Att. 2 Specifications 240301.pdf

PDF 10 MB Posted

Attached to
Septic System Replacement, Chequamegon-Nicolet National Forest - Lakewood, Wisconsin
Solicitation number
12445524Q0037
Issued by

About this file

This document is a solicitation for the replacement of a septic system at the Lakewood Ranger District Office of the Chequamegon-Nicolet National Forest in Lakewood, Wisconsin. The U.S. Department of Agriculture Forest Service is seeking quotes from small businesses for the project, which is subject to the Construction Wage Rate Requirements statute. There will be a mandatory site visit on March 14, 2024 at 9:00 a.m. Central time for interested contractors to inspect the location. Quotes must be submitted by contractors registered in the System for Award Management. The solicitation includes attachments with full details and instructions for submitting quotes. The Forest Service will award a contract under this request for quote.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

TABLE OF CONTENTS

LAKEWOOD

SPECIFICATIONS

DIVISION 01 - GENERAL

01 00 00 General Requirements

01 70 00 Execution and Closeout Requirements

DIVISION 02 – EXISTING CONDITIONS

02 41 19 Structure Demolition

DIVISION 03 – CONCRETE

03 30 00 Cast In-Place Concrete

DIVISION 26 – ELECTRICAL

26 05 00 Common Work Results for Electrical

26 05 02 Electrical Demolition for Remodeling

26 05 04 Cleaning, Inspection, and Testing of Electrical Equipment

26 05 19 Low-Voltage Electrical Power Conductors and Cables

26 05 26 Grounding and Bounding for Electrical Systems

26 05 29 Hangers and Supports for Electrical Systems

26 05 33 Raceway and Boxes for Electrical Systems

26 05 53 Identification for Electrical Systems

26 27 02 Equipment Wiring

26 27 26 Wiring Devices

26 27 28 Disconnect Switches

DIVISION 31 – EARTHWORK

31 00 00 Clearing and Grubbing

31 23 17 Trenching

31 23 23 Fill

31 25 13 Erosion Controls

DIVISION 32 – EXTERIOR IMPROVEMENTS

32 11 23 Aggregate Base Courses

32 91 13 Soil Preparation

32 92 19 Seeding

DIVISION 33 – UTILITIES

33 05 16 Utility Structures

33 31 00 Sanitary Utility Sewerage Piping

33 36 16 Utility Septic Tank Effluent Pumps

ATTACHMENTS

Septic System Design Documents

General Requirements 01 00 00 - 1

SECTION 01 00 00

GENERAL REQUIREMENTS

PART 1 GENERAL

1.1 CONTRACT DESCRIPTION

A. The project includes installation of a new septic system to serve the garage and administration building. Work includes the removal of existing septic tanks, and the installation of two new concrete tanks, duplex pumping systems, septic drain field and all items necessary to complete the work as shown on the drawings and as included in the specifications.

B. Perform Work of Contract under a unit price contract with Government in accordance with the Conditions of the Contract.

1.2 UNIT PRICE - MEASUREMENT AND PAYMENT

A. General Requirements:

1. Work under this section shall be considered incidental to the project and will not be paid under a separate unit price item.

1.3 SPECIFICATION CONVENTIONS

A. These specifications are written in imperative mood and streamlined form. This imperative language is directed to the Contractor, unless specifically noted otherwise.

The words “shall be” are included by inference where a colon (:) is used within sentences or phrases.

1.4 APPLICATIONS FOR PAYMENT

A. Contractor shall invoice electronically on the IPP.gov website.

B. Content and Format: Contractor shall attach a supplementary Contract Estimate and Invoice Forest Service Form 6300-30 to the IPP.gov website or emailed directly to the COR prior to invoicing in IPP. All pay items in the schedule of items shall be referenced in this form. The certification sheet shall be fully completed and signed.

C. Payment Period: Payment frequency and other payment requirements shall be in accordance with applicable FAR, AGAR, and other clauses incorporated in full or by reference in this contract.

1.5 CHANGE PROCEDURES

A. Contract changes can only be authorized by the Contracting Officer in writing in accordance with FAR 52.243-1 Changes-Fixed-Price, the Contractor shall submit change requests in writing to the COR for initial review.

01 00 00 - 2

1.6 COORDINATION

A. Coordinate scheduling, submittals, and Work of various sections of specifications to ensure efficient and orderly sequence of installation of interdependent construction elements.

B. Coordinate space requirements and installation of work indicated diagrammatically on Drawings.

1.7 FIELD ENGINEERING

A. If needed, the Contractor shall provide a Land Surveyor to establish reference datum and set structure at proper elevation.

B. Establish elevations, lines, and levels and certify elevations and locations of the Work conform with Contract Documents.

C. Verify field measurements are as indicated on shop drawings or as instructed by manufacturer.

1.8 PRECONSTRUCTION MEETINGS

A. The successful bidder will participate in a preconstruction conference in accordance with FAR 52.236-26. The Contracting Officer’s notification will include specific details regarding the date, time, and location of the conference, any need for attendance by subcontractors, and information regarding the items to be discussed.

Specific topics include but are not limited to:

1. Proposed start date and Notice to Proceed.

2. Construction schedule.

3. Designation of Contractor's site superintendent including their authority on behalf of the contractor.

4. Review of clauses incorporated into the contract.

B. When required in individual specification section, convene pre-installation meeting at project site prior to commencing work of section.

1.9 CUTTING AND PATCHING

A. Execute cutting, fitting, and patching including excavation and fill, to complete Work, and to:

1. Fit several parts together, to integrate with other Work and existing structure.

2. Uncover Work to install or correct ill-timed Work.

3. Remove and replace defective and non-conforming Work.

4. Remove samples of installed Work for testing.

B. Fit Work tight to adjacent elements. Maintain integrity of wall, or floor construction:

completely seal voids.

01 00 00 - 3

1.10 SUBMITTAL PROCEDURES

A. Submittal form or cover letter to identify project, contractor, subcontractor or supplier, and pertinent contract document references.

B. Apply contractor's stamp, signed or initialed, certifying that review, verification of products required, field dimensions, adjacent construction work, and coordination of information is in accordance with requirements of the work and contract documents.

C. Identify variations from contract documents and product or system limitations which may be detrimental to successful performance of completed work.

D. Email submittals to COR for review. Revise and resubmit submittals as required; identify changes made since previous submittal.

E. Submittals must be approved by COR prior to fabrication or installation.

1.11 CONSTRUCTION PROGRESS SCHEDULES

A. Contractor shall provide and adhere to FAR 52.236-15 Schedules for Construction Contracts except:

1. Contractor shall provide a written schedule for approval prior to commencing work.

2. Submittal shall be in electronic format and be in pdf or Microsoft Office compatible file (word, excel).

1.12 PRODUCT DATA

A. Product Data:

1. Submitted to COR for review for limited purpose of checking for conformance with information given and design concept expressed in Contract Documents.

2. After review, provide copies and distribute in accordance with SUBMITTAL PROCEDURES article and for record documents purposes as specified.

B. Submit in PDF format.

C. Mark each copy to identify applicable products, models, options, and other data.

Supplement manufacturer’s standard data to provide information unique to this project.

1.13 SHOP DRAWINGS

A. Shop Drawings:

1. FAR 52.2366-21 Specification and Drawings for Construction paragraphs a-g is included by reference in this contract. Contractor shall submit shop drawings and maintain "as-built: or record drawings" as required by this clause except;

electronic submittals (pdf) will be acceptable provided they are clear and legible.

B. When required by individual specification sections, provide shop drawings signed and sealed by professional engineer responsible for designing components shown on shop drawings.

01 00 00 - 4

1. Include signed and sealed calculations to support design.

2. Submit drawings and calculations in form suitable for submission to and approval by authorities having jurisdiction.

3. Make revisions and provide additional information when required by authorities having jurisdiction.

1.14 MANUFACTURER’S INSTRUCTIONS

A. When specified in individual specification sections, submit manufacturer printed instructions for delivery, storage, assembly, installation, start-up, adjusting, and finishing, in quantities specified for Product Data.

1.15 MANUFACTURER’S CERTIFICATES

A. When specified in individual specification sections, submit certifications by manufacturer to COR, in quantities specified for Product Data.

B. Indicate material or Product conforms to or exceeds specified requirements. Submit supporting reference data, affidavits, and certifications as appropriate.

C. Submit documents in PDF format.

1.16 QUALITY CONTROL

A. Monitor quality control over suppliers, manufacturers, products, services, site conditions, and workmanship, to produce Work of specified quality.

B. Comply with manufacturer’s instructions.

C. Comply with specified standards as minimum quality for the Work except when more stringent tolerances, codes, or specified requirements indicate higher standards or more precise workmanship.

1.17 INSURANCE

A. See contract documents.

1.18 TOLERANCES

A. Monitor fabrication and installation tolerance control of installed products over suppliers, manufacturers, products, site conditions, and workmanship, to produce acceptable Work.

Do not permit tolerances to accumulate.

B. Comply fully with manufacturer’s tolerances.

1.19 REFERENCES

A. Conform to reference standards by date of issue current as of date of Contract Documents.

B. When specified reference standards conflict with Contract Documents, request clarification from COR before proceeding.

01 00 00 - 5

1.20 EXAMINATION

A. Verify existing site conditions and substrate surfaces are acceptable for subsequent Work. Beginning new Work means acceptance of existing conditions.

1.21 PREPARATION

A. Clean substrate surfaces prior to applying next material or substance.

B. Apply manufacturer required or recommended substrate primer, sealer, or conditioner prior to applying new material or substance in contact or bond.

1.22 TEMPORARY ELECTRICITY

A. The Contractor is not allowed to use electricity from USFS buildings or facilities and shall provide a temporary source of electricity to be used for construction activities.

B. The Contractor shall pay the cost of electricity used. The Government will not be responsible for cost to operate on-site generators if needed.

C. Provide temporary electricity and power for construction operations, including connections, branch wiring, distribution boxes, outlets, and flexible power cords as required. Do not disrupt Government's need for continuous service.

1.23 TEMPORARY VENTILATION

A. Ventilate enclosed areas to assist cure of materials, to dissipate humidity, and to prevent accumulation of dust, fumes, vapors, or gases.

1.24 TEMPORARY SANITARY FACILITIES

A. Provide and maintain required facilities and enclosures.

B. Maintain in clean and sanitary condition.

1.25 PROGRESS CLEANING AND WASTE REMOVAL

A. Collect waste materials at least daily and maintain site in clean and orderly condition.

1.26 BARRIERS AND FENCING

A. Provide construction site barriers, fencing, and guards in accordance with 29 CFR1926.501 and related standards (Subpart G) and definitions.

1.27 PROTECTION OF INSTALLED WORK

A. Protect installed Work and provide special protection where specified in individual specification sections.

1.28 WATER CONTROL

A. Maintain excavations free of water. Provide, operate, and maintain pumping equipment.

01 00 00 - 6

B. Provide erosion and sediment control.

C. If dewatering is needed, Contractor shall submit a dewatering plan to the COR for review and approval. Dewatering must follow DNR Technical Standard 1061.

1.29 POLLUTION AND ENVIRONMENTAL CONTROL

A. Provide methods, means, and facilities to prevent contamination of soil, water, and atmosphere from discharge of noxious, toxic substances, and pollutants produced by construction operations.

B. Provide dust control, erosion and sediment control, noise control, pest control and rodent control to allow for proper execution of the Work.

1.30 PRODUCTS

A. Products: Means new material, machinery, components, equipment, fixtures, and systems forming the Work, but does not include machinery and equipment used for preparation, fabrication, conveying and erection of the Work.

1.31 DELIVERY, HANDLING, STORAGE, AND PROTECTION

A. Deliver, handle, store, and protect products in accordance with manufacturer's instructions.

1.32 PRODUCT OPTIONS

A. Products Specified by Reference Standards or by Description Only: Any Product meeting those standards or description.

B. Products listed by manufacturer name and model shall be understood as an "or equal" product designation. The contractor shall be responsible for providing sufficient documentation and in accordance with the substitutions section to establish a product as "equal" for approval by the CO.

C. Products Specified by Naming One or More Manufacturers with Provision for Substitutions:

Submit request for substitution for manufacturers not named.

1.33 SUBSTITUTIONS

A. Instructions to Bidders specifies time for submitting requests for Substitutions during bidding period to requirements specified in this section.

B. Substitutions will only be considered when Product becomes unavailable through no fault of Contractor.

C. The Contractor shall provide complete data substantiating compliance with the contract requirements and a comparison between specified product and proposed substitution, any differences shall be highlighted or spelled out by the contractor in their submittal.

01 00 00 - 7

1.34 CLOSEOUT PROCEDURES

A. Submit written certification Contract Documents have been reviewed, Work has been inspected, and Work is complete in accordance with Contract Documents and ready for COR's inspection.

B. Submit final application for payment identifying total adjusted Contract Price, previous payment, and amount remaining due to the COR for review prior to submitting invoice in the IPP.GOV website.

1.35 FINAL CLEANING

A. Execute final cleaning prior to final inspection.

B. Clean interior and exterior surfaces exposed to view.

C. Clean debris from site.

D. Remove waste and surplus materials, rubbish, and equipment from site.

1.36 PROTECTING INSTALLED CONSTRUCTION

A. Provide temporary and removable protection for installed products. Control activity in immediate work area to prevent damage.

B. Protect finished surfaces from traffic, dirt, wear, damage, or movement of heavy objects, by protecting with durable sheet materials such as plywood or composite equipment mats.

1.37 PROJECT RECORD DOCUMENTS

A. Maintain on site one set of Contract Documents to be utilized for record documents.

B. Record actual revisions to the Work. Record information concurrent with construction progress.

C. Specifications: Legibly mark and record at each Product section description of actual Products installed.

D. Record Documents and Shop Drawings: Legibly mark each item to record actual construction.

E. Submit two sets of as-built documents to COR with claim for final application for payment.

1.38 SPARE PARTS AND MAINTENANCE MATERIALS

A. As indicated in individual specification sections.

1.39 WARRANTIES

A. Provide notarized copies.

01 00 00 - 8

B. Execute and assemble transferable warranty documents from subcontractors, suppliers, and manufacturers.

C. Submit prior to final Application for Payment.

END OF SECTION

Execution and Closeout Requirements 01 70 00 - 1

SECTION 01 70 00

EXECUTION AND CLOSEOUT REQUIREMENTS

PART 1 GENERAL

1.1 SECTION INCLUDES

A. Closeout procedures.

B. Final cleaning.

C. Starting of systems.

D. Demonstration and instructions.

E. Sanitary sewer force main testing.

F. Protecting installed construction.

G. Project record documents.

H. Operation and maintenance data.

1.2 UNIT PRICE - MEASUREMENT AND PAYMENT

A. Onsite Training:

1. Basis of Measurement: By Lump Sum

2. Basis of Payment: For septic system, provide an Operations and Maintenance manual and onsite training for Forest Service personnel.

1.3 CLOSEOUT PROCEDURES

A. Submit written certification that Contract Documents have been reviewed, Work has been inspected, and that Work is complete in accordance with Contract Documents and ready for the COR’s inspection.

B. Provide submittals to COR as indicated in specification sections.

C. Submit final application for payment identifying total adjusted Contract Price, previous payment, and amount remaining due to the COR for review prior to submitting invoice in the IPP.GOV website.

1.4 FINAL CLEANING

A. Execute final cleaning prior to final project assessment.

B. Clean site; sweep paved areas, rake clean landscaped surfaces.

C. Remove waste and surplus materials, rubbish, and construction facilities from site.

01 70 00 - 2

1.5 STARTING OF SYSTEMS

A. Coordinate with manufacturer to schedule start-up of septic system.

B. Notify COR seven (7) days prior to start-up.

C. Verify pumping systems have been checked for proper operation, control sequence, and for conditions which may cause damage.

D. Verify tests and specified electrical characteristics agree with those required by equipment manufacturers.

E. Verify wiring and support components for equipment are complete and tested.

F. Contractor shall provide a representative to be present at site to inspect, check, and approve equipment or system installation prior to start-up, and to supervise placing septic system in operation.

G. Execute start-up under supervision of Contractors' personnel in accordance with manufacturers' instructions.

H. Submit a written certification in accordance with Section 01 00 00 General Requirements (paragraph 1.16) that equipment has been properly installed and is functioning correctly.

1.6 DEMONSTRATION AND INSTRUCTIONS

A. Demonstrate start-up, operation, control, adjustment, trouble-shooting, servicing, maintenance, and shutdown of pumping equipment to CO and onsite maintenance personnel at agreed time at project location prior to date of substantial completion.

B. Utilize operation and maintenance manuals as basis for instruction. Review contents of manual with Forest Service personnel in detail to explain all aspects of operation and maintenance.

C. Prepare and insert additional data in operations and maintenance manuals when need for additional data becomes apparent during instruction.

1.7 SANITARY SEWER FORCE MAIN TESTING

A. Hydrostatically test new force mains in accordance with AWWA C600, latest revision.

B. All pressure testing equipment and labor necessary to setup and run the test shall be provided by the contractor, including but not limited to:

1. Pressure Gauge (maximum pressure of 250 pounds or as approved by the COR.)

2. Pump

3. Tank

4. Fittings for the testing equipment to be connected to the force main.

5. Accurate water volume measuring device (calibrated volumetric 1-gallon graduated cylinder in ounces).

01 70 00 - 3

C. All pressure tests shall be witnessed and verified by the COR.

D. Expel all air from the pipe prior to the COR’s arrival to witness the start of the pressure test. Make the necessary taps at high points to expel the air and insert plugs after the air is expelled.

E. Hydrostatic Pressure Test Requirements:

1. Maximum test segment length of 1,000-feet.

2. 150 psi test pressure.

3. Minimum duration of 2-hours.

4. Test pressure may not drop below 125 psi at any point during the pressure test.

F. The COR reserves the right to install a locking mechanism at the test gage or install direct connect pressure recorders for the test.

G. Longer test segment lengths may be considered upon request.

H. Use only clean, disinfected containers and equipment to add make-up water at the end of the pressure testing to return to the original starting pressure of the test. Refill measurements are to be done with a graduated container, measured in ounces.

I. The COR reserves the right to require make-up water be added at any point during the pressure test if the test pressure drops more than 5 psi during the test, which restarts the 2-hour testing duration. Furnish all equipment, labor, and supplies necessary to apply pressure to the pipeline in a manner satisfactory to the COR.

J. The testing allowance (allowable makeup water) shall be no greater than as calculated in the formula:

L = (S*D*P^1/2)/133,200

Where: L = Allowable Makeup Water (Leakage), in gallons per hour S = Length of pipe tested, in feet D = Nominal diameter of the pipe, in inches P = Average test pressure during the leakage test, in psi (gauge)

K. When testing against closed metal-seated valves, an additional testing allowance per closed valve of 0.0078 gph per inch of nominal valve size is permitted.

L. If the pipe line fails the pressure test, locate the leak and repair it to like-new condition. The proposed repair method is to be reviewed by the COR and result in an end product that is equal to, or better than new construction.

M. Following location and repair of the leak, repeat the pressure test until a satisfactory result is obtained. All costs associated with testing and retesting the pipeline is considered to be incidental to sanitary sewer force main construction.

N. Contractor shall provide COR with a record of all tests performed. These records shall show the individual lengths of pipe tested and the test results.

01 70 00 - 4

1.8 PROTECTING INSTALLED CONSTRUCTION

A. Protect installed Work and provide special protection where specified in individual specification sections.

B. Provide temporary and removable protection for installed products. Control activity in immediate work area to prevent damage.

C. Prohibit traffic from landscaped areas.

1.9 PROJECT RECORD DOCUMENTS

A. Provide record documents as specified in Section 01 00 00 General Requirements.

1.10 OPERATION AND MAINTENANCE DATA

A. Submit data bound in 8-1/2 x 11-inch text pages, with durable plastic covers.

B. Prepare binder cover with printed title:

"OPERATION AND MAINTENANCE INSTRUCTIONS

LAKEWOOD RANGER STATION

PRIVATE ONSITE WASTEWATER TREATMENT SYSTEM"

C. Provide manufacturer’s operating and maintenance instructions, catalog data and literature, installation instructions, electrical diagrams, control panel diagram, drawings, and maintenance and customer service contact information.

PART 2 PRODUCTS - Not Used

PART 3 EXECUTION - Not Used

Structure Demolition 02 41 19 - 1

SECTION 02 41 19

STRUCTURE DEMOLITION

PART 1 GENERAL

1.1 SUMMARY

A. Section Includes:

1. Demolishing designated underground tanks.

2. Protecting items designated to remain.

3. Removing demolished materials.

4. Demolishing sidewalk designated for replacement.

1.2 UNIT PRICE - MEASUREMENT AND PAYMENT

A. Demolished Materials:

1. Basis of Measurement: By Lump Sum

2. Basis of Payment: Includes pumping tank(s), demolition, loading, removal of all sewage and tank materials, and removal of all demolished and excess soil material from project site.

1.3 CLOSEOUT SUBMITTALS

A. Project Record Documents: Accurately record actual locations of capped utilities and subsurface obstructions.

1.4 QUALITY ASSURANCE

A. Obtain required permits from authorities having jurisdiction. Unless otherwise noted, Contractor shall be responsible for obtaining and paying for all permits necessary to complete demolition work.

1.5 PROJECT CONDITIONS

A. Tank(s) shall be pumped out by a licensed septic hauler prior to demolition.

PART 2 PRODUCTS

Not Used.

PART 3 EXECUTION

3.1 PREPARATION

A. Call Local Utility Line Information service not less than three working days before performing Work.

1. Request underground utilities to be located and marked within and surrounding construction areas.

B. Notify affected utility companies before starting work and comply with utility's requirements.

Structure Demolition 02 41 19 - 2

C. Do not close or obstruct roadways or sidewalks without permission from CO.

D. Erect, and maintain temporary barriers and security devices, including warning signs, and similar measures, for protection of the public.

E. Protect existing trees, appurtenances, and structures indicated to remain. Removal of any tree shall be approved by CO prior to removal.

F. Prevent movement or settlement of adjacent structures. Provide bracing and shoring.

3.2 DEMOLITION REQUIREMENTS

A. Use of explosives is not permitted.

B. Conduct demolition to minimize interference with adjacent structures.

C. Cease operations immediately when adjacent structures appear to be in danger. Notify CO. Do not resume operations until directed.

D. Conduct operations with minimum interference to public or private accesses to occupied adjacent structures. Maintain egress and access from adjacent structures at all times.

3.3 DEMOLITION

A. Remove underground tank, components, and piping from site.

B. Plug all pipes to be abandoned, water-tight, with concrete or other approved method.

C. Backfill open pits and holes resulting from demolition in accordance with Section 31 23 23.

D. Rough grade and compact areas affected by demolition to maintain site grades and contours and to accommodate subsequent construction operations.

E. Continuously clean-up and remove demolished materials from site. Do not allow materials to accumulate on site.

F. Do not bury materials on site. Leave site in clean condition.

Cast-In-Place Concrete 03 30 00 - 1

SECTION 03 30 00

CAST-IN-PLACE CONCRETE

PART 1 GENERAL

1.1 SUMMARY

A. Work included in this section:

1. Formwork.

2. Reinforcement.

3. Accessories.

4. Cast-in place concrete.

5. Cleaning and finishing of formed surfaces.

6. Finishing and curing.

1.2 UNIT PRICE - MEASUREMENT AND PAYMENT

A. 4” Concrete Sidewalk:

1. Basis of Measurement: Lump Sum

2. Basis of Payment: Includes concrete, reinforcement, placement accessories, consolidating and leveling, troweling, curing, and 3rd party concrete testing and reporting.

1.3 SUBMITTALS

A. Provide the following information in accordance with Section 01 00 00 General Requirements.

B. Product Data: Indicate admixtures, and adhesive anchors.

C. Design Data: Submit mix designs.

1.4 QUALITY ASSURANCE

A. Contractor to obtain and pay for an independent testing laboratory, approved by the Government, to provide quality control testing.

B. Acceptable test results do not relieve the Contractor from making corrections to the tested work during the warranty period.

1.5 DELIVERY, STORAGE AND HANDLING

A. Comply with Section 01 00 00 General Requirements and as follows:

1. Storage of concrete components shall conform to recommended practices of ACI 304 and manufacturer's instructions.

03 30 00 - 2

PART 2 PRODUCTS

2.1 FORM MATERIALS

A. Forms for Exposed Finish Concrete Plywood, metal, metal-framed plywood faced, or other panel-type materials to provide continuous, straight, smooth, exposed surfaces. Furnish in largest practicable sizes to minimize number of joints.

B. Forms for Unexposed Finish Concrete Plywood, lumber or metal. Provide lumber dressed on at least two edges and one side for tight fit.

C. Form Release Agent Provide commercial formulation form release agent with a maximum of 350 g/L volatile organic compounds (VOCs) that will not bond with, stain, or adversely affect concrete surfaces and will not impair subsequent treatments of concrete surfaces.

D. Form Ties Factory-fabricated, adjustable length, removable or snap-off metal form ties designed to prevent form deflection and to prevent spalling of concrete upon removal. Provide units that will leave no metal closer than 1½ inches to the plane of the exposed concrete surface. Provide ties that, when removed, will leave holes not larger than 1 inch in diameter in the concrete surface.

2.2 REINFORCEMENT MATERIALS

A. Deformed Reinforcement: ASTM A615/A615M; 60 ksi yield strength, steel bars, unfinished. Bar size per drawing details.

B. Chairs, Bolsters, Bar Supports, Spacers: Sized and shaped for support of reinforcing; plastic tipped or non-corroding for supports in slabs forming finished ceilings or where supports are exposed to weather.

C. Fabricate concrete reinforcement in accordance with CRSI Manual of Practice.

2.3 CONCRETE MATERIALS

A. General

1. Concrete shall be ready-mixed concrete conforming to ASTM C94.

2. Job-mixed concrete will be permitted in amounts of one cubic yard or less, when used for patching, equipment bases, finishing, etc.

a. Job-mixed concrete shall meet same material and strength requirements as ready-mixed concrete.

b. Mixing of job-mixed concrete shall be in accordance with ACI

304.

B. Cement

1. ASTM C150, Type 1 or Type 1A.

03 30 00 - 3

2. Use only one brand of approved cement for exposed concrete throughout any one structure or composite elements.

C. Aggregates

1. Fine Aggregate

a. Sieve % passing by weight

b. 3/8-inch 100

c. No. 4 90-100

d. No. 16 45-85

e. No. 50 5-30

f. No. 100 0-10

2. Course Aggregate

a. Sieve % passing by weight

b. 1-inch 100

c. ¾-inch 90-100

d. 3/8-inch 20-55

e. No. 4 0-10

f. No. 8 0-5

D. Admixtures

1. Air-entraining Admixtures: ASTM C260

2. Fly Ash: ASTM C618, type C or F

3. Ground Granulated Blast Furnace Slag: ASTM C989, Grade 100 or 120

4. Chemical Admixtures: ASTM C494

a. Type A, water-reducing.

b. Type B, retarding.

c. Type D, water-reducing and retarding.

d. Type E, water-reducing and accelerating.

e. Type F or G, high range water-reducing.

E. Fine and Coarse Weight Aggregate: ASTM C33

F. Water: Clean and not detrimental to concrete.

G. Non-shrink Grout: Premixed compound consisting of non-metallic aggregate, cement, water reducing and plasticizing agents.

2.4 CURING MATERIALS

A. Liquid Applied

1. Liquid Membrane - Forming Compounds: ASTM C1315, Type 1, Class A, with a maximum of 700 grams per liter VOCs. Product shall restrict the loss of water to not more than 0.40 kg/m2 in 72 hours when applied at a rate of 300 square feet per gallon.

03 30 00 - 4

B. Sheet or Membrane

1. Plastic film, ASTM C171:

a. 10 mil thickness

b. White during warm weather.

c. Black during cold weather.

2. Reinforced paper, ASTM C171.

2.5 CONCRETE SPECIALTIES

A. Epoxy Bonding Agents

1. ASTM C881, two-component material suitable for use on dry or damp surfaces.

B. Finishing Grout

1. Non-reemulsifiable bonding admixture.

2. Non-yellowing, high solids modified acrylic polymer.

C. Non-Shrink Grout

1. ASTM C1107.

2. Materials:

a. Premixed, non-metallic compound.

b. 5,000 psi minimum compressive strength (7 days).

c. 7,500 psi minimum compressive strength (28 days).

2.6 CONCRETE MIX

A. Mix and deliver concrete in accordance with ASTM C94/C94M, Option C.

B. Furnish concrete of the following strength:

1. Compressive Strength 3000 psi (7 day).

2. Compressive strength 4000 psi (28 day).

3. Slump 3 to 4 inches.

4. Maximum water-cement ratio: 0.40

C. Add air entraining agent to concrete mix for concrete work exposed to exterior of 6% ±1.5% conforming to the requirements of ACI318 for severe exposure.

PART 3 EXECUTION

3.1 FORMWORK ERECTION

A. Erect formwork, shoring and bracing to achieve design requirements.

B. Camber slabs and framing to achieve ACI 301 tolerances.

03 30 00 - 5

C. Provide bracing to ensure stability of formwork.

D. Apply form release agent to formwork prior to placing form accessories and reinforcement.

E. Do not apply form release agent where concrete surfaces will receive special finishes or applied coverings affected by agent.

F. Clean forms as erection proceeds, to remove foreign matter.

3.2 INSERTS, EMBEDDED COMPONENTS, AND OPENINGS

A. Provide formed openings where required for work to be embedded in and passing through concrete members.

B. Coordinate work of other sections in forming and setting openings, slots, recesses, chases, sleeves, bolts, anchors, and other inserts.

C. Install concrete accessories straight, level, and plumb.

D. Place joint filler at perimeter of surface repair edge.

E. Install void forms. Protect forms from moisture before concrete placement and from crushing during concreting.

3.3 PLACEMENT OF CONCRETE

A. Environmental Requirements

1. Hot Weather Concreting:

a. Follow ACI 305 whenever mean surrounding air temperature equals or exceeds 80 degrees F (27 degrees C).

b. Do not place concrete whenever air temperature equals or exceeds 90 degrees F (32 degrees C).

2. Cold Weather Concreting:

a. Follow ACI 306 whenever mean surrounding air temperature is below 40 degrees F (4.5 degrees C), except that no admixtures containing chlorides are allowed.

3. Do not place concrete during rain, sleet, or snow, unless protection is provided.

B. Placement of Concrete

1. Conveying Concrete:

a. Convey concrete from mixer to place of final deposit by methods that will prevent separation or loss of materials.

b. Equipment for chuting, pumping, or pneumatically conveying concrete shall be capable of providing a supply of concrete at site of Work without separation of ingredients and without interruptions sufficient to permit loss of plasticity between successive placements.

c. Unless otherwise approved, conform to ACI 318.

03 30 00 - 6

2. Depositing Concrete:

a. Deposit concrete as nearly as practicable to its final position to avoid segregation due to rehandling or flowing.

b. Carry on concreting at such a rate that concrete is at all times plastic, and flows readily into spaces between reinforcing.

c. Do not deposit concrete that has partially hardened or that has been contaminated by foreign materials.

d. Do not use retempered or remixed concrete.

e. After concreting is started, it shall be carried on as a continuous operation until placing of a panel or section is completed.

f. Top surfaces of vertically formed lifts shall be generally level.

g. Thoroughly consolidate concrete by suitable means during placement, and thoroughly work concrete around reinforcement and embedded fixtures, and into corner of forms.

h. Vibrators may be used to aid placement, provided they are used under experienced supervision and forms have been designed to withstand their action.

i. Unless otherwise approved, conform to ACI 318.

3.4 CONSTRUCTION JOINTS

A. Use and Location

1. Use and location of construction joints shall be as shown on plans or subject to prior approval of the Contracting Officer.

2. Construction joints may be tooled or sawcut and shall match existing spacing and configuration, at intervals not exceeding 5 feet.

B. Preparation

1. Clean surface of hardened concrete and remove laitance and standing water.

2. Wet construction joints immediately before new concrete placement.

3.5 CURING AND PROTECTION

A. Immediately after placement, protect concrete from premature drying, excessively hot or cold temperatures, and mechanical injury.

1. Protect cast in place concrete from freezing for minimum 5 days.

B. Immediately after placement, protect concrete from premature drying.

C. Maintain concrete with minimal moisture loss at relatively constant temperature for period necessary for hydration of cement and hardening of concrete for not less than 7 days.

03 30 00 - 7

3.6 FORMED SURFACES

A. Sidewalks shall have a broom finish or match existing sidewalk finish.

3.7 ERECTION TOLERANCES

A. Install reinforcement within tolerances required by ACI 318 code.

3.8 QUALITY CONTROL TESTING DURING CONSTRUCTION

A. Sampling and testing for quality control during concrete placement shall conform to ASTM E329 and shall include the following:

1. Sampling Fresh Concrete: ASTM C 172, except modified for slump to comply with ASTM C 94.

a. Slump: ASTM C 143; one test at point of discharge for each day's pour of each type of concrete; additional tests when concrete consistency seems to have changed.

b. Air Content: ASTM C 173, volumetric method for lightweight or normal weight concrete; ASTM C 231, pressure method for normal weight concrete; one for each day's pour of each type of air-entrained concrete.

c. Concrete Temperature: ASTM C 1064; one test hourly when air temperature is 40 degrees F (4 degrees C) and below, when 80 degrees F (27 degrees C) and above, and one test for each set of compressive-strength specimens.

d. Compression Test Specimen: ASTM C 31; one set of four standard cylinders for each compressive-strength test, unless otherwise directed. Mold and store cylinders for laboratory-cured test specimens except when field-cured test specimens are required.

e. Compressive-Strength Tests: ASTM C 39; one set for each day's pour exceeding 5 cu. yd. plus additional sets for each 50 cu.

yd. more than the first 25 cu. yd. of each concrete class placed in any one day; one specimen tested at 7 days, two specimens tested at 28 days, and one specimen retained in reserve for later testing if required.

2. When frequency of testing will provide fewer than five strength tests for a given class of concrete, conduct testing from at least five randomly selected batches or from each batch if fewer than five are used.

3. When strength of field-cured cylinders is less than 85 percent of companion laboratory-cured cylinders, evaluate current operations and provide corrective procedures for protecting and curing the in-place concrete.

4. Strength level of concrete will be considered satisfactory if averages of sets of three consecutive strength test results equal or exceed specified compressive strength and no individual strength test result falls below specified compressive strength by more than 500 psi.

03 30 00 - 8

B. Test results will be reported in writing to the Contracting Officer, ready-mix producer, and Contractor within 24 hours after tests. Reports of compressive strength tests shall contain the Project identification name and number, date of concrete placement, name of concrete testing service, concrete type and class, location of concrete batch in structure, design compressive strength at 28 days, concrete mix proportions and materials, compressive breaking strength, and type of break for both 7-day tests and 28-day tests.

C. Nondestructive Testing Impact hammer, sonoscope, or other nondestructive device may be permitted but shall not be used as the sole basis for acceptance or rejection.

D. Additional Tests The testing agency will make additional tests of in-place concrete when test results indicate specified concrete strengths and other characteristics have not been attained in the structure, as directed by the Contracting Officer. Testing agency may conduct tests to determine adequacy of concrete by cored cylinders complying with ASTM C 42, or by other methods as directed.

3.9 DEFECTIVE CONCRETE

A. Modify or replace concrete not conforming to required lines, details and elevations, as directed by the Contracting Officer.

Common Work Results for Electrical 26 05 00 - 1

SECTION 26 05 00

COMMON WORK RESULTS FOR ELECTRICAL

HANSON DESIGN GROUP, LLC MASTER ELECTRICAL SPEC DATED 3.26.2020

PART 1 – GENERAL

1.1 GENERAL

A. Applicable provisions of Division 1 shall govern work under this Division.

B. The electrical work included in all other divisions is the responsibility of the contractor performing the Division 26 work unless noted otherwise.

C. Reference Division 33 – Utilities for additional information concerning equipment requiring electrical connections.

1.2 UNIT PRICE - MEASUREMENT AND PAYMENT

A. Electrical Work:

1. Basis of Measurement: By Lump Sum

2. Basis of Payment: Includes all labor and materials necessary to complete the work described in the Section 26 specifications and as shown on the electrical drawings.

1.3 SCOPE

A. The work under this section includes basic electrical requirements applicable to all Division 26 sections. This section includes information common to two or more technical specification sections or items that are of a general nature, not conveniently fitting into other technical sections.

1.4 REFERENCE STANDARDS

A. Abbreviations of standards organizations referenced in this and other sections are as follows:

ANSI American National Standards Institute ASTM American Society for Testing and Materials EPA Environmental Protection Agency ETL Electrical Testing Laboratories, Inc.

IEEE Institute of Electrical and Electronics Engineers IES Illuminating Engineering Society ISA Instrument Society of America NBS National Bureau of Standards NEC National Electric Code NEMA National Electrical Manufacturers Association NESC National Electrical Safety Code NFPA National Fire Protection Association UL Underwriters Laboratories Inc.

DSPS Wisconsin Department of Safety and Professional Services

1.5 REGULATORY REQUIREMENTS

A. All work and materials are to conform in every detail to applicable rules and requirements of the latest adopted editions of the National Electrical Code (NFPA 70), 26 05 00 - 2

Wisconsin State Electrical Code (SPS 316), International Building Code (IBC), Wisconsin Buildings and Structures Code (SPS 362), International Energy Conservation Code (IECC), Wisconsin Energy Code (SPS 363), International Existing Building Code (IEBC), Wisconsin Existing Building Code (SPS 366), applicable National Fire Protection Association codes, the National Electrical Safety Code, and present manufacturing standards (including

NEMA).

1.6 CONTINUITY OF EXISTING SERVICES AND SYSTEMS

A. No outages shall be permitted on existing systems except at the time and during the interval specified or specifically obtained by written permission from an authorized representative of the Owner with acknowledgment from the CO (Contracting Officer). Any outage must be scheduled when the interruption causes the least interference with normal institutional schedules and business routines. No extra costs will be paid to the Contractor for outages that must occur outside of the contractor’s regular working hours.

B. This Contractor shall restore any circuit interrupted as a result of this work to proper operation as soon as possible.

1.7 REGULATORY REQUIREMENTS

A. All work and SLEEVES AND OPENINGS

Contractor shall review all proposed openings with the CO to ensure structural integrity is maintained.

1.8 SEALING AND CAULKING

A. Sealing and caulking of sleeves/openings between conduits, cable trays, wireways, troughs, cablebus, busduct, etc. and an opening shall be the responsibility of the contractor whose work penetrates the opening. The Division 26 Contractor shall hire individuals skilled in sealing and caulking work. These hired individuals shall normally and routinely be employed in the sealing and caulking occupation. Contractor shall immediately submit valid credentials of these hired individuals to CO upon request.

1.9 INTENT

A. The Contractor shall furnish and install all the necessary materials, apparatus, and devices to complete the electrical equipment and systems installation herein specified.

B. If an item is either called for in the specifications or shown on the plans it shall be considered sufficient for the inclusion of said item in this contract. If a conflict exists within the specifications or the drawings, the Contractor shall furnish the item, system, or workmanship which is the higher quality, greater quantity, or most closely fits Owner’s intent (as determined by the CO). Refer to Division 1 for further clarification.

C. It must be understood that the details and drawings are diagrammatic. The Contractor shall verify all dimensions at the site and is responsible for their accuracy.

D. All sizes as given are minimum unless noted otherwise.

E. Materials and labor shall be new - unless noted or stated otherwise. Labor shall be first class and workmanlike. Materials and labor shall be subject to the CO's inspections, tests and approval from commencement until acceptance of completed work.

26 05 00 - 3

F. Whenever a particular manufacturer's product is named - provide the named product.

Whenever products are specified by a reference standard - provide a product meeting the named standards.

1.10 OMISSIONS

A. Contractor shall immediately call the attention of the CO to any materials or apparatus believed to be inadequate, and any necessary items of work omitted.

2.0 SUBMITTALS

A. Furnish submittals to the CO for review. Reference the following list, as well as individual technical sections, for items requiring submission.

26 05 00 – Sealing and Caulking

26 27 26 - Wiring Devices

26 27 28 - Disconnect Switches

B. Submit for all equipment and systems as indicated above or in the respective technical specification sections. Clearly mark each submittal with that specification section number. Clearly mark general catalog sheets and drawings to indicate specific items being submitted for review, and clearly identify equipment by name and/or number as indicated in the contract documents. Failure to do this may result in the submittal(s) being returned to the Contractor for correction and resubmission. Failing to follow these instructions does not relieve the Contractor from the requirement of meeting the project schedule.

C. On request from the CO, the successful bidder shall furnish additional drawings, illustrations, catalog data, performance characteristics, etc.

D. Submittals shall be grouped to include complete submittals of related systems, products, and accessories in a single submittal. Mark dimensions and values in units to match those specified. Include wiring diagrams of electrically powered equipment.

E. The submittals must be reviewed by CO before fabrication.

F. Electronic submission is acceptable. Submitted pages and drawings, whether hard copy or electronic, must be original PDFs or original photo copies. Scanned and duplicated photocopies, which in the CO’s opinion are of poor quality, will not be accepted. The Contractor is responsible for all hardcopies of submittals necessary for the O&M manuals.

2.1 WORK BY OTHER TRADES

A. Every attempt has been made to indicate in this trade's specifications and drawings all work required of this Contractor. However, there may be additional specific paragraphs in other trade specifications and addenda, and additional notes on drawings for other trades which pertain to this trade's work, and thus those additional requirements are hereby made a part of these specifications and drawings.

B. Electrical details on drawings for equipment to be provided by others are based on preliminary design data only. This Contractor shall lay out the electrical work and shall be responsible for its correctness to match equipment actually provided by others.

2.2 SALVAGE MATERIALS

A. No materials removed from this project shall be reused unless specifically noted. All materials removed shall become the property of the Contractor. Co shall dispose of removed materials in an environmentally responsible fashion.

26 05 00 - 4

2.3 CERTIFICATES AND INSPECTIONS

A. Contractor shall obtain and pay for all required State and local installation permits, certificates, and inspections. Deliver originals of these certificates to the Owner’s authorized representative. Include copies of these certificates in the O&M manuals.

2.4 OPERATION AND MAINTENANCE DATA

A. Reference Division 1 for additional requirements.

B. Assemble material in 3-ring or post binders using an index at the front of each volume and tabs for each system or type of equipment. Provide the following information, plus any requirements listed in Division 1:

Copies of all approved submittals.

Manufacturer’s wiring diagrams for electrically powered equipment.

Records of tests performed to certify compliance with system requirements.

Certificates of inspection by regulatory agencies.

Parts list for manufactured equipment.

Preventive maintenance recommendations.

Copies of all warranties (turn over originals to Owner’s authorized representative).

Additional information as indicated in the technical speciation sections.

C. Copies of required State and local permits, certificates, and inspections.

2.5 RECORD DRAWINGS

A. Reference Division 1 for additional requirements.

B. The Contractor shall maintain at least one copy each of the specifications and drawings on the job site at all times.

C. Contractor shall obtain a suitable set of contract drawings on which daily records of changes and deviations from contract shall be recorded. Buried and concealed piping, conduit, and similar items shall be located by dimensions and elevations on the record drawings.

D. The daily record of changes shall be the responsibility of Contractor's field superintendent. No arbitrary mark-ups will be permitted.

E. The Contractor shall submit the marked-up record drawings to the CO at completion of the project, and prior to final payment.

PART 2 - PRODUCTS

2.6 IDENTIFICATION

A. See Electrical section 26 05 53 – Identification for Electrical Systems.

26 05 00 - 5

2.7 SEALING AND CAULKING

A. Conduit Penetrations Through Below Grade Walls: Exterior wall openings below grade - use a modular mechanical type seal consisting of interlocking synthetic rubber links shaped to continuously fill the annular space between the uninsulated conduit and the cored opening or water-stop type wall sleeve.

B. Conduit and Cable Tray Penetrations: Conduit and cable tray penetrations of non-rated interior partitions, floors, and exterior walls above grade - use urethane caulk in annular space between conduit and sleeve or the core drilled opening.

PART 3 - EXECUTION

3.1 EXCAVATION AND BACKFILL

A. Perform all excavation and backfill work to accomplish indicated electrical systems installation unless noted otherwise.

3.2 CUTTING AND PATCHING

A. Each trade shall perform cutting and patching necessary for installation of their respective work, unless otherwise noted. Cutting and patching shall be performed by skilled technicians experienced with the procedures, equipment, and materials required. Patch disturbed surfaces and structures with materials and finishes matching adjacent surfaces and structures.

3.3 EQUIPMENT ACCESS

A. Install all piping, conduit, ductwork, and accessories to permit access to equipment for maintenance.

3.4 COORDINATION

A. The Contractor shall cooperate with other trades in locating work in a proper manner.

Should it be necessary to raise or lower or move longitudinally any part of the electrical work to better fit the general installation, such work shall be done at no extra cost. The Contractor shall check location of electrical outlets with respect to other installations before installing.

B. The Contractor shall verify that all devices are compatible for the surfaces on which they will be used.

C. Coordinate all work with other contractors prior to installation. Any installed work that is not coordinated and that interferes with other contractor's work shall be removed or relocated at the installing contractor's expense.

3.5 SEALING AND CAULKING

A. In exterior wall openings below grade, assemble rubber links of mechanical seal to the proper size for the conduit and tighten in place, in accordance with the manufacturer's instructions. Install so that the bolts used to tighten the seal are accessible from the interior of the building or vault.

B. At all interior walls and exterior walls, conduit penetrations are required to be sealed. Apply sealant to both sides of the penetration in such a manner that the annular space between the sleeve or cored opening and the conduit is completely blocked.

26 05 00 - 6

This is the start of the file's text. The full file is on GovTribe.