This document is a Statement of Requirement (SOR) for the replacement of roll-up doors at Building 141 for the Alabama Army National Guard located at Sumpter Smith Air National Guard Base in Birmingham, AL. The project requires removing three existing roll-up doors and installing two TKO CW Series Cruiserweight Impactable doors and one insulated roll-up door, with specific dimensional requirements of 124" width and 112-120" height. The new doors must match previously installed doors with high R-23 insulation value, tight perimeter weather sealing, and moisture resistance.
The scope of work includes comprehensive door removal, site preparation, installation, operator setup, weather sealing, testing, and cleanup, with a site survey recommended to verify existing conditions. The contractor must protect adjacent surfaces, ensure secure room access, and follow manufacturer installation guidelines. Delivery and installation will be at Building 141, with a point of contact for the project being CMSGT Antonio Robinson. The project includes a twelve-month warranty, and the contractor must provide all accompanying documentation and manuals. The solicitation number is W50S6M-25-Q-A016, issued by the Department of the Army Alabama Army National Guard.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Roll Up Door Questions Answers.docx | DOCX document | |
| Attachment 1 Solicitation -.docx | DOCX document | |
| W50S6M25QA016 - Provisions and Clauses.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Statement of Requirement (SOR)
1. General Information Roll-Up Doors Description
1.2.1.1 This project involves the removal of three existing roll-up doors and the installation of two TKO CW Series Cruiserweight Impactable doors and one insulated roll-up door at Building 141. With a crane already installed within the middle bay door opening, preventing the necessary clearance and hardware installation, we are proceeding with a single roll-up door instead of a sectional door. The work includes all labor, materials, equipment, and supervision necessary for the complete and functional installation of the new doors, including proper disposal of the old doors and any necessary adjustments to the existing structure. New doors must be consistent with already installed Cruiserweight Impactable TKO door in Bldg. 190 (high R-23 value in temperature-controlled environments and includes a tight perimeter weather seal with a double loop seal to prevent energy loss, moisture-resistant, 1-3/4" thick insulated foam core panel insulated doors specifications).
1.2.2 Dimensions (Approximate):
Note: Contractors must verify and confirm dimensions to ensure proper door purchase order and installation:
1.2.2.1 Door #1 – 124 ¼ ” w x 112” h
1.2.2.2 Door #2 – 124” w x 112” h
1.2.2.3 Door #3 – 124” w x 120” h
1.2.3 Site Survey is encouraged
1.2.3.1 Verify existing door dimensions and confirm new door sizes.
1.2.3.2 Assess the condition of existing door frames, jams, and headers for structural integrity and suitability for new door installation.
1.2.3.3 Identify any obstructions or interferences (e.g., electrical conduits, piping, lighting fixtures) that may impact on the installation.
1.2.3.4 Document existing conditions with photographs and/or video.
1.2.3.5 Confirm power availability and location for door operators (if applicable).
1.2.4 Protection:
1.2.4.1 Protect adjacent surfaces (walls, floors, equipment) from damage during demo/removal and installation. Use drop cloths, plastic sheeting, or other appropriate protective measures.
1.2.4.2 Provide temporary barriers or signage to restrict access to the work area and ensure safety.
1.2.5 Door Removal
1.2.5.1 Remove Existing Doors:
1.2.5.1.1 Carefully dismantle and remove the existing roll-up doors, including the door curtain, tracks, springs, hardware, and operators.
1.2.5.1.2 Ensure that the removal process does not damage the surrounding structure.
1.2.5.1.3 Ensure work is coordinated to not leave the rooms unsecured at the end of the day (1730). Rooms must have the ability to be completely secured during non-duty hours.
1.2.6 Frame Inspection and Preparation:
1.2.6.1 Clean the existing frame openings to remove debris, dirt, and old sealant.
1.2.7 Door Delivery and Inspection:
1.2.7.1.1 Receive and inspect the new two Cruiserweight TKO doors and one insulated roll-up door upon delivery to ensure they are the correct size, type, and configuration as specified in submittal.
1.2.7.1.2 Verify that all components, including the door curtain, tracks, springs, hardware, and operators (if applicable), are present and undamaged.
1.2.8 Door Installation
1.2.8.1 Install the two Cruiserweight TKO doors and one insulated roll-up door according to the manufacturer's instructions and industry’s best practices.
1.2.8.2 Ensure that the door is plumb, level, and properly aligned within the frame opening.
1.2.8.3 Securely fasten the door tracks and hardware to the existing frame using appropriate fasteners.
1.2.8.4 Install the door curtain and adjust the spring tension for smooth and balanced operation.
1.2.9 Operator Installation (Manual):
1.2.9.1 Install the new door operator according to the manufacturer's instructions.
1.2.9.2 Adjust the operator settings for proper opening and closing speed, limit switches, and safety features.
1.2.9.3 Test the operator to ensure it is functioning correctly.
1.2.10 Weather Sealing:
1.2.10.1 Apply weather stripping and sealant around the perimeter of the door to create a weathertight seal.
1.2.10.2 Ensure that the bottom of the door curtain seals properly against the floor.
1.2.11 Testing and Commissioning:
1.2.11.1 Test the operation of the door to ensure it opens and closes smoothly and reliably.
1.2.11.2 Verify that all safety features are functioning correctly.
1.2.11.3 Adjust the door operator settings as needed to optimize performance.
1.2.12 Debris Removal:
1.2.12.1 Remove all debris, waste materials, and packaging from the work area.
1.2.12.2 Dispose of the old doors and related materials in accordance with all applicable regulations.
1.2.13 Site Cleanup:
1.2.13.1 Clean the work area thoroughly to remove any dust, dirt, or debris.
1.2.13.2 Restore the area to its original condition
1.2.14 Contractor will follow ANGETL, ANG Handbook, and United Facilities Criteria guidance for the project’s entirety.
1.2.15 Should the contractor receive requests for work, which are beyond the scope of this contract, the Contracting Officer shall be notified immediately. The contractor shall not start work on these items until given notice to proceed by the Contracting Officer. An increase in construction costs over initial 100% of the budget program cost estimate will not be a basis for claim against the Government to increase fee unless it has been caused by a change in the agreed scope of work.
2. Delivery, Inspection and Acceptance
2.1. Place of Delivery: Sumpter Smith Air National Guard Base (117ARW) BLDG 141, 117 Maintenance Group 5401 E. Lake Blvd. Birmingham, AL 35217-3545, POC for delivery, installation and set up CMSGT Antonio Robinson CE Work Control 205-714-2247 antonio.robinson@us.af.mil
2.2. Inspection and acceptance will occur at the completion of installation by a government representative. A comprehensive bill of lading or delivery receipt shall accompany all deliverables that details, at minimum, all serial numbers associated with the requested trailer and internal equipment.
Warranty Twelve (12) months.
All equipment shall have the standard manufacturer’s warranty. The Contractor shall warranty all items delivered/installed and ensure all items are free from defects in material and workmanship under normal use and service. Additionally, without charge, repair or replace any equipment found to be defective in material or workmanship provided said equipment has been operated within standard procedures and instructions and such defects are not due to abuse, misuse or Acts of God.
Documentation The contractor shall provide all owner’s manuals, service manuals and any other manufacturer documentation that accompanies the purchase of this item. If any equipment installed has its own service and owner’s manual these will also be provided by the contractor.