This statement of work is for a construction survey contract to support refurbishment and improvement projects at the Lower Lehman Campground within Great Basin National Park in Nevada. The selected contractor will be responsible for completely laying out all new construction boundaries, roadways, campsites, facilities, and utility lines based on provided final construction drawings, and placing grade stakes to identify locations for park staff to perform earthwork and install assets according to final designs and grades. The contractor must use industry standard surveying methods and flagging or marking paint. Safety, security of equipment and materials, and coordination with park staff are also addressed. The estimated period of performance is 20-30 calendar days from award of the solicitation number 140P8123Q0095 issued by the Department of the Interior National Park Service Pacific West Region for an initial pre-construction survey at the Lower Lehman Campground.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Attach_5-_Questions_and_Answers_0001.pdf | ||
| Sol_140P8123Q0095_Amd_0001.pdf | ||
| Attach_4-_Elevation_Staking_Drawings_0001.pdf | ||
| Attach_2-_Landscape_Drawings_with_Notes.pdf | ||
| Sol_140P8123Q0095.pdf | ||
| Attach_3-_SCA_Wage_Determination_2015-5601.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
STATEMENT OF WORK (SOW) 1- CONSTRUCTION SURVEY FOR THE “REFURBISH AND
IMPROVE LOWER LEHMAN CAMPGROUND” PROJECT, PMIS 311594, SNPLMA FUNDING
1.0- BACKGROUND
Project Location: Great Basin National Park (GRBA), Lower Lehman Campground, Nevada.
Located off of the Wheeler Peak Scenic Drive; at the south end of the park and accessed from US 50/6, CR 487, and CR488/Lehman Caves Road. The closest town is Baker, Nevada.
2.0- SCOPE
The work under this contract consists of hiring a professional land surveying contractor experienced in construction surveying to use park provided Final Construction drawings to survey and layout the new addition to the Lower Lehman Campground so that NPS staff can complete all the earthwork tasks associated with this project using NPS day labor. Survey work will require contractor to completely layout all the new construction boundary locations as needed for the proper grades, elevations and setbacks for the overall campground boundaries, limit of construction boundaries, location of paved roadways, culverts, new back-in campsites, restroom facilities, campground host site, and potable water system mainline.
Elevation grade stakes will identify all locations needed by the park maintenance staff to remove, fill, and backfill the different project areas to their respective final grades as needed for the proper drainage, and leveling for newly installed facility assets.
If any part of scope is unclear, the Contractor shall contact the Contracting Officers Representative (COR), Project Inspector, and/or Chief of Maintenance for clarification prior to contract award. Any changes to the scope must be immediately communicated to the COR and approved by the Contracting Officer before executing any changes.
The estimated period of performance time for this contract is 20-30 calendar days from the contract award date.
The project shall be referred to as “Refurbish and Improve Lower Lehman Campground” Project, PMIS 311594, SNPLMA Funding.
3.0- SPECIFICATIONS
Contractor shall use industry standard staking, flagging, environmentally friendly marking paint, or an approved equal to survey/layout all work at the Lower Lehman Campground site.
4.0- SAFETY AND SECURITY
The Contractor is responsible for the construction site security of their equipment, materials, and supplies. PPE shall be always utilized during construction activities, and an accident prevention plan/site specific safety and health plan for all field work shall be submitted prior to Preconstruction/Survey meeting. The Contractor shall assume full responsibility and liability for compliance with all applicable regulations pertaining to the health and safety of personnel and environmental management during the execution of work and shall hold the Government harmless for any action on his/her part or that of his/her employees or subcontractors, which results in illness, injury, or death. Any hazards that would pose a danger to Contractor’s personnel or operating equipment must be identified and mitigated or avoided by the Contractor.
5.0- GENERAL
All contract work shall be completed and performed in accordance with the best practices of the trade and in compliance with all applicable federal, state, and local codes and standards.
In case of conflict with various standards, the more restrictive standard applies.
All construction debris shall be removed at least weekly, and the work site shall be kept neat, clean, and free of hazards.
Provide accessories, industry standard materials, equipment, and tools as required to provide a complete project, even though not every item or material is specifically shown, mentioned, or described.
6.0- SCHEDULING
All work shall be scheduled and coordinated with the COR, NPS technical representative, or CO. Scheduling of work between the NPS staff and Contractor’s staff will be necessary during various stages of the project work as NPS staff and Contractor staff may have overlapping work areas. This shall be discussed at a Pre-Construction meeting prior to the beginning of work.