This is a Contractor Bid Sheet for the FR244 ERFO Project that outlines estimated public works requirements and quantities for bidding purposes.

The project encompasses various civil construction and environmental remediation activities across 21 line items. Key work categories include mobilization (1 lump sum), soil and erosion control featuring filter barrier fiber rolls (105 linear feet), temporary and permanent turf establishment via hydraulic method (2 lump sum items), and clearing and grubbing (1 lump sum). Excavation and embankment work is specified at 46 cubic yards with ditch excavation at 30 linear feet. The project requires select backfill and minor crushed aggregate placement totaling 35 tons (backfill) and 2,587 tons (base course), plus 294 tons of AASHTO #1 aggregate. Rock excavation is estimated at 43 cubic yards. Riprap placement (Class 2, Acceptance Method A) is specified at 128 tons and 39 cubic yards. Road reconditioning covers 0.97 miles. Drainage infrastructure includes 24-inch HDPE pipe (88 linear feet) and 30-inch HDPE pipe (120 linear feet), both Type S, Method B. The project concludes with installation of one standard Forest Service 14-foot steel pipe gate. Unit Cost and Total Cost columns are provided but left blank for contractor completion. A "Total PW" row appears at the sheet's conclusion for summing estimated public works costs.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Unit Cost Total Cost 151 MOBILIZATION L.S. All 1

157.06 SOIL AND EROSION CONTROL (Filter Barrier, Fiber rolls)

C.Q. ft 105

157.12(b) Temporary turf establishment, hydraulic method L.S. All 1

157.13(a) Turf Establishment Permanent, hydraulic method L.S. All 1

201.01 CLEARING AND GRUBBING L.S. All 1

204.01 A EXCAVATION AND EMBANKMENT C.Q. CY 46

204.01 B

EXCAVATION AND EMBANKMENT, DITCHES (O.D.

AND L.O.D)

C.Q. LF 30

204.07 SELECT BACKFILL Minor Crushed Aggregate, comp. method 1, 1 1/2" CR

A.Q TON 35

206 ROCK EXCAVATION DQ CY 43

251.04 -A Place Riprap, Accept. Meth. A, Class 2 A.Q TON 128

251.04 -B Place Riprap, Accept. Meth. A, Class 2 A.Q CY 39

302-A Minor Crushed Aggregate, comp. method 1, AASHTO #1)

A.Q TON 294.0

302-B Minor Crushed Aggregate, comp. method 1, 1 1/2" CR / Select Back Fill

A.Q TON 2587

303 Road reconditioning A.Q MILE 0.97 602 (24) B 24 inch HDPE pipe, Type S, Method B A.Q LF 88 602 (30) 30 inch HDPE pipe, Type S, Method B A.Q LF 120

619.01

STANDARD FOREST SERVICE 14' STEEL PIPE

GATE

L.S. All 1

Total PW

Contractor Bid Sheet - FR244 ERFO Project

Item No. Description Method Measure Unit Quantity Estimated Public