Attach 4 - Mitigation Measures.docx
DOCX document 21 KB Posted
- Attached to
- Oak Flat Sewer Line Repair - Angeles NF
- Solicitation number
- 12970224R0056
- Issued by
-
Department of Agriculture Forest Service
About this file
This document contains mitigation measures for the Oak Flat Fire Station Sewer Repair project on the Angeles National Forest. Key details include:
The project requires installation of a new sewer line to connect the barracks at Oak Flat Fire Station to an existing nearby septic system. Work includes trenching, installing cleanouts and pipe, rehabilitating the existing septic tank, and assessing the existing leach field lines. Optional items are decommissioning the barracks' former septic system and repairing any damage to the lines between the tank and leach field. The contractor must provide as-built drawings of the entire septic system at project closeout.
The mitigation measures focus on protecting environmental resources such as biology, botany, heritage, and hydrology during project activities. Requirements include implementing BMPs to minimize erosion and soil disturbance, avoiding impacts to tree root systems, controlling invasive species, and properly managing hazardous materials. Procedures are outlined for addressing inadvertent discoveries of archaeological resources and for managing open excavations to prevent wildlife entrapment.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 12970224R0056 0001.pdf | ||
| 12970224R0056.pdf | ||
| Attach 3 - Schedule of Items.pdf | ||
| Attach 6 - Davis Bacon WD CA20240017 (LA County).docx | DOCX document | |
| Attach 1- Statement of Work Oak Flat Sewer Repair ANF.pdf | ||
| Attach 2 - Oak Flat DRAWINGS.pdf | ||
| Attach 5 - ANF FY24 Construction Fire Plan.docx | DOCX document |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Oak Flat Fire Station Sewer Repair MITIGATION MEASURES for Resource Impacts Biology / Botany
1. All appropriate BMPs shall be implemented to minimize damage to surface soil structure and to reduce potential for erosion and sediment transport to drainages due to project activities. All ground disturbing activities with the potential for erosion must be consistent with FSH 2509.22 – Soil and Water Conservation Practices Handbook and Best Management Practices and in compliance with the Erosion Control Plan developed for the project. All construction will remain within the existing site footprint.
2. Work and parking/staging areas along with ground and vegetation disturbance will be limited to the minimum necessary.
3. All erosion control material must be biodegradable. Wattles wrapped in “photodegradable” plastic are not acceptable as they increase trash and can cause entrapment of small wildlife.
4. All equipment and work areas must contain appropriate spill containment kits to respond to leaks and spills. Personnel must have training on proper response to any type of hazmat situation. All hazmat situations must be reported to the Forest Hazmat Coordinator according to the Forest guidelines.
5. Wildlife encountered during the course of work activities should be avoided or given the opportunity to evacuate the site. Personnel will be reminded that harassing, harming, or feeding wildlife is not permitted. This includes venomous species such as rattlesnakes. If needed, reptile species, including rattlesnakes, can be moved from the project site using non-lethal means such as sticks, shovel handles, buckets or similar containers.
6. Sites will be kept clear of garbage and debris including microtrash. All food and garbage must be properly stored and all trash including project-related construction debris will be removed from the jobsite daily.
7. Materials that are in any type of liquid, granular or powder form must be stored in sealed leak-proof containers. These containers will be stored in a manner that prevents access by wildlife.
8. All parked vehicles/equipment will be kept free of leaks, particularly anti-freeze, since this could be fatal if consumed by wildlife.
9. If excavations are to be left open and unattended for more than 12 hours, they must either be covered or an escape ramp will be constructed to the bottom of the pit with less than a 2 to1 slope to provide an escape route for small wildlife species such as lizards and rodents. To the extent feasible, excavations will not be left open at the end of the day and will be covered after confirming absence of trapped individuals. Prior to commencement of work activity each day, staff will check excavations to make sure no animals are trapped. Before backfilling or permanently closing any excavation, it must be checked to make sure no wildlife is present within the excavated area. If wildlife has become trapped, backfilling cannot begin until the individual has either been removed or exited the excavation.
10. To protect tree root systems, activities (including pedestrian use) that would lead to soil compaction or soil disturbance will be avoided within the tree’s drip line. The Forest Service will stake location of trenching centerline for new sewer line replacement.
11. To limit the introduction and spread of invasive plant species, tool, vehicle and equipment washing requirements will be implemented. All ground disturbing and vegetation removal tools and equipment (including handheld) must be cleaned prior to entering National Forest System lands. Washing of tools, equipment and vehicles would be done in a manner that will effectively remove seeds and propagules and would not further enhance the spread of invasive plants through improper disposal of rinse water. Washing of equipment and vehicles must include tires/tracks, wheel wells, bumpers, fuel/skid pans and undercarriages. Personnel transport vehicles are exempt from this requirement as long as they have not engaged in off-road travel.
12. If target invasive plants are found within the project area, they will be removed prior to commencement of work.
13. All plant material (e.g., straw, mulch, seeds, etc.) used for erosion control must be certified weed-free. Only weed-free rice straw or rice mulch is allowed.
14. All fill material (soil, sand, gravel, rock) must be from an ANF approved material site.
Heritage
1. If archaeological resources and/or historic properties are inadvertently discovered or affected during project activities, all work shall cease within 100 feet (30.5 meters) of the find, and the ANF Heritage Program Manager shall be notified. They will evaluate the significance of the resource, whether or not the resource has been affected and recommend the appropriate action.
Hydrology
1. Ground disturbance will be limited to the minimum necessary for activities. All project activities including vehicle traffic and staging will be confined to the smallest area possible. All vehicles, tools and equipment will be restricted to existing access roads, trails, or disturbed areas to the maximum extent feasible.
2. Best Management Practices (BMPs)
a. All ground disturbing activities with the potential for erosion must be consistent with FSH 2509.22 - Soil and Water Conservation Practices Handbook and Best Management Practices. During the project life, ensure all BMPs are implemented, functioning, and effective.
b. All appropriate BMPs shall be implemented to minimize damage to surface soil structure and reduce potential for erosion and sediment transport to drainages from project activities. The following BMP’s will prevent long term negative impacts to the soils and integrity of the watersheds. Therefore, an erosion control action plan will not be required for this scope of work if project work remains within the scope of the BMPs checklist above.
2. Region 5 BMPs under 12.21-Road Management BMPs: 2.13: Erosion Control Plans (roads and other activities)
a. During the project equipment will not go off road during rain events producing overland runoff.
b. Equipment will be staged on the road during rain events.
c. Watershed staff will be notified prior to commencing operations into wet weather conditions.
3. National BMPs: Veg-2. Erosion Prevention and Control
a. Operate equipment when soil compaction, displacement, erosion, and sediment runoff would be minimized (dry).
b. Avoid ground equipment operations on unstable, wet, or easily compacted soils.
c. Road-10. Equipment Refueling and Servicing
d. c. Report spills and initiate suitable cleanup action in accordance with applicable State and Federal laws, rules, and regulations.
e. Refuel and service equipment only in designated areas of containment.
f. Clean up and remove spilled materials, residues, and any other hazardous materials from NFS land according to specified requirements in appropriate guiding document.
4. Fuel vehicles and equipment in a protected area with barriers to prevent leaks from entering drainage systems or with a pan with a lip below the fueling area to catch spills.
5. Crews must have appropriate spill containment kits to respond to leaks and spills. Personnel must have training on proper response to any type of hazmat situation. All hazmat situations must be reported to the Forest Hazmat Coordinator according to the Forest guidelines.
6. Soil Management Design Features:
a. Temporary Erosion Control
a. Erosion control or soil stabilization measures will be implemented while soil disturbing work is active. Preserve existing vegetation where feasible. Limit disturbance, especially on large or steep grades and where soil exposure to rainfall and wind can cause loss if unprotected.
b. Vehicles will only be parked in designated parking areas and on flat dry stable ground.
b. Sediment Control
c. A sediment control plan must also include provisions to temporarily stabilize access points such that soil, sediment and other materials are not tracked out.
d. Consolidate and maintain position of heavy equipment.
e. Do not move machinery on wet soils.
f. Stage machinery on flat ground with high soil strength. For example, established access road.
File details come from the government source that posted it. Updated .