Attach 1- Statement of Work Oak Flat Sewer Repair ANF.pdf
PDF 556 KB Posted
- Attached to
- Oak Flat Sewer Line Repair - Angeles NF
- Solicitation number
- 12970224R0056
- Issued by
-
Department of Agriculture Forest Service
About this file
This document is a set of contract specifications for the Oak Flats Fire Station Sewer Line Repairs project on the Angeles National Forest. The key details are:
The Angeles National Forest is seeking a qualified and licensed contractor to install a new sewer line to connect the barracks at the Oak Flat Fire Station to an existing 2,000-gallon septic system. The work includes trenching, installing cleanouts and pipe, rehabilitating the existing septic tank, and assessing the existing leach field lines. Optional work includes decommissioning the former septic system for the barracks and repairing any damage to the lines between the tank and leach field. At project closeout, the contractor must provide as-built drawings of the entire septic system. The existing septic system at the fire station is not functioning properly due to age and a high water table, so the government intends to utilize a nearby septic system that was installed in 2009 for a trailer pad but is no longer in use.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 12970224R0056 0001.pdf | ||
| 12970224R0056.pdf | ||
| Attach 3 - Schedule of Items.pdf | ||
| Attach 6 - Davis Bacon WD CA20240017 (LA County).docx | DOCX document | |
| Attach 2 - Oak Flat DRAWINGS.pdf | ||
| Attach 4 - Mitigation Measures.docx | DOCX document | |
| Attach 5 - ANF FY24 Construction Fire Plan.docx | DOCX document |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
U.S. FOREST SERVICE
PACIFIC SOUTHWEST REGION, REGION 5
ANGELES NATIONAL FOREST
OAK FLATS FIRE STATION SEWER LINE
REPAIRS
CONTRACT SPECIFICATIONS
JUNE 2024
Oak Flats Fire Station Sewer Line Repairs
TABLE OF CONTENT
TABLE OF CONTENTS
SECTION NUMBER NUMBER OF PAGES
SECTION 011000 – SUMMARY 3
SECTION 012900 – PAYMENT PROCEDURES 1
SECTION 017300 – EXECUTION 5
SECTION 017419 – CONSTRUCTION WASTE MANAGEMENT 2
SECTION 017700 – CLOSEOUT PROCEDURES 4
SECTION 017839 – PROJECT RECORD DOCUMENTS 3
SECTION 221319 – SANITARY WASTE PIPING SPECIALTIES 3
SECTION 221353 – FACILITY SEPTIC TANKS 4
Copyright 2018 AIA MasterSpec Short Form 12/18
SUMMARY 011000 - 1
Copyright © 2022 by the American Institute of Architects. Warning: This AIA MasterSpec based document is protected by U.S. Copyright Law and International Treaties. A valid, current MasterSpec license is required for editing or use of this document.
SECTION 011000 - SUMMARY
PART 1 - GENERAL
1.1 SUMMARY
A. Section Includes:
1. Project information.
2. Work covered by Contract Documents.
3. Contractor's use of site and premises.
4. Coordination with occupants.
5. Work restrictions.
6. Specification and Drawing conventions.
1.2 PROJECT INFORMATION
A. Project Identification: Oak Flats Fire Station.
1. Project Location: 38001 Golden State Hwy, Castaic, CA 91384.
B. Owner: USDA U.S. Forest Service. Angeles National Forest.
1. Owner's Representative: Javier Diaz (Contracting Officer Representative).
Kevin Hernandez (Environmental Engineer).
1.3 WORK COVERED BY CONTRACT DOCUMENTS
A. The Work of Project is defined by the Contract Documents and consists of the following:
1. The Angeles National Forest is seeking a qualified and licensed contractor for the installation of a new sewer line to connect the barracks at Oak Flat Fire Station, 38001 Golden State Highway Castaic, CA 91384, to an existing septic system. Work will also include trenching, installing cleanouts and pipe, rehabilitating the existing tank, and assessing the existing lines including the four lines of the leach field.
Optional items include decommissioning of the barracks former septic system and repairing any damage to lines between the tank and leach field that will now be used. At closeout of the contract, Contractor will provide the Government with a set of as-built drawings showing the components of the entire septic system.
The existing septic system at Oak Flat Fire Station is not properly functioning due to age and a high-water table. There is a nearby septic system to utilize with 2,000-gallon tank and 4 leach lines that was installed in 2009 for a trailer pad. The system has not been in use ever since the residence was sold and is now in the process of being relocated by the new owner. The septic tank was investigated in May and found to be in good condition with an expected amount of standing water.
SUMMARY 011000 - 2
Copyright © 2022 by the American Institute of Architects. Warning: This AIA MasterSpec based document is protected by U.S. Copyright Law and International Treaties. A valid, current MasterSpec license is required for editing or use of this document.
B. Contractor's Responsibilities: The Work includes the following, as applicable:
1. Designate delivery dates of Owner-furnished products in Contractor's construction schedule, utilizing Owner-furnished earliest available delivery dates.
2. Review Owner-reviewed Product Data, Shop Drawings, and Samples, noting discrepancies and other issues in providing for Owner-furnished products in the Work.
3. Receive, unload, handle, store, protect, and install Owner-furnished products.
4. Make building services connections for Owner-furnished products.
5. Protect Owner-furnished products from damage during storage, handling, and installation and prior to Substantial Completion.
6. Repair or replace Owner-furnished products damaged following receipt.
1.4 CONTRACTOR'S USE OF SITE AND PREMISES
A. Limits on Use of Site: Limit use of Project site to Work areas. Do not disturb portions of Project site beyond areas in which the Work is indicated.
1. Driveways, Walkways, and Entrances: Keep driveways, loading areas, and entrances serving premises clear and available to Owner, Owner's employees, and emergency vehicles at all times. Do not use these areas for parking or for storage of materials.
B. Condition of Existing Building: Maintain portions of existing building affected by construction operations in a weathertight condition throughout construction period. Repair damage caused by construction operations.
C. Condition of Existing Grounds: Maintain portions of existing grounds, landscaping, and hardscaping affected by construction operations throughout construction period. Repair damage caused by construction operations.
1.5 COORDINATION WITH OCCUPANTS
A. Partial Owner Occupancy: Owner will occupy the premises during entire construction period, with the exception of areas under construction. Cooperate with Owner during construction operations to minimize conflicts and facilitate Owner usage. Perform the Work so as not to interfere with Owner's operations. Maintain existing exits unless otherwise indicated.
1.6 WORK RESTRICTIONS
A. Comply with restrictions on construction operations.
1. Comply with limitations on use of public streets, work on public streets, rights of way, and other requirements of authorities having jurisdiction.
B. On-Site Work Hours: Limit work in the existing building to normal business working hours of 08:00 a.m. to 05:30 p.m., Monday through Friday, unless otherwise indicated.
SUMMARY 011000 - 3
Copyright © 2022 by the American Institute of Architects. Warning: This AIA MasterSpec based document is protected by U.S. Copyright Law and International Treaties. A valid, current MasterSpec license is required for editing or use of this document.
C. Existing Utility Interruptions: Do not interrupt utilities serving facilities occupied by Owner or others unless permitted under the following conditions and then only after providing temporary utility services according to requirements indicated:
1. Notify Contracting Officer Representative not less than two days in advance of proposed utility interruptions.
2. Obtain Contracting Officer Representative written permission before proceeding with utility interruptions.
D. Noise, Vibration, Dust, and Odors: Coordinate operations that may result in high levels of noise and vibration, dust, odors, or other disruption to Owner occupancy with Owner.
1. Notify Contracting Officer Representative not less than two days in advance of proposed disruptive operations.
2. Obtain Contracting Officer Representative written permission before proceeding with disruptive operations.
E. Smoking and Controlled Substance Restrictions: Use of tobacco products, alcoholic beverages, and other controlled substances on Project site is not permitted.
1.7 SPECIFICATION AND DRAWING CONVENTIONS
A. Specification Content: The Specifications use certain conventions for the style of language and the intended meaning of certain terms, words, and phrases when used in particular situations.
These conventions are as follows:
1. Imperative mood and streamlined language are generally used in the Specifications. The words "shall," "shall be," or "shall comply with," depending on the context, are implied where a colon (:) is used within a sentence or phrase.
2. Text Color: Text used in the Specifications, including units of measure, manufacturer and product names, and other text may appear in multiple colors or underlined as part of a hyperlink; no emphasis is implied by text with these characteristics.
3. Hypertext: Text used in the Specifications may contain hyperlinks. Hyperlinks may allow for access to linked information that is not residing in the Specifications. Unless otherwise indicated, linked information is not part of the Contract Documents.
4. Specification requirements are to be performed by Contractor unless specifically stated otherwise.
B. Division 00 Contracting Requirements: General provisions of the Contract, including General and Supplementary Conditions, apply to all Sections of the Specifications.
C. Division 01 General Requirements: Requirements of Sections in Division 01 apply to the Work of all Sections in the Specifications.
SUMMARY 011000 - 4
Copyright © 2022 by the American Institute of Architects. Warning: This AIA MasterSpec based document is protected by U.S. Copyright Law and International Treaties. A valid, current MasterSpec license is required for editing or use of this document.
PART 2 - PRODUCTS (Not Used)
PART 3 - EXECUTION (Not Used)
END OF SECTION 011000
PAYMENT PROCEDURES 012900 - 1
Copyright © 2022 by the American Institute of Architects. Warning: This AIA MasterSpec based document is protected by U.S. Copyright Law and International Treaties. A valid, current MasterSpec license is required for editing or use of this document.
SECTION 012900 - PAYMENT PROCEDURES
PART 1 - GENERAL
1.1 SUMMARY
A. Section includes administrative and procedural requirements necessary to prepare and process Applications for Payment.
1.2 SCHEDULE OF VALUES
A. Coordination: Coordinate preparation of the schedule of values with preparation of Contractor's construction schedule.
1. Submit the schedule of values to Contracting Officer Representative at earliest possible date, but no later than five days before the date scheduled for submittal of initial Applications for Payment.
PART 2 - PRODUCTS (Not Used)
END OF SECTION 012900
Copyright 2022 AIA MasterSpec Short Form 06/22
EXECUTION 017300 - 1
Copyright © 2022 by the American Institute of Architects. Warning: This AIA MasterSpec based document is protected by U.S. Copyright Law and International Treaties. A valid, current MasterSpec license is required for editing or use of this document.
SECTION 017300 - EXECUTION
PART 1 - GENERAL
1.1 SUMMARY
A. Section includes general administrative and procedural requirements governing execution of the Work, including, but not limited to, the following:
1. Construction layout.
2. Field engineering.
3. Installation.
4. Cutting and patching.
5. Coordination of Owner's portion of the Work.
6. Progress cleaning.
7. Starting and adjusting.
8. Protection of installed construction.
9. Correction of the Work.
B. Related Requirements:
1. Section 017700 "Closeout Procedures" for submitting final property survey with Project Record Documents, recording of Owner-accepted deviations from indicated lines and levels, replacing defective work, and final cleaning.
1.2 DEFINITIONS
A. Cutting: Removal of in-place construction necessary to permit installation or performance of subsequent work.
B. Patching: Fitting and repair work required to restore construction to original conditions after installation of subsequent work.
C. Manufacturer's Installation Instructions: Obtain and maintain on-site manufacturer's written recommendations and instructions for installation of specified products and equipment.
PART 2 - PRODUCTS
2.1 MATERIALS
A. Comply with requirements specified in other Sections.
B. In-Place Materials: Use materials for patching identical to in-place materials. For exposed surfaces, use materials that visually match in-place adjacent surfaces to the fullest extent possible.
EXECUTION 017300 - 2
Copyright © 2022 by the American Institute of Architects. Warning: This AIA MasterSpec based document is protected by U.S. Copyright Law and International Treaties. A valid, current MasterSpec license is required for editing or use of this document.
1. If identical materials are unavailable or cannot be used, use materials that, when installed, will provide a match acceptable to Contracting Officer Representative (COR) for the visual and functional performance of in-place materials. Use materials that are not considered hazardous.
PART 3 - EXECUTION
3.1 EXAMINATION
A. Existing Conditions: The existence and location of underground and other utilities and construction indicated as existing are not guaranteed. Before beginning sitework, investigate and verify the existence and location of underground utilities and other construction affecting the Work.
1. Before construction, verify the location and invert elevation at points of connection of sanitary sewer, storm sewer, gas service piping, and water-service piping; underground electrical services; and other utilities.
B. Written Report: Where a written report listing conditions detrimental to performance of the Work is required by other Sections, include the following:
1. Description of the Work, including Specification Section number and paragraph, and Drawing sheet number and detail, where applicable.
2. List of detrimental conditions, including substrates.
3. List of unacceptable installation tolerances.
4. Recommended corrections.
C. Proceed with installation only after unsatisfactory conditions have been corrected. Proceeding with the Work indicates acceptance of surfaces and conditions.
3.2 PREPARATION
A. Field Measurements: Take field measurements as required to fit the Work properly. Recheck measurements before installing each product. Where portions of the Work are indicated to fit to other construction, verify dimensions of other construction by field measurements before fabrication. Coordinate fabrication schedule with construction progress to avoid delaying the Work.
B. Space Requirements: Verify space requirements and dimensions of items shown diagrammatically on Drawings.
C. Review of Contract Documents and Field Conditions: Immediately on discovery of the need for clarification of the Contract Documents, submit a request for information to COR.
EXECUTION 017300 - 3
Copyright © 2022 by the American Institute of Architects. Warning: This AIA MasterSpec based document is protected by U.S. Copyright Law and International Treaties. A valid, current MasterSpec license is required for editing or use of this document.
3.3 CONSTRUCTION LAYOUT
A. Verification: Before proceeding to lay out the Work, verify layout information shown on Drawings, in relation to the property survey and existing benchmarks and existing conditions. If discrepancies are discovered, notify COR promptly.
3.4 INSTALLATION
A. Locate the Work and components of the Work accurately, in correct alignment and elevation, as indicated.
B. Comply with manufacturer's written instructions and recommendations for installing products in applications indicated.
C. Install products at the time and under conditions that will ensure satisfactory results as judged by COR. Maintain conditions required for product performance until Substantial Completion.
D. Conduct construction operations, so no part of the Work is subjected to damaging operations or loading in excess of that expected during normal conditions of occupancy of type expected for Project.
E. Sequence the Work and allow adequate clearances to accommodate movement of construction items on-site and placement in permanent locations.
F. Tools and Equipment: Select tools or equipment that minimize production of excessive noise levels.
G. Templates: Obtain and distribute to the parties involved templates for Work specified to be factory prepared and field installed. Check Shop Drawings of other portions of the Work to confirm that adequate provisions are made for locating and installing products to comply with indicated requirements.
H. Joints: Make joints of uniform width. Where joint locations in exposed Work are not indicated, arrange joints for the best visual effect, as judged by COR. Fit exposed connections together to form hairline joints.
3.5 CUTTING AND PATCHING
A. General: Employ skilled workers to perform cutting and patching. Proceed with cutting and patching at the earliest feasible time, and complete without delay.
1. Cut in-place construction to provide for installation of other components or performance of other construction, and subsequently patch as required to restore surfaces to their original condition.
B. Existing Warranties: Remove, replace, patch, and repair materials and surfaces cut or damaged during installation or cutting and patching operations, by methods and with materials so as not to void existing warranties.
C. Temporary Support: Provide temporary support of Work to be cut.
EXECUTION 017300 - 4
Copyright © 2022 by the American Institute of Architects. Warning: This AIA MasterSpec based document is protected by U.S. Copyright Law and International Treaties. A valid, current MasterSpec license is required for editing or use of this document.
D. Cutting: Cut in-place construction by sawing, drilling, breaking, chipping, grinding, and similar operations, including excavation, using methods least likely to damage elements retained or adjoining construction.
1. In general, use hand or small power tools designed for sawing and grinding, not hammering and chopping. Cut holes and slots neatly to minimum size required, and with minimum disturbance of adjacent surfaces. Temporarily cover openings when not in use.
2. Finished Surfaces: Cut or drill from the exposed or finished side into concealed surfaces.
3. Excavating and Backfilling: Comply with requirements in applicable Sections where required by cutting and patching operations.
4. Proceed with patching after construction operations requiring cutting are complete.
E. Patching: Patch construction by filling, repairing, refinishing, closing up, and similar operations following performance of other Work. Patch with durable seams that are as invisible as practicable, as judged by COR. Provide materials and comply with installation requirements specified in other Sections, where applicable.
1. Floors and Walls: Where walls or partitions that are removed extend one finished area into another, patch and repair floor and wall surfaces in the new space. Provide an even surface of uniform finish, color, texture, and appearance. Remove in-place floor and wall coverings and replace with new materials, if necessary, to achieve uniform color and appearance.
3.6 PROGRESS CLEANING
A. Clean Project site and work areas daily, including common areas. Enforce requirements strictly.
Dispose of materials lawfully.
1. Comply with requirements in NFPA 241 for removal of combustible waste materials and debris.
2. Do not hold waste materials more than seven days during normal weather or three days if the temperature is expected to rise above 80 deg F.
3. Containerize hazardous and unsanitary waste materials separately from other waste. Mark containers appropriately and dispose of legally, in accordance with regulations.
a. Use containers intended for holding waste materials of type to be stored.
B. Site: Maintain Project site free of waste materials and debris.
C. Waste Disposal: Do not bury or burn waste materials on-site. Do not wash waste materials down sewers or into waterways.
D. Limiting Exposures: Supervise construction operations to ensure that no part of the construction, completed or in progress, is subject to harmful, dangerous, damaging, or otherwise deleterious exposure during the construction period.
EXECUTION 017300 - 5
Copyright © 2022 by the American Institute of Architects. Warning: This AIA MasterSpec based document is protected by U.S. Copyright Law and International Treaties. A valid, current MasterSpec license is required for editing or use of this document.
3.7 STARTING AND ADJUSTING
A. Adjust equipment for proper operation. Adjust operating components for proper operation without binding.
3.8 PROTECTION OF INSTALLED CONSTRUCTION
A. Provide final protection and maintain conditions that ensure installed Work is without damage or deterioration at time of Substantial Completion.
B. Comply with manufacturer's written instructions for temperature and relative humidity.
3.9 CORRECTION OF THE WORK
A. Repair or remove and replace damaged, defective, or nonconforming Work. Restore damaged substrates and finishes.
1. Repairing includes replacing defective parts, refinishing damaged surfaces, touching up with matching materials, and properly adjusting operating equipment.
B. Repair Work previously completed and subsequently damaged during construction period.
Repair to like-new condition.
C. Restore permanent facilities used during construction to their specified condition.
D. Remove and replace damaged surfaces that are exposed to view if surfaces cannot be repaired without visible evidence of repair.
E. Repair components that do not operate properly. Remove and replace operating components that cannot be repaired.
F. Remove and replace chipped, scratched, and broken glass or reflective surfaces.
END OF SECTION 017300
Copyright 2016 AIA MasterSpec Short Form 09/16
CONSTRUCTION WASTE MANAGEMENT AND DISPOSAL 017419 - 1
Copyright © 2022 by the American Institute of Architects. Warning: This AIA MasterSpec based document is protected by U.S. Copyright Law and International Treaties. A valid, current MasterSpec license is required for editing or use of this document.
SECTION 017419 - CONSTRUCTION WASTE MANAGEMENT AND DISPOSAL
PART 1 - GENERAL
1.1 SUMMARY
A. Section includes administrative and procedural requirements for the following:
1. Disposing of nonhazardous demolition and construction waste.
B. Related Requirements:
1. Section 311000 "Site Clearing" for disposition of waste resulting from site clearing and removal of above- and below-grade improvements.
1.2 DEFINITIONS
A. Construction Waste: Building, structure, and site improvement materials and other solid waste resulting from construction, remodeling, renovation, or repair operations. Construction waste includes packaging.
B. Demolition Waste: Building, structure, and site improvement materials resulting from demolition operations.
C. Disposal: Removal of demolition or construction waste and subsequent salvage, sale, recycling, or deposit in landfill, incinerator acceptable to authorities having jurisdiction, or designated spoil areas on Owner’s property.
D. Recycle: Recovery of demolition or construction waste for subsequent processing in preparation for reuse.
E. Salvage: Recovery of demolition or construction waste and subsequent sale or reuse in another facility.
F. Salvage and Reuse: Recovery of demolition or construction waste and subsequent incorporation into the Work.
1.3 ACTION SUBMITTALS
A. Waste Management Plan: Submit plan within 3 days of date established for the Notice of Award.
1.4 INFORMATIONAL SUBMITTALS
A. Waste Reduction Progress Reports: Concurrent with each Application for Payment, submit report. Include the following information:
1. Material category.
Copyright 2016 AIA MasterSpec Short Form 09/16
CONSTRUCTION WASTE MANAGEMENT AND DISPOSAL 017419 - 2
Copyright © 2022 by the American Institute of Architects. Warning: This AIA MasterSpec based document is protected by U.S. Copyright Law and International Treaties. A valid, current MasterSpec license is required for editing or use of this document.
2. Generation point of waste.
3. Total quantity of waste in tons.
B. Landfill and Incinerator Disposal Records: Indicate receipt and acceptance of waste by landfills and incinerator facilities licensed to accept them. Include manifests, weight tickets, receipts, and invoices.
1.5 QUALITY ASSURANCE
A. Waste Management Coordinator Qualifications: Experienced firm, or individual employed and assigned by General Contractor, with a record of successful waste management coordination of projects with similar requirements.
1.6 WASTE MANAGEMENT PLAN
A. General: Develop a waste management plan according to requirements in this Section. Plan shall consist of waste identification, waste reduction work plan, and cost/revenue analysis.
Distinguish between demolition and construction waste. Indicate quantities by weight or volume, but use same units of measure throughout waste management plan.
B. Waste Identification: Indicate anticipated types and quantities of demolition, site-clearing, hazmat and construction waste generated by the Work. Include estimated quantities and assumptions for estimates.
PART 2 - PRODUCTS
2.1 PERFORMANCE REQUIREMENTS (not used)
PART 3 - EXECUTION
3.1 PLAN IMPLEMENTATION
A. General: Implement approved waste management plan. Provide handling, containers, storage, signage, transportation, and other items as required to implement waste management plan during the entire duration of the Contract.
END OF SECTION 017419
CLOSEOUT PROCEDURES 017700 - 1
Copyright © 2022 by the American Institute of Architects. Warning: This AIA MasterSpec based document is protected by U.S. Copyright Law and International Treaties. A valid, current MasterSpec license is required for editing or use of this document.
SECTION 017700 - CLOSEOUT PROCEDURES
PART 1 - GENERAL
1.1 SUMMARY
A. Section includes administrative and procedural requirements for Contract closeout, including, but not limited to, the following:
1. Substantial Completion procedures.
2. Final Completion procedures.
3. List of incomplete items.
4. Submittal of Project warranties.
5. Final cleaning.
B. Related Requirements:
1. Section 017839 "Project Record Documents" for submitting Record Drawings, Record Specifications, and Record Product Data.
1.2 ACTION SUBMITTALS
A. Product Data: For Septic Tank.
B. Contractor's List of Incomplete Items: Initial submittal at Substantial Completion.
C. Certified List of Incomplete Items: Final submittal at Final Completion.
1.3 CLOSEOUT SUBMITTALS
A. Certificates of Release: From authorities having jurisdiction.
B. Warranty: Product Warranty.
1.4 SUBSTANTIAL COMPLETION PROCEDURES
A. Contractor's List of Incomplete Items: Prepare and submit a list of items to be completed and corrected (Contractor's "punch list"), indicating the value of each item on the list and reasons why the Work is incomplete.
B. Submittals Prior to Substantial Completion: Complete the following a minimum of 2 days prior to requesting inspection for determining date of Substantial Completion. List items below that are incomplete at time of request.
CLOSEOUT PROCEDURES 017700 - 2
Copyright © 2022 by the American Institute of Architects. Warning: This AIA MasterSpec based document is protected by U.S. Copyright Law and International Treaties. A valid, current MasterSpec license is required for editing or use of this document.
1. Certificates of Release: Obtain and submit releases from authorities having jurisdiction, permitting Owner unrestricted use of the Work and access to services and utilities.
Include occupancy permits, operating certificates, and similar releases.
2. Submit closeout submittals specified in individual Sections, including specific warranties, workmanship bonds, maintenance service agreements, final certifications, and similar documents.
C. Procedures Prior to Substantial Completion: Complete the following a minimum of 2 days prior to requesting inspection for determining date of Substantial Completion. List items below that are incomplete at time of request.
1. Advise Owner of pending insurance changeover requirements.
2. Participate with Owner in conducting inspection and walkthrough.
3. Terminate and remove temporary facilities from Project site, along with mockups, construction tools, and similar elements.
4. Complete final cleaning requirements.
D. Inspection: Submit a written request for inspection to determine Substantial Completion a minimum of 2 days prior to date the Work will be completed and ready for final inspection and tests. On receipt of request, Contracting Officer Representative (COR) will either proceed with inspection or notify Contractor of unfulfilled requirements. COR will prepare the Certificate of Substantial Completion after inspection or will notify Contractor of items, either on Contractor's list or additional items identified by Architect, that must be completed or corrected before certificate will be issued.
1.5 FINAL COMPLETION PROCEDURES
A. Submittals Prior to Final Completion: Before requesting final inspection for determining Final Completion, complete the following:
1. Submit a final Application for Payment in accordance with Section 012900 "Payment Procedures."
2. Certified List of Incomplete Items: Submit certified copy of COR’s Substantial Completion inspection list of items to be completed or corrected (punch list), endorsed and dated by COR. Certified copy of the list will state that each item has been completed or otherwise resolved for acceptance.
3. Certificate of Insurance: Submit evidence of final, continuing insurance coverage complying with insurance requirements.
B. Inspection: Submit a written request for final inspection to determine acceptance a minimum of 2 days prior to date the Work will be completed and ready for final inspection and tests. On receipt of request, COR will either proceed with inspection or notify Contractor of unfulfilled requirements. COR will prepare a final Certificate for Payment after inspection or will notify Contractor of construction that must be completed or corrected before certificate will be issued.
CLOSEOUT PROCEDURES 017700 - 3
Copyright © 2022 by the American Institute of Architects. Warning: This AIA MasterSpec based document is protected by U.S. Copyright Law and International Treaties. A valid, current MasterSpec license is required for editing or use of this document.
1.6 LIST OF INCOMPLETE ITEMS
A. Organization of List: Include name and identification of area affected by construction operations for incomplete items and items needing correction including, if necessary, areas disturbed by Contractor that are outside the limits of construction.
1. Include the following information at the top of each page:
a. Project name.
b. Date.
c. Name of COR.
d. Name of Contractor.
e. Page number.
2. Submit list of incomplete items in the following format:
a. MS Word Electronic File: COR will return annotated file.
b. PDF Electronic File: COR will return annotated file.
c. Three Paper Copies: COR will return one copy.
1.7 SUBMITTAL OF PROJECT WARRANTIES
A. Time of Submittal: Submit written warranties on request of COR for designated portions of the Work where warranties are indicated to commence on dates other than date of Substantial Completion, or when delay in submittal of warranties might limit Owner's rights under warranty.
Warranties in Paper Form:
1. Bind warranties and bonds in heavy-duty, three-ring, vinyl-covered, loose-leaf binders, thickness as necessary to accommodate contents, and sized to receive 8-1/2-by-11-inch paper.
B. Provide additional copies of each warranty to include in operation and maintenance manuals.
PART 2 - PRODUCTS
PART 3 - EXECUTION
3.1 FINAL CLEANING
A. Perform final cleaning. Conduct cleaning and waste-removal operations to comply with local laws and ordinances and Federal and local environmental and antipollution regulations.
1. Complete the following cleaning operations before requesting inspection for certification of Substantial Completion for entire Project or for a designated portion of Project:
a. Clean Project site of rubbish, waste material, litter, and other foreign substances.
CLOSEOUT PROCEDURES 017700 - 4
Copyright © 2022 by the American Institute of Architects. Warning: This AIA MasterSpec based document is protected by U.S. Copyright Law and International Treaties. A valid, current MasterSpec license is required for editing or use of this document.
b. Clean exposed exterior and interior hard-surfaced finishes to a dirt-free condition, free of stains, films, and similar foreign substances. Avoid disturbing natural weathering of exterior surfaces. Restore reflective surfaces to their original condition.
c. Remove labels that are not permanent.
3.2 CORRECTION OF THE WORK
A. Complete repair and restoration operations required by "Correction of the Work" Article in Section 017300 "Execution" before requesting inspection for determination of Substantial Completion.
END OF SECTION 017700
PROJECT RECORD DOCUMENTS 017839 - 1
Copyright © 2022 by the American Institute of Architects. Warning: This AIA MasterSpec based document is protected by U.S. Copyright Law and International Treaties. A valid, current MasterSpec license is required for editing or use of this document.
SECTION 017839 - PROJECT RECORD DOCUMENTS
PART 1 - GENERAL
1.1 SUMMARY
A. Section includes administrative and procedural requirements for Project Record Documents, including the following:
1. Record Drawings.
2. Record specifications.
3. Record Product Data.
B. Related Requirements:
1.2 CLOSEOUT SUBMITTALS
A. Record Drawings: Comply with the following:
1. Number of Copies: Submit three set(s) of marked-up record prints.
2. Number of Copies: Submit copies of Record Drawings as follows:
a. Final Submittal:
1) Submit three paper-copy set(s) of marked-up record prints.
2) Submit PDF electronic files of scanned record prints and one set(s) of file prints.
3) Print each drawing, whether or not changes and additional information were recorded.
1.3 RECORD DRAWINGS
A. Record Prints: Maintain one set of marked-up paper copies of the Contract Drawings and Shop Drawings, incorporating new and revised drawings as modifications are issued.
1. Preparation: Mark record prints to show the actual installation, where installation varies from that shown originally. Require individual or entity who obtained record data, whether individual or entity is Installer, subcontractor, or similar entity, to provide information for preparation of corresponding marked-up record prints.
a. Give particular attention to information on concealed elements that would be difficult to identify or measure and record later.
b. Accurately record information in an acceptable drawing technique.
c. Record data as soon as possible after obtaining it.
d. Record and check the markup before enclosing concealed installations.
e. Cross-reference record prints to corresponding photographic documentation.
PROJECT RECORD DOCUMENTS 017839 - 2
Copyright © 2022 by the American Institute of Architects. Warning: This AIA MasterSpec based document is protected by U.S. Copyright Law and International Treaties. A valid, current MasterSpec license is required for editing or use of this document.
2. Content: Types of items requiring marking include, but are not limited to, the following:
a. Dimensional changes to Drawings.
b. Revisions to details shown on Drawings.
c. Depths of trenches.
d. Locations and depths of underground utilities.
e. Actual equipment locations.
3. Mark the Contract Drawings and Shop Drawings completely and accurately. Use personnel proficient at recording graphic information in production of marked-up record prints.
4. Mark record prints with erasable, red-colored pencil. Use other colors to distinguish between changes for different categories of the Work at same location.
5. Mark important additional information that was either shown schematically or omitted from original Drawings.
6. Note Construction Change Directive numbers, alternate numbers, Change Order numbers, and similar identification, where applicable.
B. Format: Identify and date each Record Drawing; include the designation "PROJECT RECORD DRAWING" in a prominent location.
1. Record Prints: Organize record prints into manageable sets. Bind each set with durable paper cover sheets. Include identification on cover sheets.
2. Format: Annotated PDF electronic file with comment function enabled.
3. Record Digital Data Files: Organize digital data information into separate electronic files that correspond to each sheet of the Contract Drawings. Name each file with the sheet identification. Include identification in each digital data file.
4. Identification: As follows:
a. Project name.
b. Date.
c. Designation "PROJECT RECORD DRAWINGS."
d. Name of COR.
e. Name of Contractor.
1.4 RECORD PRODUCT DATA
A. Recording: Maintain one copy of each submittal during the construction period for Project Record Document purposes. Post changes and revisions to Project Record Documents as they occur; do not wait until end of Project.
B. Preparation: Mark Product Data to indicate the actual product installation where installation varies substantially from that indicated in Product Data submittal.
1. Give particular attention to information on concealed products and installations that cannot be readily identified and recorded later.
2. Include significant changes in the product delivered to Project site and changes in manufacturer's written instructions for installation.
PROJECT RECORD DOCUMENTS 017839 - 3
Copyright © 2022 by the American Institute of Architects. Warning: This AIA MasterSpec based document is protected by U.S. Copyright Law and International Treaties. A valid, current MasterSpec license is required for editing or use of this document.
PART 2 - PRODUCTS (Not Used)
END OF SECTION 017839
Copyright 2019 AIA MasterSpec Full Length 06/19
SANITARY WASTE PIPING SPECIALTIES 221319 - 1
Copyright © 2022 by the American Institute of Architects. Warning: This AIA MasterSpec based document is protected by U.S. Copyright Law and International Treaties. A valid, current MasterSpec license is required for editing or use of this document.
SECTION 221319 - SANITARY WASTE PIPING SPECIALTIES
PART 1 - GENERAL
1.1 RELATED DOCUMENTS
A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01 Specification Sections, apply to this Section.
1.2 SUMMARY
A. Section Includes:
1. Cleanouts.
1.3 DEFINITIONS
A. ABS: Acrylonitrile butadiene styrene.
B. PVC: Polyvinyl chloride.
1.4 ACTION SUBMITTALS
A. Product Data: For each type of product.
1.5 INFORMATIONAL SUBMITTALS
A. Field quality-control reports.
1.6 CLOSEOUT SUBMITTALS
A. Receipt of Actual Quantities used for this project.
PART 2 - PRODUCTS
2.1 ASSEMBLY DESCRIPTIONS
A. Sanitary waste piping specialties shall bear label, stamp, or other markings of specified testing agency.
B. Comply with NSF 14 for plastic sanitary waste piping specialty components.
SANITARY WASTE PIPING SPECIALTIES 221319 - 2
Copyright © 2022 by the American Institute of Architects. Warning: This AIA MasterSpec based document is protected by U.S. Copyright Law and International Treaties. A valid, current MasterSpec license is required for editing or use of this document.
2.2 CLEANOUTS
A. Plastic Floor Cleanouts:
1. Size: Same as connected branch.
2. Body: ABS, 2-way cleanouts.
3. Closure Plug: ABS.
4. Riser: Drainage pipe fitting and riser to cleanout of same material as drainage piping.
2.3 DISTRIBUTION PIPING
A. ABS PIPING
1. Size: Same as connected branch.
2. Body: ABS
3. Closure Plug: ABS
4. Bedding material: 6 inches
PART 3 - EXECUTION
3.1 INSTALLATION
A. Install cleanouts in aboveground piping and building drain piping according to the following, unless otherwise indicated:
1. Size same as drainage piping up to NPS 4. Use NPS 4 for larger drainage piping unless larger cleanout is indicated.
2. Locate at each change in direction of piping greater than 45 degrees.
3. Locate at minimum intervals of 100 feet for larger piping.
4. Locate at base of each vertical soil and waste stack.
5. Exception: Fitting may be omitted if trap has trap-seal primer connection.
6. Size: Same as floor drain inlet.
3.2 PIPING CONNECTIONS
A. Install new piping in approximate location of the old distribution piping. New distribution piping will extend from the district office over to the leach field tie in.
3.3 PROTECTION
A. Protect drains during remainder of construction period to avoid clogging with dirt or debris and to prevent damage from traffic or construction work.
B. Place plugs in ends of uncompleted piping at end of each day or when work stops.
SANITARY WASTE PIPING SPECIALTIES 221319 - 3
Copyright © 2022 by the American Institute of Architects. Warning: This AIA MasterSpec based document is protected by U.S. Copyright Law and International Treaties. A valid, current MasterSpec license is required for editing or use of this document.
END OF SECTION 221319
Copyright 2018 AIA MasterSpec Full Length 09/18
FACILITY SEPTIC TANKS 221353 - 1
Copyright © 2022 by the American Institute of Architects. Warning: This AIA MasterSpec based document is protected by U.S. Copyright Law and International Treaties. A valid, current MasterSpec license is required for editing or use of this document.
SECTION 221353 - FACILITY SEPTIC TANKS
PART 1 - GENERAL
1.1 RELATED DOCUMENTS
A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01 Specification Sections, apply to this Section.
1.2 SUMMARY
A. Section Includes:
1. Septic tanks.
2. Pipe and fittings.
1.3 ACTION SUBMITTALS
A. Product Data: For each type of product indicated.
1. Include construction details, material descriptions, dimensions of individual components, and profiles.
2. Include manhole openings, covers, and pipe connections.
1.4 PROJECT CONDITIONS
A. Interruption of Existing Septic Tank System Service: Do not interrupt service to facilities occupied by Owner or others unless permitted under the following conditions and then only after arranging to provide temporary service according to requirements indicated:
1. Notify Contracting Officer Representative (COR) no fewer than two days in advance of proposed interruption of service.
2. Do not proceed with interruption of service without Contracting Officer Representative (COR) written permission.
PART 2 - PRODUCTS
2.1 EXISTING SEPTIC TANKS
A. Concrete 2,000 Gallon Septic Tank
Concrete septic tank was installed in 2009 and may require some repairs. Observations were made in March 2024 that showed root intrusion occurring at the location of the septic tank.
FACILITY SEPTIC TANKS 221353 - 2
Copyright © 2022 by the American Institute of Architects. Warning: This AIA MasterSpec based document is protected by U.S. Copyright Law and International Treaties. A valid, current MasterSpec license is required for editing or use of this document.
Work will include minor sealant work for areas of the concrete tanks that have cracks which allows for the intrusion of roots. Focus should be made on the inlet/outlet components of the tank as well as the concrete collars for the manhole covers.
B. Resilient Connectors: ASTM C923 or other watertight seal, of size required for piping, fitted into inlet and outlet openings.
C. Capacity and Characteristics:
1. Capacity: 2,000 gallons.
2. Inlet and Outlet Size: 4 inches.
2.2 PVC DISTRIBUTION PIPE AND FITTINGS
A. Pipe and Fittings: ABS.
B. Solvent Cement: ASTM D2235. Include primer according to ASTM F656.
2.3 NONPRESSURE PIPE COUPLINGS
A. Description: Comply with ASTM C1173, elastomeric, sleeve-type, reducing or transition coupling, for joining underground nonpressure piping. Include ends of same sizes as piping to be joined, with corrosion-resistant-metal tension band and tightening mechanism on each end.
1. Sleeve Materials for Plastic Pipes: ASTM F477, elastomeric seal or ASTM D5926, PVC.
2. Sleeve Materials for Dissimilar Pipes: ASTM D5926, PVC or other material compatible with pipe materials being joined.
2.4 TRENCH BED
A. Fill Material: 6 inches of bedding material for Distribution Piping
PART 3 - EXECUTION
3.1 EARTHWORK
A. Excavating, trenching, and backfilling for piping are specified in Section 312000 "Earth Moving."
1. Stockpile topsoil for reuse in finish grading without intermixing with other excavated material. Stockpile materials away from edge of excavation and do not store within drip line of remaining trees.
2. Place, grade, and shape stockpiles to drain surface water. Cover to prevent windblown dust.
B. Excavating and Backfilling for Septic Tanks:
FACILITY SEPTIC TANKS 221353 - 3
Copyright © 2022 by the American Institute of Architects. Warning: This AIA MasterSpec based document is protected by U.S. Copyright Law and International Treaties. A valid, current MasterSpec license is required for editing or use of this document.
1. Excavate sufficient width and length for tanks to depth determined by tank inlet elevation. Provide level bottom.
2. Backfill with excavated soil, mounding soil above original grade without compacting.
C. Excavating and Backfilling for Distribution Piping:
1. Excavate 36 inches width at a depth that will provide at minimum 2 percent slope to promote drainage of waste away from the building and over to the leach field.
2. Install 6 inches of bedding material before backfilling. Backfill with excavated soil, mounding soil above original grade without compacting.
3.2 PIPING INSTALLATION
A. Comply with requirements for sewer pipe installation specified in Section 221313 "Facility Sanitary Sewers."
B. Install distribution piping according to the following:
1. ABS Sewer Pipe and Fittings: ASTM D2235. Include primer according to ASTM F656.
3.3 CLEANOUT INSTALLATION
A. Install cleanouts according to the following:
1. No more than 5 feet away from the exterior wall of Barracks Building.
2. On the inlet side of the septic tank
3. At approximately 150 feet of the new pipe alignment.
B. Comply with requirements for cleanouts specified in Section 221313 "Facility Sanitary Sewers."
C. ABS Cleanouts: Install with ABS riser from sewer and distribution piping to PVC cleanout at grade. Use NPS 4 ABS sewer pipe and fittings with solvent-cemented joints for risers and cleanout fitting.
D. Set top of cleanout 2 inches above surrounding rough grade.
3.4 IDENTIFICATION
A. Identification materials and their installation are specified in Section 312000 "Earth Moving."
Arrange for installation of green, detectable warning tape directly over piping, at outside edges of underground structures, and at outside edges of absorption systems.
FACILITY SEPTIC TANKS 221353 - 4
Copyright © 2022 by the American Institute of Architects. Warning: This AIA MasterSpec based document is protected by U.S. Copyright Law and International Treaties. A valid, current MasterSpec license is required for editing or use of this document.
3.5 FIELD QUALITY CONTROL
A. System Tests: Perform testing of completed septic tank system piping and structures according to authorities having jurisdiction.
B. Additional Tests: Fill underground structures with water and let stand overnight. If water level recedes, locate and repair leaks and retest. Repeat tests and repairs until no leaks exist.
3.6 CLEANING
A. Clear interior of piping and structures of dirt and other superfluous material as work progresses.
B. Maintain swab or drag in piping, and pull past each joint as it is completed. Place plugs in ends of uncompleted pipe at end of workday or when work stops.
END OF SECTION 221353
Copyright 2018 AIA MasterSpec Short Form 09/18
ASPHALT PAVING 321216 - 1
321216 - 1 Copyright © 2022 by the American Institute of Architects. Warning: This AIA MasterSpec based document is protected by U.S. Copyright Law and International Treaties. A valid, current MasterSpec license is required for editing or use of this document.
SECTION 321216 – ASPHALT PAVING
PART 1 - GENERAL
1.1 SUMMARY
A. Section Includes:
1. Hot-mix asphalt patching.
2. Asphalt curbs.
B. Related Requirements:
1. Section 312000 "Earth Moving" for subgrade preparation, fill material, separation geotextiles, unbound-aggregate subbase and base courses, and aggregate pavement shoulders.
1.2 ACTION SUBMITTALS
A. Product Data:
1. Herbicide.
B. Hot-mix asphalt designs.
1.3 INFORMATIONAL SUBMITTALS
A. Regulatory Requirements: Comply with materials, workmanship, and other applicable requirements of applicable standards for asphalt paving work.
1. Measurement and payment provisions and safety program submittals included in standard specifications do not apply to this Section.
PART 2 - PRODUCTS
2.1 ASPHALT MATERIALS
A. Asphalt Binder: ASTM D6373 binder designation PG 58-28.
2.2 AUXILIARY MATERIALS
A. Herbicide: Commercial chemical for weed control, registered by the EPA, and not classified as "restricted use" for locations and conditions of application. Provide in granular, liquid, or wettable powder form.
ASPHALT PAVING 321216 - 2
321216 - 2 Copyright © 2022 by the American Institute of Architects. Warning: This AIA MasterSpec based document is protected by U.S. Copyright Law and International Treaties. A valid, current MasterSpec license is required for editing or use of this document.
PART 3 - EXECUTION
3.1 PATCHING
A. Asphalt Pavement: Saw cut perimeter of patch and excavate existing pavement section to sound base. Excavate rectangular or trapezoidal patches, extending 12 inches into perimeter of adjacent sound pavement, unless otherwise indicated. Cut excavation faces vertically. Remove excavated material. Recompact existing unbound-aggregate base course to form new subgrade.
B. Placing Patch Material: Fill excavated pavement areas with hot-mix asphalt base mix for full thickness of patch and, while still hot, compact flush with adjacent surface.
3.2 SURFACE PREPARATION
A. Ensure that prepared subgrade is ready to receive paving. Immediately before placing asphalt materials, remove loose and deleterious material from substrate surfaces.
B. Herbicide Treatment: Apply herbicide in accordance with manufacturer's recommended rates and written application instructions. Apply to dry, prepared subgrade or surface of compacted-aggregate base before applying paving materials.
1. Mix herbicide with prime coat if formulated by manufacturer for that purpose.
3.3 HOT-MIX ASPHALT PLACEMENT
A. Machine place hot-mix asphalt on prepared surface, spread uniformly, and strike off. Place asphalt mix by hand in areas inaccessible to equipment in a manner that prevents segregation of mix. Place each course to required grade, cross section, and thickness when compacted.
1. Place hot-mix asphalt surface course in single lift.
2. Spread mix at a minimum temperature of 250 deg F
3. Regulate paver machine speed to obtain smooth, continuous surface free of pulls and tears in asphalt-paving mat.
B. Place paving in consecutive strips not less than 10 feet wide unless infill edge strips of a lesser width are required.
C. Promptly correct surface irregularities in paving course behind paver. Use suitable hand tools to remove excess material forming high spots. Fill depressions with hot-mix asphalt to prevent segregation of mix; use suitable hand tools to smooth surface.
3.4 JOINTS
A. Construct joints to ensure a continuous bond between adjoining paving sections. Construct joints free of depressions, with same texture and smoothness as other sections of hot-mix asphalt course.
1. Clean contact surfaces and apply tack coat to joints.
ASPHALT PAVING 321216 - 3
321216 - 3 Copyright © 2022 by the American Institute of Architects.