This is a Scope of Work for a federal construction project at the St. Cloud VA Health Care System.
The contractor must furnish all labor, materials, tools, and equipment to repair, remove, replace, and completely refurbish all windows in Buildings 4, 8, and 9. Work includes demolition of existing windows with safe removal of lead and asbestos-containing materials in compliance with local and national regulations, installation of new window frames, sashes, screens, and storm windows, and restoration of walls, ceilings, trim, and millwork. The contractor is responsible for moving, adjusting, and storing all furnishings disturbed during construction and must return the worksite to satisfactory condition upon completion. Work will occur in occupied buildings behind proper construction barriers, with standard contract hours of 8 a.m. to 4:30 p.m., Monday through Friday, excluding federal holidays; weekend and night work in sensitive areas requires Contracting Officer's Representative approval. Anticipated contractor trades include general contractors, general laborers, demolition contractors, abatement contractors, and painting contractors. No VA-furnished equipment is provided, and phasing will follow contract documents.
The anticipated cost range is between $5,000,000 and $10,000,000. The schedule establishes contract award at day D, pre-construction conference at D+15, Notice to Proceed at D+30, badge process and construction start at D+60, and construction completion at D+475, with substantial completion anticipated 445 calendar days after Notice to Proceed.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| 36C26326B0035_7.15.26.pdf | ||
| Attach C-Wage Determination MN202600099 5 18 2026 Stearns county.pdf | ||
| Attach F-Drawings Building 4_8 _ 9 Window Replacement.pdf | ||
| Attach D VAAR 852.219 75 Limitations on Subcontracting Cert of Compliance_JAN 2023.pdf | ||
| Attach E-Bldg 4-8-9 wdw specs use.pdf | ||
| Attach B - Questions Request Form - 1 page.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SCOPE OF WORK
“REPLACE WINDOWS BUILDINGS 4,8 & 9”
PROJECT #656-12-222
ST CLOUD VA HEALTH CARE SYSTEM
A. PART I – GENERAL
1. Base Project: The Contractor shall furnish all labor, materials, tools and equipment required to repair, remove, replace and completely refurbish all windows in Buildings
4,8 and 9. The contractor shall remove the existing internal and external window trim and wall finishes in order to successfully gain access to and cut out the existing wood windows. Incorporated into the demolition of the windows will be the safe removal of both lead and asbestos containing material as guided by the local and national rules and regulations of lead and asbestos remediation. Additionally, the contractor will be responsible for the complete and satisfactory installation of the new window frames and sashes, screens and storm windows. The window installation shall include the patching and painting of walls, ceiling installation and restoration, trim and millwork installation, and repair of all damaged items in place. This work will be completed in an occupied building; all construction activities shall be completed behind proper construction barriers as described in the specifications. The contractor shall return the worksite to the Veterans Affairs Health Care System after the work is completed, and all of the required work is satisfactorily completed and signed off by the assigned
Contracting Officer’s Representative. Refer to the contract specifications and drawings for details All work completed in accordance with the specifications and contract drawings.
2. Deducts:
a. None
3. Work includes, but is not limited to:
a. Demolition:
b. Contractor shall remove from the VA site and dispose of all equipment and materials not scheduled to be reused.
c. Contractor shall remove Lead and Asbestos materials associated with windows
d. Contractor trades anticipated:
• General contractor
• General laborer
• Demolition contractor
• Abatement contractor
• Painting contractor
1. No VA furnished equipment
2. New construction consists of but is not limited to windows, doors, general construction and abatement.
3. Contractor is responsible for the movement, adjustment and storage of all furnishings disturbed during construction.
4. Contract working hours are 8 am to 4:30 pm Monday through Friday, excluding Federal
Holidays. Weekend and night work may be necessary in sensitive areas and shall be approved by the COR.
5. Phasing will be as listed on the contract documents
B. Anticipated Schedule:
Contract award* D
Pre-construction conference D+15
Notice to Proceed D+30
Badge Process D+60
Construction starts D+60
Construction completion D+475
The anticipated substantial completion of this project is 445 calendar days after “Notice to
Proceed” (NTP).
C. Cost Range
The anticipated cost range for this project is between $5,000,000 and $10,000,000.