This is a Statement of Work (SOW) for Solicitation No. 140R3026Q0038 issued by the Bureau of Reclamation's Lower Colorado Dams Office (LCDO) Security Office. The project involves the installation of a new Vessel Exclusion Barrier (VEB) Gate at Hoover Dam to replace an existing waterborne gate that has failed on the lakeside boom line. The government-owned gate was previously purchased from Worthington Products and is currently stored at the Hoover Dam Warehouse. The contractor must install this fully operational waterborne vessel gate and verify that all components of the exclusion barrier are serviceable and operational upon completion.
The contractor must possess a minimum of three years of field experience in the assembly, installation, and verification of Worthington Products. Two deliverables are required, both due 30 days from contract award and deliverable to the LCDO: (1) installation of the existing gate ensuring effective operation and compliance with safety standards, and (2) repair and servicing of existing barriers with certification that all components are operational and meet required standards. The contractor is responsible for all travel costs. Critical security requirements apply given Hoover Dam's National Critical Infrastructure designation; all work requires prior approval from the NCI Security Manager, and contractor employees are subject to security checks. Contractor-produced information is classified as Public Information (Non Official-Use-Only), except for government-furnished work products designated Official Use Only – SENSITIVE (FOUO/SENSITIVE). The Contracting Officer's Technical Representative is Mr. Dwayne Privott, Bureau of Reclamation, Lower Colorado Dams Office, Hoover Dam, (702) 494-2210, dprivott@usbr.gov.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Attachment 1 - Statement of Work
(SOW)
Solicitation No.
140R3026Q0038
Project Title Lakeside Vessel Barrier Gate Repair at Hoover Dam
ATTACHMENT 1 - STATEMENT OF WORK (SOW)
Lakeside Vessel Barrier Gate Repair at Hoover Dam
1.0 INTRODUCTION:
1.1 Office Name/Designation: Lower Colorado Dams Office (LCDO), Security Office
2.0 SCOPE: Installation of Vessel Exclusion Barrier Gate: The LCDO Security Officer at Hoover Dam requires the Contractor to install the new Vessel Exclusion Barrier (VEB) Gate, which is already at the Hoover Dam Warehouse, to replace the existing waterborne gate, which has unfortunately failed on the Hoover Dam lakeside boom line. This installation is crucial to maintaining the integrity and effectiveness of our security measures on site.
3.0 PERSONNEL QUALIFICATIONS: Contractor personnel must possess the qualifications and training necessary to conduct thorough inspections and certifications of existing parts already in government possession. Candidates should have a minimum of three years of field experience in the assembly, installation, and verification of Worthington Products, ensuring they are well-equipped to maintain the highest standards of quality and compliance.
4.0 GOVERNMENT-FURNISHED EQUIPMENT (GFE) AND MATERIALS:
4.1 GFE: None.
4.2 Government Furnished Materials: The existing materials consist of Worthington Products, specifically the Tuffboom gate assembly. Additionally, any necessary parts (e.g. spare floatation barrel, netting and bards) required to repair the VEB may also be available to help enable timely repairs as identified during inspections.
5.0 REGULATIONS/POLICIES: No specific apply
6.0 TRAVEL: The Contractor will cover all travel cost for this effort.
7.0 GOVERNMENT VEHICLES: N/A
8.0 SECURITY: All work must receive prior approval from the National Critical Infrastructure (NCI) Security Manager before commencement. Given that Hoover Dam is designated as a NCI, any proposed activities will inherently increase risk and must be thoroughly mitigated to ensure the safety and security of the facility.
8.1 The Project Manager or Contracting Officer’s Technical Representative (COR) listed in paragraph 13.0 will assist with the Contractor’s entry into secure areas and inform the Contractor of security procedures. The Contractor shall comply with all security procedures.
8.2 Reclamation has identified specific security sensitivity designations for information related to Government facilities.
8.3 All contractor produced and Government furnished information related to this contract is designated Public Information (Non Official-Use-Only), except for the Government furnished work products which are designated Official Use Only – SENSITIVE (FOUO/SENSITIVE).
8.4 The Contractor shall be required to supply Reclamation with the legal names and other
Attachment 1 - Statement of Work
(SOW)
Solicitation No.
140R3026Q0038
Project Title Lakeside Vessel Barrier Gate Repair at Hoover Dam personal information of employees who will be working under this contract.
8.5 Reclamation reserves the right to perform security checks on Contractor employees.
9.0 TRAINING: N/A
10.0 DELIVERABLES: The contractor will install a fully operational waterborne vessel gate, which was acquired through a previous purchase from Worthington Products and is already on site at Hoover Dam. Additionally, the Contractor shall verify and make necessary adjustments to the existing boom line to ensure that all components of the exclusion barrier are serviceable and fully operational upon completion of the project.
10.1 Deliverable #1 Install existing gate: The Government-owned waterborne vessel exclusion barrier gate shall be installed, ensuring effective operation and compliance with safety standards.
10.2 Deliverable #2 Repair and service barriers: Conduct a thorough inspection and servicing of existing barriers using Government-Furnished Materials. Certify that all components are operational and meet required standards upon completion of the contract.
10.3 Deliverable Table:
PARA. DELIVERABLE DUE DELIVER TO
10.1 Install existing gate 30 days from award LCDO
10.2 Repair and service barriers 30 days from award LCDO
11.0 QUALITY: The contractor will verify that the existing replacement gate is operational and can be installed prior to the installation process. They will also ensure that the boom line is fully functional and meets the established security requirements for this specific security device, as documented according to the manufacturer's specifications.
11.1 Contractor’s Performance Assessment Reporting System (CPARS). A Contractor Performance Report may be completed by the COR at the end of the performance period. If completed, this information will be input into the CPARS website, which can be accessed at:
https://www.cpars.gov/cparsweb/home
12.0 IDENTIFICATION OF CONTRACTOR EMPLOYEES: All contract personnel are required to identify themselves as contractors. Whether attending meetings, answering Government telephones, or working in other situations where their contractor status is not obvious to third parties, they must make their status known to avoid creating an impression that they are Government employees.
13.0 POINTS OF CONTACTS (POC):
Contracting Officer’s Representative (COR):
Mr. Dwayne Privott Bureau of Reclamation Lower Colorado Dams Office, Hoover Dam Phone: (702) 494-2210 Email: dprivott@usbr.gov
File details come from the government source that posted it. Updated .