Attach_5-_Questions_and_Answers_0001.pdf
PDF 105 KB Posted
- Attached to
- INITIAL PRE-CONSTRUCTION SURVEY AT LOWER LEHMAN CA Federal contract opportunity
- Solicitation number
- 140P8123Q0095
About this file
This document contains questions and answers regarding Solicitation No. 140P8123Q0095 for an initial pre-construction survey at Lower Lehman Campground. The scope of work involves staking the exterior limits of work and point plan as described on drawing sheet L4.3. Bidders are encouraged to conduct a site visit prior to submitting their quote to familiarize themselves with site conditions. The solicitation is issued by the Department of the Interior National Park Service Pacific West Region.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Sol_140P8123Q0095_Amd_0001.pdf | ||
| Attach_4-_Elevation_Staking_Drawings_0001.pdf | ||
| Attach_1-_Statement_of_Work.pdf | ||
| Sol_140P8123Q0095.pdf | ||
| Attach_3-_SCA_Wage_Determination_2015-5601.pdf | ||
| Attach_2-_Landscape_Drawings_with_Notes.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Questions and Answers (Q&A) Solicitation No. 140P8123Q0095
GRBA – Lower Lehman Campground Survey
8/2/2023
Q1. Is the task to stake the exterior limit of work?
A1. Yes, the exterior limits of work is included under the Scope of Work, also called “Limit of Construction Boundaries”.
Q2. Is the task to stake out the Point Plan as described on Sheet L4.3, and the Scope of Work document to be completed by the contractor in one trip?
A2. Yes. Although not mandatory, it is also highly encouraged that the contractor conduct a site visit prior to submitting their quote to become familiar with the site conditions.