ATTACH_3_-_BID_SCHEDULE_FAIR_OAKS.pdf

PDF 131 KB Posted

Attached to
Fair Oaks AML Reclamation MC-023-001
Solicitation number
140S0325B0005
Issued by

About this file

This document is a Bid Quantities attachment for the Fair Oaks AML MC-023-001 project located in Wagoner County. The bid schedule includes 18 line items covering site preparation, infrastructure, and agricultural restoration activities. Key quantities include 175,086 cubic yards of earth fill, 2,235 linear feet of 5-wire fence, 850 linear feet of woven wire fence, 85 linear feet of 8" HDPE pipe, 75 tons of rock check dam, and 46 acres each of clearing/grubbing, deep disking, and seeding. Additional items involve soil amendments such as 46 tons of agricultural lime, 3,726 lbs of nitrogen, 3,680 lbs of phosphorus, and 3,220 lbs of potassium. The project also requires mobilization, an air incinerator, stabilized construction entrance, straw wattle, and traffic control, all listed as lump sum items.

View the file

Other files

Show all 15

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Item Number

Item Description Unit Estimated Quantity

Unit Price Price

1 Mobilization LSUM 1

2 Clearing and Grubbing ACRE 46

3 Air Incinerator LSUM 1

4 Earth Fill CY 175,086

5 Fence (5-wire) LF 2235

6 Fence (Woven Wire) LF 850

7 8" HDPE (SDR 26) Pipe LF 85

8 Stabilized Construction Entrance EA 1

9 Straw Wattle LF 2500

10 Rock Check Dam TON 75

11 Rip Rap Type IA (18" and 12") TON 375

12 Traffic Contriol LSUM 1

13 Deep Disking ACRE 46

14 Agriculture Lime TON 46

15 Nitrogen LBS 3726

16 Phosphorus LBS 3680

17 Potassium LBS 3220

18 Seeding ACRE 46

TOTAL COST:

FAIR OAKS AML MC-023-001

Wagoner County

BID QUANTITIES attachment 3