SCOPE OF WORK

140P8623Q0033

SAN FRANCISCO MARITIME NATIONAL HISTORICAL PARK AQUATIC PARK BATHHOUSE

THIRD FLOOR MURAL CONSERVATION AND MAINTENANCE

March 6, 2023

I. BACKGROUND

San Francisco Maritime National Historical Park’s (SAFR) Aquatic Park Bathhouse is a contributing structure to the Aquatic Park Historic District. The interior of the Bathhouse is decorated with extensive wall murals on multiple floors and in multiple rooms. The murals on the third floor underwent an extensive restoration and conservation in 2017, removing years of grime and repairing plaster, bas relief and paint damage. The scope for that conservation project included providing recommendations for ongoing maintenance and care of the murals. Those recommendations include regular examination, cleaning, maintenance, repainting, and other repairs. The National Park Service (NPS) intends to develop an ongoing, yearly maintenance program for the murals.

The 2017 conservation project did not endeavor to repair every crack and blemish. In the words of the conservator – “The goal was to present an old, but well cared‐for appearance as close to the original as possible (including anomalies and characteristic signs of the artist’s work), not to achieve a newly painted, pristine appearance.”

II. OBJECTIVE

The objective for this project is to hire an art conservator to assess, clean, conduct conservation treatments and report on the condition of the murals on the Third Floor of the Bathhouse.

III. SCOPE

This project will occur in the following location:

· Third floor of the Bathhouse – walls, columns, doors and panels, approximately 2,000 square feet of oil paint mural on plaster substrate and wood bas relief elements. Ceiling height is approximately 13’.

The scope includes:

· Assessment - Contractor shall examine murals for damage and deterioration, including but not limited to:

· Flaking paint

· Moisture damage

· Scratches, abrasions etc.

· Delamination

· Adhesion failure of bas relief elements

· Light and UV impacts

BATHHOUSE

MURAL

MAINTENANCE

Page of

· Cleaning - limited to dusting and removal of loose particulates. More intensive cleaning, if required, should be listed as a recommended treatment in the Condition and Treatment Report.

· Conservation Treatments – including but not limited to:

· Re-adhesion of flaking paint

· Treatment at condensation-stained wall areas

· In-painting at scratches, abrasions, and unrepairable flaking paint

· Reattachment of loose bay relief elements

· Condition and Treatment Report - provide a report assessing the condition of the mural, fully documenting the work performed and providing recommendations for protection of the murals. The report shall include:

· Methods and materials used to perform the cleaning

· Photographs of work performed

· Photographs and written descriptions of observed damage

· Recommended treatments of damages beyond the scope of this project

· Environmental Condition Recommendations Report – provide a report recommending environmental conditions for the murals including:

· The maximum light/UV exposure. A light level and UV report is provided for reference in evaluating light and UV impacts.

· Relative humidity and temperature parameters

The intent of the conservation treatment portion of this project is to address areas of the murals that may be failing, are problematic and are truly in need of repair. It is not the intent to repair all blemishes; cracks that are stable and reflect the historic condition of the mural should remain as is.

The contractor shall provide all personnel, equipment (except as noted below), tools, materials, supervision, and other items and incidental services necessary for examination, cleaning and generating the report.

All work will be performed under a single contract and contract period.

IV. REQUIREMENTS

A. GENERAL PROVISIONS

1. The requirements stated in this document are minimum requirements, and as such are not intended to limit the contractor from surpassing the stated requirements.

2. The Contractor shall be responsible for furnishing all services, labor, parts, equipment, personnel, tools, and materials necessary to completely examine and clean the murals and to generate a report on the mural conditions, meeting all requirements specified herein.

3. Conservator Qualifications: Contractor shall provide experienced, professionally trained conservators who have performed similar work, have at least five years of professional experience, and who will provide a resume and examples of previous, similar, projects. The contractor shall be a member of and follow AICs (American Institute for Conservation) ethical and professional standards for art conservation and maintenance as well as all federal, state, and local health and safety guidelines.

4. All hardware and equipment required for the complete examination and cleaning shall be furnished and provided by the Contractor. No government personnel, equipment or materials will be available for Contractor use.

5. The Contractor shall immediately notify the Contracting Officer of any ambiguities, inconsistencies and errors discovered in this specification or between contracting documents and existing conditions.

6. Responsibility for Site Damage: The Contractor will be held responsible for any damage or marks to existing construction resulting from activities of the Contractor and Contractor’s employees. Provide appropriate protection to existing finished surfaces.

7. Building Utilities:

a) Contractor may have use of building electrical outlets. Outlet locations are limited; Contractor is responsible for any required extension cords.

b) Lighting in the room is limited; Contractor is responsible for any required additional lighting.

c) There is no utility sink on the third floor. The nearest utility sink is the second floor men’s restroom off the veranda; this restroom will be open to the public during the project.

B. DOCUMENTS

The following documents are provided for guiding and completing the work:

1. This Scope of Work Document

2. Drawings and Photographs - of murals and surrounding spaces

3. Conservation and Treatment Report – Third Floor Murals by Richard Ayer, 1939, The Bathhouse Building by Anne Rosenthal Fine Art Conservation (2017)

4. Museum Building Third Floor Light Exposure Assessment, 2021

5. Guidance on Site Specific Safety Plans

C. SUBMITTALS

1. Schedule: Prior to start of work, provide projected timeline/schedule from date of award showing milestones for onsite work and delivery of reports.

2. Safety Plan: Prior to start of work, Contractor to provide a Site Specific Safety Plan. See document Guidance on Site Specific Safety Plans.

3. Draft Condition and Treatment Report – Following examination, cleaning and conservation treatments, produce a report explaining the work undertaken. See Scope of Work above. Provide report as an editable Microsoft Word digital document.

4. Final Condition and Treatment Report – Revise draft per comments from NPS staff and provide final report as an editable Microsoft Word digital document.

5. Draft Environmental Condition Recommendations Report – Following completion of the work produce a report assessing the environmental condition of the third floor. See Scope of Work above. Provide report as an editable Microsoft Word digital document.

6. Final Environmental Condition Recommendations Report – Revise draft per comments from NPS staff and provide final report as an editable Microsoft Word digital document.

D. PRODUCTS AND EXECUTION

All work performed will be within the standards of the American Institute for Conservation (AIC) Code of Ethics and Guidelines.

1. Products

a) Cleaning materials and equipment – per Conservation and Treatment Report – Third Floor Murals by Richard Ayer, 1939, The Bathhouse Building by Anne Rosenthal Fine Art Conservation (2017)

b) Paint and varnish – match existing paint and varnish finishes, Conservation and Treatment Report – Third Floor Murals by Richard Ayer, 1939, The Bathhouse Building by Anne Rosenthal Fine Art Conservation (2017)

2. Execution

a) Assessment – visually examine all surfaces of the murals. Examinations shall be conducted in close proximity to the mural surfaces, utilizing ladders and/or lifts to access surfaces above standing height.

b) Cleaning - Cleaning of murals is to be consistent with recommendations in the Conservation and Treatment Reports for the room and murals (see included documents).

c) In-painting is to be consistent with recommendations in the Conservation and Treatment Report (Rosenthal, 2017).

d) Equipment shall not be dragged, skidded, slid, or moved in any way which would scratch, dent, or otherwise damage building surfaces, such as floors, walls, ceilings, windows.

e) Existing surfaces must be protected from damages or marks that may be caused by equipment, staging, or other supplies.

E. CONTRACT LINE ITEMS

Separate pricing shall be provided for the following Contract Line Items:

1. Contract Line Item #1 – Assessment, Cleaning and Conservation Treatment Price for the examination, cleaning and treatment portions of the scope.

2. Contract Line Item #2 – Condition and Treatment Report Price for preparing the Condition and Treatment Report portion of the scope.

3. Contract Line Item #3 – Environmental Condition Recommendations Price for preparing the environmental condition report portion of the scope.

V. DELIVERY

A. CONTRACTOR IDENTIFICATION

When performing as contractor, the contractor shall identify themselves as contractors for the government both orally and in writing. Under no circumstances shall the contractor state or imply that it is acting on behalf of the government.

B. DELIVERY AND PRODUCTS

1. Delivery of materials and equipment will be directly to the work site.

2. Transport of equipment and materials to the Third Floor shall be via the elevator only; no equipment or materials are to be transported via the stairwells.

VI. GOVERNMENT FURNISHED PROPERTY (GFP)

A. Access - The government will provide access to the facility for site visits.

B. No other government equipment will be provided.

VII. SECURITY

The contractor and its representatives must coordinate with National Park Service staff for access to the building.

VIII. TRAVEL

There are no travel requirements or provisions.

IX. OTHER UNIQUE REQUIRMENTS AND CONSIDERATIONS

A. WORK HOURS

Work shall take place on weekdays (Monday – Friday) between 8:30 AM and 4:00 PM, excluding federal holidays and closures. Contractor shall, at all times, conduct its operations to ensure that inconvenience to SAFR employees who work within the area is kept to a minimum.

B. USE OF FACILITY

The third floor will be closed to the public and NPS use during the project. Other areas of the building will remain open to the public and NPS during the project including the second and first floors and the elevator. Contractor will share use of these facilities.

C. WALL/CEIILNG HEIGHT

The murals extend to the ceiling, at a height of approximately 13 feet. Adequate equipment and safety measures (complying with OSHA standards for working at elevated heights) will need to be provided by the contractor.

X. PLACE OF PERFORMANCE

The work will be performed at 900 Beach Street, San Francisco, CA, which is part of the San Francisco Maritime National Historical Park (SAFR), National Park Service.

XI. PERIOD OF PERFORMANCE

Work shall begin no later than 60 days after contract award notice to proceed and be completed within 10 working days. Reports shall be completed within 30 days after completion of examination and cleaning.

XII. ACCEPTANCE

A. The Contracting Officer’s Representative, and NPS preservation staff, will review cleaning procedures while in process.

B. The Contracting Officer’s Representative, and NPS preservation, will review the draft reports and respond with comments within 10 working days of receipt.

C. Final acceptance will be considered complete when the Contracting Officer’s Representative determines that the established criteria as identified in this Scope of Work have been met.

D. After all deficiencies, if any, have been corrected, a Letter of Acceptance will be issued.

END OF SCOPE OF WORK