This is a Performance Work Statement (PWS) for mold remediation and reconstruction services at the USDA Forest Service Lake City Airtanker Base Administrative Operations building located at 475 SE County Road 245, Lake City, FL 32025. The project consists of two phases: Phase 1 involves complete mold remediation of affected areas, selective demolition and removal of mold-impacted materials, HVAC system and ductwork cleaning, facility-wide cleaning, and post-remediation clearance testing. Phase 2 requires reconstruction of all remediated areas to pre-loss condition or better, including installation of moisture-resistant wall assemblies, commercial luxury vinyl tile (LVT) flooring, cabinetry and millwork, and new appliances. The affected building is approximately 3,000 square feet with CMU block exterior, metal roof, and conventional lumber framing interior with existing HVAC split systems and electrical services.
The contractor must comply with 2024 International Building Codes, IICRC S520 mold remediation standards, EPA guidelines, OSHA regulations, and Florida mold remediation licensing requirements. All work must be completed within a 60-day base period of performance beginning no later than 10 calendar days after Notice to Proceed, with substantial completion required by day 45 and final acceptance by day 60. The contractor must provide a Florida mold remediation license, minimum 10 years of commercial mold remediation and construction experience, and furnish all materials, labor, equipment, and disposal services. Key submittals include project schedules, site-specific safety plans, and pre-work documentation due within 5-10 days of Notice to Proceed. Post-remediation verification reports must be completed by a licensed Florida mold assessor before reconstruction commences. This is a firm-fixed-price contract with estimated construction magnitude between $25,000 and $100,000, set-aside for small business concerns under NAICS 236220, with quotes due July 6, 2026 by 5:00 PM ET.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Sol_12445226Q0036_Amd_0001.pdf | ||
| Lake City ATB Questions and Answers.docx | DOCX document | |
| Attach 3- Floor Plan.pdf | ||
| Attach 7- Map.pdf | ||
| RFQ _12445226Q0036.pdf | ||
| Attach 2- Schedule of Items.xlsx | XLSX spreadsheet | |
| Attach 8 -Wage Determination FL20260008.txt | TXT text file | |
| Attach 4- Photos.pdf | ||
| Attach 5 - H2H Report.pdf | ||
| Attach 6- H2H Post Remediation Report.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
USDA Forest Service – Region 8 | Lake City Airtanker Base – Mold Remediation & Reconstruction | PWS | May 2026
US Department of Agriculture (USDA) USDA Forest Service – Region 8 Southern Region Performance Work Statement Lake City Airtanker Base Mold Remediation and Reconstruction Osceola National Forest, Lake City, FL 32025 May 2026
Project Project Name: Lake City Airtanker Base Mold Remediation and Reconstruction Location: Osceola National Forest, 475 SE County RD 245, Lake City, FL 32025 General Information
1.0 Scope of Work
The USDA Forest Service (the “Government”) requires mold remediation and reconstruction at the Lake City Airtanker Base Administrative Operations building located on federally leased land at the Lake City Gateway Airport, 475 SE County RD 245, Lake City, FL 32025. This work includes two (2) phases:
Phase 1 – Mold Remediation and Selective Demolition The Contractor will perform complete mold remediation of all affected areas, selective demolition, removal, and proper disposal of mold-impacted building materials, HVAC system and ductwork cleaning, facility-wide cleaning, and comprehensive post-remediation clearance testing to confirm remediation has been successfully completed prior to initiating reconstruction. Work shall include at a minimum wood framing and sill plates, sheathing, vapor barrier, insulation, flooring (VCT and Carpet Tile), cabinetry and millwork, and MEP incidentals.
Phase 2 – Reconstruction Upon successful completion and clearance of Phase 1, the Contractor shall reconstruct all remediated areas to pre-loss condition or better. Work shall include at a minimum wood framing and sill plates, sheathing, vapor barrier (wall assemblies shall be moisture-resistant), insulation, flooring (LVP), cabinetry and millwork, and MEP incidentals.
1.1 Project Location
This project is located on the Osceola National Forest, at the Lake City Airtanker Base, 475 SE County RD 245, Lake City, FL 32025.
1.2 Background
The Lake City Airtanker Base is an integral part of the National Forests in Florida’s wildland firefighting capabilities and serves as a national asset for wildfire fighting. The facility specializes in fire retardant operations for large air tankers and facilitates rapid aerial firefighting response to wildfires across the Southeastern United States. The base is a key component of the National Interagency Aviation Committee’s efforts to ensure standardized, safe, and efficient aerial firefighting operations.
The Lake City Airtanker Base (ATB) Operations Building is the affected facility. It is an administrative building where site aviation operations including dispatch are managed. A facility inspection by the Government in August 2025 found mold growth in the kitchen area, which was then contracted to a specialist (H2H Indoor Air Solutions Report, 08/10/2025) to complete an assessment of the water damage, mold contamination, and mold type.
The building is an approximately 3,000 sf CMU block exterior, metal roof, and concrete slab on grade. The interior is conventional lumber framing and drywall with paint finish. Interior wall assembly is assumed to be fiberglass insulation and vapor barrier. The MEP systems consist of an HVAC system with ceiling-mounted vents, 5-ton and 3-ton split system air conditioner with a high-efficiency gas heater, and typical electrical services from a 400-amp main panel.
The Government contracted previous mold remediation services based on the 08/06/2025 H2H Indoor Air Solutions Report. A Post-Remediation Assessment was completed on 01/22/2026. The 01/22/2026 Report identified the post-remediation result as “FAIL – Needs Further Remediation.” The building was vacated during the initial discovery and assessment. Building systems remained operational, but the facility has been and will remain unoccupied until the building passes the testing requirements. The objective of this work is to re-complete mold remediation and selective demolition work and perform facility-wide white-glove cleaning to achieve a post-remediation assessment pass result. This will be followed by reconstruction of all impacted areas to make the building fully operational and safely re-occupiable by employees.
1.3 Government Points of Contact
| Role |
| Name | Title |
| Phone |
| Contracting Officer (CO) |
| Keisha Robinson |
PPS Contracting Officer
| keisha.robinson@usda.gov |
| 404-347-2970 |
| Contracting Officer's Rep. (COR) |
| Wesley McCall |
Facilities Management Specialist
| wesley.mccall@usda.gov |
| 828-556-1665 |
| Facilities Access |
| Robin Staten |
Airtanker Base Manager
| robin.staten@usda.gov |
| 850-559-2838 |
| Gov't Technical Monitor (GTM) |
| Chris Cason |
RLEO/Engineering Technician
| christopher.cason@usda.gov |
| 386-623-5261 |
| Gov't Technical Monitor (GTM) |
| Brandon Roberts |
Facilities Program Manager
| brandon.roberts@usda.gov |
| 479-518-6010 |
| District POC |
| David Quisenberry |
Fire Management Officer
| david.quisenberry@usda.gov |
| 850-666-1806 |
| District POC |
| Thomas Scott |
District Ranger
| Thomas.scott@usda.gov |
| 386-288-9212 |
Contractor Requirements
2.0 Technical Requirements / Tasks
Unless otherwise specified, the Contractor is responsible for all materials, labor, equipment, supervision, safety, sampling, testing, records, disposal, valid licenses and certifications, and incidentals required to perform the Work and shall comply with all applicable federal, state, local, and authorities having jurisdiction (AHJ) laws, codes, policies, and regulations.
For Forest Service-owned facilities or facilities leased or rented where there is no applicable state or local building code, the following documents shall serve as “the code” for projects starting design on or after October 1, 2024. These codes are adopted as published and without local amendments:
· IBC: International Building Code, 2024
· IEBC: International Existing Building Code, 2024
· IFC: International Fire Code, 2024
· IFGC: International Fuel Gas Code, 2024
· IGCC: International Green Construction Code, 2024
· IPC: International Plumbing Code, 2024
· IMC: International Mechanical Code, 2024
· IWUIC: International Wildland-Urban Interface Code, 2024
· NFPA 70: National Electrical Code, 2023
· NFPA 101: Life Safety Code, 2024
· FBC: Florida Building Code, current edition In addition to the codes listed above, the following are also incorporated into the definition of “the code” for the purposes of this project, except for administrative provisions. For the standards below, the Authority Having Jurisdiction is the US Forest Service:
· ABAAS: Architectural Barriers Act (ABA) Standards
· ADA: Americans with Disabilities Act Standards for Accessible Design
· ASHRAE: American Society of Heating, Refrigerating and Air-Conditioning Engineers
· ISC: The Risk Management Process: An Interagency Security Committee Standard, 2024
· NFPA: National Fire Protection Association
1. OSHA: Occupational Safety and Health Administration
1. EPA: Environmental Protection Agency All demolition and mold remediation shall comply with the following current standards:
· IICRC S520 Standard and Reference Guide for Professional Mold Remediation
· NADCA ACR-2013 – Assessment, Cleaning and Restoration of HVAC Systems
· EPA 402-K-01-001 Mold Remediation in Schools and Commercial Buildings
· OSHA applicable standards for worker health and safety
· State of Florida mold remediation licensing requirements
· H2H Indoor Air Solutions Mold Assessment & Protocol Report (OID 11461, 08/06/2025)
· H2H Indoor Air Solutions Post-Remediation Clearance Report (OID 11991, 01/22/2026)
2.1 Submittals
The Contractor will furnish submittals on all project materials and obtain prior approval before installation. Submittals shall be made prior to and approved before purchasing and installing any work related to the respective submittal. Incomplete information on proposed items will result in rejection. The Contractor shall submit manufacturer’s information (cut sheets) via email as editable PDFs.
· Action Submittals: Written and graphic information that requires Government approval.
· Informational Submittals: Written information that does not require Government approval. Submittals may be rejected for not complying with requirements.
· Initial Review: Government will review initial submittal within 10 working days.
· Resubmittals: If a resubmittal is necessary, it will be processed in the same timeframe as the initial submittal.
Each submittal shall include:
1. Product name and model number
1. Manufacturer
1. Product description (include sizes if different from specified)
1. Technical data
1. Warranties
1. Proposed plan of work
1. Shop drawings (if applicable)
| Submittal Item |
| Required Before |
| Type |
| Contractor & subcontractor licenses, certifications |
| NLT 5 days after NTP |
| Informational |
| Proposed Project schedule |
| NLT 5 days after NTP |
| Informational |
| Site-specific safety plan |
| NLT 5 days after NTP |
| Informational |
| Pre-work photos |
| NLT 10 days after NTP |
| Informational |
| Post Remediation Verification Report |
| NLT 2 days after remediation complete |
| Informational |
| GFE Acceptance Letter |
| NLT 2 days after remediation complete |
| Informational |
| Mold Remediation Chain of Custody Manifest |
| NLT 2 days after remediation complete |
| Informational |
| Drywall & Cement Board |
| NLT 10 days after NTP |
| Action |
| Fasteners, screws, nails, incidentals |
| NLT 10 days after NTP |
| Action |
| Wall Vapor Barrier / WRB |
| NLT 10 days after NTP |
| Action |
| Insulation |
| NLT 10 days after NTP |
| Action |
| Primer, paints, adhesives, sealants, caulks |
| NLT 10 days after NTP |
| Action |
| Baseboard, molding, trim, transitions |
| NLT 10 days after NTP |
| Action |
| Appliances: stove, microwave, dishwasher, refrigerator |
| NLT 10 days after NTP |
| Action |
| Cabinetry & millwork shop drawings |
| NLT 10 days after NTP |
| Action |
2.2 Quality Control
Upon award of contract, coordinate with the COR. The Contractor shall provide personnel, including subcontractors, that satisfy the minimum qualifications required to complete the work, with the necessary expertise, licenses, certifications, and training to perform the work safely and in accordance with industry standards. All work shall be completed in a professional manner. The Contractor is responsible for providing any factory representatives, subcontractors, or consultants as needed at no additional cost to the Government. All materials and workmanship shall be of high quality, new, operable, and free from defects.
The Contractor shall perform work in a manner that will protect the safety of the public and employees. The building will not be occupied during construction. All quantities provided are approximate; the Contractor shall verify all existing quantities before bidding.
Repair or remove and replace construction that fails inspection. Restore damaged substrates and finishes. Repairing includes replacing defective parts, refinishing damaged surfaces, touching up with matching materials, etc.
The Contractor is responsible for protecting existing work, utilities, infrastructure, the building, surfaces, materials, equipment, etc., from damage because of its operations, and shall repair or replace any damaged items to the satisfaction of and at no additional cost to the Government.
The Contractor shall provide daily reports and photos to the COR until the contract is complete.
Notify the Contracting Officer’s Representative (COR) 48 hours before starting work. The COR is the primary point of contact for technical direction. The Contractor shall notify the COR immediately of any safety incident or unforeseen conditions.
The program shall ensure all work conforms to this PWS, applicable IICRC, EPA, OSHA, and NADCA standards, and all Federal and State regulatory requirements. The Government reserves the right to inspect all work at any time without prior notice.
2.3 Mold Remediation, Selective Demolition, and Cleaning
A. The Contractor shall perform work in accordance with the H2H Indoor Air Quality Reports, including the following tasks:
1. Contractor is responsible for verifying all estimated quantities provided upon award.
2. Contractor shall detach, clean, disinfect, and remove all furniture and appliances identified by the COR not identified for disposal from areas of construction, and place items in an on-site uncontaminated area for temporary storage.
a. Appropriate storage area will be identified by the COR to store items securely until re-installed.
b. Pack items to prevent damage during transport and storage.
c. After construction is complete, reinstall items in original locations.
3. Contractor shall properly cut and cap the water supply line to the exterior faucet where the leak occurred. This includes sealing the exterior penetration from weather and pest intrusion and installing an exterior cover for a finished appearance. Clean exterior block staining from the leak.
4. All disconnected plumbing components, including supply and DWV, shall be properly capped to prevent water damage and gases from entering the facility.
5. Contractor shall remove and properly dispose of all flooring materials:
a. Kitchen and Ready Room: 535 sf (VCT and Carpet)
b. Laundry and Janitorial Rooms: 140 sf (VCT)
6. Contractor shall remove and dispose of all drywall, insulation, materials, and trim from floor to ceiling on the highlighted walls on the floor plan:
a. Kitchen and Ready Room: 300 sf
b. Laundry and Janitorial Rooms: 300 sf
7. Contractor shall remove and dispose of all base and wall cabinets and millwork from the Kitchen and Laundry Rooms.
8. Contractor shall inspect all floors, wall cavities and framing, sheathing, and sill plates for structural integrity, moisture, damage, and mold growth. Contractor shall inspect all exterior ventilation independent of the HVAC system, including the kitchen range hood and dryer vent, for mold growth. If additional areas are determined to be affected, the Contractor must immediately notify the COR to identify additional removal and replacement required until all affected areas are addressed. No work can occur without prior written authorization by the CO.
9. Contractor shall follow, at a minimum, all recommendations and procedures provided in the H2H Reports, including the additional items for facility-wide cleaning and the HVAC system.
10. Contractor shall dispose of mold-contaminated materials per EPA and Florida DEP regulations. Provide disposal manifests to the COR.
11. Protect construction indicated to remain against damage and soiling during selective demolition.
12. Remove demolition waste materials from the project site and dispose of them at an approved waste landfill.
a. Do not allow demolished materials to accumulate on-site.
b. Return adjacent areas to the condition existing before selective demolition operations began.
2.4 Post-Remediation Clearance and Testing
A. Before calling for a clearance inspection, the Contractor shall confirm ALL of the following:
1. All remediation, encapsulation, and disposal are fully complete and all pre-clearance requirements have been met.
2. A written certification signed by the on-site supervisor shall be provided to the assessor and the COR confirming all pre-clearance conditions have been met.
B. Prior to reconstruction, the Contractor shall complete and pass testing as documented in the H2H Reports and provide a Post Remediation Verification (PRV) or Clearance Report verifying that remediation was successful.
C. Clearance shall be based on visual inspection, odor, containment condition, moisture measurements, and the air testing thresholds per H2H pass criteria and IICRC S520.
D. The licensed mold assessor shall collect spore trap air samples throughout the building as they determine appropriate. The assessor may add additional sample locations based on conditions observed during the visual inspection.
E. If the resultant PRV or Clearance Report determines the remediation has failed, the Contractor shall perform re-remediation or re-cleaning of the affected area(s) at no additional cost to the Government. This process shall repeat until a passing PRV is provided to the COR.
2.5 Reconstruction
A. General Requirements – The Contractor shall:
1. Install materials and construction in accordance with industry standards for commercial buildings and per manufacturer’s written instructions and recommendations.
2. All materials shall be new, commercial grade, and durable (moisture-resistant, high-impact, high-traffic/use scratch-resistant) and installed per manufacturer instructions and recommendations.
3. All materials shall be low-VOC, low-emitting products.
4. All new work to match existing materials and finishes unless specified otherwise.
5. Contractor shall identify and protect all existing fire-rated walls and assemblies. Restore all fire-rated wall and floor assemblies to their original rating. Verify all penetrations through fire-rated assemblies (electrical, plumbing, HVAC) are fire-stopped. All construction, including reconstruction, must maintain the integrity of fire-rated assemblies. Any new penetrations, modifications, or joints must be sealed appropriately.
6. All appliances shall be new, installed per manufacturer instructions and recommendations.
7. Field-verify dimensions affecting the work of this contract before ordering products. Locate the work and components of the work accurately, in correct alignment and elevation to fit with existing construction. Make vertical work plumb and make horizontal work level.
8. Clean the project site and work areas daily, including common areas. Dispose of materials lawfully offsite to an approved waste landfill.
9. Provide protection and maintain conditions that ensure installed work does not get damaged or deteriorated prior to Substantial Completion acceptance by the COR.
10. Protect installed products from damage until project completion.
11. Prepare all surfaces, joints, and substrates per manufacturer’s written instructions and recommendations, including but not limited to grinding, leveling, patching, primers, filling, cleaning, removal of coatings and chemicals, and moisture protection, to ensure clean, uniform, smooth, and seamless surfaces appropriate for installation of new work indiscernible from existing surfaces and conditions.
12. Provide manufacturer’s warranty and maintenance instructions.
B. Moisture-Resistant Wall Assembly
1. Inspect all remaining wood framing and sill plates for structural integrity; if any member shows visible decay, splitting, or structural compromise, notify the COR immediately.
2. Verify all framing members are dry (≤19% MC) before enclosing walls.
3. Install a continuous vapor-permeable, water-resistive barrier (WRB) over all exposed lumber framing prior to drywall to match existing.
4. Provide and install 5/8” (match existing) moisture- and mold-resistant gypsum board on all affected walls from floor to ceiling.
a. All drywall shall meet ASTM C1396 standards for gypsum board and be GREENGUARD certified for low emissions.
b. Panels shall feature fiberglass mat facing on both sides for enhanced mold resistance and durability in high-humidity environments.
5. Tape, mud, and finish to a smooth surface ready for paint, ensuring proper joint treatment.
6. Apply two coats of primer and two coats of low-VOC finish paint to all reconstructed wall surfaces to match in kind.
7. Provide and install baseboard molding and window and door trim to match existing.
8. Final approval for finish colors to be approved by the COR prior to purchase and installation.
C. Flooring
1. Remove any remaining debris and prepare the substrate for installation for commercial luxury vinyl tile (LVT) flooring.
2. Commercial grade LVT, minimum 20 mil wear surface, minimum 4.5 mm thick, non-slip, minimum 10 year commercial wear warranty.
a. Interface LVT Textured Stones 4.5mm Dark Concrete A00310 or approved equal https://shop.interface.com/US/en-US/resilient/lvt/textured-stones-4.5-mm/A003R.html
3. Install moisture barrier for moisture protection and LVT flooring in the Kitchen, Ready Room, and Laundry Room. Janitorial Closet floor tile to remain in place.
4. Contractor shall provide and install thresholds between all flooring transitions.
5. Provide manufacturer’s warranties and maintenance instructions.
D. Cabinetry and Millwork
1. Install new base and wall cabinets in the Kitchen, and a base cabinet and countertop in the Laundry Room. Final cabinetry and millwork layout must be approved by the COR prior to purchase and installation.
2. Kitchen cabinetry and countertops includes plumbing, stainless steel sinks, faucets, and sprayer for a complete and functional kitchen.
3. Cabinets shall be high-quality plywood (no particleboard or MDF) with moisture-resistant finish, ¾” minimum thickness (sides/top/bottom), ½” back, no staple-only assembly. Cabinet type, color or stain shade shall be approved by the COR prior to purchase and installation.
4. Countertops will be solid surface Corian, ½” minimum thickness, color matched seams, matte finish, NSF/ANSI 51 certified for food contact, minimum 10 year warranty. Color shall be approved by the COR prior to purchase and installation.
5. Contractor shall provide and install all blocking and backing required to mount and support the cabinetry, millwork and countertops.
6. All installations shall comply with ADA accessibility requirements.
E. Appliances
1. Contractor shall furnish and install the following new appliances in the Kitchen:
a. Refrigerator
b. Electric stove
c. Over-the-range microwave (with vent hood)
d. Dishwasher
2. Appliances shall be free-standing, commercial stainless steel, matt finish, energy start certified, minimum 5 year warranty.
a. GE Appliances or approved equal https://www.homedepot.com/p/sets/GE-Profile-22-3-cu-ft-Counter-Depth-Refrigerator-with-4-Burner-Induction-Range-and-Dishwasher-with-Custom-Wash-Cycles/337934087
3. Provide all manufacturer documentation and warranties.
F. Mechanical, Electrical, and Plumbing (MEP)
1. Reseat and secure all HVAC vents and returns to fit properly.
2. Reconnect all supply and drain lines; verify no leaks before wall closure.
3. Verify dryer duct and stove hood vent is properly routed and terminated at the exterior.
G. Final Cleaning
1. Provide final cleaning. Conduct cleaning and waste-removal operations in compliance with local laws and ordinances and Federal and local environmental and antipollution regulations.
2. Use cleaning materials and agents recommended by the manufacturer or fabricator of the surface to be cleaned. Do not use cleaning agents that are potentially hazardous to health or property or that might damage finished surfaces.
3. Complete cleaning operations to the level of move-in ready for the Government before requesting final inspection.
2.6 Special Requirements
All post-construction clearance testing shall be performed by a licensed Florida mold assessor. H2H Indoor Air Solutions has provided all previous pre- and post-assessments for the work. For continuity, H2H Indoor Air Solutions is the preferred assessor, but any qualified licensed mold remediation assessor is acceptable.
2.7 Safety
The Contractor shall assume full responsibility and liability for compliance with all applicable codes, standards, and regulations pertaining to the health and safety of personnel during execution of the Work. The Contractor shall take all necessary precautions to ensure safety for the specific site conditions and limitations, and to prevent injury to their employees, the public, occupants, or damage to property during execution of the Work.
The Contractor shall provide a copy of a site-specific safety plan to the COR as an informational submittal no later than 5 days after receipt of the Notice to Proceed (NTP).
2.8 Site Information and Limitations
The site is a Government land lease at the Lake City Gateway Airport and is subject to the security and access requirements of the lessor. The site and building have limited access due to airport security requirements. Vehicles and personnel coming and going from the site are closely monitored.
Transportation Security Administration (TSA) Badge Policy compliance is required at the Lake City Gateway Airport. Personnel within airfield security fences must display a current Airport Authority-issued TSA badge. Unbadged personnel must be escorted. Badged Forest Service personnel will provide escort and access to contractor personnel.
The site is a government fire and aviation facility that supports wildland fire operations including helicopters, planes, and air tanker operations. The site is currently operational. Confine construction operations to the immediate area of work. Do not disturb portions of the project site beyond areas in which the Work is indicated. Keep driveways, parking areas, loading areas, and entrances to buildings and other adjacent areas to occupied facilities clear and available to the Government, Government employees, and emergency vehicles at all times. Do not use these areas for parking or storage of materials.
The Government will remain vacated from the building during the entire contract period of performance. Perform the work so as not to interfere with the Government’s day-to-day operations on the site.
Typical operating hours are Monday through Friday, 8:00 AM – 4:30 PM. The Contractor shall perform the work during operating hours, excluding Federal Holidays, unless prior arrangements have been made with the COR.
Any required utility outages must be requested and coordinated with the COR at least 48 hours in advance of the outage.
Use of Government existing facilities will be permitted without metering and without payment of use charges, as long as facilities are cleaned and maintained in an acceptable condition. The site has cellular coverage. The Government can provide the Contractor access to restrooms, water, sewer, and electric services while on site performing work. All access shall be coordinated with the COR.
The Contractor is responsible for providing waste-collection containers in sizes and types adequate to handle waste from construction operations. Containerize and clearly label hazardous, dangerous, or unsanitary waste materials separately from other wastes.
2.9 Contract Closeout
The Contractor shall provide all technical data and warranty information for the materials provided.
The Contractor shall provide a minimum warranty of one (1) year on workmanship and shall register the manufacturer’s warranty for all materials and appliances.
Final acceptance will occur after a final inspection performed by the COR confirming compliance with the Contract.
3.0 Government Furnished Information, Property & Services
The Government will provide the following items of Government Information, Property, and/or Services to the Contractor for use in the performance of this contract. Property shall be used and maintained by the Contractor and returned upon completion of the Work prior to final payment.
A. Property – Not Used B. Information
1. Floor Plan (with highlighted areas)
2. Exterior and Interior Photos
3. H2H Indoor Air Solutions Mold Assessment & Protocol Report, 08/06/2025
4. H2H Indoor Air Solutions Post-Remediation (Clearance) Assessment Report, 01/22/2026 C. Services – Not Used
4.0 Period of Performance
The Contractor must begin work no later than (NLT) 10 calendar days after the award and receipt of the Notice to Proceed (NTP). The Period of Performance for this project shall include a base period of 60 days from the issuance of the NTP.
Item 0001 Base Period Anticipated PoP 60 days
4.1 Pre-Bid/Pre-Proposal Conference
The Government is planning a pre-bid/pre-proposal conference. The building interior cannot be accessed during the site visit due to the mold present. In no event shall failure to inspect the site and buildings constitute grounds for a contract modification or claim.
4.2 Inspection of Work Site
The Contractor acknowledges they have taken the necessary steps to ascertain the nature and location of the work and have investigated and satisfied themselves as to the general and local conditions that can affect the Work or its cost. Any failure of the Contractor to take the actions described and acknowledged in this paragraph will not relieve the Contractor from the responsibility of estimating properly the difficulty and cost of successfully performing the work, or for proceeding to successfully perform the work without additional expenses to the Government.
5.0 Deliverables / Schedule
| Item No. |
| Deliverable |
| Objective |
| Due Date |
| 1 |
| Proposed Project Plan/Schedule |
| Provides specific site location, dates, and sequencing for coordination and communication |
| 5 Days after NTP |
| 2 |
| Certifications/Licenses/Credentials |
| Provide copies of all accreditations, certifications, and licenses of professionals performing the work |
| 5 Days after NTP |
| 3 |
| Submittals |
| Provide contract submittals prior to purchase and installation for review and/or approval; provide post-remediation reports |
| Prior, during, and after each phase |
| 4 |
| Post-Remediation Report(s) |
| Written Post-Remediation Verification (PRV) / clearance letter from the licensed mold assessor to authorize reconstruction |
| Prior to reconstruction phase |
| 5 |
| Daily Reports & Photos |
| Contractor provides COR with daily progress reports and supporting photos throughout performance |
| Daily during all active work |
| 6 |
| Final Inspection |
| Completed and approved punch list by COR after reconstruction activities, prior to final cleaning |
| 45 Days after NTP |
| 7 |
| Final Acceptance & Closeout Package |
| Final walkthrough, COR acceptance, and submission of all warranties, manifests, and as-built documentation confirming building ready for occupancy |
| 60 Days after NTP |
6.0 Payment
The Contractor must have an active registration in SAM.gov prior to award.
The Contractor understands and agrees that the maximum total amount payable for the services must not exceed the amount approved and authorized by the Government unless a formal written amendment is executed and formally approved by the Government prior to commencement of the Work. The Government will not pay for any services nor distribute any funds that would exceed the contracted amount.
Measurement and payment for contract work will be made only for and under those pay items included in the Schedule of Items. All other work, labor, materials, equipment, and incidentals necessary to successfully complete the Work will be considered as included in the payment for items shown. All work not specifically identified as a separate bid item is “Incidental.”
This is a Firm-Fixed Price Contract. The pay unit included in the Schedule of Items shall include all costs required to complete the work and bring the building back to fully operational status that can be occupied by employees.
7.0 Contractor’s Key Personnel
The Contractor will provide all necessary qualified and accredited personnel to perform the Work as necessary for safe operations and to ensure that all work is conducted in conformance with the Contract and to the level of quality specified.
7.1 Contractor’s Qualifications
A. The Contractor must provide documentation of:
5. Valid Florida Mold Remediator license.
6. Required licensed/certified specialist identified in the H2H Indoor Air Solutions Reports.
7. Minimum of 10 years of experience in commercial mold remediation and commercial building construction of equal or greater complexity and scale necessary to perform the Work.
8.0 Security Requirements
The Contractor shall comply with site security protocols and provide a personnel list for access clearance, to include any subcontractors. Transportation Security Administration (TSA) Badge Policy compliance is required at the Lake City Gateway Airport. Personnel within airfield security fences must display a current Airport Authority-issued TSA badge. Unbadged personnel must be escorted. Badged Forest Service personnel will provide escort services to contractor personnel.
All Contractor personnel performing on-site work shall wear visible, identifiable company badging or clothing at all times while in Government facilities.
9.0 Data Rights
Not Used
10.0 Section 508 – Electronic and Information Technology Standards Not Used
11.0 Quality Assurance Surveillance Plan (QASP) / Acceptable Quality Levels (AQL) This QASP establishes the Government’s method for evaluating contractor performance against the requirements of this PWS. The Contracting Officer’s Representative (COR) is responsible for conducting surveillance as described below. Performance standards designated as “Critical” represent zero-defect requirements; any failure shall result in immediate stop-work, re-performance at no cost, and documentation in the contractor’s performance record. Performance standards designated “High” allow for a single notice of non-conformance before a cure notice is issued. “Medium” weight items are monitored and may affect the contractor’s past performance evaluation.
| PWS Ref. |
| Performance Objective |
| Performance Standard / AQL |
| Surveillance Method |
| Incentive / Remedy |
| Weight |
| 2.4.B–E |
| All mold remediation and selective demolition completed per H2H Reports and EPA/IICRC S520 standards |
| Zero visible mold; all affected materials removed per protocol |
| Licensed third-party mold assessor pre-clearance walkthrough and post remediation verification pass results |
| Contractor re-remediates at no cost until passed; reconstruction cannot begin until passing PRV |
| Critical |
| 2.5.B |
| Post remediation reconstruction phase start |
| Demolished materials removed and properly disposed, substrates prepped for new construction |
| COR inspection before close-up and finishes applied |
High
| 2.5 |
| Wall assembly complete (WRB, insulation, drywall) including finish paint |
| Smooth finish, no drips, overspray, visible joints or seams |
| COR visual inspection at finish stage |
| Contractor re-finishes non-conforming areas marked during inspection at no cost |
| Medium |
| 2.5 |
| Flooring complete including moisture barrier |
| No gaps, buckling, bumps, or significant observable damage (gouges, scratches, stains) |
| COR inspection with the Contractor after installation |
| Defective, damaged or incorrectly installed LVT removed and replaced at no cost |
| High |
| 2.5 |
| Kitchen and laundry cabinetry, millwork and countertops installed per layout approved by COR |
| All items level, plumb, properly secured; ADA-compliant; layout completed per approved shop drawings |
| COR inspection with the Contractor after installation |
| Defective, damaged or incorrectly installed cabinetry, millwork and countertops repaired for re-inspection and approval |
| High |
| 2.5 |
| New appliances installed and operational |
| All four appliances (refrigerator, electric stove, OTR microwave, dishwasher) installed |
| COR functional test at final inspection |
| Non-functional appliances repaired prior to final acceptance |
| High |
| 2.5 |
| MEP reconnections completed and verified leak-free |
| HVAC registers reseated; washer/dryer connections leak-free; dryer duct and hood vent properly routed and terminated at exterior; verified prior to wall closure |
| COR inspection prior to drywall close-up and at final walkthrough |
| Deficiencies corrected prior to drywall close-up |
| High |
| 2.1 |
| All required submittals delivered on schedule and approved before installation |
| 100% action submittals approved before purchase/installation |
| COR review submittal log |
| Non-compliant installations without prior approval removed and replaced |
| Medium |
| 2.2 |
| Daily reports and photos provided throughout performance |
| 95% compliance; less than 5 missed daily reporting days during active work |
| COR review of daily reports |
| Withhold partial payment; document in performance record |
| Medium |
| 5.0 |
| Project completed within Period of Performance |
| Substantial completion by 45 Days after NTP; final acceptance by 60 Days after NTP |
| COR approval of punch list and final acceptance inspection |
| Performance record notation |
| High |
Note: This QASP is incorporated into the contract. The COR shall document all surveillance activities in a Surveillance Activity Checklist (SAC) and provide copies to the Contracting Officer. Any finding of non-conformance shall be documented in writing and provided to the Contractor within 24 hours of identification. Contractor responses to cure notices are due within 48 hours of receipt.
12.0 Attachment(s)
· Attachment 1 – Floor Plan (with highlighted areas)
· Attachment 2 – Exterior and Interior Photos
· Attachment 3 – H2H Indoor Air Solutions Mold Assessment & Protocol Report, 08/06/2025
· Attachment 4 – H2H Indoor Air Solutions Post-Remediation (Clearance) Assessment Report, 01/22/2026 image1.png