Att A_Specifications.docx
DOCX document 23 KB Posted
- Solicitation number
- S-73000-00005843
- Issued by
- Tillamook County, Oregon
About this file
This document is the Specifications Attachment A for a state and local contract opportunity issued by the Oregon Department of Transportation (ODOT) for scaffolding work on the Tillamook River Bridge in Tillamook, Oregon. The required work consists of furnishing, erecting, and dismantling three 5' wide by 45' long hanging scaffolding floors at bents 6, 8, and 14 on the bridge to facilitate repair work. The scaffolding must be erected by July 27, 2023 and dismantled starting on August 14, 2023, unless the ODOT Project Manager approves additional time. The contractor must provide an engineer-stamped design and ensure the scaffolding meets or exceeds OSHA requirements. Traffic control, if needed, must be provided by the contractor at no additional cost.
The pricing for this contract opportunity is outlined in the Competitive Quote Form, Part 2. Work hours are limited to daylight hours Monday through Friday, excluding state-recognized holidays, unless approved in advance by the ODOT Project Manager. This contract opportunity is open to eligible contractors in Marion County and the city of Salem, Oregon.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Att B - Proposed Locations and Existing Plans.pdf | ||
| RFCQ~1.doc | DOC document | |
| Bid tabulation~6.xlsx | XLSX spreadsheet | |
| Att C_Insurance Requirements.docx | DOCX document | |
| Sample PO~2.docx | DOCX document | |
| 00005844_Att C_Bid Pricing Form.xlsx | XLSX spreadsheet |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
ATTACHMENT A - SPECIFICATIONS
1. The work required under this Contract consists of furnishing, erecting, and dismantling three 5’ wide by 45’ long (or similarly dimensioned) hanging scaffolding floors at bents 6, 8,and 14 on the Tillamook River Bridge (BR#01345c) located on OR131 at MP 7.5 in Tillamook. This work is to facilitate bridge repair.
2. The ODOT Project Manager/Contract Administrator for this project is:
| Mike Metz |
| 455 Airport Rd SE Bldg. B |
| Salem, OR 97301 |
| 503-509-0015 |
3. Contractor shall have erected the scaffolding by July 27, 2023 and shall begin dismantling scaffolding on August 14, 2023. (Dismantling date is subject to change by ODOT Project Manager. If additional days are required, they will be paid at the per day rate stated in the Competitive Quote Form, Part 2.
4. Scaffold shall be three sections – 5’ wide by 45’ long (approximate measurements). Floor shall be set 66 inches below the bottom of the lower cord. All scaffolding shall have railing. Scaffolding shall be set at bents 6, 8,and 14 (Attachment A for bent locations).
5. Contractor must provide a design stamped by an engineer registered to practice in Oregon.
6. Scaffold must meet or exceed OSHA rules and regulations.
7. If traffic control is required during erection or dismantling, it will be provided by the Contractor at no additional cost to ODOT.
8. Contractor’s hours of work to erect and dismantle the scaffolding shall by daylight hours Monday through Friday, excluding State-recognized holidays. Any deviations from this schedule must be approved in advance by the ODOT Project Manager.