QA Red Run Repairs Pt.1.pdf
PDF 194 KB Posted
- Attached to
- MOF-CON ER02- Red Run Repairs
- Solicitation number
- 12445526Q0024
- Issued by
-
Department of Agriculture Forest Service
About this file
This is a Questions and Answers document for federal contract MOF-CON ER02 – Red Run Repairs project. The Q&A addresses 19 contractor inquiries regarding project specifications, payment procedures, and material requirements.
Key technical clarifications include: dry seeding is acceptable as an alternative to hydraulic seeding methods, with weed-free straw required for hand application; silt sock is acceptable in place of silt screen if weed-free; compaction testing requires visible testing with material compacted to surrounding area at 6-inch lifts; all culverts require headwall and outlet pad installation; and armor ditches utilize item 251.04-A (AASHTO #1 aggregate for road sections) with outlet pads measured in cubic yards. Stumps from cut trees must be removed and scattered over fill slopes with treetops. Road grading applies only to specified sections per item 303 on page A-4, though contractors may grade the entire road if willing to absorb costs for unspecified sections. The Contracting Officer's Representative (COR) will stake culverts and set slope stakes, but contractors are responsible for setting culverts to grade during installation and obtaining all required permits and licenses. A bid bond at 20% is required. Invoice submission occurs through the IPP system with approval routing to the Contracting Officer before payment, typically within one week. A rock storage area exists near the lower gate for material transfer to smaller trucks. Table 705-1 provides rip-rap size specifications for reference.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Q&A: MOF-CON ER02- Red Run Repairs
1. Q: Revegetation calls for Hydraulic method, Is dry method acceptable?
A: Yes acceptable
2. Q: Is there a source for water for Hydro seeding?
A: Yes, there is a good water source
3. Q: Is silt sock acceptable instead of silt screen?
A: Yes, but need to be weed free.
4. Q: Is there a standard request template to request progress payments and generally how long does it take to receive payment?
A: After you submit invoice in IPP I will look over it and if I find everything is order, I will approve invoice. Then it will go to the CO to look over and if all is correct the CO will approve and after that it should take about a week to be paid.
5. Q: Are there any special permits/licenses that contractors are required to obtain?
A: Contractor will need to obtain all permits and or licenses to perform the work.
6. Q: Is compaction testing required for fill?
A: Visible testing and compacted back to the surrounding area (at 6” lifts)
7. Q: Is the contractor responsible for survey of grades/pipe locations?
A: The COR will stake culvert and set slope stakes, but contractor will need to set culvert to grade when installing.
8. Q: Do we need to do dust control, traffic control for a road that’s gated and where is the fill section on the road?
A: remove dust control, remove Traffic control plan, and remove installation of fill section on roadbed in the note section page A-3.
9. Q: Do the stumps need removed?
A: If trees are cut the stumps will be removed and placed over fill slope with the treetops.
Scatter method.
10. Q: Do you know where to get a hard copy of the FAR Clauses?
A: The FAR clauses are in PDF format only no hard copy that I can find available.
11. Q: Do all culverts need headwall and outlet pads?
A: Yes, All culverts shall have headwalls and outlet pads installed please see culvert drainage summary on page A-4.
12. Q: Do we grade the whole road?
A: No, Grading of road please see Summary for grading item 303 on page A-4.
13. Q: Is there a spot that we can use to store rock to transfer to smaller trucks?
A: There is a small area to dump rock by the lower gate to transfer to smaller truck if needed.
14. Q: Is a Bid Bond Needed?
A: Yes, a Bid Bond is needed at 20%.
15. Q: Items 157.12(b) and 157.13(a): Please confirm whether these items are intended to be installed via hydroseeding, or if hand application (broadcast seeding/mulching) is acceptable
A: Hand seeding is acceptable using weed free straw.
16. Q: Item 251.04-B: Please confirm the intended unit of measurement for this item— should it be measured and paid as tons (TON) or cubic yards (CY)?
A: This is CY and this is for the outlet pads Location of outlet pad can be found on page
A-4 under drainage summary.
17. Q: Sheet A4 – Armor Spec Ditch Table: The detail references an armored ditch section; however, the material type is unclear. Please confirm whether this ditch is to be constructed using AASHTO #1 aggregate or Class 2 Riprap?
A: This will be item be 251.04-A is for the armor ditches and the ASHTO #1 is for the road sections that call for ASHTO #1.
18. Q: The contractor asks if they could grade the whole road?
A: Yes, but only gets paid for sections that call for grading.
19. Q. Do you have a size table for Rip-Rap size?
A. Yes, see table 705-1 below for stone size