This Statement of Work outlines furniture removal services required at Robins Air Force Base Building 2051S. The contractor must remove 439 furniture items (including desks, demountable walls, and 5 long tables) from 22 specified rooms, transport them off-base, and dispose of them in accordance with local, state, and federal regulations. The work must be performed between 7:00 AM and 5:00 PM Monday through Friday, with alternative hours requiring CO approval.

The related solicitation indicates a site visit will be held on January 21, 2025, at 9 AM EST, with registration required by January 17, 2025, at 1 PM EST. Questions are due by January 22, 2025, at 4 PM EST, and the solicitation closes on January 24, 2025, at 3 PM EST. This will be a firm-fixed-price contract, though funds are not currently available. Contractors must be registered in SAM.gov, and the Air Force Sustainment Center will manage the contract. POCs are Maj Robert Hannum and MSgt David Stocks for building access, and Adriana Lytle and Bobby Ballow for the solicitation.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

STATEMENT OF WORK

SC FURNITURE REMOVAL FROM BUILDING 2051S

1. The Contractor shall provide a service to remove furniture from building of 2051S, rooms 116, 150, 153, 155, 167, 180, 186, 194, 198, 213, 235, 240, 309, 356, 360, 382, 383, 519, 598, 996, 1428, and 1510 on Robins Air Force base. The contractor shall 1) remove the furniture from the building, 2) transport the furniture for disposal, and 3) dispose of the furniture.

2. Furniture Moving Services: The Contractor shall provide services as follows:

a) REMOVAL: Contractor shall breakdown and remove the 439 furniture items to include desks, demountable walls, and 5 long tables from building 2051S on Robins Air Force Base.

b) TRANSPORT: Contractor shall transport all removed furniture from the buildings of 2051S to disposal site.

c) DISPOSAL: Contractor shall dispose of all furniture and items transported from the building to an off-base disposal location.

d) DIMMENSIONS: Refer to attached inventory list.

3. Location of Project Site:

a. Bldg. 2051S – 635 Blunk Drive, Robins AFB, GA (Remove)

4. Delivery of Service period:

a. Vendor must begin service upon contract award.

b.

5. Availability of the site. The project area will be available for the contact work between 7:00 am and 5:00 pm, Monday through Friday, (government holidays excluded) for scheduled work. Contractor personnel will be permitted in the area for routine contract work only between the hours specified. If contractor wishes to perform work at times other than those stated for the workday, or on Sunday, they shall include the number of work hours, starting times, and the dates of the proposed work. Contractor personnel shall begin during the requested times only on approval of such request by Contracting Officer.

6. Security. Contractor shall provide a list of all technicians to perform work; their social security number and any other information prior to commencement of work. Initial entry to the work areas will be gained by contacting:

Bldg. 2051S: Maj Robert Hannum or MSgt David Stocks Phone: (478) 468-4471 (478) 472-8826

7. Continuity. All tools, labor, and materials required to complete any items of work within a given work area or requiring an outage of any building utility or system, shall be provided by the contractor and available at the site prior to commencement thereof. Once work has commenced on an item of work, said work shall be continuously and diligently performed to completion and acceptance.

8. Safety. Contractor shall conform to all applicable safety standards published in the Federal Register or any other national Consensus Standard adopted by the Secretary of Labor in compliance with the Occupational Safety and Health Act, OSHA, Public Law 91-956.

9. Cleanup. The contractor shall dispose of scrap and waste generated in the performance of the contract at the end of each workday. The contractor shall perform cleanup duties after each visit to the site.

10. Disposal. The contractor shall remove all refuse, scrap, and waste materials from the project sites. Waste shall be removed from the Base and disposed of by the contractor in conformance with local, State, and federal Regulations.

11. Contractor Liability for Damage. The contractor shall be liable for any damage to the building systems resulting from improper installation, negligence, or inexperienced technicians.

12. Points of Contact: Primary: Maj Robert Hannum Phone: (478) 468-4471 Alternate: MSgt David Stocks Phone: (478) 472-8826

File details come from the government source that posted it. Updated .