Attach 2 - Schedule of Services 24Q0001.xlsx

XLSX spreadsheet 25 KB Posted

Attached to
PREVENTIVE MAINTENANCE (PM) AND CORRECTIVE MAINTENANCE (CM) SERVICES ON INDUSTRIAL WOODWORING EQUIPMENT FOR DLA DISTRIBUTION ALBANY, GEORGIA
Solicitation number
SP330024Q0001
Issued by

About this file

This document is a Schedule of Services for a federal contract opportunity related to Preventive Maintenance (PM) and Corrective Maintenance (CM) services on industrial woodworking equipment for the DLA Distribution Albany, Georgia facility.

The contract includes a base year and four one-year option periods. The total estimated contract value is $60,000. The contract includes firm-fixed price for biannual PM services as well as time-and-materials pricing for CM labor, replacement parts, and travel. The estimated quantity for CM labor is 120 hours per year, and the estimated cost for replacement parts is $12,000 per year. The solicitation number is SP330024Q0001, and the contracting agency is the Defense Logistics Agency Distribution.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Overview

Base YearOY1OY2OY3OY4Totals
Firm Fixed (Preventative Maintenance)$0.00$0.00$0.00$0.00$0.00$0.00

Time & Materials (Corrective Maintenance) $12,000.00 $12,000.00 $12,000.00 $12,000.00 $12,000.00 $60,000.00

Totals $12,000.00 $12,000.00 $12,000.00 $12,000.00 $12,000.00 $60,000.00

SOURCE SELECTION INFORMATION – See FAR 2.101 and 3.104

SOURCE SELECTION INFORMATION – See FAR 2.101 and 3.104

BaseYear

DESCRIPTIONEST QTYU/IUNIT PRICEEST TOTAL PRICE
Base Year
FIRM-FIXED PRICE
0001Biannual Peventive Maintenance (PM) Services for Box Shop Equipment at DLA Distribution Albany, Georgia.
See Performance Work Statement and Equipment List.2EA$ - 0
TIME AND MATERIALS
0002Labor to perform Corrective Maintenance (CM). The number of hours shown is an estimate only and reflects an estimate of 20 hours of maintenance service for each piece of equipment. Contractor will only be paid for the actual number of hours worked.120HR$ - 0

0003 Replacement Parts required for repairs in conjunction with Corrective Maintenance. The dollars shown is an estimate only and reflects an allowance of $2,000 for each piece of equipment. Contractor will be paid for the actual dollars used. 12,000 EA $ 1.00 $ 12,000.00

0004 Travel costs (round trip) required for repairs in conjunction with Corrective Maintenance. Contractor will be paid for the actual dollars used. 5 EA $ - 0

Total Costs T & M $ 12,000.00

Total Costs for Base Year $ 12,000.00

4.27041$ 189.94
4.7058$ 209.31

&"Arial,Bold"IGCE PM and RM Maintenance Services and Crane Rental Support Services at DLA Distribution Anniston, AL &D

&P

OptionYear1

DESCRIPTIONEST QTYU/IUNIT PRICEEST TOTAL PRICE
Option Year 1
FIRM-FIXED PRICE
1001Biannual Peventive Maintenance (PM) Services for Box Shop Equipment at DLA Distribution Albany, Georgia.
See Performance Work Statement and Equipment List.2EA$ - 0
TIME AND MATERIALS
1002Labor to perform Corrective Maintenance (CM). The number of hours shown is an estimate only and reflects an estimate of 20 hours of maintenance service for each piece of equipment. Contractor will only be paid for the actual number of hours worked.120HR$ - 0

1003 Replacement Parts required for repairs in conjunction with Corrective Maintenance. The dollars shown is an estimate only and reflects an allowance of $2,000 for each piece of equipment. Contractor will be paid for the actual dollars used. 12,000 EA $ 1.00 $ 12,000.00

1004 Travel costs (round trip) required for repairs in conjunction with Corrective Maintenance. Contractor will be paid for the actual dollars used. 5 EA $ - 0

Total Costs T & M $ 12,000.00

Total Costs for Option Year 1 $ 12,000.00

&"Arial,Bold"&8IGCE PM and RM Maintenance Services and Crane Rental Support Services at DLA Distribution Anniston, AL &D

OptionYear2

DESCRIPTIONEST QTYU/IUNIT PRICEEST TOTAL PRICE
Option Year 2
FIRM-FIXED PRICE
2001Biannual Peventive Maintenance (PM) Services for Box Shop Equipment at DLA Distribution Albany, Georgia.
See Performance Work Statement and Equipment List.2EA$ - 0
TIME AND MATERIALS
2002Labor to perform Corrective Maintenance (CM). The number of hours shown is an estimate only and reflects an estimate of 20 hours of maintenance service for each piece of equipment. Contractor will only be paid for the actual number of hours worked.120HR$ - 0

2003 Replacement Parts required for repairs in conjunction with Corrective Maintenance. The dollars shown is an estimate only and reflects an allowance of $2,000 for each piece of equipment. Contractor will be paid for the actual dollars used. 12,000 EA $ 1.00 $ 12,000.00

2004 Travel costs (round trip) required for repairs in conjunction with Corrective Maintenance. Contractor will be paid for the actual dollars used. 5 EA $ - 0

Total Costs T & M $ 12,000.00

Total Costs for Option Year 2 $ 12,000.00

&"Arial,Bold"&8IGCE PM and RM Maintenance Services and Crane Rental Support Services at DLA Distribution Anniston, AL &D

OptionYear3

DESCRIPTIONEST QTYU/IUNIT PRICEEST TOTAL PRICE
Option Year 3
FIRM-FIXED PRICE
3001Biannual Peventive Maintenance (PM) Services for Box Shop Equipment at DLA Distribution Albany, Georgia.
See Performance Work Statement and Equipment List.2EA$ - 0
TIME AND MATERIALS
3002Labor to perform Corrective Maintenance (CM). The number of hours shown is an estimate only and reflects an estimate of 20 hours of maintenance service for each piece of equipment. Contractor will only be paid for the actual number of hours worked.120HR$ - 0

3003 Replacement Parts required for repairs in conjunction with Corrective Maintenance. The dollars shown is an estimate only and reflects an allowance of $2,000 for each piece of equipment. Contractor will be paid for the actual dollars used. 12,000 EA $ 1.00 $ 12,000.00

3004 Travel costs (round trip) required for repairs in conjunction with Corrective Maintenance. Contractor will be paid for the actual dollars used. 5 EA $ - 0

Total Costs T & M $ 12,000.00

Total Costs for Option Year 3 $ 12,000.00

OptionYear4

DESCRIPTIONEST QTYU/IUNIT PRICEEST TOTAL PRICE
Option Year 4
FIRM-FIXED PRICE
4001Biannual Peventive Maintenance (PM) Services for Box Shop Equipment at DLA Distribution Albany, Georgia.
See Performance Work Statement and Equipment List.2EA$ - 0
TIME AND MATERIALS
4002Labor to perform Corrective Maintenance (CM). The number of hours shown is an estimate only and reflects an estimate of 20 hours of maintenance service for each piece of equipment. Contractor will only be paid for the actual number of hours worked.120HR$ - 0

4003 Replacement Parts required for repairs in conjunction with Corrective Maintenance. The dollars shown is an estimate only and reflects an allowance of $2,000 for each piece of equipment. Contractor will be paid for the actual dollars used. 12,000 EA $ 1.00 $ 12,000.00

4004 Travel costs (round trip) required for repairs in conjunction with Corrective Maintenance. Contractor will be paid for the actual dollars used. 5 EA $ - 0

Total Costs T & M $ 12,000.00

Total Costs for Option Year 4 $ 12,000.00

File details come from the government source that posted it. Updated .