This is a Statement of Work (SOW) for the Lone Cone Chinking project on the Grand Mesa, Uncompahgre, and Gunnison (GMUG) National Forests, issued by the US Department of Agriculture (USDA).

The project involves removal and replacement of chinking material on the exterior of the Lone Cone Cabin, a log structure built in the late 1940s located approximately 25 miles southeast of Norwood, Colorado. The contractor must prepare the exterior log surface through power washing or media blasting to remove old stain, paint, and surface wrought, then clean all voids 3/8 inches or greater. The south wall includes two windowsills and sub-sills requiring vertical flush cutting to remove decayed portions. The contractor shall chink all horizontal and vertical exterior joints using an appropriate chinking product or wood filler, ensuring full contact with logs to eliminate air pockets. Following void filling, the contractor must apply a heavy coat of borate wood preservative for decay and carpenter bee protection, then apply a high-quality exterior log stain matching the existing color. The estimated project duration is 2-4 weeks. Key deliverables include a Proposed Project Plan due within five business days after the pre-work meeting, weekly status reports documenting tasks and issues throughout the contract period, and product submittals due within five business days after the pre-work meeting. The contractor must provide names and qualifications of personnel performing the work. The government furnishes access to the cabin with non-potable water and electricity on site; lodging at the cabin may be permitted pending work timeframe and approval from the Rec Staff Officer. All travel costs must be included in the final contract cost with no government reimbursement.

View the file

Other files

File Type Posted
C04-Solicitation 1240LT26Q0187.pdf PDF
Att.4-C04-Lone Cone House Pictures.pdf PDF
Att.2-C04-Schedule of Items.xlsx XLSX spreadsheet
Att.3-C04-Location Map.pdf PDF
Att.5-C04-DBA Wage Determination.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

US Department of Agriculture (USDA)

Statement of Work Lone Cone Chinking

Grand Mesa, Uncompahgre, and Gunnison (GMUG) National Forests Norwood Road/Recreation

Contents Project General Information

1.0 Scope of Work

2.0 Background

Contractor Requirements

3.0 Technical Requirements / Tasks

4.0 Government Furnished

5.0 Deliverables / Schedule

6.0 Travel

7.0 Contractor’s Key Personnel

Attachments

Project Lone Cone Chinking Project

General Information

1.0 Scope of Work

This project is for removal and replacement of the chinking material on the building exterior. Contractor is required to prepare exterior log surface to ensure optimal adhesion.

2.0 Background

The Lone Cone Cabin is a rental facility in the summer months and an outfitter cabin in the winter months located on the Grand Mesa, Uncompahgre, and Gunnison National Forest on the Norwood Ranger District. This is a log cabin built in the late 1940s. There are large gaps between the logs and holes from woodpeckers and other varmints, throughout the exterior of the cabin which has allowed rodents and insects to infest the cabin’s interior. It is unknown when the last time any chinking maintenance was done on this cabin, however, it is apparent that the Lone Cone Cabin is in dire need of this service and this should be scheduled on 15–20-year basis or when needed.

Location: Latitude 37°53'35.3"N, Longitude 108°09'31.1"W

Contractor Requirements

3.0 Technical Requirements / Tasks

- Contractor should prep building exterior by power washing or media blasting to remove old stain/paint and surface wrought. Clean all voids in the exterior (including upward facing checks 3/8” or greater). The exterior surface must be clean and free of all contaminants, including dust, dirt, loose wood fibers, and uncured oils.

- The south wall specifically has 2 windowsills and sub-sills that can be vertically flush cut to remove the decayed portion.

- Chink all horizontal and vertical joints on the exterior structure of the cabin. Ensure chinking material makes full contact with logs for proper adhesion and to eliminate any air pockets or voids.

- Fill with an appropriate chinking product or wood filler that is appropriate for each specific location. After the voids are filled, chink all log joints with a high-quality product.

- Apply a heavy coat of borate wood preservative to protect against decay and carpenter bees, then apply a high-quality exterior log stain, colored like the existing color.

4.0 Government Furnished

Contractor will need access to the Lone Cone Cabin, which is located about 25 miles southeast of Norwood, CO off County Road 49G. There are water (not potable) and electricity on site. Use of the cabin could be permitted to the contractor during this service depending on timeframe of chinking/maintenance work on the cabin.

Permission to stay in the cabin will need to be granted by the Rec Staff Officer on the district, Krystina Smith.

5.0 Deliverables / Schedule

• Contractor is required to provide a Proposed Project Plan before any work is implemented, and written progress reports on a weekly basis for the extent of the project (estimating 2-4 weeks for completion).

The progress report shall identify any problems that arose and a statement explaining how the problem was resolved. The contractor is to check in with the COR if there are any questions that come up during work on the cabin, especially if there is a unique circumstance or problem applying chinking material/maintenance to the cabin.

Key Deliverables Item No. Deliverable Objective Due 1 Proposed Project

Plan Defining the responsibilities, timeline, risks and milestones of contract objectives.

No later than five (5) business days after pre-work meeting

2 Weekly Status Report

Report documenting tasks & issues weekly. Weekly until the contract expires

3 Submittals Provide products submittals No later than five (5) business days after pre-work meeting

6.0 Travel

No known travel requirements for this project other than to and from the project site. See #4 above for possible lodging on site while work is being carried out. All travel costs should be included in final contract cost; the Government will not reimburse travel costs.

7.0 Contractor’s Key Personnel

Contractors should provide names and qualifications of personnel performing the work.

Attachments Location Map Lone Cone House pictures

Project
General Information
1.0 Scope of Work
2.0 Background
Contractor Requirements
3.0 Technical Requirements / Tasks
4.0 Government Furnished
5.0 Deliverables / Schedule
6.0 Travel
7.0 Contractor’s Key Personnel