Attach 01 PWS WW Chiller repairs.pdf

PDF 127 KB Posted

Attached to
Repair Chillers on Building 6 OCPARC Woodward OK
Solicitation number
12805B23Q0544
Issued by

About this file

This performance work statement outlines repairs required for two chillers on the roof of Building 6 at the USDA Agricultural Research Service location in Woodward, Oklahoma. The repairs include replacing compressor components on Chiller 1 and replacing three condenser fan motors and contactors on Chiller 2. Bidders are advised to visit the site and familiarize themselves with the conditions. The contractor will furnish all labor, tools, equipment, transportation and materials except what is explicitly listed as government furnished. Successful completion of the work within 45 days of award is required. Standard warranties and safety plans are also addressed.

The related federal contract opportunity is a solicitation issued by the USDA Agricultural Research Service Plains Area to obtain repair services for the two chillers as detailed in the attached performance work statement. Bids are due by the date specified in the solicitation.

View the file

Other files

File Type Posted
Attach 03 Bid Schedule Fillable.xlsx XLSX spreadsheet
Attach 04 Fill In Biobased Statement Letter.docx DOCX document
12805B23Q0544 RFQ Chiller Repairs.pdf PDF
Attach 03 Bid Schedule Fillable.xlsx XLSX spreadsheet
Attach 04 Fill In Biobased Statement Letter.docx DOCX document
Attach 02 Wage Determinatin Woodward OK.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

USDA ARS OCPARC-Woodward 2000 18th St., Woodward, Oklahoma 73801

Performance Work Statement Chiller #1 and Chiller #2 repairs

SECTION 01010 ‐ SCOPE OF WORK

A. GENERAL: It is the intent of these general conditions, specifications, together with the contract, to include all labor, materials, equipment, transportation, permits and fees, temporary protection and supervision necessary to complete the required work. All work shall be done under the direction of and completion to the satisfaction of the Contracting Officer.

1. Project Description:

Replace compressor A2 and B1 on chiller #1: Carrier chiller S/N: 3703F54063.

Replace 3 condenser fan motors, blades, and contactors on chiller #2: Carrier chiller S/N:

3703F54062.

Both chillers are on the roof top of Building 6 located at 2000 18th St., Woodward, Oklahoma 73801.

Chiller #1 work includes:

1‐1. Recover refrigerant from both circuits and store for reuse in unit.

1‐2. Disconnect and remove defective A2 and B1 compressors.

1‐3. Install new OEM compressors on each circuit.

1‐4. Leak check each circuit with dry nitrogen.

1‐5. Evacuate each circuit and charge with previously recovered refrigerant.

1‐6. Start chiller and verify proper operation.

1‐7. Note any additional repair needs found.

1‐8. Clean up jobsite. Off‐site disposal is the contractor’s responsibility. Some of the equipment/parts being replaced may be of use to the facility. Maintenance staff will be allowed to keep some/any of the removed equipment/parts for facility needs.

Chiller #2 work includes:

1‐1. Disconnect and remove the 3 (B 1‐3) defective condenser fan motors and contactors.

1‐2. Install 3 new OEM fan motors, blades, and contactors.

1‐3. Start chiller and verify proper operation.

1‐4. Note any additional repair needs found.

1‐5. Clean up jobsite. Off‐site disposal is the contractor’s responsibility. Some of the equipment/parts being replaced may be of use to the facility. Maintenance staff will be allowed to keep some/any of the removed equipment/parts for facility needs.

The contractor shall furnish all labor, tools, equipment, transportation to the job site, and supervision for the job indicated above. The contractor shall furnish all material except material listed in the government furnished material section of this document.

2. Government Furnished Equipment: None

3. Site Visit: Recommended

4. Codes and Standards: Construction shall comply with the requirements of ARS Facilities Design Standards Manual 242.1, ARS Energy Management Plan 134.2 and all other applicable federal, state and local code requirements as well as current industry standards, (ie. UBC, UPC, NFPA, UL, ASTM, ACI, NEC, NEMA., etc,) and health and safety codes, in effect at the time of contract award. ARS Design and construction manuals can be found on the website under “P&P and Manuals” at http://www.afm.ars.usda.gov/facilities/pplist‐FD.htm.

5. Permits: Where governing regulations and imposed codes and standards require notices, permits, licenses, inspections, tests, and similar items or actions in order to lawfully proceed with the required work, Contractor shall obtain items and take those actions in accordance with the regulations of the governing authority. The costs of such permits, licenses, inspections, etc., are the responsibility of the Contractor.

6. Application: It shall be the responsibility of the Contractor to perform all work in accordance with the manufacturers’ recommendations and Industry Standards. If any item specified herein and/or on the drawings conflicts with applicable codes and recommendations, the contractor shall bring it to the attention of the Contracting Officer for immediate resolution.

SECTION 01050 ‐ FIELD ENGINEERING/INSPECTION OF SITE

A. The Contractor shall be responsible for verifying site conditions, making quantity take‐offs, obtaining accurate measurement of existing conditions, and performing any act or operation which may be necessary to properly bid the work and complete the same as depicted and specified. Failure to verify the existing site conditions shall not relieve the Contractor of the responsibility to complete the work as required.

SECTION 01300 ‐ SUBMITTALS

A. Manufacturer's descriptive literature sufficient to determine conformance of the proposed product to the contract requirements shall be submitted to the CO for review and approval. The descriptive literature shall be annotated/highlighted to show its conformance with contract requirements.

B. Installation procedures supplied by the manufacturer.

SECTION 01400 ‐ QUALITY CONTROL

A. GENERAL: To satisfy the requirement for Quality Control, the work performed under this contract shall be subject to continuous audit by the Location Site Monitor (LSM). Quality control is the exclusive responsibility of the Contractor.

B. FINAL ACCEPTANCE: Acceptance of the completed work will be based upon its conformance to the contract.

C. WARRANTY: The warranty period for workmanship shall be for one (1) year from the date the government accepts the work.

SECTION 01525 ‐ SAFETY REQUIREMENTS

A. The Contractor shall implement, and provide to the Contracting Officer (CO) for review, a site specific, SITE SAFETY AND HEALTH PLAN in accordance with all local, state and federal regulations. The plan shall address, at a minimum all responsible parties by name, all safety/health hazards, personal protective equipment and other hazard controls, all required training, emergency procedures, and other required information to perform the work. The plan shall be implemented by contractor supervisor signature. Two copies shall be provided to the Contracting Officer and one copy will be maintained at the site. In the event of changing site conditions or hazards, the plan shall be appended in writing and a copy of the change provided to the CO and COR.

SECTION 01545 ‐ PROTECTION OF WORK AND PROPERTY

A. The Contractor shall protect the work, the site, and all existing property and structures within the limit of construction activities or that may be affected thereby until acceptance of the work.

Any damage to property shall be repaired at the Contractor’s expense, to pre‐damaged condition to the satisfaction of the COR.

B. Safety and health matters, as they relate to the work, are the exclusive responsibility of the Contractor. The Contractor shall furnish, erect, and maintain barricades, warning lights, signs, guards, or take other precautions as may be required by law or local authorities for protection and security.

SECTION 01560 ‐ TEMPORARY FACILITIES

A. Temporary utilities (water and electricity) will be furnished to the Contractor by the Government, if so requested. Contractor shall maintain and protect all such utilities during the course of construction and shall repair or replace any items damaged through is own negligence.

B. Should the Contractor require any power or utility shutdown during construction, he shall receive approval for such shutdown from the LSM three working days prior to this need.

SECTION 01600 ‐ MATERIALS AND EQUIPMENT

A. The material and equipment to be furnished under these contract documents shall be the standard products of manufacturers regularly engaged in the production of such materials and equipment and shall be the manufacturer's latest standard design.

B. All materials and equipment to be incorporated in the work shall be handled and stored by the manufacturer, fabricator, supplier and Contractor before, during and after shipment in a manner to prevent warping, twisting, breaking, chipping, rusting and any injury, theft or damage of any kind whatsoever to the materials and equipment. All materials and equipment furnished by Contractor shall be subject to inspection and approval by the CO/LSM.

D. EXECUTION:

(a) The Contractor shall provide the necessary tools, equipment, labor, coordination, and related materials necessary for the completion of work.

(b) Erection techniques employed by the Contractor must be in accordance with the manufacturing company's suggested erection procedures. Work is expected to be completed no later than 45 days after notice of award.

SECTION 01710 ‐ CLEANING

Upon completion of project, and prior to final inspection, the Contractor shall remove from the premises all unused material, trash, and debris resulting from the work to the satisfaction of the

LSM.

SECTION 01711 – WARRANTY

Submit data concerning the standard one year warranty for workmanship, including the warranty period (dates), and warranty contacts with names, addresses and telephone numbers.

Extended Equipment/Product Warranties: Obtain and furnish to the Contracting Officer all written warranties for equipment/products that have extended warranties (warranty periods exceeding the standard one‐year warranty) furnished under the contract. The warranty period shall begin on the same date as project acceptance and shall continue for the full/product warranty period. The warranties shall be fully executed and delivered to the Contracting Officer prior to final acceptance of the facility.