Federal and State Regulators: Contractor shall immediately notify the Designated Government Representative (DGR) and COR of the arrival on site of any Federal, State, and/or DoD environmental regulator or enforcement agent and/or the receipt of any correspondence from a Federal or State environmental agency.
4.2.5 Inspections of Work Sites: Contractor shall submit to potential Federal, State, Army and installation work site environmental regulatory inspections and/or investigations into noncompliance, and fully cooperate with such inspections/investigations by providing the appropriate records and documentation. Environmental regulatory agencies are authorized by law to inspect any work site for environmental compliance with regulatory requirements. If an inspection is conducted, it will not stop or disrupt ongoing contract activities. The inspection will only require the work site environmental officer, or supervisor/manager to answer questions and/or escort the inspector to specific work site areas with the potential to affect environmental quality.
4.2.6 Reporting Noncompliance: Contractor shall immediately report any nonconformance and/or noncompliance with applicable Federal, State or Local environmental laws, Army and installation environmental regulations or policies to the COR and DGR.
4.2.7 Verification of National Environmental Policy Act Documents. Contractor shall obtain from the COR or DGR a copy of the National Environmental Policy Act (NEPA) environmental analysis and/or status of the NEPA review done if analysis was not required. NEPA review and analysis is done in accordance with 32 CFR Part 651 and addresses actions to be taken by contractor prior to and during commencement of contract actions. The NEPA process consists of evaluating the environmental effects of a federal action including its alternatives.
There are three levels of analysis depending on whether or not the construction activity or project could significantly affect the environment. These three levels are: categorical exclusion determination; preparation of an environmental assessment/finding of no significant impact (EA/FONSI); and preparation of an
EIS.
4.2.8 Assignment of Environmental Compliance Designee (ECD): Contractor shall appoint an ECD for all contract work periods exceeding 180 consecutive days.
Contractor shall appoint a primary and alternate ECD for each production, shop or work area that uses and/or stores hazardous materials and/or generates hazardous wastes.