Nemo Domestic Well Construction Specifications and Requirements

This document is a construction specification package for the U.S. Department of Agriculture Forest Service to develop a new domestic water well at 12782 Nemo Road, Nemo, Lawrence County, South Dakota on the Black Hills National Forest. The project requires furnishing all labor, materials, equipment, and incidentals for drilling one new potable water well to a minimum depth estimated at 170 linear feet, installing an 8-inch diameter steel casing with pressure grouting, developing the well to produce a minimum of 6 gallons per minute, installing a submersible pump system with controls, constructing a 280-foot underground 1-inch HDPE water distribution line from the well to an existing utility vault, and performing disinfection and water quality testing. The contractor must be a South Dakota-licensed well driller holding an active license in accordance with South Dakota Codified Law (SDCL) 46-6-6 to 46-6-31 and Administrative Rules (ARSD) 74:02:04:38. The well is designed as a Hard Rock Well construction type based on Precambrian igneous and metamorphic rock geology in the area, with expected water depth between 65 to 200 feet below ground surface.

The project scope includes ten base contract items covering drilling (170 LF estimated), well casing (40 LF estimated), well development, pump testing, submersible pump installation, well seal construction, water distribution piping (280 LF estimated), disinfection, water quality testing, and general requirements, with six corresponding increase/decrease items to accommodate quantity variations beyond 15 percent of base estimates. All work must comply with South Dakota Department of Agriculture and Natural Resources regulations, NSF/ANSI standards for potable water components, AWWA standards for wells, and National Electrical Code requirements. The contractor shall provide a detailed Construction Schedule within ten calendar days of Notice to Proceed, submit Operations and Maintenance manuals before final acceptance, complete a Well Completion Report per SD DANR forms, and provide comprehensive water quality laboratory analysis testing for primary contaminants, secondary contaminants, and other parameters including bacteriological analysis. The site is located at approximately 4,645 feet elevation with anticipated winter snow conditions and rocky terrain; meals and lodging are available in the nearby town of Nemo or surrounding communities.

View the file

Other files

File Type Posted
1240LT26Q0175_A0001.pdf PDF
Att.1-C04-Statement of Work.pdf PDF
Att.4-C04-Nemo Well Drawings-S.pdf PDF
C04-Solicitation 1240LT26Q0175.pdf PDF
Att.2-C04-Schedule of Items.xlsx XLSX spreadsheet
Att.5-C04-DBA Wage Determination.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

United States Department of Agriculture

Forest Service

Black Hills National Forest

June 2026

Nemo Domestic Well

Specifications

Construction Documents

NEMO DOMESTIC WELL

BLACK HILLS NATIONAL FOREST

001500-1

LIST OF DRAWINGS AND SPECIFICATIONS

SECTION 001500

LIST OF DRAWINGS AND SPECIFICATIONS

PART 1 – GENERAL

1.1 DESCRIPTION

A. List of Contract Drawings:

1. Index of Sheets:

SHEET 1 TITLE SHEET AND INDEX

SHEET 2 SITE MAP

SHEET 3 DETAILS

Total Plan Sheets in this Contract 3

B. List of Contract Specifications

1. Index of Specifications

DIVISION 1 – GENERAL REQUIREMENTS

Section 010150 General Requirements Section 010250 Definition of Contract Items and Measurement and Payment

DIVISION 22 – PLUMBING

Section 221113 Facility Water Distribution Piping

DIVISION 26 - ELECTRICAL

Section 260010 General Work Results for Electrical Section 260519 Low Voltage Electrical Power Conductors and Cables Section 260526 Grounding & Bonding for Electrical Systems Section 260543 Underground Ducts and Raceways for Electrical Systems Section 262726 Wiring Devices Section 262816 Enclosed Switches and Circuit Breakers

DIVISION 31 – EARTHWORK

Section 312317 Trenching, Bedding, and Backfill for Utilities

DIVISION 33 – UTILITIES

Section 331113 Potable Water Supply Wells

END OF SECTION 001500

010150 – 1

GENERAL REQUIREMENTS

SECTION 010150

PART 1 – SUMMARY OF WORK

1.1 DESCRIPTION

A. Work for this project requires the contractor to be responsible for furnish all labor, materials, equipment, utilities, miscellaneous items, and freight necessary for the construction, development, testing and disinfection of one new domestic water well and underground water distribution line from new well to an existing utility vault as shown on the plans and detailed in these specifications. Contractor shall also provide and install a new submersible pump with associated parts and accessories and make all necessary electrical and water system connection and install controls to make new system fully operational.

B. Construction and development of the new well and installation of a submersible pump shall be performed by a SD licensed well driller in accordance with South Dakota (SD) Codified Law (SDCL) 46-6-6 to 46-6-31 and SD Administrative Rules (ARDS) 74:02:04:38. Proof of active and valid SD Well Driller License shall be required for this Contract.

1.2 LOCATION

A. This project is located at 12782 Nemo Road, Nemo, Lawrence County, SD 57759. The site is in Section 27 of T 3 N, R 5 E, Black Hills Meridian.

1.3 GENERAL SITE CONDITIONS

A. The elevation of the site is approximately 4,645 feet above mean sea level.

B. Snow may be on the ground long-term or intermittently throughout the winter months.

Most spring and fall snow falls are typically short-lived and complete closure of site access is not likely.

C. In-depth soil surveys have not been conducted. Rocks are evident throughout the area.

The Contractor should expect to encounter rock during drilling and excavation operations.

D. In-depth water table surveys have not been conducted. Information from Well

Completion reports available from SD Department of Agriculture and Natural Resources (SD DANR) show depth to water in wells ranges from about 65 ft to about 200 ft below ground surface.

E. Available geologic information, nearby Government project knowledge, and the SD

DANR well completion reports in this area show the dominant geology and statigraphy in the area is Precambrian igneous and metamorphic rock. Based on this, the well is designed as a Hard Rock Well in accordance with ARSD 74:02:04:32.

010150 – 2

1.4 USE OF PREMISES

A. General; Contractor shall have limited use of premises for construction operations and during construction period.

B. Use of Site: Confine constructions operations to immediate area of work. Do not disturb portions of Project site beyond areas in which the Work is indicated.

C. Work is being performed for the Government on residentially occupied land. The land and dwelling may be occupied during entire construction period. The resident/occupant will have no direct contractual involvement with the Contract or Contractor.

Contractor shall minimize interactions with the resident/occupant, but remain courteous and respectful. Minimize conflicts and facilitate resident/occupant usage of site. Perform the Work so as not to interfere with resident/occupant's day-to-day operations.

D. Driveways and Entrances: Keep driveways, parking areas, loading areas and entrances serving premises clear and available to Government and resident/occupant, and emergency vehicles at all times. Do not use these areas for parking or storage of materials. Do not close or obstruct walkways, corridors, or other occupied or used facilities. Any needed use of these spaces shall be coordinated between Contractor and Contracting Officer who will then coordinate with resident/occupant.

E. Contractor shall at all times conduct his operations to ensure the least inconvenience to the public, the Government or the resident/occupant at the site.

1.5 WORK RESTRICTIONS

A. Nonsmoking Site: Smoking is not permitted at this project site, inside or outside.

B. Do not schedule work during holidays, weekends, or between 6:00 PM to 7:00 AM without written approval from the Contracting Officer.

C. Project Scheduling: Schedule work to minimize impacts to Government.

D. The Contracting Officer will designate areas on the site for material storage. Confine storage of materials to areas as approved by the CO.

1.6 CONTRACTOR’S RESPONSIBILITIES

A. Provide adequate signing and barricades and take necessary safety measures to protect the public during all construction operations. Minimize disturbance of all undisturbed areas.

B. Protect trees and vegetation within project area from damage.

C. Damage to areas adjacent to and/or within the project area that are not included as an element of the project, including lawns and landscape features, shall be repaired by

010150 – 3 the Contractor at no additional cost to the Government.

D. Coordination of Trades: Coordinate construction operations included in the various sections of the Specifications to provide an efficient and orderly installation of each part of the Work. Coordinate construction operations included under different sections of the Specifications that depend on each other for proper installation, connection or operation.

1.7 FIELD VERIFICATION

A. Field verify all new and existing dimensions affecting the work of this contract before ordering products.

1.8 EXISTING UTILITIES

A. Notify CO and utility companies of proposed locations and times for excavation.

B. Contractor shall be responsible for locating and preventing damage to known utilities.

Contractor shall contact “One-Call” at 811 prior to initiating excavation work to locate utility companies buried utilities. Additionally, obtain the services of a locating company to locate other buried utilizes including government owned utilities. Do not initiate any excavation work until utilities have been located and marked.

C. If damage to utilities occurs, the Contractor shall be responsible for repairs at no additional expense to the Government. .

D. Existing buried utilities are shown on the drawings as accurately as existing records permit. Use caution when excavating in areas where buried utilities are anticipated.

Repair any damage to buried utilities caused through work associated with this contract.

E. Interruption of Existing Utility Service: Notify CO at least 48 hours in advance of any planned interruption of existing utilities.

1.9 PERMITS AND INSPECTIONS

A. Obtain permits for work required by County, State, or Federal laws or regulations.

1.10 PRESERVATION OF NATURAL FEATURES

A. Confine all operations to work limits of the project. Prevent damage to natural surroundings. Restore damaged areas, repairing or replacing damaged trees and plants, at no additional expense to the Government.

1. Provide temporary barriers to protect existing trees and plants and root zones.

2. Do not remove, injure, or destroy trees or other plants without prior written approval from the CO. Consult with the CO and remove agreed-on roots and branches that interfere with construction.

3. Do not fasten ropes, cables, or guys to existing trees.

4. Carefully supervise excavating, stockpiling, grading, filling and other

010150 – 4 construction operations near trees to prevent damage.

1.11 MEALS AND LODGING

A. Meals and lodging are commercially available in the town of Nemo within approximately ¾ miles north of the project site, though some may be seasonally closed.

B. Meals and lodging are also available in towns further away – such as Sturgis, Deadwood, Rapid City, and Spearfish.

C. Meals or lodging will not be available at the Government facilities.

D. Camping will not be allowed on the Project stie.

PART 2 – ACCIDENT PREVENTION

2.1 DESCRIPTION

A. This section consists of establishing an effective accident prevention plan and providing a safe environment for personnel and visitors.

2.2 SUBMITTALS

A. Accident Prevention Plan: Before on-site work begins, submit a company approved accident prevention plan. This plan will be posted in the contract file. Design the plan to address Federal, State, and Local Occupational Safety and Health requirements that apply to this project. Notice to Proceed will not be made until the plan is received. As a minimum the plan shall include:

1. Name, position title and contact information of company executive responsible for approving the Accident Prevention Plan.

2. Name and contact information of supervisor responsible to carry out the plan.

3. Outline of each phase of the work, the hazards associated with each major phase, and the methods proposed to ensure property protection and safety of the public, government personnel, and the Contractor's employees. Identify the work included under each phase by reference to specification section or division numbers.

4. Contingency plans for emergency situations such as medical, fire, hazard material spills and other contract assessed hazard prevention and abatement requirement needs that apply to this project.

B. Certificates: Provide certificates from a mechanic that all mechanical equipment has been inspected and meets OSHA requirements.

C. Submit a copy of test reports, as required by OSHA, for personnel working with hazardous materials.

D. Submit a brief report of safety meetings and of inspections within 7 days of the meeting or

010150 – 5 inspection. Include a list of attendees.

E. Upon request, submit proof of employees' qualifications to perform assigned duties in a safe manner.

2.3 ACCIDENT REPORTING

A. Accidents: Report accidents immediately to the CO and assist the CO and other officials as required in the investigation and documentation of the accident.

2.4 FIRST AID FACILITIES

A. Provide adequate facilities for the number of employees and the type of construction at the site.

2.5 PERSONNEL PROTECTIVE EQUIPMENT

A. Meet requirements of NIOSH and MSHA, where applicable, as well as ANSI.

2.6 EMERGENCY INSTRUCTIONS

A. Post telephone numbers and reporting instructions for ambulance, physician, hospital, fire department, and police in conspicuous locations at the work site.

2.7 PROTECTIVE EQUIPMENT

A. Inspect personal protective equipment daily and maintain in a serviceable condition.

Clean, sanitize, and repair, as appropriate, personal items before issuing them to another individual.

B. Inspect and maintain other protective equipment and devices before use and on a periodic basis to ensure safe operation.

2.8 SAFETY MEETINGS

A. As a minimum, conduct weekly 15-minute "toolbox" safety meetings. These meetings shall be conducted by a foreman and attended by all construction personnel at the worksite.

2.9 HARD HATS AND PROTECTIVE EQUIPMENT AREAS

A. Designate and post a hard hat area. Working with and around drilling equipment designates the site as a hard hat area.

B. It is the Contractor's responsibility to require all those working on or visiting the site to wear hard hats and other necessary protective equipment at all times. As a minimum, provide two hard hats for use by visitors. Change liners before reissuing hats.

2.10 TRAINING

010150 – 6

A. First Aid: Provide adequate training to ensure prompt and efficient first aid.

B. Hazardous Material: Train and instruct each employee exposed to hazardous material in safe and approved methods of handling and storage. Hazardous materials are defined as explosive, flammable, poisonous, corrosive, oxidizing, irritating, or otherwise harmful substances that could cause death or injury.

PART 3 – SUBMITTAL PROCEDURES

3.1 DESCRIPTION

A. This section includes administrative, procedural, and construction schedule requirements for submittals.

3.2 PROCEDURES

A. Processing Time: Allow 10 working days for submittal review, including time for re-submittals, as follows. Time for review shall commence on CO's receipt of submittal.

B. Use for Construction: Use only final submittals with mark indicating action taken by CO in connection with construction.

3.3 CONSTRUCTION SCHEDULE

A. General: This section includes preparation and submittal of Construction Schedules.

1. Number of Copies: Submit two copies or one electronic pdf of each submittal, unless otherwise indicated. CO will not return copies.

B. Procedures:

1. Within ten calendar days after date of Notice to Proceed, submit a detailed

Construction Schedule setting forth requirements for complete execution of the work. Provide schedules in electronic format.

a. Include a written summary narrative to explain basis of approach to work.

C. Field Verification: Field verify all new and existing dimension affecting the work of this contract before ordering products.

D. Construction Sequence: Well shall be drilled and completed prior to construction of the pipeline.

PART 4 – TEMPORARY FACILITIES AND CONTROLS

4.1 DESCRIPTION

A. This section consists of requirements for temporary facilities and controls, including utilities, support facilities, and security and protection facilities.

010150 – 7

4.2 UTILITIES

A. Water Service: Use of private or Government water will not be permitted. Contractor shall provide all needed construction and development water for the project.

B. Sanitary Facilities: Contractor shall provide temporary sanitary facilities for the duration of the project.

C. Electric Services: Use of private or Government electric services will not be permitted.

Contractor shall provide portable generator power supply as needed for the project.

Contractor shall be responsible for cleanup and remediation of all leaks or damage that may occur from the portable power supply.

D. Telephone Service: The Contractor is responsible for providing telephone service deemed necessary for the duration of the construction.

4.3 CONSTRUCTION WASTE DISPOSAL

A. Provide waste-collection containers in sizes adequate to handle waste from construction operations. Containerize and clearly label hazardous, dangerous, or unsanitary waste materials separately from other waste.

B. Cleanup construction debris at the completion of each day’s work. Do not use existing on-site trash receptacles for disposal or interim storage of construction debris.

C. Burning of construction debris is not allowed on lands administered by the Forest Service.

D. Dispose construction debris at an established Sanitary Landfill. Schedule disposal frequency to ensure waste containers are not overflowing.

4.4 STAGING AND SUPPORT FACILITIES INSTALLATION

A. Staging: An area at the project site will be made available for use as a staging area.

Refer to drawings, but if not shown, coordinate size and location of staging area with Contracting Officer prior to storing materials. Security and clean-up of staging and support facilities is the responsibility of the Contractor.

B. Storage: Confine storage of materials to storage areas. Coordinate on-site storage requirements with the Contracting Officer.

4.5 SECURITY AND PROTECTION

A. Environmental Protection: Provide protection, operate temporary facilities, and conduct construction in ways and by methods that comply with environmental regulations and that minimize possible air, waterway, and subsoil contamination or pollution or other undesirable effects.

010150 – 8

B. Barricades, Warning Signs, and Lights: Comply with standards and code requirements for erecting structurally adequate barricades.

C. Fire Protection:

1. Store combustible materials in containers in fire-safe locations.

2. Maintain unobstructed access to fire extinguishers, fire hydrants, fire-protection facilities, stairways, and other access routes for firefighting. Prohibit smoking in hazardous fire-exposure areas.

3. Supervise welding operations, combustion-type temporary heating units, and similar sources of fire ignition.

PART 5 – EXECUTION REQUIREMENTS

5.1 DESCRIPTION

A. This section consists of general procedural requirements governing execution of the

Work including, but not limited to, the following:

1. General construction

2. Protection

3. Correction

5.2 EXAMINATION

A. Existing Conditions: Before beginning work, Contractor shall contact South Dakota

One-Call, 811, to have utility providers underground utilities before digging, drilling, and excavating.

5.3 PREPARATION

A. Field Measurements: Take field measurements as required to fit the Work properly.

B. Review of Contract Documents and Field Conditions: Immediately on discovery of the need for clarification of the Contract Documents, submit a request for information to CO.

Include a detailed description of problem encountered, together with recommendations for changing the Contract Documents.

5.4 INSTALLATION

A. General: Locate the Work and components of the Work accurately, in correct alignment and elevation, as indicated.

1. Make vertical work plumb and make horizontal work level.

2. Where space is limited, install components to maximize space available for maintenance and ease of removal for replacement.

010150 – 9

B. Comply with manufacturer's written instructions and recommendations for installing products.

C. Hazardous Materials: Use products, cleaners, and installation materials that are not considered hazardous.

5.5 PROGRESS CLEANING

A. General: Clean Project site and work areas daily, including common areas.

1. Dispose of materials lawfully.

2. Site: Maintain Project site free of waste materials and debris.

3. Waste Disposal: Burying or burning waste materials on-site will not be permitted. Washing waste materials down sewers or into waterways will not be permitted. Legally dispose all waste at approved landfills.

5.6 CORRECTION OF THE WORK

A. Repair or remove and replace defective construction.

1. Repairing includes replacing defective parts, refinishing damaged surfaces, touching up with matching materials, and properly adjusting operating equipment.

PART 6 – OPERATIONS AND MAINTENANCE MANUALS

6.1 SUBMITTALS

A. Submit two hard copy manuals and one electronic copy of Operations and Maintenance manuals for submersible well pump and pump controls before final acceptance of the project.

PART 7 – CLOSEOUT PROCEDURES

7.1 DESCRIPTION

A. This section consists of administrative and procedural requirements for contract closeout, including, but not limited to, the following:

1. Well Completion Report, submitted to CO and to SD DANR

2. Lab test results.

7.2 FINAL COMPLETION

A. Notify CO of satisfactory completion of well pump tests, waterline pressure testing, and lab results.

1. Submit Well Completion Report to CO and SD DANR.

010150 – 10

2. Submit 2 hard copies and 1 electronic file of Operation and Maintenance Manual for:

a. Submersible well pump

b. Well controls

7.3 PROJECT RECORD DOCUMENTS

A. General: Do not use Project Record Documents for construction purposes. Protect Project Record Documents from deterioration and loss. Provide access to Project Record Documents for CO's reference during normal working hours.

B. Submit hard copies or electronic copy of record documents for review prior to request for final inspection.

C. Project records include:

1. Well Completion Report – submit to CO and SD DANR

2. Submersible Pump – Operations and Maintenance Manual

3. Submersible Pump – Warranty

4. Well Controls – Operations and Maintenance Manual

5. Well Controls - Warranty

7.4 FINAL CLEANING

A. General: Provide final cleaning. Conduct cleaning and waste-removal operations to comply with local laws and ordinances and Federal and local environmental and antipollution regulations.

B. Restore disturbed area of site to like-original condition. Rake spoils to blend.

C. Comply with safety standards for cleaning. Do not burn waste materials. Do not bury debris or excess materials on Government property. Do not discharge volatile, harmful, or dangerous materials into drainage systems. Remove waste materials from Project site and dispose of lawfully.

END OF SECTION 010150

SECTION 010250

DEFINITION OF CONTRACT ITEMS

AND

MEASUREMENT AND PAYMENT

PART 1 - GENERAL

1.1 SUMMARY

A. The intent of this section is to explain, in general; what is and what is not included in a contract item; the limits or cut-off points where one item ends and another begins; and method of measurements and basis of payment for work items listed in the Schedule of Items.

B. Work: Furnishing all labor, materials, equipment, and other incidentals necessary to successfully complete the project or any portion of it, and carrying out all duties and obligations imposed by the contract on the Contractor.

C. Payment: For each individual item listed here and in the Schedule of Items, payment shall be full compensation for all work related to the particular item in accordance with these specifications and as shown on the drawings.

D. Measurement and payment for contract work shall be made only for and under those pay items included in the Schedule of Items. All other work and materials shall be considered incidental or as included in the payment for items shown.

1.2 UNITS OF MEASUREMENT

A. Payment shall be by units defined and determined according to U.S. Standard measure and by the following:

B. Lump Sum (LS): Do not measure directly. The bid amount is complete payment for all work described in the contract and necessary to complete the work for that item.

C. Linear Foot (LF): Linear Feet measured horizontally or vertically.

PART 2 - METHOD OF MEASUREMENT

2.1 GENERAL

A. One of the following methods of measurement for determining final payment is designated on the Schedule of Items for each pay item:

B. ACTUAL QUANTITIES (AQ)

1. These estimated quantities which are determined from actual measurements of completed work.

C. DESIGNED QUANTITIES (DQ)

1. These quantities denote the final number of units to be paid for under the terms of the contract. They are based upon the original design data available prior to advertising the project. Original design data include the preliminary survey information, design assumptions, calculations, drawings, and the presentation in the contract. Changes in the number of units shown in the Schedule of Items may be authorized under any of the following conditions:

a. As a result of changes in the work authorized by the CO.

b. As a result of the CO determining that errors exist in the original design that cause a pay item quantity to change by 15 percent or more.

c. As a result of the Contractor submitting to the CO a written request showing evidence of errors in the original design that cause a pay item quantity to change by 15 percent or more. The evidence must be verifiable and consist of calculations, drawings, or other data that show how the designed quantity is believed to be in error.

D. LUMP SUM QUANTITIES (LSQ)

1. These quantities denote one complete unit of work as required by or described in the contract, including necessary materials, equipment, and labor to complete the job. They shall be measured complete and in-place.

PART 3 – DEFINITION OF CONTRACT ITEMS

3.1 DETERMINATION OF QUANTITES

A. The Contractor shall perform, or cause to be performed, all measurements of quantities of materials incorporated into the work processes that are to be measured under the provisions of the contract.

B. Quantity Measurements

1. The Contractor shall make all measurements for computation of quantities for all work items except thos specified for payment by Designed Quantity (DQ) or Lump Sum Quantity (LS)

2. The Contractor shall compute the quantities for periodic progress payments: the Contracting Officer shall compute the quantities for the final payment based on measurements taken by the Contractor.

3. All Contractor measures are subject to verification.

4. The Contractor shall submit all field notes, calculation sheets, and other data used to determine quantities.

5. The Contractor shall certify in writing as to the accuracy of the measurements and computations submitted.

PART 4 – DEFINITION OF CONTRACT ITEMS

4.1 SCHEDULE OF ITEMS

A. The project Schedule of Items includes several sections to organize the contract items into Base Items and Increase/Decrease Items.

B. Provide item pricing for all items listed in the Schedule of Items.

C. Contract award will be made for all Base Items (BI).

D. Items listed as Actual Quantities (AQ) will be paid for the actual quantity of work completed. The AQ listed is the best estimate available at the time of design. FAR 52.211-18 Variation in Estimate Quantity allows equitable price adjustment if actual quantities vary by more than 15% above or below the initial estimate. Due to the work conditions of drilling and well construction, establishing up-front pricing for the changes is an opportunity to avoid contract delays. The Increase/Decrease Items are intended to provide pricing AQ items when quantities exceed the 15% variance.

E. Those items listed as Increase/Decrease (ID) may or may not be awarded. Contractor shall provide unit cost pricing for performing or not performing the item of Work when quantities differ more than 15% from the amount established in the Base Items.

1. The ID Items establish the price for the increase in quantities of Base Item work to be performed, when more than 15% above the stated amount. A contract modification will still need to be executed to authorize the Increase work.

2. The ID Items establish the price for contract price decrease adjustment for actual quantities more than 15% below the stated quantity in the Base Bit Item.

4.2 DEFINITION OF BASE ITEMS

A. Base Item No. 1 (BI-1) – Drilling New Well

1. Description of Work: This item includes all materials, equipment, labor and incidentals to drill a domestic water well to the project location in Nemo, SD.

This also includes incidental drill standby time and time related to gathering lithologic data and measurements of depth to water as necessary for driller to determine required well depth for domestic water well producing minimum of 6 gallons per minute. This also includes all technical components and equipment necessary to drill the boring true and plumb. Completion of the Well Log and Well Completion Report and filing the Well Completion Report with SD DANR and the CO is also included in this item. This item also includes contractor’s professional determination of required well depth for domestic water well producing minimum of 6 gallons per minute. Well is expected to be Hard Rock Well as defined by ARSD 74:02:02:32

2. Base Item Depth of Well: For initial planning and pricing, this Base Item is for drilling well to depth of 170 feet below ground surface. Changes in quantity will be addressed through the Increase/Decrease items.

3. Measurement: This item is measured as Actual Quantity of linear feet of drilling conducted.

4. Payment: The Contract Unit Price for LF includes all materials, equipment, labor, materials, supplies, and incidentals for drilling based on unit of linear feet.

The Base Item quantity is designed to be 170 ft.

B. Base Item No. 2 (BI-2) – Well Casing incidentals to case the drilled well with 8” diameter steel casing. Based on geologic information and local well completion reports, the well is designed to be completed as Hard Rock Well Construction as shown on the drawings and described in the specifications. This item also include installation of pressure grout in the annual space between bore walls and casing and construction the well in accordance with ARSD 74:02:04 Well Construction Standards.

2. Base Item Well Casing: For initial planning and pricing, this Base Item is for providing and installing 40 LF of 8” diameter steel casing, to include minimum 2 ft above ground surface and minimum 20 feet below bottom of the pitless adapter. drilling well to depth of 170 feet below ground surface. Changes in quantity will be addressed through the Increase/Decrease items.

3. Measurement: This item is measured as Actual Quantity of linear feet of steel well casing provided and installed.

4. Payment: The Contract Unit Price for LF includes all materials, equipment, labor, materials, supplies, and incidentals for steel well casing as described above and in these specifications and as shown on drawings. The Base Item quantity is designed to be 40 ft.

C. Base Item No. 3 (BI-3) – Well Development incidentals to successfully and completely develop the well to maximize the its production rate, including but not limited to the removal of drilling muds, drilling fluids, fine sediments, foreign materials, debris, and obstruction in accordance with ARSD 74:02:04 Well Construction Standard and to enhance well productivity to meet design production rate of 6 pgm This items also includes materials, equipment, labor and incidentals for the surging process, including providing water and water collection mechanisms and erosion and runoff control devises.

2. Measurement: This item is measured as a Lump Sum Quantity.

3. Payment: The contract lump sum price as shown in the Schedule of Items includes all deliverables, materials, equipment, labor, and incidentals to completely and successfully develop the water well at the project site.

D. Base Item No. 4 (BI-4) – Pump Test incidentals to perform well pump test to measure the well’s sustainable yield, pumping capacity, and overall hydraulic characteristics. This item includes providing and installing necessary temporary pumps and associated equipment and incidentals, not limited to wiring and power sources, and devises for erosion and runoff control, timing and measuring devices. This item also includes driller’s knowledge and recommendation for the submersible pump to serve the new well and includes providing pump curves to support recommendation.

2. Measurement: This item is measured as a Lump Sum Quantity.

3. Payment: The contract lump sum price as shown in the Schedule of Items includes all deliverables, materials, equipment, labor, and incidentals to perform full pump test to provide necessary information for sizing and placing the permanent well pump as described above and in the specifications.

E. Base Item No. 5 (BI-5) – Submersible Pump incidentals to provide and install submersible well pump, pump controls, pitless adapter, torque arrestor, and pump saver for complete and fully functional system to provide domestic water at design production rate of 6 pgm. This item also includes all downhole wiring, downhole components, and accessories for complete startup and operation of submersible pump. Item also includes providing warranty and operating manuals for pumps, controls and associated accessories and equipment.

2. Measurement: This item is measured as a Lump Sum Quantity.

3. Payment: The contract lump sum price as shown in the Schedule of Items includes all deliverables, materials, equipment, labor, and incidentals to provide and install submersible well pump as described above and in these specifications and as shown on the drawings

F. Base Item No. 6 (BI-6) – Well Seal incidentals to provide and install new well seal at ground surface including but not limited to 24” steel casing extending above ground surface and associated vented well cap with appropriate accessories for required water and electric connections including but not limited to grounding and bonding and water tight seal. This item also includes grading and establishing positive drainage away from the well as shown on the drawings. This item includes all components to meet ARSD 74:02:04 Well Construction Standards for well seals.

2. Measurement: This item is measured as a Lump Sum Quantity.

3. Payment: The contract lump sum price as shown in the Schedule of Items includes all deliverables, materials, equipment, labor, and incidentals to provide and install well seal as describe above and in these specifications and as shown on the drawings.

G. Base Item No.7 (BI-7) – Water Distribution Line incidentals for providing and constructing new water distribution line from the well to the existing utility vault as shown on the drawings and staked in the field.

This item includes excavation, trenching, bedding and backfill for new water distribution line, and 1” HDPE water distribution pipeline with connections to pitless adapter and to water lines in existing utility vault. This also includes pipe, tees, connections, elbows, joints, unions, thrust blocks and other incidentals as necessary for complete, leak-free and fully operational water distribution line system. This item also include pressure testing of the line.

2. Base Item Length of Water Distribution Line: For initial planning and pricing, this Base Item is for providing and installing, with excavation, bedding, and backfill, 280 feet of water distribution line. Changes in quantity will be addressed through the Increase/Decrease items.

3. Measurement: This item is measured as Actual Quantity of linear feet of water distribution line.

4. Payment: The Contract Unit Price for LF includes all materials, equipment, labor, materials, supplies, and incidentals for construction of new water distribution line based on unit of linear feet. The Base Item quantity is designed to be 280 ft.

H. Base Item No. 8 (BI-8) – Disinfection incidentals for cleaning and disinfection of the well and the water distribution line and associated accessories and appurtenances. Cleaning and disinfection shall be done in accordance with these specifications and requirements of ARSD 74:02:04. This items also includes providing all chemicals and chlorine and mixing devices needed for producing the appropriate disinfection solution, cleaning and disinfection. It also includes testing for efficacy, and providing materials, equipment, labor and incidentals for the disinfection and rinsing processes including providing water and water collection mechanisms and erosion and runoff control devises.

2. Measurement: This item is measured as a Lump Sum Quantity.

3. Payment: The contract lump sum price as shown in the Schedule of Items includes all deliverables, materials, equipment, labor, and incidentals to successfully disinfect well and distribution line as described above and in these specifications.

I. Base Item No. 9 (BI-9) – Water Quality Testing incidentals for collecting water samples and submitting them to certified laboraty for water quality analyses, and reporting the results. The analytical parameters are listed below.

2. Measurement: This item is measured as a Lump Sum Quantity.

3. Payment: The contract lump sum price as shown in the Schedule of Items includes all deliverables, materials, equipment, labor, and incidentals to successfully disinfect well and distribution line as described above and in these specifications.

J. Base Item No. 10 (BI-10) – General Requirements

1. Description of Work: This item includes, but is not limited to all preparatory work and operations necessary for the mobilization and movement of personnel, equipment, supplies, bonding and incidentals to the project site; all quality control testing and quality control plan; all construction signing; any other work and operations that must be incurred prior to the beginning of work; and demobilization at the completion of work. This item also includes accident prevention and safety plan, protection of the public, ,submittals, erosion control and vegetation protection, O& M manuals and construction documentation.

2. Measurement: This item is measured as a Lump Sum quantity.

3. Payment: The contract lump sum price as shown in the Schedule of Items will be paid for preparatory work described above and for work that must be performed or that cause costs to be incurred prior to beginning work on the various items on the project site.

3.2 DEFINITION OF INCREASE/DECREASE ITEMS

A. GENERAL

1. Items listed as Actual Quantities (AQ) will be paid for the actual quantity of work completed. The AQ listed is the best estimate available at the time of design. FAR 52.211-18 Variation in Estimate Quantity allows equitable price adjustment if actual quantities vary by more than 15% above or below the

PRIMARY CONTAMINANT SECONDARY CONTAMINANT OTHER

Antimony Aluminum Alkalinity Arsenic Calcium Bacteriological Analysis Barium Chloride Bicarbonate Beryllium Specific Conductance Bromine Cadmium Corrosivity Carbonate Chromium Hardness EDB

Copper Iron Potassium Fluoride Langlier Index Sodium Lead Magnesium

Mercury Manganese

Nitrate pH

Nitrite Silver

Selenium Sulfate initial estimate. Due to the work conditions of drilling and well construction, establishing up-front pricing for the changes is an opportunity to avoid contract delays. The Increase/Decrease Items are intended to provide pricing AQ items when quantities exceed the 15% variance.

2. Those items listed as Increase/Decrease (ID) may or may not be awarded.

Contractor shall provide unit cost pricing for performing or not performing the item of Work when quantities differ more than 15% from the amount established in the Base Items.

3. The ID Items establish the price for the increase in quantities of Base Item work to be performed, when more than 15% above the stated amount. A contract modification will still need to be executed to authorize the Increase work.

4. The ID Items establish the price for contract price decrease adjustment for actual quantities more than 15% below the stated quantity in the Base Bit Item.

5. Contract modification will have to be executed for the Increase/Decrease items.

This up-front pricing reduces the time for the contract modification.

4.2 DEFINITION OF INCREASE/DECREASE ITEMS

A. Increase/Decrease No. 1 (ID-1) – Increase Quantity Drilling New Well

1. Description: Increase of BI-1 when actual quantity of drilling is more than 15% above the estimated base quantity of 170 LF – specifically when drilling quantity exceeds 195 LF.

2. Measurement: This item is measured as Actual Quantity of linear feet of drilling conducted .

3. Payment: The Contract Unit Price for LF includes all materials, equipment, labor, materials, supplies, and incidentals for drilling based on unit of linear feet.

The ID-1 Increase Quantity would apply when actual quantity exceeds 195 LF.

B. Increase/Decrease No. 2 (ID-2) – Decrease Quantity Drilling New Well

1. Description: Increase of BI-1 when actual quantity of drilling is more than 15% below the estimated base quantity of 170 LF – specifically when drilling quantity is less than 145 LF.

2. Measurement: This item is measured as Actual Quantity of linear feet of drilling conducted .

3. Payment: The Contract Unit Price for LF includes all materials, equipment, labor, materials, supplies, and incidentals for drilling based on unit of linear feet.

The ID-2 Decrease Quantity would apply when actual quantity is less than 145

LF.

C. Increase/Decrease No. 3 (ID-3) – Increase Well Casing

1. Description: Increase of BI-2 when actual quantity of steel well casing provided and installed is more than 15% above the estimated base quantity of 40 LF – specifically when well casing quantity exceeds 46 LF.

2. Measurement: This item is measured as Actual Quantity of linear feet of well casing.

3. Payment: The Contract Unit Price for LF includes all materials, equipment, labor, materials, supplies, and incidentals for providing and installing well casing based on unit of linear feet. The ID-3 Increase Quantity would apply when actual quantity exceeds 46 LF.

D. Increase/Decrease No. 4 (ID-4) – Decrease Well Casing

1. Description: Increase of BI-2 when actual quantity of steel well casing provided and installed more than 15% below the estimated base quantity of 40 LF – specifically when quantity is less than 34 LF.

2. Measurement: This item is measured as Actual Quantity of linear feet of drilling conducted .

3. Payment: The Contract Unit Price for LF includes all materials, equipment, labor, materials, supplies, and incidentals for providing and installing well casing based on unit of linear feet. The ID-4 Decrease Quantity would apply when actual quantity is less than 34 LF.

E. Increase/Decrease No. 5 (ID-5) –Increase Water Distribution Line

1. Description: Increase of BI-7 when actual quantity of water distribution line is more than 15% below the estimated base quantity of 280 LF – specifically when quantity exceeds 322 LF.

2. Measurement: This item is measured as Actual Quantity of linear feet of drilling conducted .

3. Payment: The Contract Unit Price for LF includes all materials, equipment, labor, materials, supplies, and incidentals for water distribution line based on unit of linear feet. The ID-5 Increase Quantity would apply when actual quantity exceeds 322 LF.

F. Increase/Decrease No. 6 (ID-6) – Decrease Water Distribution Line

1. Description: Increase of BI-7 when actual quantity of water distribution line is more than 15% below the estimated base quantity of 280 LF – specifically when quantity is less than 238 LF.

2. Measurement: This item is measured as Actual Quantity of linear feet of drilling conducted .

3. Payment: The Contract Unit Price for LF includes all materials, equipment, labor, materials, supplies, and incidentals for water distribution line based on unit of linear feet. The ID-6 Decrease Quantity would apply when actual quantity is less than 238 LF.

END OF SECTION 010250

221113

FACILTY WATER DISTRIBUTION PIPING

SECTION 221113

FACILITY WATER DISTRIBUTION PIPING

A. This Section includes water-distribution piping and related components outside the existing utility vault for water service. This Section also includes flushing, testing, and disinfecting water lines.

1.2 SUBMITTALS

A. Product Data: For each type of product indicated:

1. Pipe and fittings

1.3 QUALITY ASSURANCE

A. Regulatory Requirements:

1. Comply with standards of South Dakota Department Of Agriculture and Natural Resources (SD DANR) for potable-water-service piping, including materials, installation, testing, and disinfection.

B. Piping materials shall bear label, stamp, or other markings of specified testing agency.

C. Comply with ASTM F645 for selection, design, and installation of thermoplastic water piping.

D. NSF Compliance:

1. Comply with NSF/ANSI 14 for plastic potable water service piping.

2. Comply with NSF 61 for materials for water-service piping and specialties for domestic water.

1.4 SYSTEM PERFORMANCE REQUIREMENTS

A. Minimum Working Pressures: The following are minimum pressure requirements for piping and specialties, unless otherwise indicated:

1. Potable Water Service: 160 psig

1.5 PROJECT CONDITIONS

A. Interruption of Existing Water-Distribution Service: Do not interrupt service to facilities occupied by Government or others unless permitted under the following conditions and then only after arranging to provide temporary water-distribution service according to requirements indicated:

1. Notify CO no fewer than 48 hours in advance of proposed interruption of service.

2. Do not proceed with interruption of water-distribution service without CO’s written permission.

1.6 DELIVERY, STORAGE, AND HANDLING

A. Delivery piping with factory-applied end caps. Maintain end-caps through shipping, storage and handling to prevent pipe=end damage and to prevent entrance of dirt, debris, and moisture.

B. Protect flanges, fillings, and specialties from moisture and dirt.

C. Store plastic piping protected form direct sunlight. Support to prevent sagging and bending.

1.7 COORDINATION

A. Coordinate connection of new water line from well to pitless adapter and to existing utility vault serving residence.

B. Install new well piping and controls in existing utility vault and connect to existing connection for complete and fully operational water system with well controls.

C. Disconnect old service connection and cut off no closer than 4 ft and no further than 10 feet from structure. Remove severed connection lines. Buried service line can remain in-place below ground.

D. Coordinate piping materials, sizes, entry locations, and pressure requirements with existing water services as existing at utility vault.

PART 2 - PRODUCTS

2.1 GENERAL

A. All waterlines, pipes, and fittings shall be new and unused, of the type, pressure rating or class, and size specified and as shown on the drawings.

2.2 HIGH DENSITY POLYTHEYLENE (HDPE) PIPE

A. Pipe

1. PE plastic pipe shall be PE 4710 as defined ASTM D3350, with a minimum cell classification of 345444C in accordance with ASTM D3350. The pipe shall be SDR11, 160 psig minimum pressure rating and comply dimensionally with ASTM D3035.

2. Pipe shall be manufactured in accordance with AWWA C901 for sizes ½” through 3”

3. The joining method shall butt fusion method and shall be performed in strict accordance with the pipe manufacturer’s recommendations. Butt fusion equipment used in the joining procedures shall be capable of meeting all conditions recommended by the pipe manufacturer, including but not limited to, temperature requirements, alignment, and fusion pressures. Ribbed steel inserts with stainless steel clamps are not approved for PE pipe.

4. Water pipe shall be NSF/ANSI 61 certified for drinking water system components.

B. Fittings:

1. PE fittings shall be made from material meeting the same requirements as the pipe.

2. Molded fittings shall be manufactured in accordance with either ASTM D 2683 for socket-fused or ASTM D3261 for butt-fused and shall be so marked.

3. All HDPE fittings shall have the same or higher pressure rating and compositions as the HDPE pipe.

2.3 GALVANIZED STEEL PIPE (GSP)

A. Pipe

1. ASTM A53 for pipe 4-inch diameter and smaller. Schedule 40.

2. Plain ends for joining with standard manufactured couplings.

3. Threaded ends shall meet requirements of ASME B1.20.1.

B. Fittings

1. ASTM A53. Schedule 40.

2. For threaded ends use Teflon thread sealing tape.

2.4 JOINING MATERIALS

A. Shall be compatible with HDPE pipe and as recommended by pipe manufacturer.

B. Heat fusion and welding methods shall be performed in strict accordance with the pipe manufacturer/s recommendations.

C. Ribbed steel inserts with stainless steel clamps are not approved for HDPE pipe for this application.

2.5 COUPLINGS FOR SIMILAR OR DISSIMILAR PIPE

A. Compression type transition fittings for making connections between like and dissimilar pipe materials shall be designed to enable a variety of connections between polyethylene pipe to various pipes, sizes 2” and smaller, using the same central body and different inserts and collets

B. Manufactured fitting or coupling same size as, with pressure rating at least equal to and ends compatible with, piping to be joined.

C. Do not use flanges or unions for underground piping.

D. Flanges, unions, and special fittings may be used, instead of joints indicated, on aboveground piping and piping in vaults.

E. Couplings for joining HDPE pipe with other materials shall be fully pressure rated and fully thrust restrained such that when installed in accordance with manufacturer's recommendations, a longitudinal load applied to the coupling will cause the pipe to yield before the coupling disjoints.

2.6 PIPE CORROSION PROTECTION FOR GSP

A. Cold applied mastic type 1200.

2.7 BACKFLOW PREVENTERS

A. Dual Check Backflow Preventers:

1. Standard: ASSE 1024

2. Operation: Continuous-pressure applications.

3. Pressure Loss: 10 psig (700kPa) maximum, across the entire device at maximum rated flow.

4. Size: to match the diameter of the water pipe.

5. Design Flow Rate: 10-20 gpm (0.6 to 1.2 (L/s).

6. Selected Unit Flow Range Limits: Ass determined by manufacturer’s maximum intermittent and continuous flow capacities.

7. Pressure Loss at Design Flow Rate: 3-8 psig (14-55 kPa)

8. Body: Bronze.

9. End Connections: Threaded

10. Configuration: Designed for horizontal, straight through flow.

11. Accessories:

a. Air-Gap Fitting: ASME A112.1.2, matching backflow preventer connection.

PART 3 - EXECUTION

3.1 EARTHWORK

A. Refer to Section 312317 “Trenching, Bedding, and Backfill for Utilities” for excavating, trenching, and backfilling.

3.2 PIPE INSTALLATION, GENERAL

A. Construct the water system to the lines and grades shown or established in the field.

B. Stake locations of water lines as shown on the drawings. The CO shall approve the water line location prior to the start of excavation. Pipeline may be relocated slightly, if necessary, to avoid existing obstacles.

C. All waterline installations shall be graded to drain. Waterlines not meeting this requirement shall be removed by the Contractor and replaced at no cost to the Government.

D. All pipe, fittings, and appurtenances shall be handled and laid in strict conformance to the manufacturer’s recommendations.

E. The interior of all pipe, fittings, and other accessories shall be kept as free as possible from dirt and foreign matter at all times. Each piece of pipe as it is laid shall be cleaned of all debris.

Pipeline that has become dirty on the inside shall be swabbed out by drawing a damp swab through the line before laying. Care shall be taken to keep all joining surfaces clean. Any pipe with contaminated or damaged joining surfaces which cannot be satisfactorily cleaned or repaired shall be discarded. Under no circumstance shall pipe be laid in water. No pipe shall be laid when trench conditions or the weather is unsuitable for such work. At all times when work is not in progress, all open ends of the pipe and fittings shall be securely closed to the satisfaction of the CO so that no trench water, rodents, earth, or other substance will enter the pipe or fittings.

F. Any section of pipe already laid and found to be defective shall be taken up and replaced with new pipe at the Contractor’s expense.