Attach 1 SOW Demo of PA I Bldgs at BARC 24May24.pdf

PDF 438 KB Posted

Attached to
Demolition of Programmatic Agreement Phase I Buildings at BARC in Beltsville, MD
Solicitation number
12305B24R0037
Issued by

About this file

This document is a Statement of Work (SOW) for the demolition of 14 buildings at the Beltsville Agricultural Research Center (BARC) in Beltsville, Maryland, as part of the Programmatic Agreement (PA) Phase I.

The SOW requires the contractor to provide demolition services, including removal of existing building structures, hazardous materials, site improvements, utilities, and vegetation, and to restore the building sites to natural contours and vegetation. The contractor must comply with all federal, state, and local laws and regulations. The SOW provides detailed technical requirements and tasks, as well as pricing, deliverables, and schedule information. The contractor is required to provide submittals such as a demolition plan, environmental protection plan, and health and safety plan. The SOW also outlines requirements for handling and disposing of hazardous materials, reclamation of valued salvaged materials, and coordination with the government. The period of performance for the base scope is 180 calendar days from the Notice to Proceed.

View the file

Other files

Show all 15

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

2024-05-08 Page 1 of 11

US Department of Agriculture (USDA)

BELTSVILLE AGRICULTURAL RESEARCH CENTER (BARC)

FACILITIES SERVICE PROPERTY MANAGEMENT UNIT

BUILDING 426A, BARC-EAST

10300 BALTIMORE AVENUE

BELTSVILLE, MARYLAND 20705-2350

Demolition of Programmatic Agreement Phase I Buildings

May 8, 2024

2024-05-08 Page 2 of 11

Contents Project General Information

1.0 Background

2.0 Scope

Contractor Requirements

3.0 Technical Requirements / Tasks

4.0 Pricing

5.0 Deliverables / Schedule

2024-05-08 Page 3 of 11

Project Demolition of Beltsville Agricultural Research Center (BARC) buildings per Phase I of Programmatic Agreement (PA)

Table 1: Programmatic Agreement Phase I Buildings for Demolition

# ID Name Built Area Levels Structure Reclaim Hazardous Document

009 Green house Range 3 1943 19,577 1 Block X MIHP

2 018 Smallwood House 1935 2,304 1 Wood X X MIHP 3 038 Potato House 1934 1,079 1 Block X MIHP 4 039 Bulb House 1934 1,040 2 Block X MIHP 5 040 Fruit Storage House 1934 1,040 1 Block X MIHP 6 041 Fallout Shelter 1943

796 1 Concrete X MIHP 7 050 Headhouse with Greenhouse 1960s

41,173 1 Block/Glass X MIHP 8 085A Granary Service Building 1950 1,200 1 Block X MIHP 9 166A Silo Shed 1934

100 1/4 Block/Metal X MIHP 10 541C Hog House 1942

460 1 Block X MIHP 11 541D Hog House 1942

460 1 Block X MIHP 12 1052 Chemical Storage Building 1940 1 Block X MIHP 13 1073 Foreman's House Garage 1935

180 1 Brick X MIHP 14 1100 Parasitological Laboratory 1936 3,290 1 Block X MIHP

General Information

1.0 Background

United States Department of Agriculture, Agricultural Research Service (USDA-ARS) operates the Beltsville Agricultural Research Center (BARC) in Beltsville, Maryland. BARC is considered an historic district and is eligible for inclusion in the National Register of Historic Places (NRHP). USDA-ARS intends, per USDA-ARS’s obligation to dispose of surplus property in compliance with the 2015 Reduce the Footprint Policy (Executive Office of the President, Office of Management and Budget, 2015), to demolish 14 buildings that contribute to the NRHP-eligible historic district. As a Federal agency, USDA- ARS is required to comply with Section 106 of the National Historic Preservation Act (NHPA), which requires the agency to consider the effects of Federal undertakings on properties included in or eligible for the NRHP.

The USDA-ARS has determined that disposal of surplus properties that contribute to the NRHP-eligible BARC Historic District will have an adverse effect on the NRHP-eligible BARC Historic District, and the Maryland State Historic Preservation Office (SHPO) agreed. USDA-ARS has a Programmatic Agreement (PA) to minimize and mitigate the effects of the proposed demolition program on historic properties, including the buildings themselves and the overall NRHP-eligible historic district. This Statement Of Work (SOW) addresses Phase I of the PA.

2.0 Scope

Following guidelines defined here, provide demolition of buildings site improvement, and utility connection up to point of utility infrastructure tap, and after removal of demolished material, restore of building site to natural contours and vegetation. There are additional requirements identified for removal and disposal of hazardous material, removal and storage (as Value Salvaged Materials) of reclaimed material, and preparation of documentation for compliance with historical preservation requirements.

Building Descriptions

1. Building 009 consists of a long, horizontal headhouse. Originally, the building had six greenhouses attached at right angles to the headhouse. However, since the completion of the 1995 Maryland Inventory of Historic Properties Form and National Register of Historic Places (NRHP) Determination of Eligibility, the six greenhouses attached to the rear of the building have been demolished. Because of its sloped site, and to prevent shading of the greenhouses, the

2024-05-08 Page 4 of 11 building is stepped to follow the contours of the topography. The 1-1/2-story Georgian Revival headhouse is of concrete block construction with brick veneer walls and concrete foundations. All downspouts and gutters are copper; the roof is covered with rubber slate shingles that originally had slate throughout. Decorative detailing is of limestone, with the exception of windowsills and interior door lintels, which are of cast stone. The building, vacant since 2009, is in poor/fair condition. Per attached HAZMAT report, the following is noted for removal and disposal:

Asbestos-Containing Materials (ACM), Lead-Based Paint (LBP), and Other Potentially Regulated Materials (OPRM).

2. Building 018 is located at the North Farm of BARC and was constructed in 1933-1934 by the USDA as a foreman’s cottage for early superintendents and facility staff. The residential building is a one-story, wood-frame bungalow clad with painted horizontal cement board siding. It features a concrete-block foundation, a gable roof with a south-facing cross-gable, and an interior brick chimney. The roof is clad with asphalt shingles and features overhanging soffits. A screened façade porch is supported by brick piers, covers the entry, and spans three of the elevation’s four bays (south to north). The fourth bay contains an exterior storm window sash over plywood, and the remaining fenestration is covered with plywood. The building features full-sized and one half-sized windows that are filled with exterior storm sashes over plywood and double-hung six-over-one wood window sash with exterior storm windows.

The south elevation of the basement story features an overhead panel garage door. The garage is accessed by a ramp with poured concrete walls. This feature was likely added when the building was moved in the 1940s, as it was not mentioned in the 1935 description. Per attached HAZMAT report, the following is noted for removal and disposal: LBP and OPRM.

Reclamation: The pier on the right side of the porch when standing facing the house from the street. See photo-reclaim pier from the top of the porch/door frame (there is a small capital at the top, include this) to the porch floor.

2024-05-08 Page 5 of 11

3. Building 038 was used as a potato storage building on the North Farm within the U.S. Department of Agriculture’s (USDA) Agricultural Research Service (ARS) Beltsville Agricultural Research Center (BARC). It was built in 1934 and was in an area used by the Bureau of Plant Industry (BPI). Building 038 is a single-story, rectangular building built into the side of embankment. The three-bay vernacular building is of rusticated concrete block construction. The central entry features paired doors and is flanked by windows with double-hung replacement vinyl sashes with six-light snap-in muntins. The foundation is not visible. The roof was historically covered with composition shingles, and most recently by corrugated metal, which has partially been removed, and is in poor condition especially on the west end. Two ventilators on the roof have been removed. An exterior brick chimney pierces the roof near the northeast corner. The building has been vacant since 2008 and was damaged by a circa 2010 fire in the attic. It is in poor condition. Per attached HAZMAT report, the following is noted for removal and disposal: ACM, LBP and OPRM.

4. Building 039 was used as a bulb storage building on the North Farm within the U.S. Department of Agriculture’s

(USDA) Agricultural Research Service (ARS) Beltsville Agricultural Research Center (BARC). It was built in 1934 and was in an area used by the Bureau of Plant Industry (BPI). Building 039 is a two-story, rectangular building built into the side of embankment. The three-bay vernacular building is of rusticated concrete block construction. The central entry is flanked by windows, all of which are currently covered by wood panels. The foundation is not visible. The roof was historically covered with composition shingles, and most recently by corrugated metal, which has partially been removed, and is in poor condition especially on the west end. Two ventilators on the roof have been removed.

An exterior brick chimney pierces the roof near the northeast corner. The building has been vacant since 2008 and is in poor condition. Per attached HAZMAT report, the following is noted for removal and disposal: LBP and OPRM.

5. Building 040 was used as a fruit storage building on the North Farm within the U.S. Department of Agriculture’s

(USDA) Agricultural Research Service (ARS) Beltsville Agricultural Research Center (BARC). It was built in 1934 and was in an area used by the Bureau of Plant Industry (BPI). Building 040 is a single-story, rectangular building built into the side of embankment. The three-bay vernacular building is of rusticated concrete block construction. The central garage bay has a paneled overhead door, and is flanked by windows with double-hung, six-light wood sashes.

The foundation is not visible. The roof was historically covered with composition shingles, and most recently by corrugated metal. Two ventilators project from the roof. An exterior brick chimney near the southwest corner has been partially removed to below the eave. The building has been vacant since 2008 and is in fair condition. Per attached HAZMAT report, the following is noted for removal and disposal: LBP and OPRM.

6. Building 041 was a bomb or fallout shelter on the North Farm within the U.S. Department of Agriculture’s (USDA)

Agricultural Research Service (ARS) Beltsville Agricultural Research Center (BARC). It was built in 1943 and was in an area used by the Bureau of Plant Industry (BPI). Building 041 is a single-story, rectangular building built into the side of embankment. The single-bay vernacular building is of poured-in-place construction. The single bay is filled with a metal door. The roof and sides are covered by mounded earth, and a large metal ventilator projects from the west end of the mound. The building has been vacant since 2008 and is in fair/good condition. Per attached HAZMAT report, the following is noted for removal and disposal: OPRM.

7. Building 050, constructed in phases in the early to mid-1960s, is located on the North Farm within the U.S.

Department of Agriculture’s (USDA) Agricultural Research Service (ARS) Beltsville Agricultural Research Center (BARC). The headhouse with greenhouse consists of a long horizontal headhouse and four greenhouses attached at right angles to the headhouse. The front of the building faces northeast onto South Drive. The 1-1/2-story headhouse is of concrete block construction with brick veneer walls, has a gable roof, and is 254’-6” long and 35’-6” wide. The headhouse is separated into four sections, each of which leads to a separate greenhouse, with an extra bay between the first and second headhouse. The four sections of the headhouse are like each other. Each of these sections of the building has three to five windows with a central metal door. The extra bay has a single window. All the windows are three-light metal-frame awning windows. The four front entrances have concrete stairs with brick foundations and metal handrails. The headhouse and greenhouses rest on poured concrete basements. The four greenhouses have cross gable roofs with four gable-roofed, stucco covered dormers. The greenhouses are galvanized steel-frame and glass construction and attached perpendicular to the headhouse. Per attached HAZMAT report, the following is noted for removal and disposal: ACM, LBP and OPRM.

2024-05-08 Page 6 of 11

8. Building 085A. The one-story brick building has a rectangular plan. Building 085A has a flat roof with a central interior brick chimney. The windows are mostly twelve light hopper metal windows with brick sills; most windows are boarded over. There is one nine-light hopper metal window on the east (rear) elevation. The main facade (west elevation) has an off-center door flanked to the south and north by one window and by three windows, respectively.

The north (side) elevation has a metal door and a window. The east (rear) elevation has an off-center double metal door near the north elevation, and two windows. The south (side) elevation has a metal door and a window. The interior of Building 085A has concrete block walls and concrete floors. Building 085A has been vacant for an unknown period. Per attached HAZMAT report, the following is noted for removal and disposal: ACM, LBP and

OPRM.

9. Building 166A is four bays wide, was constructed of concrete blocks, and has a concrete slab foundation. The windows are filled with two-light steel hopper-style casement sashes. It originally featured six-light sliding wood doors on each end. The shed roof is covered with corrugated metal and features exposed rafter tails. The south side of the building has four large openings, oriented to the four adjoining silos. The four silos are approximately 40-50’ tall cylinders made of curved metal panels. They have rounded metal roofs, from which former filling pipes project.

A metal cage ladder extends to the top of each silo. The silos are supported by concrete slab foundations. The building has been vacant since 2008 and is in fair/good condition. Per attached HAZMAT report, the following is noted for removal and disposal: LBP.

10. Building 541C was built and used as a hog house within the U.S. Department of Agriculture’s (USDA)Agricultural

Research Service’s Beltsville Agricultural Research Center (BARC). Building 541C was built in 1942 and was in an area used by the Bureau of Animal Industry’s (BAI) Swine Research unit. Building 541C is a single-story, masonry building is a single bay wide and constructed of concrete blocks. The foundation of Building 541C has a concrete slab.

Building 541C has a single-light, paneled wood door on its north end and two small, wood animal doors on both ends of the east elevation. The front-gable roof is covered in corrugated metal, and two large metal ventilators pierce the ridgeline of the roof. The interior of Building 541C contains two rooms divided by a concrete-block wall with a wood access panel. Long metal tie bars are mounted along the walls. Building 541C was vacated circa 2000 and is in good condition. Per attached HAZMAT report, the following is noted for removal and disposal: LBP.

11. Building 541D is a single-story, masonry building that is a single-bay wide and constructed of concrete blocks. The foundation of Building 541D has a concrete slab. Building 541D has a single-light, paneled wood door on its north end and two small, wood animal doors on both ends of the west elevation. The front-gable roof is covered in corrugated metal, and two large metal ventilators pierce the ridgeline of the roof. The interior of Building 541D contains two rooms divided by a concrete-block wall with a wood access panel. Long metal tie bars are mounted along the walls. Building 541D was vacated circa 2000 and is in good condition. Per attached HAZMAT report, the following is noted for removal and disposal: LBP.

12. Building 1052 is a rectangular, one-story, front-gable building constructed of concrete masonry block and covered with stucco. The roof is clad with slate shingles. Building 1052 is oriented on an east-west axis, and the primary entrance is located in the east elevation. The entrance is offset toward the northeast corner of Building 1052 and features an infill wood panel door, within a larger framed door opening which has been partially enclosed with wood panels. The east gable end features a rectangular louvered vent. The north and south elevations feature two, eight-pane metal-sash windows, which are located high on the walls, below the edge of the roof. The window panes are arranged with a central hopper window with four panes, flanked by two fixed panes on either side. The west elevation features an internal brick chimney in the northwest bay. The chimney has no openings, but features a round plug high on the elevation, roughly in line with the tops of the windows. The chimney emerges through the roofline at the approximate mid-point of the span. The west elevation also features a rectangular louvered vent below the roof peak, and an off-center wood door located in the southwest bay. The interior of Building 1052 is not subdivided. Building 1052 is presently vacant and is in fair condition. Per attached HAZMAT report, the following is

13. Building 1073. The one-story building rests on a concrete foundation and is built into a small hill. Building 1073 is constructed of wood and brick set in a common bond pattern. The gable ends are clad with wood clapboard. The east and west elevations each have a single, fixed, six-pane, wood window with a brick sill. The south elevation has

2024-05-08 Page 7 of 11 no openings. The front façade contains an overhung, wood garage door with six panes of glass in the uppermost leaf. The front-gable roof is steeply pitched and covered with slate. Per attached HAZMAT report, the following is

14. Building 1100. The one-story building is three bays in length, 11 bays in width, and is constructed of concrete blocks with a stucco finish. Building 1100 has a medium-pitch front gable roof covered by slate shingles. Building 1100 has one-over-one, metal-frame, awning windows with brick sills. The main entry is centered on the north elevation and is flanked by single windows. The east (side) elevation has 13 bays with windows. The south (rear) elevation has a centered ancillary entry with metal double doors that have windows near the upper half of the door. The west (side) elevation has 10 bays with windows and one with a side entrance. The interior consists of a full-length central hallway with offices and laboratory spaces on either side of the hallway. Per attached HAZMAT report, the following is noted for removal and disposal: ACM and OPRM.

Contractor Requirements

3.0 Technical Requirements / Tasks

The contractor shall provide all labor, material, equipment, utilities, technical skills, hauling, hazardous / waste disposal and transportation to demolish these buildings in their entirety in accordance with all Federal, State, and local laws, regulations, codes, USDA and ARS directives. This includes removing existing building structures, removing hazardous materials, existing site development such as paving, sidewalks, foundation walls, shrubs, trees, and vegetation. Also remove all HVAC equipment, electrical generators, and electrical transformers. After foundation and site improvement removal, regrade to match local topology, provide fine grade topsoil with hydro seeding and cover, and provide watering of seed. Special consideration shall be given to remove and dispose safely hazardous materials such as asbestos, lead, mold, oils, mercury, and PCBs. It is the responsibility of the contractor to identify and remove all hazardous materials as per EPA regulations and requirements. The contractor shall notify the contracting officer within 24 hours in the event of the discovery of any material that in his judgment may contain asbestos.

1. FIELD VERIFICATION: It is the responsibility of the contractor to field verify the existing building and site conditions such as: the building construction type, building construction material content, fixed, moveable building content, equipment, stored goods, clearing, grubbing, removing of existing fencing material etc. to have accessibility to the building that will be demolished.

2. UTILITIES: All utilities outside the building (plumbing, mechanical, water service, gas service, steam lines, waste sewer line, and electrical service) shall be turned off by the government. The government will turn the water valves/steam valves off at the building support termination. The contractor will cap service lines at support termination prior to building connected utility removal. Coordinating with the government and power utility, contractor shall remove the building electrical service drop from the building to the electrical utility connection. This shall include demolishing of all associated sub part of the system such as concrete, conduit, piping, electrical wiring and the like.

3. SEDIMENT AND EROSION CONTROL: The contractor shall follow all Maryland Department of the Environment

(MDE) sediment and erosion control requirements for this project. The contractor shall supply and install a 3'-0" silt fence around the entire demolition site. The contractor shall supply and install soil erosion silt fence device 30' -0" from area the of disturbance line and round the entire building. The silt fence shall be installed inside the construction fence line. For temporary staging, the contractor shall supply and install a stone construction entrance that is 20' -0" wide x 30' -0" long x 6" deep and the stones shall be 2" in diameter, which is to be removed after demolition. The contractor shall not at any time permit the silt fence to collapse, dirt and/or debris flow into the street, other paved and adjacent areas. The contractor shall supply dust control and/or protection as required to ensure no damage to the surrounding vegetation or pavement.

4. TREE AND DRAINAGE INLET PROTECTION: The contractor shall supply and install orange protective fencing around existing trees that will remain and/or any area that needs to be protected. The contractor shall supply and install straw bale dikes at any drainage inlet in the limits of disturbance and/or areas where a silt fence can't be installed such as in asphalt or concrete paving material areas.

2024-05-08 Page 8 of 11

5. SECURITY: The construction site shall be secured by the contractor at the end of each day and on weekends. The contractor is responsible for securing his equipment, materials, and supplies that are related to this project. Also, a portable 8'-0" high chain link construction fence shall be installed around the entire demolition site. The fence shall have a construction gate entrance 20'-0" wide and shall be able to swing freely over the 2" stone construction entrance. The silt fence shall be installed inside the construction fence. The contractor shall not perform any work outside the construction fence line without the expressed permission from the COR. All equipment supplies and materials shall be stored in the work area at the contractor's risk. Although the buildings and grounds at BARC will be secured at the end of each day by BARC Security, BARC is not responsible for any of the contractor's stored material, equipment, either inside or outside the building at any times.

6. TEMPORARY FACILITIES: The contractor is responsible for their utilities such as electrical, plumbing, water, and toilet facilities. The government has the right to permit the contractor to use their utilities in reasonable quantities.

For temporary site water use, the contractor shall provide an approved Reduce Pressure Zone Backflow Preventer ASSC 1013 and the USDA will inspect and certify that the appliance is usable and functioning properly when connected to BARC water source.

7. COORDINATION: The contractor shall coordinate with the COR on any situation that will directly or indirectly adversely impact the government such as: work that will require an inconvenience or work stoppage to the government research or personnel (due to power outage, utility disruption, etc.).

8. VALUED SALVAGED MATERIALS: The Government reserves the right to make claim in part or in whole to all material that is buried in the ground, located on grade, or in the building structure such as: equipment, fixtures, switch gear, laboratory materials, and stored materials. The word valued salvage shall be defined two ways: 1) anything that has a salvage value over $500.00 and 2) if the item is a discontinuation from being manufactured such as steam valves. Prior to disposal of any valued material being discarded the contractor shall notify the COR of their findings and allow the government first refusal. If the government makes claim to such valued material the contractor shall transport such valued material to a storage facility within a five (5) mile radius of Beltsville Agricultural Research Center (BARC), Beltsville, Maryland as instructed by the COR.

9. SUBMITTALS: The contractor shall provide the following submittals: Demolition Plan, Environmental Protection Plan, Stormwater Pollution Prevention Plan, as required by the Environmental Protection Agency (EPA), Health and Safety Plan, Demolition Schedule, and Material Safety Data Sheet MSDS

10. Limit of Disturbance (LOD): The contractor shall maintain a distance of 30 feet between the building and the outer limit of disturbance. That means the contractor shall not extend beyond 30 feet of the building during demolition.

The contractor shall notify the CO and COR at any time should this become an issue.

11. MOBILIZATION & DEMOBILIZATION: The contractor shall notify the COR 24 hours prior to mobilization & demobilization of heavy equipment onto or from USDA-BARC property. The contractor shall deliver or pickup equipment from the construction entrance on a stone gravel bed when transported on the flatbed trailer. When equipment is transported using a flatbed trailer, the contractor shall deliver and pick up equipment from the construction entrance on stone gravel bed. At no time shall the contractor have heavy equipment on pavement that is not being demolished or within the limits of disturbance without permission from the COR. Any vehicle or equipment that is dirty shall be cleaned on the construction entrance stone gravel bed prior to transport and at no time should any dirt or debris flow into the street.

12. NOTE: All equipment, materials, and waste brought in or on-site shall be taken off- site via a route designated by the COR. Prior to building demolition PCM Finals shall be taken.

13. SITE DEMOLITION: The contractor shall protect areas that are not to be disturbed and remove concrete paving, curbs, sidewalks, equipment pads and abandon utilities etc. The contractor shall provide dust control to prevent the spread of dust and avoid the creation of a nuisance in the surrounding area. The work area shall not produce a dust cloud during performance of work. This may require a water tanker truck or a similar system. Do not use water if it results in hazardous or objectionable condition such as, but not limit to, ice, flooding, or pollution. Sweep

2024-05-08 Page 9 of 11 pavements as often as necessary to control the spread of debris. Do not begin demolition until authorization is received from the Contracting Officer. Removing rubbish and debris from the demolition site; do not allow accumulations on site. Store materials that cannot be removed daily in areas specified by the COR.

14. BUILDING DEMOLITION: The contractor shall demolish and backfill one building at a time but will be permitted to hydro seed all building sites at one time unless soil erosion poses a problem. The contractor shall supply all labor, materials, supplies technical skills, tools equipment, safety items, transportation and supervise demolishment of building/buildings in this statement of work. The contractor shall totally remove the building/buildings from the site.

This will require that the drain tile, footings, foundation walls, floor slab/slabs, exterior walls, interior walls, ceilings, and roof system etc. be demolished and removed from site. Upon completion of the building demolition there shall not be any building materials present. The contractor shall inform the COR of completion prior to backfilling hole.

The contractor shall remove all hazardous materials from building structure prior to demolition. The contractor shall remove and dispose of Government property, all items indicated as TO BE REMOVED. Such items become the property of the contractor and shall be loaded, transported per applicable DOT regulations, and disposed of at approved landfills.

15. HAZARDOUS MATERIAL REMEDIATION & ABATEMENT: A hazardous materials survey (HMS) of each building will accompany this document. Provide documentation of personnel training and compliance with regulations regarding proper personnel and environmental protective measures and disposal requirements of hazardous materials in the scope of this Statement Of Work (SOW). Provide disposal of Hazardous materials in compliance with all rules and regulations and provide chain of custody for the proper disposal of hazardous materials. Please note the following rules and regulations listed below are not all inclusive of all applicable laws, rules, regulations and guidelines:

15.1. Federal Facility Compliance with Asbestos NESHAP (EPA Document # 315F24001)0 – February 2024)

15.2. OSHA and EPA regulations regarding LBP and OPRM removal and disposal

16. TOPSOIL & HYDRO SEDDING: The contractor shall use topsoil for finish grading and grade in manner that water will drain toward drainage inlets and away from surrounding buildings. But the grade shall follow the contour of the rough grade and the topography of the surrounding landscape. The COR will determine if the site shall be Hydro Seeded once the back filling is completed or when multiple sites are involved then Hydro Seeding all at one time. The contractor shall use a minimum of 6"-8" inches of topsoil in finish grading.

17. Clean Backfill Requirements: The contractor will provide clean fill free of frozen soils, waste, petroleum, and stones/aggregate greater than four inches in diameter. Contractor shall follow MDE guidance on selecting clean fill and will meet requirements for Category 1 fill material (Residential Unrestricted Use Soil and Fill Material) unless otherwise approved in writing by ARS. ARS may consider Category 2 fill materials for soils buried greater than four feet.

The proposed source(s) of the fill soils will be provided to ARS prior to commencement of backfill operations and will be screened for common contaminants based on their source location characteristics in accordance MDE’s guidance for fill soils. Source materials will be sampled at a rate in accordance with MDE’s clean fill guidance unless otherwise approved in writing by ARS. Contractors may opt to screen the potential fill soils against MDE’s Soil Cleanup Levels for residential soils (Category 1 Fill Material) or non-residential soils (Category 2 Fill Material) rather than performing a risk screening.

Clean Fill Reference Documents

1. MDE Guidance for Selecting and Screening Clean Fill Materials -https://mde.maryland.gov/programs/Marylander/Documents/Dredging/NoTrackChangesFillMaterial_andSoilM anagementFactSheet82217.pdf).

2. MDE VCP Clean Fill Fact Sheet -https://mde.maryland.gov/programs/Land/MarylandBrownfieldVCP/Documents/www.mde.state.md.us/assets/ document/Clean%20Imported%20Fill%20Material(2).pdf https://gcc02.safelinks.protection.outlook.com/?url=https%3A%2F%2Fmde.maryland.gov%2Fprograms%2FMarylander%2FDocuments%2FDredging%2FNoTrackChangesFillMaterial_andSoilManagementFactSheet82217.pdf&data=05%7C02%7Ctom.callsen%40usda.gov%7C6c8fc04eb25342a529dc08dc2291b61b%7Ced5b36e701ee4ebc867ee03cfa0d4697%7C1%7C0%7C638423256415030880%7CUnknown%7CTWFpbGZsb3d8eyJWIjoiMC4wLjAwMDAiLCJQIjoiV2luMzIiLCJBTiI6Ik1haWwiLCJXVCI6Mn0%3D%7C0%7C%7C%7C&sdata=%2B%2FUAy0DAtu5T6ksr3lg8BWKPQPmhZrVTZ73v41LXk7Y%3D&reserved=0 https://gcc02.safelinks.protection.outlook.com/?url=https%3A%2F%2Fmde.maryland.gov%2Fprograms%2FMarylander%2FDocuments%2FDredging%2FNoTrackChangesFillMaterial_andSoilManagementFactSheet82217.pdf&data=05%7C02%7Ctom.callsen%40usda.gov%7C6c8fc04eb25342a529dc08dc2291b61b%7Ced5b36e701ee4ebc867ee03cfa0d4697%7C1%7C0%7C638423256415030880%7CUnknown%7CTWFpbGZsb3d8eyJWIjoiMC4wLjAwMDAiLCJQIjoiV2luMzIiLCJBTiI6Ik1haWwiLCJXVCI6Mn0%3D%7C0%7C%7C%7C&sdata=%2B%2FUAy0DAtu5T6ksr3lg8BWKPQPmhZrVTZ73v41LXk7Y%3D&reserved=0 https://gcc02.safelinks.protection.outlook.com/?url=https%3A%2F%2Fmde.maryland.gov%2Fprograms%2FLand%2FMarylandBrownfieldVCP%2FDocuments%2Fwww.mde.state.md.us%2Fassets%2Fdocument%2FClean%2520Imported%2520Fill%2520Material(2).pdf&data=05%7C02%7Ctom.callsen%40usda.gov%7C6c8fc04eb25342a529dc08dc2291b61b%7Ced5b36e701ee4ebc867ee03cfa0d4697%7C1%7C0%7C638423256415041140%7CUnknown%7CTWFpbGZsb3d8eyJWIjoiMC4wLjAwMDAiLCJQIjoiV2luMzIiLCJBTiI6Ik1haWwiLCJXVCI6Mn0%3D%7C0%7C%7C%7C&sdata=U5uB0F4gA1dL8WVt%2BVTheqYkMOxMtMwQC5r3ZnS%2FZew%3D&reserved=0 https://gcc02.safelinks.protection.outlook.com/?url=https%3A%2F%2Fmde.maryland.gov%2Fprograms%2FLand%2FMarylandBrownfieldVCP%2FDocuments%2Fwww.mde.state.md.us%2Fassets%2Fdocument%2FClean%2520Imported%2520Fill%2520Material(2).pdf&data=05%7C02%7Ctom.callsen%40usda.gov%7C6c8fc04eb25342a529dc08dc2291b61b%7Ced5b36e701ee4ebc867ee03cfa0d4697%7C1%7C0%7C638423256415041140%7CUnknown%7CTWFpbGZsb3d8eyJWIjoiMC4wLjAwMDAiLCJQIjoiV2luMzIiLCJBTiI6Ik1haWwiLCJXVCI6Mn0%3D%7C0%7C%7C%7C&sdata=U5uB0F4gA1dL8WVt%2BVTheqYkMOxMtMwQC5r3ZnS%2FZew%3D&reserved=0

2024-05-08 Page 10 of 11

3. Maryland Soil Cleanup Standards -https://mde.maryland.gov/programs/Marylander/Documents/Dredging/NoTrackChangesFillMaterial_andSoilM anagementFactSheet82217.pdf).

18. Hydro Seeding shall be done during the spring approximately April 1st thru June 5th and September 1st thru October

20th. The contractor shall thoroughly moisten soil before seeding to a depth of 150 mm. Do not seed when the ground is muddy, frozen or snow covered or in an unsatisfactory condition for seeding. The contractor shall not start Hydro Seeding until the COR approves the soil’s conditions suitability. If special conditions exist that may warrant a variance in the above seeding dates or conditions, submit a written request to the COR stating the special conditions and request for variance. The contractor shall not proceed until a variance is granted and the conditions of the variance are met. Apply seed within twenty-four hours after seedbed preparation. Sow seed by Hydro seeding using the appropriate equipment. After seeding is completed spread straw, hay, or humus over seed bed area to an even depth of 13 mm. Take precautionary measures to prevent topdressing materials from spilling onto pavements, utilities structures, or planting beds. The contactor shall maintain a watering schedule that keeps the grass moist in 70-degree weather and above the grass shall be watered twice a day for 45 days after completion of all Hydro Seeding. Please note when the contractor is connected to any water source on the property of the USDA, they shall use a backflow preventer that meets or exceed the ASSC1013 Specification. Once the device is installed the contractor shall contact the COR for inspection by the USDA, BARC, FS, and Shops. Upon approval, the contractor can proceed with using the water source. The work shall extend the full interior area of the silt fence.

4.0 Pricing

Provide base and option pricing.

1. Base scope shall include buildings 038, 039, 040, 041, and 050.

2. Option scope shall include buildings 009, 018, 085A, 1052, 166A, 541C, 541D 1073 and 1100.

5.0 Deliverables / Schedule

1. DEMOLITION SCHEDULE: The contractor shall provide a critical path schedule to include each task and the duration of the contract period to the COR for approval.

2. CLEAN-UP & FINAL PUNCH LIST: The contractor shall clean the site of any loose debris and schedule a final walk thru with the COR. Upon completion of all punch list items, the parking passes and badges shall be returned to COR.

3. STAGING: All equipment supplies and materials for this contract shall be stored in the work area at the contractor's risk.

4. Submittals: The contractor shall submit the manufacturer's technical data sheets and shop drawings for the list of items within identified due schedule per table below and attached submittal log. Each submittal shall be attached to a Submittal Transmittal Form (enclosed), signed by the Contractor, and delivered to the COR.

5. Coordination: The contractor shall coordinate with the COR, with adequate advance notice, all work which will require an inconvenience or work stoppage to Government personnel due to noise, dust, extreme temperatures, and exposure to chemical fumes or interruption in utilities. The contractor shall provide dust protection as required to ensure the delicate scientific equipment housed in this building is not damaged.

6. Guaranty and Warranty: All contracted work shall be guaranteed by the contractor for a period of one (1) year from the date of final acceptance against workmanship. ALL WARRANTIES SHALL BE TURNED OVER TO THE COR PRIOR

TO FINAL INVOICING.

https://gcc02.safelinks.protection.outlook.com/?url=https%3A%2F%2Fmde.maryland.gov%2Fprograms%2FMarylander%2FDocuments%2FDredging%2FNoTrackChangesFillMaterial_andSoilManagementFactSheet82217.pdf&data=05%7C02%7Ctom.callsen%40usda.gov%7C6c8fc04eb25342a529dc08dc2291b61b%7Ced5b36e701ee4ebc867ee03cfa0d4697%7C1%7C0%7C638423256415048892%7CUnknown%7CTWFpbGZsb3d8eyJWIjoiMC4wLjAwMDAiLCJQIjoiV2luMzIiLCJBTiI6Ik1haWwiLCJXVCI6Mn0%3D%7C0%7C%7C%7C&sdata=TPWGTVWnpO84BzRUiil4BCYoZ5oA5rrt38K2fBCZfk0%3D&reserved=0 https://gcc02.safelinks.protection.outlook.com/?url=https%3A%2F%2Fmde.maryland.gov%2Fprograms%2FMarylander%2FDocuments%2FDredging%2FNoTrackChangesFillMaterial_andSoilManagementFactSheet82217.pdf&data=05%7C02%7Ctom.callsen%40usda.gov%7C6c8fc04eb25342a529dc08dc2291b61b%7Ced5b36e701ee4ebc867ee03cfa0d4697%7C1%7C0%7C638423256415048892%7CUnknown%7CTWFpbGZsb3d8eyJWIjoiMC4wLjAwMDAiLCJQIjoiV2luMzIiLCJBTiI6Ik1haWwiLCJXVCI6Mn0%3D%7C0%7C%7C%7C&sdata=TPWGTVWnpO84BzRUiil4BCYoZ5oA5rrt38K2fBCZfk0%3D&reserved=0

2024-05-08 Page 11 of 11

Table 2: Submittal Schedule

Item No. Deliverable Objective Due 1 Proposed Project Plan Defining the responsibilities, timeline, risks and milestones of contract objectives.

No later than five (5) business days after contract award

2 Weekly Status Report Report documenting tasks & issues weekly.

Weekly, every Friday, by 3:00 PM EDST until the contract expires

3 HAZMAT Manifests Tracking of proper disposition of hazardous materials per EPA Compliance Advisory Document #315F24001 dated February 2024.

Report per building structure

4 Soil / Fill Certification Compliance with USDA Requirements Before Delivery

Project
General Information
1.0 Background
2.0 Scope
Contractor Requirements
3.0 Technical Requirements / Tasks
4.0 Pricing
5.0 Deliverables / Schedule