This federal solicitation calls for construction services to complete infrastructure upgrades at the Montana VA Medical Center located in Fort Harrison. The scope of work includes architectural, structural, electrical, HVAC, plumbing, data communication, and civil infrastructure improvements to buildings 141, 154A, 154B, 169, 154, 170, 171, 16, 20, and associated site work. Specific upgrades involve architectural demolition and construction, structural alterations, electrical system and lighting updates, HVAC and control modifications, plumbing modifications, data cabling replacement, fiber infrastructure upgrades, site work including concrete duct banks and manholes, building waterproofing, and landscaping restoration. The project will also abate asbestos and lead paint, install fire suppression and alarm systems, provide firestopping and caulking, and implement physical security enhancements.
View the file
Other files
Show all 35
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
100 % Construction Documents:
Technical Specifications
May 20, 2022
Department of Veterans Health Administration
Electronic Health Record Modernization (EHRM) Infrastructure
Upgrades – Fort Harrison, MT
Contract No. 36C77621C0112
Montana VA Health Care
Fort Harrison Campus
3687 Veterans Dr.
Fort Harrison, MT 59636
US Department of Veterans Affairs
Program Contracting Activity Central (PCAC)
6150 Oak Tree Blvd., Suite 300
Independence, OH 44131
Prepared by:
GDM of Oregon
1000 W Steuben Street, Unit 3
Bingen, WA 98605
Volume 1 Divisions 1 - 13
Montana VA Health Care System (MVAHCS) Fort Harrison, MT
100% Construction Documents 05/20/2022
Electronic Health Records Modernization
(EHRM) Infrastructure Upgrades
Fort Harrison, MT VA Project No. 436-21-700
00 01 10 - 1 of 6
TABLE OF CONTENTS
SECTION 00 01 10
THE SPECIFICATIONS LISTED BELOW FORM A PART OF THE CONTRACT.
DIVISION 00 - SPECIAL SECTIONS # of Pages
00 01 10 Table of Contents……………………………………………………………………5
00 01 15 List of Drawing Sheets……………………………………………………
(See Index Included with Drawings)
DIVISION 01 - GENERAL REQUIREMENTS
01 00 00 General Requirements…………………………………………………………29
01 32 16.15 VA Project Schedule………………………………………………………………9
01 33 00 Submittal Procedures……………………………………………………………8
01 33 23 Shop Drawings, Product Data, and Samples………8
01 35 26 Safety Requirements……………………………………………………………45
01 42 19 Reference Standards………………………………………………………………9
01 45 00 Quality Control………………………………………………………………………10
01 45 29 Testing Laboratory Services………………………………………13
01 57 19 Temporary Environmental Controls……………………………6
01 74 19 Construction Waste Management……………………………………6
01 81 11 Sustainable Construction Requirements………………8
01 91 00 General Commissioning Requirements……………………40
DIVISION 02 – EXISTING CONDITIONS
02 41 00 Selective Demolition……………………………………………………………3
02 81 00 Transportation and Disposal of Hazardous
Materials………………………………………………………………………………………15
02 82 00 Asbestos Remediation…………………………………………………………90
02 83 00 Lead Remediation……………………………………………………………………47
DIVISION 03 – CONCRETE
03 30 00 Cast-In-Place Concrete………………………………………………………35
DIVISION 04 – MASONRY – NOT USED
DIVISION 05 – METALS
05 12 00 Structural Steel Framing…………………………………………………6
05 50 00 Metal Fabrications…………………………………………………………………7
Fort Harrison, MT VA Project No. 436-21-700
00 01 10 - 2 of 6
DIVISION 06 – WOOD, PLASTICS AND COMPOSITES
06 10 00 Rough Carpentry………………………………………………………………………10
06 20 00 Finish Carpentry………………………………………………………………………4
DIVISION 07 - THERMAL AND MOISTURE PROTECTION
07 50 05 Roof Systems…………………………………………………………………………………6
07 51 13.13 Cold-Applied Built-Up Asphalt Roofing………………6
07 53 23 Ethylene-Propylene-Diene-Monomer Roof (EPDM)
System) Patching……………………………………………………………………18
07 71 00 Roof Specialties…………….…………………………………………………… 7
07 84 00 Firestopping…………………………………………………………………………………6
07 92 00 Joint Sealants……………………………………………………………………………8
DIVISION 08 – OPENINGS
08 11 10 Hollow Metal Doors and Frames………………………………… 7
08 14 16 Flush Wood Veneer Doors……………………………………………………5
08 31 13 Access Doors and Frames……………………………………………………5
08 34 00.10 Cold Aisle Containment System……………………………………4
08 34 53 Security Doors AND Frames………………………………………………8
08 71 00 Door Hardware……………………………………………………………………………19
08 90 00 Louvers and Vents……………………………………………………………………4
DIVISION 09 – FINISHES
09 05 16 Subsurface Preparation for Floor Finishes……3
09 06 00 Schedule for Finishes…………………………………………………………2
09 22 16 Non-Structural Metal Framing………………………………………6
09 29 00 Gypsum Board…………………………………………………………………………………5
09 51 13 Acoustical Panel Ceilings……………………………………………10
09 65 13 Resilient Base……………………………………………………………………………2
09 65 36 Static Dissipative Resilient Flooring…………… 6
09 91 00 Painting……………………………………………………………………………………………8
DIVISION 10 – SPECIALTIES
10 14 00 Signage………………………………………………………………………………………………5
10 28 00 Toilet, Bath, and Laundry Accessories………………7
Fort Harrison, MT VA Project No. 436-21-700
00 01 10 - 3 of 6
10 44 13 Fire Extinguisher Cabinets……………………………………………2
DIVISION 11 – EQUIPMENT (NOT USED)
DIVISION 12 – FURNISHINGS (NOT USED)
DIVISION 13 - SPECIAL CONSTRUCTION
13 05 41 Seismic Restraint Requirements for Non-
Structural Components…………………………………………………………9
DIVISION 14– CONVEYING EQUIPMENT (NOT USED)
DIVISION 21- FIRE SUPPRESSION
21 08 00 Commissioning of Fire Suppression Systems……4
21 13 13 Wet-Pipe Sprinkler System Modifications…………6
21 13 45 Sprinkler Guards………………………………………………………………………2
21 22 00 Clean Agent Fire Suppression System…………………18
DIVISION 22 – PLUMBING
22 05 11 Common Work Results for Plumbing…………………………27
22 05 23 General-Duty Valves for Plumbing Piping…………7
22 07 11 Plumbing Insulation………………………………………………………………9
22 08 00 Commissioning of Plumbing Systems…………………………3
22 11 00 Facility Water Distribution…………………………………………8
22 13 00 Facility Sanitary and Vent Piping………………………12
22 14 29 Sump Pumps………………………………………………………………………………………5
22 62 00 Vacuum Systems for Laboratory and Healthcare
Facilities……………………………………………………………………………………15
22 63 00 Gas Systems for Laboratory and Healthcare
Facilities……………………………………………………………………………………12
DIVISION 23 – HEATING, VENTILATING, AND AIR CONDITIONING (HVAC)
23 05 11 Common Work Results for HVAC……………………………………30
23 05 41 Noise and Vibration Control for HVAC Piping and
Equipment………………………………………………………………………………………9
23 05 93 Testing, Adjusting, and Balancing for
HVAC……………………………………………………………………………………………………10
23 07 11 HVAC and Boiler Plant Insulation…………………………12
23 08 00 Commissioning of HVAC Systems……………………………………4
23 09 23 Direct-Digital Control System for HVAC…………82
Fort Harrison, MT VA Project No. 436-21-700
00 01 10 - 4 of 6
23 21 13 Hydronic Piping………………………………………………………………………21
23 23 00 Refrigerant Piping…………………………………………………………………9
23 31 00 HVAC Ducts and Casings………………………………………………………9
23 36 00 Air Terminal Units…………………………………………………………………4
23 37 00 Air Outlets and Inlets………………………………………………………4
23 81 23 Computer-Room Air-Conditioners………………………………15
DIVISION 25 – INTEGRATED AUTOMATION (NOT USED)
DIVISION 26 – ELECTRICAL
26 05 11 Requirements for Electrical Installations…12
26 05 19 Low-Voltage Electrical Power Conductors and
Cables…………………………………………………………………………………………………9
26 05 26 Grounding and Bonding for Electrical
Systems………………………………………………………………………………………………8
26 05 33 Raceway and Boxes for Electrical Systems……16
26 05 41 Underground Electrical Construction…………………10
26 05 73 Overcurrent Protective Device Coordination
Study……………………………………………………………………………………………………5
26 24 16 Panelboards……………….…………………………………………………………………7
26 27 26 Wiring Devices……………………………………………………………………………9
26 29 21 Enclosed Switches and Circuit Breakers……………6
26 33 53 Static Uninterruptible Power Supply…………………26
26 43 13 Surge Protective Devices…………………………………………………3
26 51 00 Interior Lighting…………………………………………………………………10
DIVISION 27 – COMMUNICATIONS
27 05 26 Grounding and Bonding for Communication
Systems………………………………………………………………………………………………6
27 05 33 Conduits and Backboxes for Communications
Systems……………………………………………………………………………………………12
27 05 36 Cable Trays for Communication Systems………………3
27 05 53 Identification for Communications Systems……2
27 10 00 Structured Cabling…………………………………………………………………5
27 11 16 Communications Cabinets, Racks, Frames, and
Enclosures………………………………………………………………………………………5
Fort Harrison, MT VA Project No. 436-21-700
00 01 10 - 5 of 6
27 11 19 Communications Termination Blocks and Patch
Panels…………………………………………………………………………………………………4
27 11 26 Communications Rack Mounted Power Protection and Power Strips………………………………………………………………………4
27 13 13 Communications Copper Backbone Cabling……………2
27 13 13.13 Communications Copper Cable Splicing and
Terminations…………………………………………………………………………………2
27 13 23 Communications Optical Fiber Backbone
Cabling………………………………………………………………………………………………3
27 15 13 Communications Copper Horizontal Cabling………2
27 15 13.13 Communications Optical Fiber Cable Splicing and
Terminations…………………………………………………………………………………1
27 16 19 Communications Patch Cords, Station Cords, and
Cross Connect Wire…………………………………………………………………2
DIVISION 28 – ELECTRONIC SAFETY AND SECURITY (NOT USED)
DIVISION 31 – EARTHWORK
31 20 11 Earthwork………………………………………………………………………………………18
31 23 19 Dewatering…………………………………………………………………………………….6
31 23 23.33 Flowable Fill………………………………………………………………………………8
DIVISION 32 – EXTERIOR IMPROVEMENTS
32 05 23 Cement and Concrete for Exterior
Improvements.………………………………………………………………………………19
32 12 16 Asphalt Paving……………………………………………………………………………7
32 17 23 Pavement Markings …………………………………………………………………7
32 90 05 Turfgrass Sodding……………………………………………………………………4
DIVISION 33 – UTILITIES (NOT USED)
DIVISION 34 – TRANSPORTATION (NOT USED)
DIVISION 48 – ELECTRICAL POWER GENERATION (NOT USED)
APPENDIX A – HAZARDOUS MATERIALS SURVEY……………………………………………………………………………………132
APPENDIX B – VA EQUIPMENT NAMING CONVENTION………………………………………………………………………………6
- - - E N D - - -
Fort Harrison, MT VA Project No. 436-21-700
00 01 10 - 6 of 6
- - - THIS PAGE LEFT INTENTIONALLY BLANK - - -
System (MVAHCS) Fort Harrison, MT
09/15/2022
Fort Harrison, MT VA Project No. 436-21-700
01 00 00 - 1/27
GENERAL REQUIREMENTS
SECTION 01 00 00
GENERAL
1.1 SAFETY REQUIREMENTS
A. Refer to section 01 35 26, SAFETY REQUIREMENTS for safety and infection control requirements.
1.2 GENERAL INTENTION
Contractor shall completely prepare site for building operations, including demolition and removal of existing structures, and furnish labor and materials and perform work for Electronic Health Records
Modernization(EHRM) Infrastructure Upgrades, Fort Harrison, MT VA
Project No. 436-21-700 as required by drawings and specifications.
A. Visits to the site by Bidders shall be made in accordance with the solicitation.
B. Offices of GDM of Oregon as Architect-Engineers, will render certain technical services during construction. Such services shall be considered as advisory to the
Government and shall not be construed as expressing or implying a contractual act of the Government without affirmations by Contracting
Officer or his duly authorized representative.
C. Work subject to tests and/or testing laboratory shall be retained by
General Contractor. Also see 014529 Testing and Laboratory Services, and 019100 General Commissioning Requirements.
D. All employees of general contractor and subcontractors shall comply with VA security management program and obtain permission of the VA police, be identified by project and employer, and restricted from unauthorized access.
1.3 STATEMENT OF BID ITEM(S)
A. ITEM I, General Construction:
1. Work includes general construction, alterations, necessary removal and/or modifications of existing structures and construction, patching and finishing work, and certain other items.
Fort Harrison, MT
Fort Harrison, MT VA Project No. 436-21-700
01 00 00 - 2/27
B. ITEM II, Mechanical Work:
1. Work includes all labor, material, equipment and supervision to perform the required Mechanical construction work on this project including:
a. Installation of new split system air conditioning units.
b. Modifications to existing DDC controls.
c. Setup, programming, and adjustment of new & modified systems.
C. ITEM III, Electrical System Work:
1. Work includes all labor, material, equipment and supervision to perform the required electrical and telecommunications systems construction work on this project including:
a. Provide new power connections for new mechanical equipment.
b. Provide new power connections for MDF/IDF rack locations.
c. Provide new UPS units for MDF/IDF locations.
D. ITEM IV, Hazardous Materials Allowance:
In addition to the work included in Base Bid Items I-III, this project will require an ALLOWANCE of $165,000.00 to account for all work related to asbestos and lead paint abatement. Hazardous material removal shall not be included in any other line item as part of the bid. This includes all hazardous abatement submittals, planning, and work required in the specifications and drawings, as well as any unidentified hazardous material abatement. If at the end of the project, there are funds left over from this allowance, the VA shall be credited this amount.
If for some reason the amount of asbestos work in this Bid Item exceeds the allowance, the contractor shall notify the Post Award
Contracting Officer immediately for direction. The amount of work performed for this Bid Item must be tracked for billing purposes.
1.4 SPECIFICATIONS AND DRAWINGS FOR CONTRACTOR
A. Drawings and contract documents may be obtained from the website where the solicitation is posted. Additional copies will be at Contractor's expense.
1.5 CONSTRUCTION SECURITY REQUIREMENTS
A. Security Plan:
Fort Harrison, MT
Fort Harrison, MT VA Project No. 436-21-700
01 00 00 - 3/27
1. The security plan defines both physical and administrative security procedures that will remain effective for the entire duration of the project.
2. The General Contractor is responsible for assuring that all sub-contractors working on the project and their employees also comply with these regulations.
B. Security Procedures:
1. General Contractor’s employees shall not enter the project site without appropriate badge. They may also be subject to inspection of their personal effects when entering or leaving the project site.
2. Before starting work the General Contractor shall give one week’s notice to the Contracting Officer so that security escort and arrangements can be provided for the employees. This notice is separate from any notices required for utility shutdown described later in this section.
3. No photography of VA premises is allowed without written permission of the Contracting Officer. Patients and staff are not to be photographed at any time.
4. VA reserves the right to close down or shut down the project site and order General Contractor’s employees off the premises in the event of a national emergency. The General Contractor may return to the site only with the written approval of the Contracting Officer.
C. Key Control:
1. Only a limited number of keys will be issued to the contractor. Key requests shall be made in writing to the COR.
2. If the Contractor loses a key, a charge of $30 will be billed for a replacement key.
3. Ensure all doors leading to and from construction are either monitored or locked to prevent access to the area from unauthorized persons.
D. Document Control:
1. Before starting any work, the General Contractor/Sub Contractors shall submit an electronic security memorandum describing the approach to following goals and maintaining confidentiality of
“sensitive information”.
Fort Harrison, MT
Fort Harrison, MT VA Project No. 436-21-700
01 00 00 - 4/27
2. The General Contractor is responsible for safekeeping of all drawings, project manual and other project information. This information shall be shared only with those with a specific need to accomplish the project.
3. Certain documents, sketches, videos or photographs and drawings may be marked “Law Enforcement Sensitive” or “Sensitive Unclassified”.
Secure such information in separate containers and limit the access to only those who will need it for the project. Return the information to the Contracting Officer upon request.
4. These security documents shall not be removed or transmitted from the project site without the written approval of Contracting
Officer.
5. All paper waste or electronic media such as CD’s and diskettes shall be shredded and destroyed in a manner acceptable to the VA.
6. Notify Contracting Officer and Site Security Officer immediately when there is a loss or compromise of “sensitive information”.
7. All electronic information shall be stored in specified location following VA standards and procedures using an Engineering Document
Management Software (EDMS).
Security, access and maintenance of all project drawings, both scanned and electronic shall be performed and tracked through the
EDMS system.
“Sensitive information” including drawings and other documents may be attached to e-mail provided all VA encryption procedures are followed.
E. Motor Vehicle Restrictions
1. Contractor may have designated areas pending campus activities, to be coordinated by the COR or COR representative.
1.6 OPERATIONS AND STORAGE AREAS (FAR 52.236-10)
A. The Contractor shall confine all operations (including storage of materials) on Government premises to areas authorized or approved by the Contracting Officer. The Contractor shall hold and save the
Government, its officers and agents, free and harmless from liability of any nature occasioned by the Contractor's performance.
Fort Harrison, MT
Fort Harrison, MT VA Project No. 436-21-700
01 00 00 - 5/27
B. Temporary buildings (e.g., storage sheds, shops, offices) and utilities may be erected by the Contractor only with the approval of the
Contracting Officer and shall be built with labor and materials furnished by the Contractor without expense to the Government. The temporary buildings and utilities shall remain the property of the
Contractor and shall be removed by the Contractor at its expense upon completion of the work. With the written consent of the Contracting
Officer, the buildings and utilities may be abandoned and need not be removed.
C. The Contractor shall, under regulations prescribed by the Contracting
Officer, use only established roadways, or use temporary roadways constructed by the Contractor when and as authorized by the Contracting
Officer. When materials are transported in prosecuting the work, vehicles shall not be loaded beyond the loading capacity recommended by the manufacturer of the vehicle or prescribed by any Federal, State, or local law or regulation. When it is necessary to cross curbs or sidewalks, the Contractor shall protect them from damage. The
Contractor shall repair or pay for the repair of any damaged to curbs, sidewalks, and roads.
D. *** Lay down area, conditioned storage area for fiber/etc, working space and space available on campus for storing materials shall be the procured by the contractor unless identified on the drawings. ***
E. Workers are subject to rules of Medical Center applicable to their conduct.
F. N/A G. Execute work so as to interfere as little as possible with normal functioning of Medical Center as a whole, including operations of utility services, fire protection systems and any existing equipment, and with work being done by others. Use of equipment and tools that transmit vibrations and noises through the building structure, are not permitted in buildings that are occupied, during construction, jointly by patients or medical personnel, and Contractor's personnel, except as permitted by COR where required by limited working space.
1. Do not store materials and equipment in other than assigned areas.
Fort Harrison, MT
Fort Harrison, MT VA Project No. 436-21-700
01 00 00 - 6/27
2. Schedule delivery of materials and equipment to immediate construction working areas within buildings in use by Department of
Veterans Affairs in quantities sufficient for not more than two work days. Provide unobstructed access to Medical Center areas required to remain in operation.
3. Where access by Medical Center personnel to vacated portions of buildings is not required, storage of Contractor's materials and equipment will be permitted subject to fire and safety requirements.
H. Utilities Services: Where necessary to cut existing pipes, electrical wires, conduits, cables, etc., of utility services, or of fire protection systems or communications systems (except telephone), they shall be cut and capped at suitable places where shown; or, in absence of such indication, where directed by COR . All such actions shall be coordinated with the COR or Utility Company involved:
1. Whenever it is required that a connection fee be paid to a public utility provider for new permanent service to the construction project, for such items as water, sewer, electricity, gas or steam, payment of such fee shall be the responsibility of the Government and not the Contractor.
I. Phasing:
1. The Medical Center must maintain its operation 24 hours a day 7 days a week. Therefore, any interruption in service must be scheduled and coordinated with the COR to ensure that no lapses in operation occur.
It is the CONTRACTOR'S responsibility to develop a work plan and schedule detailing, at a minimum, the procedures to be employed, the equipment and materials to be used, the interim life safety measure to be used during the work, and a schedule defining the duration of the work with milestone subtasks.
2. To ensure such executions, Contractor shall furnish the COR with a schedule of approximate phasing dates on which the Contractor intends to accomplish work in each specific area of site, building or portion thereof. In addition, Contractor shall notify the COR two weeks in advance of the proposed date of starting work in each specific area of site, building or portion thereof. Arrange such phasing dates to ensure accomplishment of this work in successive phases mutually agreeable to COR.
Fort Harrison, MT
Fort Harrison, MT VA Project No. 436-21-700
01 00 00 - 7/27
3. Contractor shall take all measures and provide all material necessary for protecting existing equipment and property in affected areas of construction against dust and debris, so that equipment and affected areas to be used in the Medical Centers operations will not be hindered. Contractor shall permit access to Department of
Veterans Affairs personnel and patients through other construction areas which serve as routes of access to such affected areas and equipment. These routes whether access or egress shall be isolated from the construction area by temporary partitions and have walking surfaces, lighting etc. to facilitate patient and staff access.
Coordinate alteration work in areas occupied by Department of
Veterans Affairs so that Medical Center operations will continue during the construction period.
4. N/A.
J. Construction Fence: Before construction operations begin, Contractor shall provide a chain link construction fence, 2.1m (seven feet) minimum height, around the construction area indicated on the drawings.
Provide gates as required for access with necessary hardware, including hasps and padlocks. Fasten fence fabric to terminal posts with tension bands and to line posts and top and bottom rails with tie wires spaced at maximum 375mm (15 inches). Bottom of fences shall extend to 25mm
(one inch) above grade. Remove the fence when directed by COR.
K. When a building and/or construction site is turned over to Contractor, Contractor shall accept entire responsibility including upkeep and maintenance therefore:
1. Contractor shall maintain a minimum temperature of 4 degrees C (40 degrees F) at all times, except as otherwise specified.
2. Contractor shall maintain in operating condition existing fire protection and alarm equipment. In connection with fire alarm equipment, Contractor shall make arrangements for pre-inspection of site with Fire Department or Company (Department of Veterans Affairs or municipal) whichever will be required to respond to an alarm from
Contractor's employee or watchman.
L. Utilities Services: Maintain existing utility services for Medical
Center at all times. Provide temporary facilities, labor, materials, Fort Harrison, MT
Fort Harrison, MT VA Project No. 436-21-700
01 00 00 - 8/27 equipment, connections, and utilities to assure uninterrupted services.
Where necessary to cut existing water, steam, gases, sewer or air pipes, or conduits, wires, cables, etc. of utility services or of fire protection systems and communications systems (including telephone), they shall be cut and capped at suitable places where shown; or, in absence of such indication, where directed by COR.
1. No utility service such as water, gas, steam, sewers or electricity, or fire protection systems and communications systems may be interrupted without prior approval of COR. Electrical work shall be accomplished with all affected circuits or equipment de-energized.
When an electrical outage cannot be accomplished, work on any energized circuits or equipment shall not commence without a detailed work plan. Refer to specification Sections 26 05 11, REQUIREMENTS FOR ELECTRICAL INSTALLATIONS, 27 05 11 REQUIREMENTS FOR
COMMUNICATIONS .
2. Contractor shall submit a request to interrupt any such services to
COR, in writing, 7 days in advance of proposed interruption. Request shall state reason, date, exact time of, and approximate duration of such interruption.
3. Contractor will be advised (in writing) of approval of request, or of which other date and/or time such interruption will cause least inconvenience to operations of Medical Center. Interruption time approved by Medical Center may occur at other than Contractor's normal working hours.
4. Major interruptions of any system must be requested, in writing, at least 15 calendar days prior to the desired time and shall be performed as directed by the COR.
5. In case of a contract construction emergency, service will be interrupted on approval of COR. Such approval will be confirmed in writing as soon as practical.
6. Whenever it is required that a connection fee be paid to a public utility provider for new permanent service to the construction project, for such items as water, sewer, electricity, gas or steam, payment of such fee shall be the responsibility of the Government and not the Contractor.
Fort Harrison, MT
Fort Harrison, MT VA Project No. 436-21-700
01 00 00 - 9/27
M. Abandoned Lines: All service lines such as wires, cables, conduits, ducts, pipes and the like, and their hangers or supports, shall be removed back to their source. Those which are indicated to be abandoned but are not required to be entirely removed, shall be sealed, capped or plugged at the main, branch or panel they originate from. The lines shall not be capped in finished areas, but shall be removed and sealed, capped or plugged in ceilings, within furred spaces, in unfinished areas, or within walls or partitions; so that they are completely behind the finished surfaces.
N. To minimize interference of construction activities with flow of
Medical Center traffic, comply with the following:
1. Keep roads, walks and entrances to grounds, to parking and to occupied areas of buildings clear of construction materials, debris and standing construction equipment and vehicles. Wherever excavation for new utility lines cross existing roads, at least one lane must be open to traffic at all times with approval.
2. Method and scheduling of required cutting, altering and removal of existing roads, walks and entrances must be approved by the COR.
O. Coordinate the work for this contract with other construction operations as directed by COR. This includes the scheduling of traffic and the use of roadways.
P. N/A
1.7 ALTERATIONS
A. Survey: Before any work is started, the Contractor shall make a thorough survey with the COR and a representative of VA Supply Service, buildings and campus in which alterations occur and areas which are anticipated routes of access, and furnish a report, signed by COR and contractor. This report shall list by rooms and spaces:
1. Existing condition and types of resilient flooring, doors, windows, walls and other surfaces not required to be altered throughout affected areas of buildings.
2. Existence and conditions of items such as plumbing fixtures and accessories, electrical fixtures, equipment, venetian blinds, shades, etc., required by drawings to be either reused or relocated, or both.
Fort Harrison, MT
Fort Harrison, MT VA Project No. 436-21-700
01 00 00 - 10/27
3. Shall note any discrepancies between drawings and existing conditions at site.
4. Shall designate areas for working space, materials storage and routes of access to areas within buildings where alterations occur and which have been agreed upon by Contractor and COR.
B. Any items required by drawings to be either reused or relocated or both, found during this survey to be nonexistent, or in opinion of COR, to be in such condition that their use is impossible or impractical, shall be furnished and/or replaced by Contractor with new items in accordance with specifications which will be furnished by Government.
Provided the contract work is changed by reason of this subparagraph B, the contract will be modified accordingly, under provisions of clause entitled "DIFFERING SITE CONDITIONS" (FAR 52.236-2) and "CHANGES" (FAR
52.243-4).
C. Re-Survey: Thirty days before expected partial or final inspection date, the Contractor and COR together shall make a thorough re-survey of the areas of buildings involved. They shall furnish a report on conditions then existing, of resilient flooring, doors, windows, walls and other surfaces as compared with conditions of same as noted in first condition survey report:
1. Re-survey report shall also list any damage caused by Contractor to such flooring and other surfaces, despite protection measures; and, will form basis for determining extent of repair work required of
Contractor to restore damage caused by Contractor's workers in executing work of this contract.
D. Protection: Provide the following protective measures:
1. Wherever existing roof surfaces are disturbed they shall be protected against water infiltration. In case of leaks, they shall be repaired immediately upon discovery.
2. Temporary protection against damage for portions of existing structures and grounds where work is to be done, materials handled and equipment moved and/or relocated.
3. Protection of interior of existing structures at all times, from damage, dust and weather inclemency. Wherever work is performed, floor surfaces that are to remain in place shall be adequately
Fort Harrison, MT
Fort Harrison, MT VA Project No. 436-21-700
01 00 00 - 11/27 protected prior to starting work, and this protection shall be maintained intact until all work in the area is completed.
1.8 DISPOSAL AND RETENTION
A. Materials and equipment accruing from work removed and from demolition of buildings or structures, or parts thereof, shall be disposed of as follows:
1. Reserved items which are to remain property of the Government are identified by attached tags and/or noted on drawings or in specifications. Items that remain property of the Government shall be removed or dislodged from present locations in such a manner as to prevent damage which would be detrimental to re-installation and reuse. Store such items where directed by COR.
2. Items not reserved shall become property of the Contractor and be removed by Contractor from Medical Center.
3. Items of portable equipment and furnishings located in rooms and spaces in which work is to be done under this contract shall remain the property of the Government. Room owner will not be occupying the space during construction, however the room office equipment will remain. **** It shall be the construction contractor responsibility to “gently move” office equipment locally (desks, chairs, cabinets, etc) to complete the construction work, clean, and return office equipment to their original locations. Contractor shall understand the VA does not have labor to assist with this effort.****
4. If applicable PCB Transformers and Capacitors: The Contractor shall be responsible for disposal of the Polychlorinated Biphenyl (PCB) transformers and capacitors. The transformers and capacitors shall be taken out of service and handled in accordance with the procedures of the Environmental Protection Agency (EPA) and the
Department of Transportation (DOT) as outlined in Code of Federal
Regulation (CFR), Titled 40 and 49 respectively. The EPA's Toxic
Substance Control Act (TSCA) Compliance Program Policy Nos. 6-PCB-6 and 6-PCB-7 also apply. Upon removal of PCB transformers and capacitors for disposal, the "originator" copy of the Uniform
Hazardous Waste Manifest (EPA Form 8700-22), along with the Uniform
Hazardous Waste Manifest Continuation Sheet (EPA Form 8700-22A) shall be returned to the Contracting Officer who will annotate the
Fort Harrison, MT
Fort Harrison, MT VA Project No. 436-21-700
01 00 00 - 12/27 contract file and transmit the Manifest to the Medical Center's
Cemetery's Chief.
a) Copies of the following listed CFR titles may be obtained from the Government Printing Office:
40 CFR 261........Identification and Listing of Hazardous Waste
40 CFR 262........Standards Applicable to Generators of Hazardous
Waste
40 CFR 263........Standards Applicable to Transporters of
Hazardous Waste
40 CFR 761........PCB Manufacturing, Processing, Distribution in
Commerce, and use Prohibitions
49 CFR 172........Hazardous Material tables and Hazardous
Material Communications Regulations
49 CFR 173........Shippers - General Requirements for Shipments and Packaging
49 CRR 173........Subpart A General
49 CFR 173........Subpart B Preparation of Hazardous Material for
Transportation
49 CFR 173........Subpart J Other Regulated Material; Definitions and Preparation
TSCA..............Compliance Program Policy Nos. 6-PCB-6 and 6-
PCB-7
1.9 PROTECTION OF EXISTING VEGETATION, STRUCTURES, EQUIPMENT, UTILITIES, AND
IMPROVEMENTS (FAR 52.236-9)
A. The Contractor shall preserve and protect all structures, equipment, and vegetation (such as trees, shrubs, and grass) on or adjacent to the work site, which are not to be removed and which do not unreasonably interfere with the work required under this contract. The Contractor shall only remove trees when specifically authorized to do so, and shall avoid damaging vegetation that will remain in place. If any limbs or branches of trees are broken during contract performance, or by the careless operation of equipment, or by workers, the Contractor shall trim those limbs or branches with a clean cut and paint the cut with a tree-pruning compound as directed by the COR.
Fort Harrison, MT
Fort Harrison, MT VA Project No. 436-21-700
01 00 00 - 13/27
B. The Contractor shall protect from damage all existing improvements and utilities at or near the work site and on adjacent property of a third party, the locations of which are made known to or should be known by the Contractor. The Contractor shall repair any damage to those facilities, including those that are the property of a third party, resulting from failure to comply with the requirements of this contract or failure to exercise reasonable care in performing the work. If the
Contractor fails or refuses to repair the damage promptly, the
Contracting Officer may have the necessary work performed and charge the cost to the Contractor.
C. Refer to Section 01 57 19, TEMPORARY ENVIRONMENTAL CONTROLS, for additional requirements on protecting vegetation, soils and the environment. Refer to Articles, "Alterations", "Restoration", and
"Operations and Storage Areas" for additional instructions concerning repair of damage to structures and site improvements.
D. Refer to FAR clause 52.236-7, "Permits and Responsibilities," which is included in General Conditions. A National Pollutant Discharge
Elimination System (NPDES) permit is required for this project. The
Contractor is considered an "operator" under the permit and has extensive responsibility for compliance with permit requirements. VA will make the permit application available at the (appropriate medical center) office. The apparent low bidder, contractor and affected subcontractors shall furnish all information and certifications that are required to comply with the permit process and permit requirements.
Many of the permit requirements will be satisfied by completing construction as shown and specified. Some requirements involve the
Contractor's method of operations and operations planning and the
Contractor is responsible for employing best management practices. The affected activities often include, but are not limited to the following:
1. Designating areas for equipment maintenance and repair;
2. Providing waste receptacles at convenient locations and provide regular collection of wastes;
3. Locating equipment wash down areas on site, and provide appropriate control of wash-waters;
Fort Harrison, MT
Fort Harrison, MT VA Project No. 436-21-700
01 00 00 - 14/27
4. Providing protected storage areas for chemicals, paints, solvents, fertilizers, and other potentially toxic materials; and
5. Providing adequately maintained sanitary facilities.
1.10 RESTORATION
A. Remove, cut, alter, replace, patch and repair existing work as necessary to install new work. Except as otherwise shown or specified, do not cut, alter or remove any structural work, and do not disturb any ducts, plumbing, steam, gas, or electric work without approval of the
COR. Existing work to be altered or extended and that is found to be defective in any way, shall be reported to the COR before it is disturbed. Materials and workmanship used in restoring work, shall conform in type and quality to that of original existing construction, except as otherwise shown or specified.
B. Upon completion of contract, deliver work complete and undamaged.
Existing work (walls, ceilings, partitions, floors, mechanical and electrical work, lawns, paving, roads, walks, etc.) disturbed or removed as a result of performing required new work, shall be patched, repaired, reinstalled, or replaced with new work, and refinished and left in as good condition as existed before commencing work.
C. At Contractor's own expense, Contractor shall immediately restore to service and repair any damage caused by Contractor's workers to existing piping and conduits, wires, cables, etc., of utility services or of fire protection systems and communications systems (including telephone) which are not scheduled for discontinuance or abandonment.
D. Expense of repairs to such utilities and systems not shown on drawings or locations of which are unknown will be covered by adjustment to contract time and price in accordance with clause entitled "CHANGES"
(FAR 52.243-4) and "DIFFERING SITE CONDITIONS" (FAR 52.236-2).
1.11 AS-BUILT DRAWINGS
A. The contractor shall maintain two full size sets of as-built drawings which will be kept current during construction of the project, to include all contract changes, modifications and clarifications.
B. All variations shall be shown in the same general detail as used in the contract drawings. To ensure compliance, AutoCAD (DWG) as-builts, complete with all relevant shape files, XREFS, fonts, tables, and other
Fort Harrison, MT
Fort Harrison, MT VA Project No. 436-21-700
01 00 00 - 15/27 background implementations/links necessary to recreate the Acrobat PDF files provided in full, shall be made available for the COR review, as often as requested. Scanned PDFs of as-builts are not acceptable. They must be AutoCAD exported PDFs, complete with the appropriate layers.
Only red-line versions of field drawings may be scanned as PDFs.as-built drawings.
C. Contractor shall deliver two approved completed sets of as-built drawings in the electronic version (scanned PDF) to the COR within 15 calendar days after each completed phase and after the acceptance of the project by the COR.
D. Paragraphs A, B, & C shall also apply to all shop drawings.
1.12 WARRANTY MANAGEMENT
A. Warranty Management Plan: Develop a warranty management plan which contains information relevant to FAR 52.246-21 Warranty of Construction in at least 30 days before the planned pre-warranty conference, submit two sets of the warranty management plan. Include within the warranty management plan all required actions and documents to assure that the
Government receives all warranties to which it is entitled. The plan must be in narrative form and contain sufficient detail to render it suitable for use by future maintenance and repair personnel, whether tradesman, or of engineering background, not necessarily familiar with this contract. The term “status” as indicated below must include due date and whether item has been submitted or was approved. Warranty information made available during the construction phase must be submitted to the Contracting Officer for approval prior to each monthly invoice for payment. Assemble approved information in a binder and turn over to the Government upon acceptance of the work. The construction warranty period will begin on the date of the project acceptance and continue for the product warranty period. A joint 4 month and 9 month warranty inspection will be conducted, measured from time of acceptance, by the Contactor and the Contracting Officer. Include in the warranty management plan, but not limited to, the following:
1. Roles and responsibilities of all personnel associated with the warranty process, including points of contact and telephone numbers within the company of the Contractor, subcontractors, manufacturers or suppliers involved.
Fort Harrison, MT
Fort Harrison, MT VA Project No. 436-21-700
01 00 00 - 16/27
2. Furnish with each warranty the name, address and telephone number of each of the guarantor’s representatives nearest project location.
3. Listing and status of delivery of all Certificates of Warranty for extended warranty items, to include roofs, HVAC balancing, pumps, motors, transformers and for all commissioned systems such as fire protection and alarm systems, sprinkler systems and lightning protection systems, etc.
4. A list for each warranted equipment item, feature of construction or system indicating:
a. Name of item.
b. Model and serial numbers.
c. Location where installed.
d. Name and phone numbers of manufacturers and suppliers.
e. Name and phone numbers of manufacturers or suppliers.
f. Names, addresses and phone numbers of sources of spare parts.
g. Warranties and terms of warranty. Include one-year overall warranty of construction, including the starting date of warranty of construction. Items which have extended warranties must be indicated with separate warranty expiration dates.
h. Starting point and duration of warranty period.
i. Summary of maintenance procedures required to continue the warranty in force.
j. Cross-reference to specific pertinent Operation and Maintenance manuals.
k. Organizations, names and phone numbers of persons to call for warranty service.
l. Typical response time and repair time expected for various warranted equipment.
5. The plans for attendance at the 4 and 9-month post construction warranty inspections conducted by the government.
6. Procedure and status of tagging of all equipment covered by extended warranties.
7. Copies of instructions to be posted near selected pieces of equipment where operation is critical for warranty and/or safety reasons.
Fort Harrison, MT
Fort Harrison, MT VA Project No. 436-21-700
01 00 00 - 17/27
B. Performance & Payment Bonds: The Performance & Payment Bonds must remain effective throughout the construction period.
1. In the event the Contractor fails to commence and diligently pursue any construction warranty work required, the Contracting Officer will have the work performed by others, and after completion of the work, will charge the remaining construction warranty funds of expenses incurred by the Government while performing the work, including, but not limited to administrative expenses.
2. In the event sufficient funds are not available to cover the construction warranty work performed by the Government at the contractor’s expenses, the Contracting Officer will have the right to recoup expenses from the bonding company.
3. Following oral or written notification of required construction warranty repair work, the Contractor shall respond in a timely manner. Written verification will follow oral instructions. Failure to respond will be cause for the Contracting Officer to proceed against the Contractor.
C. Pre-Warranty Conference: Prior to contract completion, and at a time designated by the Contracting Officer, the Contractor shall meet with the Contracting Officer to develop a mutual understanding with respect to the requirements of this section. Communication procedures for
Contractor notification of construction warranty defects, priorities with respect to the type of defect, reasonable time required for
Contractor response, and other details deemed necessary by the
Contracting Officer for the execution of the construction warranty will be established reviewed at this meeting. In connection with these requirements and at the time of the Contractor’s quality control completion inspection, furnish the name, telephone number and address of a licensed and bonded company which is authorized to initiate and pursue construction warranty work action on behalf of the Contractor.
This point of contract will be located within the local service area of the warranted construction, be continuously available and be responsive to Government inquiry on warranty work action and status. This requirement does not relieve the Contractor of any of its responsibilities in conjunction with other portions of this provision.
D. Contractor’s Response to Construction Warranty Service Requirements:
Fort Harrison, MT
Fort Harrison, MT VA Project No. 436-21-700
01 00 00 - 18/27
E. Following written notification by the Contracting Officer, the
Contractor shall respond to construction warranty service requirements in accordance with the “Construction Warranty Service Priority List” and the three categories of priorities listed below. Submit a report on any warranty item that has been repaired during the warranty period.
Include within the report the cause of the problem, date reported, corrective action taken, and when the repair was completed. If the
Contractor does not perform the construction warranty within the timeframe specified, the Government will perform the work and back charge the construction warranty payment item established.
1. First Priority Code 1. Perform onsite inspection to evaluate situation, and determine course of action within 4 hours, initiate work within 6 hours and work continuously to completion or relief.
2. Second Priority Code 2. Perform onsite inspection to evaluate situation, and determine course of action within 8 hours, initiate work within 24 hours and work continuously to completion or relief.
3. Third Priority Code 3. All other work to be initiated within 3 work days and work continuously to completion or relief.
4. The “Construction Warranty Service Priority List” is as follows:
a) Code 1-Life Safety Systems Fire suppression systems.
Fire alarm system(s).
b) Code 1-Air Conditioning Systems Air conditioning leak in part of the building, if causing damage.
Air conditioning system not cooling properly.
c) Code 1 Doors
Overhead doors not operational, causing a security, fire or safety problem.
1) Interior, exterior personnel doors or hardware, not functioning properly, causing security, fire or safety problem.
d) Code 3-Doors Overhead doors not operational.
Fort Harrison, MT
Fort Harrison, MT VA Project No. 436-21-700
01 00 00 - 19/27
Interior/exterior personnel doors or hardware not functioning properly.
e) Code 1-Electrical
Power failure (entire area or any building operational after 1600 hours).
Security lights.
Smoke detectors.
f) Code 2-Electrical
Power failure (no power to a room or part of building).
Receptacle and lights not operational (in a room or part of building).
g) Code 3-Electrical Exterior lights not operational.
h) Code 1-Gas Leaks and pipeline breaks.
i) Code 1-Heat
Power failure affecting heat.
j) Code 1-Plumbing
Hot water heater failure.
2) Leaking water supply pipes
k) Code 2-Plumbing
Flush valves not operating properly Fixture drain, supply line or any water pipe leaking.
Toilet leaking at base.
l) Code 3- Plumbing
Leaky faucets.
m) Code 3-Interior Floors damaged.
Paint chipping or peeling.
Casework damaged.
n) Code 1-Roof Leaks
Damage to property is occurring.
o) Code 2-Water (Exterior)
No water to facility.
p) Code 2-Water (Hot)
No hot water in portion of building listed.
Fort Harrison, MT
Fort Harrison, MT VA Project No. 436-21-700
01 00 00 - 20/27
q) Code 3
All work not listed above.
F. Warranty Tags: At the time of installation, tag each warranted item with a durable, oil and water-resistant tag approved by the Contracting
Officer. Attach each tag with a copper wire and spray with a silicone waterproof coating. Also submit two record copies of the warranty tags showing the layout and design. The date of acceptance and the QC signature must remain blank until the project is accepted for beneficial occupancy. Show the following information on the tag.
Warranty Tags
Type of product/material
Model number
Serial number
Contract number
Warranty period from/to
Inspector’s signature
Construction Contractor
Address
Telephone number
Warranty Contact
Address
Telephone number
Warranty response time priority code
1.13 USE OF ROADWAYS
A. For hauling, use only established public roads and roads on Medical
Center property and, when authorized by the COR, such temporary roads which are necessary in the performance of contract work. Temporary roads shall be constructed and restoration performed by the Contractor at Contractor's expense. When necessary to cross curbing, sidewalks, or similar construction, they must be protected by well-constructed bridges.
B. When certain buildings (or parts of certain buildings) are required to be completed in advance of general date of completion, all roads
Fort Harrison, MT
Fort Harrison, MT VA Project No. 436-21-700
01 00 00 - 21/27 leading thereto must be completed and available for use at time set for completion of such buildings or parts thereof.
1.14 RESIDENT ENGINEER'S FIELD OFFICE: N/A
1.15 TEMPORARY USE OF MECHANICAL AND ELECTRICAL EQUIPMENT
A. Use of new installed mechanical and electrical equipment to provide heat, ventilation, plumbing, light and power will be permitted subject to written approval and compliance with the following provisions:
1. Permission to use each unit or system must be given by COR in writing. If the equipment is not installed and maintained in accordance with the written agreement and following provisions, the
COR will withdraw permission for use of the equipment.
2. Electrical installations used by the equipment shall be completed in accordance with the drawings and specifications to prevent damage to the equipment and the electrical systems, i.e. transformers, relays, circuit breakers, fuses, conductors, motor controllers and their overload elements shall be properly sized, coordinated and adjusted.
Installation of temporary electrical equipment or devices shall be in accordance with NFPA 70, National Electrical Code, (2014
Edition), Article 590,…