Attach.1 - Statement of Work.pdf

PDF 1 MB Posted

Attached to
Premise Wiring
Solicitation number
FA462025QA965
Issued by

About this file

This Statement of Work (SOW) details a premises wiring upgrade project for Building 307 at Joint Base Lewis-McChord, Washington. The project requires engineering, furnishing, installing, and testing a new NIPR Cat-6 cabling infrastructure, which includes replacing existing racks/rack cabinets, installing new AC power for rack cabinets, relocating wall-mount fibers, and providing new Ethernet switch equipment. The contractor will remove all outdated Cat-3/Cat-5 cabling, existing racks, and residual materials.

Specific requirements include installing three new 19-inch, 42U rack cabinets, four Juniper EX4400-48MP Multigigabit 48-port PoE++ switches, one Juniper EX4400-EM-4S 4-port network uplink module, and associated power distribution units. The project encompasses 198 new dual-drop Cat-6 outlets (396 total drop cables), with comprehensive specifications for cable routing, termination, labeling, and testing. The contractor must comply with multiple federal, military, and commercial standards, provide detailed documentation, and complete the project within a timeframe determined by the contract award date, with all work subject to government inspection and approval.

View the file

Other files

File Type Posted
Amendment 0001.pdf PDF
25QA965 Combo.pdf PDF
Attach.2 - Wage Determination 2015-5537 Rev. 26.pdf PDF
Attach.3 - Brand Name J&A_Redacted.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

FA462025QA965

Attach.1 – Statement of Work

STATEMENT OF WORK

For

PREMISES WIRING UPGRADE, BUILDING 307

At

Joint Base Lewis-McChord, WA

Prepared By

38 ES/ENIU

4064 Hilltop Road Tinker AFB, OK 73145-2713

14 Feb 2025

SOW - Premises Wiring Upgrade, Building 307 at Joint Base Lewis-McChord i

TABLE OF CONTENTS

1. SCOPE

2. GENERAL INFORMATION

2.1 Place of Performance

2.2 Performance Period

2.3 Hours of Operation

2.4 Holidays/Down Days

3. GENERAL REQUIREMENTS

3.1 Site Coordination

3.2 Project Management

3.3 Contractor Supervision

3.4 Personnel Training and Certifications

3.5 Safety

3.6 Accident/Incident Reporting and Investigation

3.7 Base Access

3.8 Identification/Marking

3.9 Environmental Management

3.10 Pre-performance and Final Inspection

3.11 Work Area(s)

3.12 Packaging, Handling, Storage, and Transportation

3.13 Documentation

3.14 Implementation

4. SPECIFIC REQUIREMENTS

4.1 Standards

4.2 Labelling

4.3 Rack Cabinet

4.3.1 Power Distribution Unit (PDU)

4.4 Ethernet Switch Equipment

ii

4.4.1 Power Distribution Unit (PDU)

4.5 Bonding and Grounding

4.6 Fiber Relocation

4.7 Structured Cable Pathway

4.8 Structured Cat-6 Copper Cabling

4.9 Removal and Disposal

4.10 Restoration

4.11 Service Outages

4.12 Warranty

4.13 Quality Assurance

4.14 Weekly Status Reports

4.15 Project Schedules

4.16 Test Plan

4.17 Testing Requirements

4.18 Test Report

4.19 As-Built Drawings

4.20 Final Acceptance/Project Completion

4.21 Deliverables

5. GOVERNMENT-FURNISHED PROPERTY, EQUIPMENT, AND SERVICES

APPENDIX A APPLICABLE DOCUMENTS AND STANDARDS .....................................A-1

APPENDIX B LABELING STANDARDS ............................................................................. B-1

ATTACHMENT A LAYOUT DRAWINGS ....................................................................... ATT-1

ATTACHMENT B EQUIPMENT LISTING........................................................................ ATT-2

1. SCOPE. This Statement of Work (SOW) defines the requirements for the Contractor to engineer, furnish, install, and test (EFI&T) a premise wiring upgrade to new NIPR Cat-6 cabling for the building 307 (B307) at Joint Base Lewis-McChord (JBLM), WA. The premises wiring upgrade shall also include: replacing existing racks/rack cabinets and telecom grounding busbar, installing new AC power for the new rack cabinets, relocating existing wall-mount fibers to the new rack cabinets, and providing new Ethernet switch equipment. The Contractor shall remove all existing outdated and abandoned-in-place (AIP) Cat-3/Cat-5 cabling, existing racks/rack cabinets, and any residual materials from the building, and dispose of them accordingly.

2. GENERAL INFORMATION.

2.1 Place of Performance. The place of performance shall be JBLM, WA.

2.2 Performance Period. The period of performance for this project shall be determined based on the proposed schedule and the actual contract award date. All work shall be completed within the scheduled timeframe. Any request or justification for changes shall be made to the designated Contracting Officer (CO) in writing and must be approved by the CO.

2.3 Hours of Operation. The Contractor shall perform routine work during the normal duty hours of the base (normally Monday to Friday, 0730-1630 PST). However, mission requirements may necessitate work outside of normal hours, such as during maintenance windows, nights, and/or weekends, especially if existing services must be interrupted. Any site work requested by the Contractor to be performed outside of normal duty hours shall be coordinated in advance with the CO and the designated base Point of Contact (POC) for pre-approval.

2.4 Holidays/Down Days. The Contractor shall not perform work under this contract on federal holidays or site-specific down days unless expressly authorized by the CO and coordinated with the base POC.

3. GENERAL REQUIREMENTS. The Contractor shall provide all personnel, transportation, supervision, management, coordination, labor, tools and materials for the entire premises wiring upgrade project.

3.1 Site Coordination. The Contractor shall coordinate with the base POC a minimum of 10 business days prior to arrival on-site.

3.2 Project Management. The Contractor shall identify by name a project manager (PM), who shall be the prime Contractor’s employee, responsible as the single POC from award to final acceptance. The PM shall remain on site while work is performed to ensure successful performance. The Contractor shall identify the PM’s range of authority to act for the Contractor relating to daily contract operation.

3.3 Contractor Supervision. The Contractor shall be responsible for supervision of all contract personnel and performance of all Contractor-related functions.

3.4 Personnel Training and Certifications. All Contractor personnel identified to support this requirement shall be trained and/or certified on the systems involved in this effort. The Contractors performing the premises wiring upgrade must be BICSI Installer 2 and/or BICSI Technician certified. The Contractors performing electrical work must be US-licensed electricians. The Contractor shall be able to provide current certifications or qualifications upon Government request.

3.5 Safety. The Contractor shall comply with all Federal, State, and Base security and safety laws, regulations, policies, and requirements. If at any time it is determined that equipment is unsafe and/or work is being performed in an unsafe manner, all work will be immediately suspended until the Contractor has corrected the problem to the satisfaction of the Contracting Officer and SCXP

POC.

3.6 Accident/Incident Reporting and Investigation. The Contractor shall record and report all available facts relating to each instance of injury to either Contractor or Government personnel to the base SO or POC unless otherwise stated in the SOW. The Contractor shall secure the scene of any accident and wreckage until released by the accident investigative authority through the base POC. If the Government elects to investigate the incident, the Contractor shall cooperate fully and assist the Government personnel until the investigation is completed.

3.7 Base Access. The Contractor shall coordinate with the base POC for base access/entry pass requirements and process a Site Visit Access Request Letter to obtain access to the base. This letter shall identify the name, home address, birth date and place, nationality, physical description, passport number, driver’s license number or government issued identification (ID), social security number, etc. of the personnel who will be performing work on this project. This information is required to grant access to the base.

3.8 Identification/Marking. The Contractor shall clearly mark all Contractor-furnished Property/ Contract-furnished Equipment (CFP/CFE) with their company's name. The Contractor shall place an easily read, very visible sign (minimum 8.5" x 11") on large containers, construction equipment, or un-manned rental vehicles while on the base or Government installation indicating the company name and both the Contractor POCs and local telephone numbers.

3.9 Environmental Management. The Contractor shall comply with most stringent federal, state, local, and base environmental laws and regulations and Air Force policies, instructions, and plans. The Government is not exempt from compliance with environmental laws and regulations.

The Contractor shall maintain an awareness of changing environmental regulatory requirements to avoid environmental deficiencies for activities on the base. The prime Contractor shall ensure their sub-contractors, if any, comply with these requirements.

3.10 Pre-performance and Final Inspection. The Contractor shall conduct a pre-performance meeting with the MFT members prior to the start of implementation, as well as an final inspection after project completion. The pre-performance meeting shall cover all of the Contractor’s implementation plans and necessary support requirements. The final inspection shall cover all equipment installations, implementation results, required maintenance, and warranties, at a minimum.

3.11 Work Area(s). At day’s end, the Contractor shall remove all debris and surplus materials from the workplace. Equipment and materials required to complete the work effort may remain on site as long as they are secured in a manner that does not cause a safety hazard.

3.12 Packaging, Handling, Storage, and Transportation. The Contractor shall be responsible for the packaging, handling, storage, transportation, staging, and deployment of any equipment and materials required as part of this project. The Contractor shall coordinate with the base POC to identify any necessary base support, such as laydown and storage areas, and provide a plan for delivering all materials to the work site. The Contractor shall also be responsible for equipment inventory. The Contractor shall return all government-furnished laydown and storage areas to their original condition upon completion of the project. In addition, the Contractor shall be responsible for off-base disposal of all waste, packaging, debris residues and removed equipment IAW the base POC’s instructions, Defense Logistics Agency (DLA) and AFB policies, and federal, state, and local environmental laws and regulations.

3.13 Documentation. The Contractor shall verify the accuracy of all government-furnished documents and drawings. The Contractor shall comply with DoD security provisions and shall not divulge any government-furnished documentation or other knowledge that may be gained to anyone who is not authorized to have access to such information. All Contractor deliverables shall be marked IAW DoDM 5200.01, Vol. 3 & Vol. 4, Information Security, and DoDM 5400.07, Freedom of Information Act Program, or as directed by the Government.

3.14 Implementation. The Contractor shall have ultimate responsibility for the successful completion of the project. Any work deemed non-compliant shall be reworked immediately at the Contractor’s expense. The Contractor shall plan and manage daily operations and activities associated with project performance. The Contractor will employ effective management tools and methods to ensure control of cost, schedule, and performance. The Contractor shall conduct, support, and/or participate in program management and technical reviews, meetings, and conferences, as required, to ensure the effective and efficient execution of this project. The Contractor shall ensure the protection of government property to prevent damage during project performance.

4. SPECIFIC REQUIREMENTS. The Contractor shall comply with all current ANSI/TIA telecommunications installation and testing commercial standards. All upgrade equipment, supplies, hardware, and materials shall be new and not refurbished.

4.1 Standards. All installations, including rack cabinets, racks, cabling (communications, power, grounding, etc.), equipment, pathways, raceways, cable management, patch panels, and related hardware/components, shall be IAW the standards referenced in Appendix A, Applicable Documents and Standards. In secure areas, all installations shall comply with AFSSI 7702 “Emission Security Countermeasures” and NSTISSAM Tempest/2-95 “NSTISSAM Red/Black Installation Guidelines.”

4.2 Labelling. All equipment, rack cabinets, racks, cables, faceplates, patch panels, powers, and relevant components shall be labeled appropriately IAW the standards referenced in Appendix B, Labeling Standards, as well as the current version of TIA-606. All labeling shall be completed using a permanent method; handwritten labeling shall not be authorized.

4.3 Rack Cabinet. The Contractor shall remove all existing racks/rack cabinets and associated equipment in the B307 Comm Room as shown in Attachment A, Figure-ATT-5, Existing Racks/Rack Cabinets in B307 Comm Room and coordinate with the base POC and CE prior to removal. The Contractor shall provide three (3) new 19-inch, 42U, 29.53” (W) x 42.13” (D), 4-post, adjustable-depth, floor-mounted, lockable rack cabinets (APC AR3150B2 or equivalent), IAW the current version of EIA/ECA-310 standard, and securely install it to the true floor at the proposed locations in the Comm Room as shown in Attachment A, Figure ATT-2, B307 Comm Room with New Rack Cabinet Layout. The new rack cabinet shall include ventilated doors, top cover plates with fan module and cable entry brush, M6 screw & cage nut set, vertical potential equalization bonding busbar (vertical rack bonding busbar), rack bonding conductors, horizontal finger duct cable managers with covers, vertical finger duct cable managers with covers, rear vertical PDU/accessory bars, blank panels, and all other associated accessories. All equipment rack rails shall be telecommunications-style rails that are unpainted and have drilled and tapped mounting holes IAW DISN Implementation Standards, Chapters 2.7.20 to 2.7.26. The rack cabinet installation shall align as closely as possible to the new cable ladder to facilitate cabling installation and shall be properly bonded and grounded to the new secondary bonding busbar (SBB) in the Comm Room.

4.3.1 Power Distribution Unit (PDU). The Contractor shall provide two (2) new TAA-compliant, vertical rack-mount 240VAC 30A NEMA L6-30P PDU (Eaton EMI104-10 or equivalent) and install one (1) in each of the two new rack cabinets RC-01 and 02 for AC power distribution to the rack cabinet equipment. The Contractor shall provide and install one (1) new TAA-compliant, vertical rack-mount 120VAC 30A NEMA L5-30P PDU (Eaton EMI102-10 or equivalent) in the new rack cabinet RC-03.

4.4 Ethernet Switch Equipment. The Contractor shall procure the following new Ethernet switch equipment and provide them to the base POC and 627 CS/SCOI for installation, commissioning, configuration, and integration of the switches into the base network. All the new Ethernet switch equipment must be TAA-compliant. The Contractor shall verify the equipment models with the base POC and 627 CS/SCOI prior to procurement.

• Four (4) Juniper EX4400-48MP Multigigabit 48-port PoE++ Switches, each comes with a preinstalled 1600W AC power supply

• One (1) Juniper EX4400-EM-4S 4-port 1GbE/10GbE SFP+ Network Uplink Module

• Four (4) Juniper 50CM QSFP28 100GB Virtual Chassis Stacking Cables

4.4.1 Power Distribution Unit (PDU). The Contractor shall provide two (2) new TAA-compliant, vertical rack-mount 240VAC 30A NEMA L6-30P PDU (Eaton EMI104-10 or equivalent) and install one (1) in each of the two new rack cabinets RC-01 and 02 for AC power distribution to the rack cabinet equipment. The Contractor shall provide and install one (1) new TAA-compliant, vertical rack-mount 120VAC 30A NEMA L5-30P PDU (Eaton EMI102-10 or equivalent) in the new rack cabinet RC-03.

4.5 Bonding and Grounding. All new rack cabinets with rack bonding busbars, as well as all equipment, cable trays, ladders, and risers, shall be bonded and grounded to the building grounding system IAW Mil-Hdbk-419A, Vol. I and II, and the current version of TIA-607. The Technical Order (TO) 31-10-24, “Installation Practices – Communication Systems Grounding, Bonding, and Shielding,” shall also be adhered to. The TO will be provided after award. The Contractor shall provide and install one (1) new 2” W x 1/4” T x 12” L SBB in the B307 Comm Room. The Contractor shall provide a new, insulated, minimum-sized bonding copper conductor of #3/0 AWG and properly bond and ground the new SBB to the B307's existing primary bonding busbar (PBB) or telecom bonding backbone (TBB), and coordinate with the base POC and CE for locations of the PBB or TBB in the B307. The Contractor shall then provide new, insulated, minimum-sized bonding copper conductors of #6 AWG and properly bond and ground the new rack cabinets' rack bonding busbar to the SBB. All bonding and grounding conductors shall be continuous and routed in the shortest practical straight-line path. The Contractor shall test and document all new or extended grounding points at each new rack cabinet and at any new bonding locations. The Government reserves the right to perform verification testing to ensure compliance.

4.6 Fiber Relocation. The existing wall-mount fiber optic patch panels (FOPPs) are shown in Attachment A, Figure 6, Existing Wall-Mount SM/MM ST FOPPs, and the proposed face equipment layout for each new rack cabinet is shown in Attachment A, Figure ATT-3, Proposed New Rack Cabinet Face Equipment Layout. The Contractor shall relocate two (2) existing 48-port SM/MM ST FOPPs and their associated fiber cables from the current wall-mount locations to the new rack cabinet RC-03 and reconnect the fibers to the same ports on these existing FOPPs. The Contractor shall then provide and install a new 12-port SM ST FOPP in the new rack cabinet RC- 01, remove the existing 12-port SM ST FOPP and its associated fiber cable from the current wall-mount location, and reconnect the fibers to the corresponding ports on this new FOPP.

4.7 Structured Cable Pathway. The Contractor shall provide and install all new, necessary cable pathway support hardware for the entire NIPR Cat-6 cable runs, including but not limited to, cable trays, ladders, risers, drop-outs, caddy straps/slings, J-hooks, conduits, ducts, sleeves, raceways, and wireways, IAW industry and installation standards. All penetrations through fire-rated walls, floors, or ceilings shall have fire-stop sleeves installed IAW fire safety codes. The proposed new main above-ceiling Cat-6 cable tray pathway is shown in Attachment A, Figure ATT-1, B307 Premises Wiring Upgrade with New Drop Location Layout, with the basket-type cable tray preferred for this main cable pathway installation. The proposed new cable ladder in the Comm Room is shown in Attachment A, Figure ATT-2, B307 Comm Room with New Rack Cabinet Layout, with the cable ladder size preferred at 12” wide. The Contractor shall ensure that the cable pathway support hardware is properly sized, with the calculated maximum fill ratio and/or non-continuous cable support (J-hooks or caddy straps/slings) intervals IAW UFC 3-580-01. All cable tray, ladder, and riser sections shall be properly bonded together and grounded to the building grounding system.

4.8 Structured Cat-6 Copper Cabling. The layout of the new Cat-6 drop outlets/locations for B307 is shown in Attachment A, Figure ATT-1, and the proposed face equipment layout for each new rack cabinet is shown in Attachment A, Figure ATT-3. There is a total of 198 new NIPR cat-6 dual-drop outlets required for the building, resulting in a total of 396 drop cables. The drop locations indicated on the layout are approximate and not to scale.

4.8.1 The Contractor shall provide all new cables, termination hardware, connections, and other associated components, which must be Cat-6 compliant. All Cat-6 cables shall be unshielded twisted pair (UTP) and made of solid pure copper wire no smaller than 24 AWG. Plenum-rated Cat-6 cables shall be utilized as required by industry and applicable standards.

4.8.2 All Cat-6 cables shall be wired and terminated using the T568B wiring scheme. All Cat- 6 cable installations shall be tested IAW the current version of TIA-568.2 to meet wiremap, length, and performance specifications.

4.8.3 All Cat-6 cable jackets and outlets, including patch cords, shall be blue in color.

4.8.4 All Cat-6 labeling shall be IAW the standards referenced in Appendix B, Labeling Standards. The Contractor shall verify the labeling scheme with the base POC prior to installation. All labeling must be completed using a permanent method; handwritten labeling is not authorized.

4.8.5 The Contractor shall provide nine (9) new UTP 48-port Cat-6 patch panels and install four

(4) in the new rack cabinet RC-01 and five (5) in the new rack cabinet RC-02. The Contractor shall also install new horizontal cable managers for the patch panels, along with new vertical cable managers, to keep the cable runs and patch cords organized and routed neatly within the new rack cabinets.

4.8.6 Unless otherwise noted, all Cat-6 cables from the new drop locations shall be routed directly through the installed structured cable pathway supports to the new Cat-6 patch panels in the new rack cabinets. These cables shall be terminated at both the Cat-6 patch panels and the faceplates at the drop locations. All Cat-6 cabling shall adhere to the same wiring and termination standards, and no cable run shall exceed 295 ft (90 m) in length.

4.8.7 All Cat-6 cables shall be routed in a structured and orderly manner and secured within cable pathway support hardware. All Cat-6 cables shall be fanned and formed using Velcro straps to support the cabling.

4.8.8 The Contractor shall provide and install new Cat-6 patch cords for cross-connections within the rack cabinet, from the Cat-6 patch panels to the network Ethernet switches for all drops. These patch cords shall be pre-made in the same length or in a variety of lengths.

4.8.9 If surface-mounted raceway is installed on wall surfaces, the surface-mounted raceway shall be secured with appropriate anchor and screw hardware and be “off-white” in color. The surface-mounted raceway installed with adhesive tape is not authorized.

4.8.10 The existing cable routes within the walls shall be reused where possible, provided they are within the general location of user drops.

4.8.11 The Contractor shall fire-stop all cable entrances that are cut, drilled, or core-drilled into walls IAW industry and safety codes.

4.8.12 New drop installations shall be positioned at a mounting height above the finished floor IAW the base building codes and Architectural Barriers Act (ABA) compliance to allow for easy access for user patch cord connections (18 in as general practice).

4.8.13 All Cat-6 cables shall be protected from rough or sharp edges and burrs when routed through cable openings. All penetrations into the rack cabinet must be reamed, filed, and fitted with bushings or grommets. No exposed metal edges shall come into contact with the Cat-6 cabling.

4.8.14 The Contractor shall verify the specific required lengths of Cat-6 patch cords from the drop locations’ faceplates to user network devices (e.g., laptop, desktop, printer) and provide and install new Cat-6 patch cords for these connections. These patch cords shall be pre-made in a variety of lengths. The Contractor shall ensure that the total length of the cable run, cross-connection patch cord, and user-connection patch cord does not exceed 328 ft (100 m).

4.8.15 The Contractor shall remove the existing outdated and AIP Cat-3/Cat-5 cabling, including any residual materials, from the building. For the voice analog cabling, the Contractor shall coordinate with the base POC prior to removal. If the existing cables are removed from a drop location, and either no longer needed to be replaced with new Cat-6 cables or cannot be replaced, the drop location shall be covered with a blank faceplate.

4.9 Removal and Disposal. The Contractor shall provide for the removal and disposal of any existing equipment, cabinets, racks, cabling, hardware, and associated termination equipment, including all residues, except Automatic Data Processing Equipment (ADPE) IAW the base POC’s instructions. The Contractor shall dispose of them off/on-base IAW the base POC’s instructions.

The Contractor must ensure compliance with DLA and AFB policies, as well as any relevant federal, state, and local environmental laws and regulations regarding disposal.

4.10 Restoration. The Contractor shall restore all disturbed areas and base property to the “as found” conditions or better after installation. Any wall penetrations shall be restored to meet the NFPA 1 and NFPA 70.

4.11 Service Outages. The Contractor shall be responsible for preventing any unscheduled interruptions of services caused by the Contractor (i.e., cutting or disabling any in-service cables or equipment) that are properly identified. The Contractor shall minimize downtime and interruptions to network services for base customers as much as possible during installation. If the implementation necessitates a disruption of service (e.g., communications, electrical, or other utilities), the Contractor shall coordinate planned outages with the base POC at least 2 calendar days in advance.

4.12 Warranty. The Contractor shall provide warranty services for workmanship deficiencies and installed equipment for a minimum period of one (1) year, starting from the date of final acceptance. The Contractor shall provide written procedures and required information for warranty services prior to final acceptance. This information shall include, but is not limited to, written confirmation of the warranty period, as well as phone numbers, contact information, and procedures for technical support, troubleshooting assistance, and replacement of faulty equipment.

Unless otherwise specified, the Contractor shall provide copies of commercial-off-the-shelf (COTS) technical or equipment manuals, warranty documentation, and maintenance procedures for the Contractor-furnished end-item system equipment. The Contractor shall transfer warranties to the Government upon project acceptance.

4.13 Quality Assurance. The Government reserves the right to perform inspections of the Contractor’s work during any and all phases of the installation.

4.14 Weekly Status Reports. The Contractor shall prepare a weekly status report and distribute it electronically. The purpose of the report is to inform MFT members of project progress, problems encountered, and other topics necessary to ensure the success and timely completion of contract requirements.

4.15 Project Schedules. The Contractor shall provide a complete milestone schedule that outlines project activities, including time-phased start and completion dates for the project and its associated sub-projects relating to the installation (CDRL A002) within 7 calendar days of contract award. The

Contractor shall establish a preliminary project schedule/plan.

4.16 Test Plan. The Contractor shall provide a test plan clearly detailing how the upgraded premises wiring will be pre-tested, in-progress tested, and post-tested (CDRL A005). The Contractor shall test the upgraded premises wiring to demonstrate to the Government that it is correctly installed, properly functioning, fully complaint with standards, and meet or exceed all performance parameters and specified requirements. These tests shall be completed prior to cutover and placement into service.

4.17 Testing Requirements. The Contractor shall provide all test equipment and personnel required to conduct testing and ensure compliance with the standards referenced in Appendix A, Applicable Documents and Standards. During any testing phase, the Government reserves the right to inspect a minimum of 10% of wiring. The Contractor shall provide on-site support during acceptance testing.

4.18 Test Report. The Contractor shall document and provide a test report of all results from the testing completed under the test plan to the base POC and 627 CS/SCXP (CDRL A006).

4.19 As-Built Drawings. The Contractor shall provide clear drawings showing the “as-built” condition in Visio and PDF formats (CDRL A001). The drawings shall depict the details of the entire premises wiring upgrade, including, but not limited to, entrance/equipment/comm room locations, rack cabinets, drop locations, drop outlet numbers, rack elevation, pathways, labeling, cabling, wiring, cross-connections, patch panels, grounding, and other relevant details.

4.20 Final Acceptance/Project Completion. The final acceptance shall conclude upon the successful completion and receipt of all deliverables. The Contractor shall schedule a final project walkthrough with the base POC, CO, and 627 CS/SCXP at least five (5) calendar days prior to acceptance. The Government reserves the right to refuse final acceptance until all discrepancies and problems have been resolved to its satisfaction.

4.21 Deliverables. All deliverables are subject to Government acceptance and approval. They shall meet the professional standards and requirements set forth in this SOW. All deliverables shall be produced using software tools and versions recommended and accepted by the Government. The Contractor shall submit the following deliverables:

Table 1. Contract Data Requirement List (CDRL) CDRL Data Item Title Data Item Title A001 As Built DI-DRPR-80151A/T A002 Work Schedule DI-MISC-81382/T A003 Status Report DI-MGMT-80368A A004 Meeting Minutes DI-ADMIN-81505/T A005 Cutover and Test Plan DI-NDTI-80566A/T A006 Test Report DI-QCIC-80512

A-1

APPENDIX A. APPLICABLE DOCUMENTS AND STANDARDS

The Contractor shall comply with all military and commercial standards where applicable. Other commercial standards may apply to individual projects and will be specified in the respective task orders. In the event of a conflict between a commercial document and a Federal or Military Standard, the Federal or Military Standard shall take precedence. It is the Contractor's responsibility to identify and obtain the applicable standards proposed for the project in the SOW.

The following tables are not all-inclusive lists of standards. The Contractor shall obtain and comply with any other applicable manuals not identified in these tables that are required to meet industry standards.

Table A-1. Federal Government Standards

NUMBER TITLE WEBSITE OR

LOCATION

OSHA Occupational Safety and Health Administration (OSHA) http://www.osha.gov OSHA CFR 29 Part 1910-268 - (1988)

Telecommunications

EPA Environmental Protection Agency (EPA) http://www.epa.gov/ EPA EPA Rules, Regulations, and Legislation ABA/ADA Architectural Barriers/Americans with Disabilities Acts DODD 5220.22 DOD Industrial Security Program Directive DOD JTA ver. 4 Department of Defense Joint Technical Architecture AFI 31-101 The Air Force Installation Security Plan

Table A-2. Military Standards

NUMBER TITLE

MIL-STD-188-154A Subsystem, Equipment, and Interface Standards for Common Long Haul and

Tactical Telecommunications Control Facilities MIL-STD-188-124B Grounding, Bonding and Shielding for Common Long Haul/Tactical

Communications Systems

MIL-HDBK 419A,

Vol. I and II

Grounding, Bonding, and Shielding for Electronic Equipment and Facilities

MIL-HDBK-232A Red/Black Engineering Installation Guidelines MIL-HDBK-411B Power and the Environment for Sensitive DoD Electronic Equipment AFI 32-1065 Grounding Bonding and Shielding for Electronic Equipment and Facilities AFI 91-203 Air Force Consolidated Occupational Safety Instruction MIL-HDBK-1857 Grounding, Bonding and Shielding Design Practices MIL-HDBK-454B General Guidelines for Electronics Equipment UFC 3-580-01 Telecommunications Interior Infrastructure Planning and Design Local Standards Joint Base Lewis-McChord Construction Standards

(Copies of the above documents may be obtained from the Naval Publications and Forms Center (NPFC 105), 5801 Tabor Ave, Philadelphia PA 19120.)

http://www.osha.gov/ http://www.epa.gov/

A-2

Table A-3. Commercial Standards and Manuals

NUMBER TITLE WEBSITE OR LOCATION

BICSI TDM

Manual

Building Industry Consulting Service International, Inc. (BICSI) Telecommunications Distribution Methods (TDM) Manual http://www.bicsi.org/

NFPA 70 National Fire Protection Association (NFPA) National Electric Code (NEC) http://www.nfpa.org/

NFPA 72 National Fire Alarm Code EIA/ECA-310-E Racks, Panels and Associated Equipment http://www.eia.org/ http://www.tiaonline.org/ TIA-526-7 Measurement of Optical Power Loss of Installed

Single-mode Fiber Cable Plant

TIA-526-14-B Optical Power Loss Measurement of Installed Multimode Fiber Cable Plant

ANSI/TIA 568.0-E Generic Telecommunications Cabling for Customer Premises

ANSI/TIA-568.1-E Commercial Building Telecommunications Cabling Standard

ANSI/TIA-568.2-E Balanced Twisted-Pair Telecommunications Cabling and Components Standard

ANSI/TIA-568.3-E Optical Fiber Cabling Components Standard ANSI/TIA 569-E Telecommunications Pathways and Spaces

Standard

TIA-570-D Residential Telecommunications Infrastructure Standard

TIA-598-C Optical Fiber Cable Color Coding ANSI/TIA-606-C Administration/Labelling Standards for the Telecommunications Infrastructure of Commercial

TIA/EIA-607-D Generic Telecommunications Grounding and Bonding (Earthing) for Customer Premises

TIA-758-B Customer-owned Outside Plant Telecommunications Infrastructure

ANSI/TIA-862-D Structured Cabling Infrastructure Standard for Intelligent Building System

ANSI/TIA-942-C Telecommunications Infrastructure Standard for Data Centers

ANSI/NECA/BICSI

-002

Data Center Design and Implementation Best Practices

RUS Bulletin 1751F-801

Electrical Protection Fundamentals

RUS Bulletin

1753F-201 (PC-4)

RUS Standard for Acceptance Tests and Measurements of Telecommunications Plant

RUS Bulletin

1753F-207 (PE-

REA Specification for Terminating Cables

TIA-604 Series Fiber Optic Connector Intermateability Standard

(FOCIS)

http://www.bicsi.org/ http://www.nfpa.org/ http://www.eia.org/ http://www.tiaonline.org/

B-1

APPENDIX B. LABELING STANDARDS

B.1 LAN Faceplate Labeling.

B.1.1 Two Position UTP Wall Plate.

ROOM Actual room number from the facility drawings at time of design.

TELECOM ROOM (TR) Actual TR or Equipment Room where the end of the wall plate cables terminate. In existing facilities with no TR numbers, the TR room identifier shall be floor number, room number where room number starts with the letter A with additional TR labeled B, C etc.

RACK # Actual Rack number that contains the patch panel where the cable terminates.

PATCH PANEL # Actual patch panel number.

PORT #’s Actual port numbers in the patch panel.

The bottom position of the UTP wall plate shall be marked with the Room Number that the wall plate is installed. This information is reflected in the site cable plan.

Top Position Example:

110-1-1-1, 2

TR 110

Rack # 1 Patch Panel # 1 Port #’s 1, 2 (On the patch panel)

Bottom Position Example:

32 = Room Number (Actual room # from the cable plan and facility drawings at time of design)

Top Position Example: (no comm. room identifier)

1A-1-1-1, 2 = TR 1A, Rack # 1, Patch Panel # 1, Port #’s 1, 2 (On the patch panel)

B-2

Figure B-1. Two-Position Wall Plate Numbering Scheme

B-3

B.1.2 Four Position Wall Plate.

ROOM Actual room number from the facility drawings at time of design.

TELECOM ROOM (TR) Actual TR or Equipment Room where the end of the wall plate cables terminate. In existing facilities with no Telecom Room (TR) numbers the TR room identifier shall be floor number, room number where room number starts with the letter A with additional TR labeled B, C etc.

RACK # Actual Rack number that contains the patch panel where the cable terminates.

PATCH PANEL # Actual patch panel number.

PORT #’s Actual port numbers in the patch panel.

The bottom position of the wall plate shall be marked with the Room Number that the wall plate is installed. This information is reflected in the site cable plan.

Top Position Example:

110-1-1-1, 2, 3, 4

TR 110

Rack # 1 Patch Panel # 1 Port #’s 1,2,3,4 (On the patch panel)

Bottom Position Example:

32 = Room Number (Actual room # from the cable plan and facility drawings at time of design)

Top Position Example: (no comm. room identifier)

1A-1-1-1, 2, 3, 4 = TR 1A, Rack # 1, Patch Panel # 1, Port #’s 1,2,3,4 (On the patch panel)

B-4

Figure B-2. Four-Position Wall Plate Numbering Scheme

B-5

B.2 Patch Panel Labeling Patch panel shall be labeled using the following format. Room number (actual room where user wall plate is located), face plate number, jack designator, 110-1 A B C D.

Figure B-4. Patch Panel Numbering Scheme

B.3 Fiber Marking.

B.3.1 Fiber Optic Distribution Panel (FODP)/Fiber Optic Patch Panel (FOPP) Marker.

All new FODPs or FOPPs shall be marked to identify those that terminate fibers, using the following formats:

Inter-building fiber backbone:

FOPP [Building #] (or FODP [Building #]) FO [Route: Source Building# - Destination Building#], [Strand Count] [Fiber Type]

Intra-building fiber backbone:

TIE FOPP [Room #] TIE FO [Route: Source Room# - Destination Room#], [Strand Count] [Fiber Type]

Example:

FOPP B395

FO B395 - B1203, 1-12 SM

TIE FOPP R100

TIE FO R100 – R122, 1-12 SM

B.3.2 Fiber Cable Marker Tag.

All fiber cables shall be tagged and marked to identify their size, type, cable number, and strand count, using the following format:

Example:

12L8.3F

FO B395 – B1203, 1-12 SM

First line: “12” stands for Fiber Count. “L” stands for Loose Tube Buffer or (“T”) for Tight Tube Buffer. “8.3” stands for Single Mode. “F” stands for Filled Core (otherwise leave blank).

ATTACHMENT A. LAYOUT DRAWINGS

Figure ATT-1. B307 Premises Wiring Upgrade with New Drop Location Layout

ATT-1

Figure ATT-2. B307 Comm Room with New Rack Cabinet Layout

Figure ATT-3. Proposed New Rack Cabinet Face Equipment Layout

ATT-2

Figure ATT-4. Typical Rack Cabinet AC Power Distribution Configuration without UPS

Figure ATT-5. Existing Racks/Rack Cabinets in B307 Comm Room

Figure ATT-6. Existing Wall-Mount SM/MM ST FOPPs

Existing Wall-mount 48-port MM ST FOPPs

Existing Wall-mount 12-port SM ST FOPP

ATTACHMENT B. EQUIPMENT LISTING

This is a consolidated equipment listing. The items in Table 1. are an estimate for quantities, adjustments may be needed once surveyed. Items listed in Table 2. are exact quantities.

Table 1.

ITEM QTY UI

Horizontal Cable Tray/Support (incl. install hardware) 656 ft Surface raceway 528 ft Base Clips for Raceway 176 ea Drop Ceiling Adapter 198 ea Gang Box 198 ea Snap in Frame for Faceplate 198 ea Faceplates 198 ea Blank Faceplates 50 ea TIA568 Cat6 wall jacks 396 ea Cat 6 cable 1000' roll PVC Solid Conductor Plenum Rated 92 bx J hooks (4 per drop - 4 per drop assumes multiple runs using same hooks) 792 ea Patch Cord 3 ft Cat 6 RJ45 (Panels, all patched to equipment)

396 ea

Patch Cord 10 ft Cat 6 RJ45 396 ea Velcro straps (pkg of 10) 460 pk Tie wraps (pkg of 100) 46 pk Document & Label 396 ea Grounding TGB/SBB (run 3/0AWG to MTGB/PBB or grounding backbone) 90 ft Grounding rack cabinet (run 6AWG to TGB/SBB) 60 ft Core Drill w/ EMT/fire-rated sleeve (sheetrock/other) 7 ea Core Drill w/ EMT/fire-rated sleeve (brick/concrete) 12 ea Misc. Supplies & Hardware (fittings, tapes, lugs, sealants, labels, clamps, brackets, etc.)

1 lo

Table 2.

ITEM QTY UI

Cat 6 Patch Panel 48 Port for Data 11 ea Cable Management Panels, Horizontal 11 ea 42U Rack Cabinet, 29.53"W x 42.13"D, 19-inch, 4-post, adjustable-depth, floor-mounted, lockable, including ventilated doors, top cover plates with fan module and cable entry brush, M6 screw/cage nut set, vertical potential equalization bonding busbar, rack bonding conductors, vertical finger duct cable managers, rear vertical PDU/accessory bars, blank panels, and all other accessories (APC AR3150B2 or equivalent)

3 ea

Juniper EX4400-48MP Multigigabit 48-port PoE++ w/ 1600W AC Power Supply, TAA 4 ea Juniper EX4400-EM-4S 4-port 1GbE/10GbE SFP+ Network Uplink Module, TAA 1 ea Juniper 50CM QSFP28 100GB Virtual Chassis Stacking Cable 4 ea Rack PDU, 120V 30A, NEMA Twist Lock L5-30P (Eaton EMI102-10 or equivalent) 1 ea Rack PDU, 240V 30A, NEMA Twist Lock L6-30P (Eaton EMI104-10 or equivalent) 2 ea TGB/SBB Ground busbar kit (install TGB/SBB 2"Wx1/4"Tx12"L busbar in comm rm) 1 ea

APPENDIX A. APPLICABLE DOCUMENTS AND STANDARDS
APPENDIX B. LABELING STANDARDS
ATTACHMENT A. LAYOUT DRAWINGS