This document is a Statement of Work (SOW) for a federal contract opportunity to furnish, deliver, install, and test new dishwashing and tabling equipment for the Warrior Dining Facility at Fairchild Air Force Base.
The contractor shall provide one (1) BRAND NAME OR EQUAL Hobart Model No. CLPS86EN-ADV+BUILDUP conveyor-type dishwasher and a BRAND NAME OR EQUAL Aerowerks Inc Model No. QP244100 soiled breakdown system and tabling. The dishwasher must have specific salient characteristics including 342 racks/hour capacity, 0.39 gallon/rack usage, and various add-ons. The tabling system must include a soiled dish table, knuckle belt rack transfer conveyor, clean dish roller table, and other components. All equipment shall be new, energy-efficient, and made in the USA if possible. The work must be completed within 60 days after award. Security requirements include personnel background checks and escorts on the military installation during performance. The contract will be awarded by the Department of the Air Force Air Mobility Command.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Attach. 1 - Statement of Work (Amend 02).pdf | ||
| Amend 02.pdf | ||
| Attach. 2 - Concept Drawing.pdf | ||
| Amendment 0001 SF30.pdf | ||
| Amend 0001 24QA233 Combo.pdf | ||
| 24QA233 DFAC Dishwasher.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
STATEMENT OF WORK
FOR
WARRIOR DINING FACILITY DISHWASHER AND TABLING
May 2024
FA462024QA233
Warrior DFAC Dishwasher
Attach. 1 - SOW
1. BACKGROUND: The Warrior Dining Facility provides meals for military and civilian members at Fairchild Air Force Base. The dishwasher purchased in 2020 has failed and is no longer able to be repaired. The lack of reliable dishwashing could cause a decline in food safety and cleanliness standards and capabilities.
2. SCOPE OF WORK: The Contractor shall provide all labor, tools, and materials to furnish, deliver, install, and test new and unused BRAND NAME OR EQUAL dishwashing and tabling equipment in accordance with this Statement of Work and associated salient characteristics.
3. OBJECTIVES: To provide efficient, effective, professional, and safe food service to both military and civilian personnel assigned to Fairchild Air Force Base.
4. REQUIREMENTS: The contractor shall provide all labor, tools, and materials required to provide the BRAND NAME OR EQUAL dishwashing and tabling equipment items identified in Appendix A: Parts List and Salient Characteristics. No used, previously owned, or refurbished equipment will be accepted. All items shall be energy star certified and made in the United States of America if possible. Some items require removal of existing appliances, disposal of removed appliances, and installation of new equipment. All garbage, waste, and debris shall be disposed of in accordance with state, local, and federal environmental regulations.
5. DELIVERY: 60 days ARO
6. SECURITY REQUIREMENTS: All personnel employed by the Contractor in the performance of this contract, or any representative of the Contractor entering the government installation, shall abide by all Fairchild Air Force Base security regulations. Personnel performing the work requested will be escorted for the duration on the installation. Individuals must be able to pass a background check that will be conducted prior to entry of the installation.
Individuals performing the work will be required to provide their full name, DOB, SSN, driver’s license issuing state and license number to gain access to the installation.
7. PLACE OF PERFORMANCE: All work shall be performed on Fairchild Air Force Base with delivery to Warrior Dining Facility at 100 W Bong St, FAFB WA 99011 Additionally, all delivery and installation shall be scheduled in advance.
8. GENERAL INFORMATION:
8.1. HOURS OF OPERATION: Hours of operation are 0700-1630 Monday through Friday, excluding Federal Holidays and any other designated down day. Work can be done at other than the normal hours of operation with the approval of the Contracting Officer. The contractor shall coordinate in advance all hours of work and any service interruptions with MSgt Emailina San Agustin at (509) 247-2641.
FA462024QA233
January 1 New Year’s Day 3rd Monday in January Martin Luther King, Jr. Day 3rd Monday in February President’s Day Last Monday in May Memorial Day June 19 Juneteenth July 4 Independence Day 1st Monday in September Labor Day 2nd Monday in October Columbus Day November 11 Veterans Day 4th Thursday in November Thanksgiving Day December 25 Christmas
9. APPENDICES:
Appendix A: BRAND NAME OR EQUAL Parts list with Salient Characteristics
FA462024QA233
Appendix A: BRAND NAME OR EQUAL Parts List with Salient Characteristics
ITEM 0001: Dishwasher, conveyor type The government is requesting one (1) BRAND NAME OR EQUAL Hobart Model No.
CLPS86EN-ADV+BUILDUP. Item will be installed at the Warrior Dining Facility, 100 W. Bong St. FAFB, WA 99011-6010.
Specifications:
Conveyor Dishwasher to include following minimum salient characteristics and add-ons: (2) tank with a Power Scrapper, (342) racks/hour, insulated hinged doors, .39 gallon/rack, stainless steel enclosure panels, microprocessor controls with low temperature & dirty water indicators, NSF Pot & Pan mode, programable de-lime notification, power scrapper vent cowl curtain kit, ITEM Manufacturer Part Number (P/N) Description Qty 0001 Hobart CLPS86EN-
ADV+BUILDUP
Conveyor type Dishwasher 1
Dishwasher add-on
CLPS86EN-ADVHTE15K Electric tank heat 15kW wash/10kW rinse
CLPS86EN-ADVERH30K 30kW electric booster 1 CLPS86EN-ADVELE0AX 208v/60/3-ph 1 SGLPT-KIT3-CLE Single Point Electrical Connection, kit 3, for CLen units
CLPS86EN-ADVHGTSTD Standard height 1 CLPS86EN-ADVDIR0LR Left to right operation 1 FLGFT-CLE Flanged Feet, <CLPS & CLCS models (66”, 76” & 86”) require 3 sets (6 feet)>
EXTHD/E-ADJ E-series extended hood (adjustable) 1 SHTHD/E-ADJ E-series vent hood short
(adjustable)
SYNCRO-24V-CLE External Conveyor Synchronization 24v - Receives external signal from customer conveying system to start or stop the warewash unit (pumps and conveyor); provides a dry contact interface which closes when dish machine conveyor is running.
0002 Aeroworks QP244100 Soiled breakdown system 1 Tabling add-on
KBC-200 C/W perforated grating, scrap sump with perforated scrap basket and electrical control panel
GRC C/W 1.9” PVC rollers, Photoelectric diffuser sensor and pre-wired limit switch
FA462024QA233
30 kW stainless booster, energy recovery (DWER), automatic soil removal (ASR), drain water tempering kit, ENERGY STAR®
We are also requesting the following additions to the unit:
• CLPS86EN-ADVHTE15K Electric tank heat 15kW wash/10kW rinse
• CLPS86EN-ADVERH30K 30kW electric booster
• CLPS86EN-ADVELE0AX 208v/60/3-ph
• SGLPT-KIT3-CLE Single Point Electrical Connection, kit 3, for CLen units
• CLPS86EN-ADVHGTSTD Standard height
• CLPS86EN-ADVDIR0LR Left to right operation
• FLGFT-CLE*3 Flanged Feet, <CLPS & CLCS models (66”, 76” & 86”) require quantity of 3 sets (6 feet)>
• EXTHD/E-ADJ E-series extended hood (adjustable)
• SHTHD/E-ADJ E-series vent hood short (adjustable)
• SYNCRO-24V-CLE External Conveyor Synchronization 24v - Receives external signal from customer conveying system to start or stop the warewash unit (pumps and conveyor); provides a dry contact interface which closes when dish machine conveyor is running.
ITEM 0002: Tabling The government is requesting BRAND NAME OR EQUAL Aerowerks Inc Model No.
QP244100. Item shall be installed at the Warrior Dining Facility, 100 W. Bong St. FAFB, WA 99011-6010.
Specifications:
(1) Soiled breakdown system to include following minimum salient characteristics and add-ons:
A. Soiled dish table, c/w waste trough, (02) perforated s/s ledges, magnetic silver saver, (02) pre rinse stations, end gusher, stainless steel undershelf and overhead rack & storage shelf – Qty 1 B. Knuckle belt rack transfer conveyor, model Aerowerks KBC-200, c/w perforated grating, scrap sump with perforated scrap basket and electrical control panel – Qty 1 C. 90º Tite turn loader – Qty 1 D. Clean dish roller table, model Aerowerks GRC, c/w 1.9” PVC rollers, Photoelectric diffuser sensor and pre-wired limit switch – Qty 1 E. Aerowerks waste collector – Qty 1 F. Hose clean up station – Qty 1 G. Mobile soak sink – Qty 1
The existing 3 compartment sink in the facility will be reused.