Attach. 1 - Statement of Work (SOW).pdf
PDF 314 KB Posted
- Attached to
- Building 2045 Carpet Federal contract opportunity
- Solicitation number
- FA462024QA257
About this file
This document is a Statement of Work (SOW) for a carpet removal and installation project at Building 2045 on Fairchild Air Force Base in Washington. The contractor shall be responsible for removing approximately 12,289 square feet of old carpet and 2,360 linear feet of cove base, and installing approximately the same amount of new carpet and cove base. The work must be performed in accordance with federal, state, and local regulations, as well as commercial standards and the Fairchild Air Force Base Installation Facilities Standards. The contractor will be required to coordinate the installation dates with the Contracting Officer (CO) prior to beginning work. The government has conducted an asbestos test, and if asbestos is discovered during removal, the government will coordinate a bilateral modification to the contract for abatement. The contractor must be experienced in carpet and flooring installation and possess the required insurance. The government will not be providing any materials, services, or supplies for this project.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Attach. 3 - Building 2045 Floor Plan (Amend 02).pdf | ||
| Amend 02 - SF 30 QandA.pdf | ||
| 24QA257 COMBO (Amend 02).pdf | ||
| Attach. 1 - Statement of Work (Amend 02).pdf | ||
| Attach. 5 - Pricing Schedule (Amend 02).pdf | ||
| Amend 01 - SF 30 Extend Due Date.pdf | ||
| Attach. 4 - Carpet Selections.pdf | ||
| 24QA257 COMBO.pdf | ||
| Attach. 2 - USAF Carpet II Program Ordering Guide.pdf | ||
| Attach. 5 - Pricing Schedule.pdf | ||
| Attach. 3 - Building 2045 Floor Plan.pdf |
Show all 11
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
FA462024QA257 – Building 2045 Carpet Attach. 1 - Statement of Work
STATEMENT OF WORK (SOW)
FOR CARPET REMOVAL AND INSTALLATION
FOR
92d LRS B. 2045
FAIRCHILD AFB, WA
August 2024
1 DESCRIPTION OF SERVICES
1.1 This requirement is being solicited in accordance with the US Air Force Carpet II Program. All ordering will be done in accordance with the USAF Carpet II Program Ordering Guide (Attach. 2).
1.2 The contractor shall furnish all labor, materials, equipment, equipment rental, transportation, and supervision necessary to perform all work in accordance with these specifications, relevant drawings, and contract documents for installation of carpet and cove base at Fairchild Air Force Base, Washington.
1.3 The government has conducted an asbestos test prior to contractor beginning work. While not anticipated, if the contractor discovers the presence of asbestos during removal and installation of old carpet, the government will coordinate with the contractor to accomplish a bilateral modification to the contract for abatement and remove the asbestos discovered.
2 SCOPE OF WORK
2.1 The contractor shall be responsible for removing approximately 12,289 square feet of old carpet and approximately 2,360 linear feet of cove base, procuring, and installing approximately 12,289 square feet of new carpet and approximately 2,360 linear feet of new cove base in accordance with the Statement of Work (SOW). Contractors shall review Attach. 3 – Building 2045 Floor Plan for all areas on the first and second floor of Building 2045 to have carpet and cove base removed and new carpet and cove base installed. All work shall be performed in accordance with all federal, state, and local regulations, commercial standards and 2022 Fairchild Air Force Base Installation Facilities Standards (IFS).
2.2 The contractor shall prepare all floor surfaces in accordance with standard commercial practices, the
SOW, and Attach. 3 – Building 2045 Floor Plan. The contractor shall ensure all surfaces to be carpeted are clear of old carpet, adhesive, and clean before applying new carpet to ensure an even, finished product. The government will ensure all floor obstructions, such as furniture, will be removed prior to contractor beginning removal/installation of new carpet and cove base.
2.3 Contractor will ensure carpet edges meet wall edges sufficiently to ensure cove base will present a professional finished appearance once installed. The contractor shall dispose of removed carpet and cove base at a location off base and in accordance with all federal, state, and local regulations and standard commercial practices.
3 QUALIFICATIONS
3.1 The contractor shall be experienced in carpet and flooring installation. The contractor shall be in possession of insurance required to cover all removal and installation of carpet in accordance with standard commercial practices.
4 SPECIFIC WORK REQUIREMENTS.
4.1 The contractor will be responsible for coordinating the installation dates with the CO prior to beginning work. The CO will confirm the installation dates with the mission partner and building occupants before authorizing the dates. The contractor will be required to perform the following before, during, and after carpet installation:
• Survey the site prior to award to validate all measurements and ensure adequate carpet, adhesive, and additional materials are procured to complete the job.
• Order necessary carpet and adhesive from USAF mandatory sources in accordance with SOW and Air Force Carpet II Ordering Guide.
• Install all carpet, cove base and adhesive in accordance with SOW and manufacturer recommendations.
• Dispose of removed carpet, cove base and adhesive.
4.2 Cove Base provided shall conform to the following salient characteristics:
• Color – Black, Charcoal or Gray
• Size – 4 inches tall, no more than 1/8 inch thick
• Material – Rubber
5 GOVERNMENT FURNISHED MATERIALS, SERVICES, AND SUPPLIES
5.1 Government furnished supplies and property are not applicable to the performance of this contract.
6 GENERAL INFORMATION
6.1 Normal hours of operation are 0730 to 1630, Monday through Friday with a one-hour lunch. Federal
Holidays are excluded. The following federal holidays are observed:
January 1 New Year's Day 3rd Monday in January Martin Luther King, Jr. Day 3rd Monday in February President's Day Last Monday in May Memorial Day June 19th Juneteenth July 4th Independence Day 1st Monday in September Labor Day 2nd Monday in October Columbus Day November 11th Veterans Day 4th Thursday in November Thanksgiving Day December 25th Christmas
6.2 Quality Control. The contractor shall utilize its own internal quality control processes to ensure services are performed in accordance with commonly accepted commercial practices and this SOW.
The contractor's quality control plan and supporting documentation shall be made available to the government upon request.
6.3 Security Requirements All personnel employed by the Contractor in the performance of this contract, or any representative of the Contractor entering the government installation, shall abide by all Fairchild Air Force Base security regulations.
File details come from the government source that posted it. Updated .