DESCRIPTION OF WORK
Road Repair Sites
De Soto National Forest
Road 301F Washout Moody’s Landing Recreational Area
This project will repair a washout along FSR 301F in the Moody’s Landing Recreational Area on the De Soto National Forest near Brooklyn in Forrest County, MS where major flows in Black Creek overtop the road causing washout of existing rock on the other side. Borrow excavation will be hauled in to restore the road bank and the affected washout area will be protected with geotextile, 100 lb gradation rock riprap and concrete grout and grout cutoff. The project location is 4.3 miles East of Brooklyn off of FSR
301. Travel mileage will vary due to detour. Road 301F is an aggregate surfaced road. Coordinates of approximate site location are 31.051894, -89.116827 in decimal degrees. The recreational area is locked with a Forest Service lock. Forest Service personnel will be needed prior to accessing the site.
Quantities of rock riprap, geotextile, concrete grout and borrow excavation are estimated for an approximate affected washout area of 30’x15’. Remove vegetation, debris and existing loose rock to the limits where existing rock is stable on the lower bank and reshape bank along the washout vicinity.
Restore 2’ of shoulder with borrow excavation and fill in the eroded volume so as to place rock riprap to 1.5’ thickness and uniform slope to the natural grade. Place geotextile with 6” overlap before placing the 100 lb rock. See detail sheet for placement of rock, grout and grout cutoff.
A quantity of #610 (crusher run) crushed limestone aggregate is included to build back the roadbed from recurring overtopping in the washout vicinity and spot surfacing of FSR 301F as needed. Grade the edges to pull all aggregate back into the travel way and leave a straight, uniform edge, and grade the aggregate to create a smooth, uniform surface and compact.
Estimated quantities Borrow Excavation 25 CY Roadway Aggregate, Grade 610 45 Tons Rock Riprap 50 Tons Geotextile 82 SY Concrete Grout 3.5 CY
Applicable specifications may be found in FHWA’s FP-14 and the attached supplemental specifications.
Attachment 0001 Desoto National Forest Statement of Work Moody’s Landing Recreational Area