ATT 4 Experience Questionairre.pdf

PDF 138 KB Posted

Attached to
Janitorial Services for White Sulphur Springs
Solicitation number
1284LM25Q0058
Issued by

About this file

The document is an Experience Questionnaire from the USDA Forest Service designed to assess a contractor's qualifications for a potential contract. The form requires detailed information about the contractor's business, including years of experience, past project history, current contractual commitments, employee and equipment resources, and key personnel qualifications. Specific sections require contractors to list completed projects from the last three years, ongoing contractual commitments, available employees and equipment, and the experience of principal individuals who will be directly involved in the contract. The form also includes certification language where the contractor attests to the accuracy of the provided information and authorizes the Forest Service to verify their capability to perform the project.

View the file

Other files

File Type Posted
1284LM25Q0058_0001.pdf PDF
ATT 1 Revised Statement of Work.pdf PDF
ATT 2 Revised Quality Assurance Plan.pdf PDF
SF30 1284LM25Q0058_0001.pdf PDF
ATT 2 Quality Assurance Plan.pdf PDF
1284LM25Q0058.pdf PDF
ATT 1 Statement of Work.pdf PDF
ATT 3 Wage Determinations.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

USDA Forest Service

EXPERIENCE QUESTIONNAIRE

Instructions: See Box 11, Remarks, if extra space is needed to answer any item below, Mark “X: in appropriate boxes.

1. Contractor Name, Address, and Telephone Number

2. Submitted to (Office Name and Address)

3. Business [ ] Company [ ] Co-partnership [ ] Corporation [ ] Individual [ ] Non-profit Organization

4. How many years do you or your firm have in the line of work contemplated by this solicitation?

5. How many years experience have you or your business had as a (a) prime contractor ____ and/or (b) sub-contractor ____?

6. List below the projects your business has completed within the last three years:

Contract Amount

Type of Project Date Completed

Name, Address, and Telephone No. of Owner/Person to Contact for Project Information

7. List below all of your firm’s contractual commitments running concurrently with the work contemplated by this solicitation:

Number

Dollar Amt.

of Award

Name, Address, and Telephone No. of Business/Government Agency Involved

Awarded (Units)

Percent Completed

Date

Complete

8a. Have you ever failed to complete any work awarded to you? [ ] Yes [ ] No 8b. Has work ever been completed by performance bond? [ ] Yes [ ] No 8c. Did you look at the project site(s) on-the-ground? [ ] Yes [ ] No 8d. If “Yes” to either item 8a. or 8b., specify location(s) and reason(s) why:

EXPERIENCE QUESTIONNAIRE CONTINUED

9. Employees and equipment that will be available for this project:

a. (1) Minimum number of employees: _____ and (2) Maximum number of employees: _____

b. Are employees regularly on your payroll: [ ] Yes [ ] No

c. Specify equipment available for this contract:______________________________________________________

d. Estimate rate of progress below (such as 2.0 acres/man/day):

(1) Minimum progress rate:________________ and (2) Maximum progress rate: _________________________

10. List below the experience of the principal individuals of your business: (Who will directly be involved in this contract?)

Individual’s Name Present Position Years of Experience

Magnitude and Type of Work

11. Remarks -- Specify Box Numbers (Attach sheets if extra space is needed to fully answer any above question.):

NOTE: PLEASE PROVIDE ANY ADDITIONAL INFORMATION THAT WILL HELP EVALUATE YOUR ABILITY TO

SUCCESSFULLY COMPLETE THIS PROJECT.

CERTIFICATION

I certify that all of the statements made by me are complete and correct to the best of my knowledge, and that any persons named as references are authorized to furnish the Forest Service with any information needed to verify my capability to perform this project.

12a. CERTIFYING OFFICIAL’S NAME AND TITLE

b. SIGNATURE (Sign in ink) 13. DATE

File details come from the government source that posted it. Updated .