This is a Statement of Work (SOW) for the Crystal Lakes Work Center Waterline Improvements project for the USDA Forest Service's Pike-San Isabel National Forests & Cimarron and Comanche National Grasslands, Leadville Ranger District. The project involves installing a 2-inch HDPE waterline to transmit clean drinking water from the water treatment system in Dwelling 1 to the water distribution system on the east side of Colorado Highway 24, connecting two previously separate water systems.
The key scope of work includes: obtaining a CDOT permit for directional boring under Highway 24, installing approximately 900 feet of water pipe, connecting to existing water treatment and distribution systems, decommissioning the east side well, installing a new well pump to achieve 15 GPM supply, and performing static pressure tests and disinfection. The contract period of performance is from the date of award until May 30, 2026, with anticipated winter work limitations from October to April. Deliverables include a construction schedule, material submittals, quality control reports, operations and maintenance manual, and as-built drawings. A site visit is planned, with contact information provided for Landon Wigton and Phillip Krieble from the USDA Forest Service.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
UNITED STATES
DEPARTMENT OF
AGRICULTURE
FOREST SERVICE
REGION 2
PIKE - SAN ISABEL
NATIONAL FORESTS &
CIMARRON AND
COMANCHE NATIONAL
GRASSLANDS
LEADVILLE RANGER
DISTRICT
June 2, 2025
Crystal Lakes Work Center Waterline
Improvements
Statement of Work
Project Crystal Lakes Work Center Waterline Improvements Pike-San Isabel National Forests & Cimarron and Comanche National Grasslands Leadville Ranger District
General Information
1.0 Project Location
The Crystal Lakes Work Center on the Leadville Ranger District supports mission critical activities and houses up to 11 Forest Service employees. The Crystal Lakes Work Center is located approximately 6 miles south of Leadville, CO on US Hwy 24. The work center consists of an eight-person bunkhouse, a shop/garage, a two-person dwelling and a one-person dwelling. Please see figure 1 below for reference.
2.0 Scope of Work
2.0 Background
Currently (February 2025) there exist two separate water systems. One water system on the West side of Colorado Highway 24 serves Dwelling 1 and Dwelling 2. There is another well and water distribution system that serves drinking water to the shop/garage and the bunkhouse on the east side of HWY 24.
The water quality on the East side of the highway is poor compared with the West side of the highway.
This project will include the installation of a water treatment system in the basement of dwelling one located on the West side of Colorado highway 24. The east side well (permit # 117217) will be decommissioned. This project will include directional boring underneath HWY 24 to connect the west side water distribution with the east side water distribution. The west side well (permit 268119) will ultimately serve clean drinking water to the entire work center (both sides of HWY 24).
Figure 1
3.0 Statement of Work
The purpose of this contract is to install a 2-inch HDPE waterline to transmit clean, drinking water from the water treatment system located in the basement of Dwelling 1 (Brown House) to the distribution system located on the East side of the Colorado Highway 24.
The work generally consists of the following:
A. Perform all requirements (including producing a Subsurface Utility Engineering (SUE)) to attain a permit from the Colorado Department of Transportation to bore a 2-inch HDPE (SDR-11) waterline under Colorado HWY 24.
B. Install approximately 900 feet of 2-inch SDR11 HDPE water pipe from the basement of Dwelling 1 to the existing 2-inch schedule 40 PVC water distribution system located on the East side of HWY 24.
C. Install necessary pipe and fittings including valves and adapters to connect to the existing water treatment system located in the basement of DWELLING 1 on the West Side of HWY 24.
D. Install necessary pipe and fittings including a tee, curb stops, and adapters to connect to the existing water distribution system located on the East Side of HWY 24.
E. The water distribution system shall be installed at a minimum depth of 10 feet below grade.
F. Removal of existing well pump and installation of a new Well pump to attain 15 GPM supply flowrate to Dwelling 1.
G. Connect well pump to existing electrical supply and control panel, provide level sensor in water storage tank to energize well pump on and off.
Figure 2
H. Decommission well on East side of Highway in accordance with State of Colorado regulations.
I. Decommission and abandon pressure tank and water distribution system from the well located on the East side of Colorado HWY 24.
J. Perform a static pressure test and disinfection of new infrastructure per specification requirements.
4.0 Government Furnished
Water and electricity are available at the site for construction purposes.
5.0 Period of Performance
The contract period of performance shall be [date of award] until May 30, 2026. Winter conditions which may impede utility and earthwork activities can be anticipated approximately from October to April.
6.0 Deliverables / Schedule
KEY DELIVERABLES
Item No.
Deliverable Objective Due
1 Construction Schedule
Defining the responsibilities, timeline, risks, and milestones of contract objectives.
No later than the date of the prework conference
2 Material and Equipment Submittals
All material specifications, product data, manufacturer’s instructions, and material safety data sheets
During construction according to schedule
3 Quality Control Reports
Materials testing, construction observation, and special inspections documenting compliance with the Contract Documents.
During construction as indicated
4 Operations & Maintenance (O&M) Manual
Binder including equipment manufacturer’s data, system schematics and descriptions, maintenance schedules, etc.
Prior to final inspection
5 As-built Drawings Drawings that recognize any changes in the plans, specifications, and/or approved submittal of equipment supplied
Prior to final inspection
7.0 Travel
All costs associated with travel to and from the job site, including mobilization of all equipment and materials shall be included in the Contractor’s cost proposal.
8.0 Contractor’s Key Personnel
Project Manager – individual designated by the General Contractor, serves as primary points of contact and shall have overall responsibility for managing and coordinating the performance of the Contractor’s obligations under this contract, including performance of all Subcontractors, and be authorized to act for and bind Contractor and Subcontractors in connection with all aspects of this contract.
Project Superintendent – onsite representative of the General Contractor, responsible for overall management of the project and capable of discussing technical aspects of the project.
9.0 Site Visit
Contact Landon Wigton (307)-760-9172; landon.wigton@usda.gov and Phillip Krieble at (303)514-9751;
phillip.krieble@usda.gov for the site visit that will be held on (Date), at (Time) a.m. Mountain Time.
Location of Site Visit: 10553 Hwy 24 S LEADVILLE, COLORADO 80461
10.0 Attachments
1. Project Manual
a. See file
2. Construction drawings
a. See file Construction drawings Crystal Lakes Work Center Waterline Improvements
3. Well Permits
a. See file Well Permit Number 268119 (West side HWY 24).pdf
b. See file Permit Number 117217 (East side HWY 24).pdf