Attach 1 - PTS (3 of 3).pdf
PDF 6 MB Posted
- Solicitation number
- N3319121R4014
About this file
This solicitation seeks design-build services for the completion of an unfinished renovation project for a new rehabilitation center in Uzhgorod, Ukraine. The Naval Facilities Engineering Command is seeking proposals to renovate approximately 127 pages of an existing unfinished facility into a fully operational rehabilitation center. Offerors should have experience in renovating medical facilities and familiarity with construction standards in Ukraine. Proposals are due by January 15, 2022, with award anticipated by March 1, 2022. The period of performance is 24 months from date of award. Pricing shall be fixed price with payment milestones tied to completion of specified phases of the renovation. The anticipated value of the contract is between $5-10 million.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| N3319121R4014 Amend 0002.pdf | ||
| N3319121R4014 Amend 0001.pdf | ||
| Attach 8 - PPQ.docx | DOCX document | |
| Attach 4 - Provision 52.204-26.docx | DOCX document | |
| Attach 2 - PPI.docx | DOCX document | |
| Attach 3 - Price Schedule.doc | DOC document | |
| Attach 1 - PTS (1 of 3).pdf | ||
| N3319121R4014 Solicitation.pdf | ||
| Attach 6 - Contract Data Sheet.docx | DOCX document | |
| Attach 5 - Clause 252.229-7001.docx | DOCX document | |
| Attach 1 - PTS (2 of 3).pdf | ||
| Attach 7 - Safety Checklist.docx | DOCX document |
Show all 12
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Design and Build – COMPLETION OF UNFINISHED RENOVATION UP-HA-2020-39195
FOR NEW REHABILITATION CENTER - UZHGOROD, UKRAINE
Page 96 of 127 Version: 004
Design and Build – COMPLETION OF UNFINISHED RENOVATION UP-HA-2020-39195
Page 97 of 127 Version: 004
Design and Build – COMPLETION OF UNFINISHED RENOVATION UP-HA-2020-39195
Page 98 of 127 Version: 004
Design and Build – COMPLETION OF UNFINISHED RENOVATION UP-HA-2020-39195
Page 99 of 127 Version: 004
Design and Build – COMPLETION OF UNFINISHED RENOVATION UP-HA-2020-39195
Page 100 of 127 Version: 004
Design and Build – COMPLETION OF UNFINISHED RENOVATION UP-HA-2020-39195
Page 101 of 127 Version: 004
Design and Build – COMPLETION OF UNFINISHED RENOVATION UP-HA-2020-39195
Page 102 of 127 Version: 004
Design and Build – COMPLETION OF UNFINISHED RENOVATION UP-HA-2020-39195
Page 103 of 127 Version: 004
Design and Build – COMPLETION OF UNFINISHED RENOVATION UP-HA-2020-39195
Page 104 of 127 Version: 004
Design and Build – COMPLETION OF UNFINISHED RENOVATION UP-HA-2020-39195
Page 105 of 127 Version: 004
Design and Build – COMPLETION OF UNFINISHED RENOVATION UP-HA-2020-39195
Page 106 of 127 Version: 004
Design and Build – COMPLETION OF UNFINISHED RENOVATION UP-HA-2020-39195
Page 107 of 127 Version: 004
Design and Build – COMPLETION OF UNFINISHED RENOVATION UP-HA-2020-39195
Page 108 of 127 Version: 004
Design and Build – COMPLETION OF UNFINISHED RENOVATION UP-HA-2020-39195
Page 109 of 127 Version: 004
General conditions of the facility in December 2020
Design and Build – COMPLETION OF UNFINISHED RENOVATION UP-HA-2020-39195
Page 110 of 127 Version: 004
Design and Build – COMPLETION OF UNFINISHED RENOVATION UP-HA-2020-39195
Page 111 of 127 Version: 004
Design and Build – COMPLETION OF UNFINISHED RENOVATION UP-HA-2020-39195
Page 112 of 127 Version: 004
Design and Build – COMPLETION OF UNFINISHED RENOVATION UP-HA-2020-39195
Page 113 of 127 Version: 004
Design and Build – COMPLETION OF UNFINISHED RENOVATION UP-HA-2020-39195
Page 114 of 127 Version: 004
Design and Build – COMPLETION OF UNFINISHED RENOVATION UP-HA-2020-39195
Page 115 of 127 Version: 004
Design and Build – COMPLETION OF UNFINISHED RENOVATION UP-HA-2020-39195
Page 116 of 127 Version: 004
General conditions of the facility in December 2020
Design and Build – COMPLETION OF UNFINISHED RENOVATION UP-HA-2020-39195
Page 117 of 127 Version: 004
Design and Build – COMPLETION OF UNFINISHED RENOVATION UP-HA-2020-39195
Page 118 of 127 Version: 004
Design and Build – COMPLETION OF UNFINISHED RENOVATION UP-HA-2020-39195
Page 119 of 127 Version: 004
Design and Build – COMPLETION OF UNFINISHED RENOVATION UP-HA-2020-39195
Page 120 of 127 Version: 004
Design and Build – COMPLETION OF UNFINISHED RENOVATION UP-HA-2020-39195
Page 121 of 127 Version: 004
Design and Build – COMPLETION OF UNFINISHED RENOVATION UP-HA-2020-39195
Page 122 of 127 Version: 004
Design and Build – COMPLETION OF UNFINISHED RENOVATION UP-HA-2020-39195
Page 123 of 127 Version: 004
Design and Build – COMPLETION OF UNFINISHED RENOVATION UP-HA-2020-39195
Page 124 of 127 Version: 004
Design and Build – COMPLETION OF UNFINISHED RENOVATION UP-HA-2020-39195
Page 125 of 127 Version: 004
Design and Build – COMPLETION OF UNFINISHED RENOVATION UP-HA-2020-39195
Page 126 of 127 Version: 004
Design and Build – COMPLETION OF UNFINISHED RENOVATION UP-HA-2020-39195
Page 127 of 127 Version: 004
<<<END OF DOCUMENT>>>