This document provides specifications for infrastructure upgrades required for an Electronic Health Records Modernization project at the Fort Harrison VA Medical Center in Montana. The scope of work includes architectural, structural, electrical, HVAC, plumbing and security system upgrades. It also involves upgrading the data and fiber optic infrastructure including the recabling of all existing data cabling campus wide to CAT6A, installing new precast manholes and conduit duct banks for the fiber backbone between buildings. Additional requirements are abatement of asbestos and lead paint, fire suppression and alarm upgrades, and physical security enhancements such as access control and cameras. The contractor shall demolish existing structures as needed and perform all work in accordance with the specifications and drawings to ready the site and buildings for the new EHR system. The federal agency issuing this solicitation is the Department of Veterans Affairs Technology Acquisition Center located in Austin, Texas.
View the file
Other files
Show all 35
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Construction Documents – 100% Submittal:
Technical Specifications – Appendix B
Equipment Naming Convention
May 20, 2022
Department of Veterans Health Administration
Electronic Health Record Modernization (EHRM)
Infrastructure Upgrades – Fort Harrison, MT
Contract No. 36C77621C0112
Montana VA Health Care System
Fort Harrison
3687 Veterans Drive
Fort Harrison, Montana 59636
US Department of Veterans Affairs
Program Contracting Activity Central (PCAC)
6150 Oak Tree Blvd., Suite 300
Independence, OH 44131
Prepared by:
GDM of Oregon
1401 W 34th Ave Suite 200
Anchorage, Alaska 99503
Montana VA Health Care System (MVAHCS) 100% Construction Documents
Fort Harrison, MT 5/20/2022
Electronic Health Records Modernization (EHRM)
Infrastructure Upgrades
Fort Harrison, MT
VA Project No. 463-21-700
EQUIPMENT NAMING CONVENTION
TABLE OF CONTENTS
Page #
Unique Equipment Identification and Acronyms………………………………………………………1-6
VAMT
LOTO And Equipment
Inventory Unique Equipment Identification and Acronyms
UNIQUE EQUIPMENT IDENTIFICATION AND ACRONYMS
PART 1. GENERAL
1.01 OVERVIEW
A. This convention identifies mechanical and plumbing equipment naming sequences, including acronyms, for the identification of equipment in the Lockout Tagout instructions.
PART 2. MECHANICAL EQUIPMENT NAMING CONVENTION
1.02 GENERAL
A. The first set of characters are the Building Code. This is 1 - 4 digits and precedes the first dash in the sequence.
Unique Identification in Bold
2 0 0 - X X X X - X X - X X X X
Building Designator
B. Following the Building Designator, Equipment Designator and Sequence Designator are dashes which serve as a placeholders.
Unique Identification in Bold
X X X - X X X X - X X - X X X X
Placeholders
C. The second set of characters is the Equipment Designator Code. This is an acronym for the equipment being named and labeled. This does not represent any equipment upstream, or downstream, from the equipment. This code must comply with the Equipment Acronym List.
For example, a Hot Water Pump for an Air Handler will be labeled HWP, and not AHU.
Unique Identification in Bold
X X X - H W P - X X - X X X X
Equipment Designator Code
Ft Harrison Veterans Hospital
Inventory
Ft Harrison Veterans Hospital Unique Equipment Identification and Acronyms
UNIQUE EQUIPMENT IDENTIFICATION AND ACRONYMS
D. The third set of characters is the Sequential Equipment Number. This is a unique sequential NUMBER ONLY. This number set should not have any letters or equipment designation.
Unique Identification in Bold
X X X - X X X X - 3 - X X X X
Sequential Equipment Numbers
E. The fourth and final set of characters are the Service Identifiers. This identification can be the area served by the equipment (ie. 200-AHU-7-OR) or the upstream equipment served (ie. 200-
CHWP-3-CHLR1.
The Service Identifier does not make up the Unique Identification. It is a description which identifies the service of the equipment for personnel use only.
Unique Identification in Bold
X X X - X X X X - X X - I C U
Service Identifiers
F. Examples of a Unique ID for a chilled water pump in Building 200.
1. Unique ID without a Service Identifier:
Chilled Water Pump = CHWP
Example: 200-CHWP-3
2. Example of the same Unique ID for a chilled water pump in Building 200 with a Service Identifier.
Chilled Water Pump = CHWP
Example: 200-CHWP-3-CHLR1
G. Special Note regarding Unique ID with Service Identifier: The Service Identifier does not factor into the Unique ID designation.
1. Two similar pieces of equipment cannot have the same Sequence Number within a building, even if they have different or unique Service Identifiers.
2. Example of correct Unique ID for two chilled water pumps in Building 200 with a Service Identifier.
Example 1: 200-CHWP-3-CHLR1
Example 2: 200-CHWP-9-CHLR3
Inventory
Ft Harrison Veterans Hospital Unique Equipment Identification and Acronyms
UNIQUE EQUIPMENT IDENTIFICATION AND ACRONYMS
In these examples, the sequence number for the CHWP is unique. There is only one CHWP 3 and one CHWP 9. The sequence does not reset, or start at one (1), for a chiller’s pump. This avoids any conflict with the numbering.
3. Example of incorrect Unique ID for two chilled water pumps in Building 200 with a Service Identifier.
Example 1: 200-CHWP-3-CHLR1
Example 2: 200-CHWP-3-CHLR3 (Example is highlighted as an INCORRECT exhibit)
In these examples, the sequence number for the second CHWP is not unique. This error in labelling may result in the lockout or maintenance of the wrong pump.
PART 3. MECHANICAL and PLUMBING ACRONYMS
ABCH Absorbtion Chiller
ACOM Air Compressor Unit
ACU Air Conditioning Unit
ACUC Air Conditioning Unit – Computer Room
ACUP Packaged Air Conditioning Unit
AHU Air Handling Unit
AHUO Outside Air Handling Unit
ANT Acid Neutralization Tank
AS Air Separator
ATS Automatic Transfer Switch
AV Air Valve
AVB Atmospheric Vacuum Breaker
BFP Boiler Feed Pump
BFP Backflow Preventer
BRKR Breaker
CC Cooling Coil
CF Chemical Feeder
CHLR Chiller
CHWP Chilled Water Pump
COCM Carbon Dioxide Cylinder Manifold
COMP Compressor Unit
CONT Condensation Tank
COT Carbon Dioxide Tank
COTG Cleanout To Grade (Exterior)
COWP Pump - Condensing Water
CP Condensate Pump
CPAC Compactor
CR Condensate Receiver
CT Cooling Tower
CTK Compression Tank
CU Condensing Unit
CUAC Air Cooled Condensing Unit
CWHE Chilled Water Heat Exchanger
CWSF Condenser Water Side Stream Filter
CWT Combination Fire And Domestic Water Storage (Surge) Tank
D Damper
DA Deareator
DA Deaerator Tank
DB Dialysis Water Supply and Drain
DGV Dental Gas/Vacuum Zone Valve
DHWRP Domestic Hot Water Recirculating Pump
DIS De-ionized Water System
DISC Disconnect Switch
Inventory
Ft Harrison Veterans Hospital Unique Equipment Identification and Acronyms
UNIQUE EQUIPMENT IDENTIFICATION AND ACRONYMS
DP Distribution Panel
DSTR Duplex Strainer
DWBT Domestic Water Bladder Tank
DWEXT Domestic Hot Water Expansion Tank
DWP Domestic Water Booster Pump
DWPRV Domestic Water Pressure Regulating Valve
DWT Domestic Water Storage (Surge) Tank
EDF Electric Drinking Fountain
EDP Elevator Panel
EF Exhaust Fan - General
EFB Exhaust Fan - Biological
EFC Exhaust Fan - Cage Wash
EFF Exhaust Fan - Fume Hood
EFI Exhaust Fan - Isolation
EFK Exhaust Fan - Kitchen
EFP Pump - Emergency Feedwater
EFR Exhaust Fan - Radiological
EFT Exhaust Fan - Toilet
EHC Electric Heating Coil
ERU Energy Recovery Unit
ES Emergency Shower
ESEW Emergency Shower and Eyewash Unit
ESP Elevator Sump Pump
ETK Expansion Tank
EUH Electric Unit Heater
EW Eyewash
EWC Electric Water Cooler
EWH Electric Water Heater
FCO Floor Cleanout
FCU Fan Coil Unit
FCV Flow Control Valve
FD Fire Damper
FD Floor Drain
FDC Fire Department Connection
FFH Final Filter Housing
FHC Fire Hose Cabinet
FLTR Filter Caisson
FM Flow Meter
FOP Pump - Fuel Oil
FOT Fuel Oil Tank (Diesel)
FP Fire Protection Water Pump
FPATS Fire Pump Automatic Transfer Switch
FPBFP Fire Protection Backflow Preventer
FPDAC Fire Protection Dry Air Compressor
FPSG Fire Pump Switch Gear Assembly
FS Floor Sink
FSD Fire/Smoke Damper
FTK Flash Tank
FWT Fire Protection Water Storage (Surge) Tank
GCC Glycol Cooling Coil
GCH Glycol Chiller
GEN Emergency Generator
GI Grease Interceptor
GUH Gas Unit Heater
GWH Gas Fired Domestic Water Heater
HB Hose Bibb
HC Hot Water Heating Coil
HD Humidifier
HED Electric Duct Heater
HEX Steam to Water Heat Exchanger
HOP Pump - Heating Oil
HPAC Electric Heat Pump
HRCH Heat Recovery Chiller
HUH Hot Water Unit Heater
HWB Hot Water Boiler
HWP Hot Water Pump
IW Indirect Waste Receptor
Inventory
Ft Harrison Veterans Hospital Unique Equipment Identification and Acronyms
UNIQUE EQUIPMENT IDENTIFICATION AND ACRONYMS
JP Jockey Pump
LAC Laboratory Air Compressor
LAV Lavatory
LGA Lavatory Gas/Vacuum Local Alarm Panel
LGMA Laboratory Gas/Vacuum Master Alarm Panel
LGV Laboratory Gas/Vacuum Zone Valve
LI Linter Interceptor
LNT Liquid Nitrogen Tank
LOT Liquid Oxygen Tank
LVP Laboratory Vacuum Pump
MAC Medical Air Compressor
MCC Motor Control Center
MGA Medical Gas/Vacuum Local Alarm Panel
MGMA Medical Gas/Vacuum Master Alarm Panel
MGV Medical Gas/Vacuum Zone Valve
MOTE Motor - Elevator
MS Mop Sink
MSB Main Switch Board
MSG Main Switchgear
MVP Medical Vacuum Pump
NCM Nitrogen Cylinder Manifold
NOCM Nitrous Oxide Cylinder Manifold
OCM Oxygen Cylinder Manifold
OD Overflow Roof Drain (Secondary)
OH Oil Heater
OI Oil Interceptor
P Pump
PPUR Pump - Purge
PRS Pressure Reducing Station
PT Plaster Trap
PVB Pressure Vacuum Breaker
RD Roof Drain (Primary)
RF Return Fan – General
ROS Reverse Osmosis System
SA Shock Absorber (Water Hammer Arrestor)
SAMPW Sampling Well (Exterior Drainage)
SB Steam Boiler
SC Steam Heating Coil
SD Smoke Damper
SE Sewage Ejector
SF Supply Fan - General
SG Clean Steam Generator
SH Shower
SK Sink
SP Sump Pump
SPAC Steam Pac
SPF Stairwell Pressurization Fan
STP Storm Sump Pump
SWH Steam Domestic Water heater
T Transformer
TD Trench Drain
TE Transformer (Emergency Power)
TMV Thermostatic Master Mixing Valve
TN Transformer (Normal Power)
TP Trap Primer
UPS Uninterruptible Power System
UR Urinal
VACP Pump - Vacuum
VAV VAV Terminal Unit
VAVF VAV Terminal Unit – Fan Powered
VFD Variable Frequency Drive
WC Water Closet (Toilet)
WCO Wall Cleanout
WH Wall Hydrant
WS Water Softener
Inventory
Ft Harrison Veterans Hospital Unique Equipment Identification and Acronyms
UNIQUE EQUIPMENT IDENTIFICATION AND ACRONYMS
REFERENCES
This document incorporates the Acronym and Equipment lists, with adaptations for specific use at the SFVA, from The University of Texas, Baylor University, and the MD Anderson Cancer Center. ODG080113
The Unique Identification convention detailed in this document is consistent with the LOCKOUT TAGOUT application for iOS, version 1.0 #7 and used for SFVA Lockout Tagout instructions for SFVA Buildings 200, 203 and 205.
The Unique Identification convention detailed in this document follows the identification of equipment for SFVA Engineering, Operations and Maintenance, Lockout Tagout, for 2011- 2013.
Naming Convention Example
00 00 00 cover 100% specs Appedix B