Solicitation 140P8420Q0033, Attachment No. 02
RADON MITIGATION IN BUILDINGS 75 AND 77
POINT REYES NATIONAL SEASHORE
BACKGROUND:
Point Reyes National Seashore (PORE) is a unit of the National Park Service (NPS) with Headquarters in Point Reyes Station, CA. Park buildings identified as buildings 75 and 77 have proven to have high levels of Radon through local testing measures. Radon levels in the buildings ranged from 4.0-8.0 pCi/L. PORE requires that mitigation measures be installed in the two buildings that will reduce radon levels to EPA’s radon mitigation post remediation level of
4.0 pCi/L radon.
Buildings 75 and 77 provide office space for the Buildings and Utilities Branch, the park Preservation Crew and Law Enforcement staff. Radon testing identified a radon levels of 6.0 and 6.7 in the office areas of the buildings.
Building #75 was constructed in the 1940’s. It is a two-story structure with a footprint of 4,300 square feet. No construction plans are available, so conditions beneath the foundation are unknown.
Building #77 was constructed in the 1940’s. It is a two-story structure with a footprint of 4,000 square feet. No construction plans are available, so conditions beneath the foundation are unknown.
Both buildings have been determined eligible for listing on the National Register of Historic Places.
TASKS:
After award, Contractor shall provide pre-work submittals as required under contract, such as proof of insurance, Safety Plan, Quality Control Plan, etc.
Contractor shall provide preliminary results of sub-slab diagnostic testing of both structures.
Contractor shall provide basic plan outlining proposed construction methods for NPS review and approval (NPS will review and evaluate impacts to the historic fabric of the structures).
Contractor shall provide basic floor plan identifying proposed installation of equipment for NPS review and approval (NPS will review and evaluate impacts to the historic fabric of the structures).
Contractor shall install Radon mitigation systems.
Contractor shall prepare and submit Final Report to NPS: Upon completion of the installation work, the Contractor shall provide a Final Report summarizing all field activities including conclusions and recommendations.
Contractor shall provide (either as an appendix to the Final Report or a separate report) operations, maintenance and warranty information on installed systems. Include detailed photos of pre-existing conditions, work performed, and final conditions. Photos shall include unit numbers and written descriptions as necessary.
Contractor shall coordinate Post Testing by an independent third party: Following the installation of radon mitigation systems, coordinate the performance of radon tests in each unit in accordance with EPA Guidance (EPA 402-R-93-003) by an independent third party. The radon test shall be a continuous monitoring system which will measure the radon levels over a minimum period of 91 days. If the results of the test exceed 4.0 pCi/L, the Contractor shall take immediate corrective action in order to reduce radon levels within the required threshold, then re-test system(s). Repeat process until radon levels are within the required threshold.
SCOPE:
In accordance with the terms and conditions herein, the prime contractor and any sub-contractors shall perform the work of this contract for the NPS under the following assumptions:
Contractor will provide all material, equipment, parts and labor required to perform all of the work of this contract.
The material installation methods will be consistent with the material manufacture requirements and construction industry standards.
Key personnel must be “Qualified Mitigation Personnel” as established in the certification requirements of the National Radon Proficiency Program (NRPP) or the National Radon Safety Board (NRSB), and as required by the State of California.
All equipment, material and waste removed or generated by work of this contract shall be properly disposed of offsite by the contractor.
Contractor shall verify the quantity of materials needed to complete the tasks identified above.
All installed exterior hardware and components shall be corrosion resistant suitable for coastal marine environments.
Provide electrical wire from new suction fan to existing circuit breaker panel board. New interior conduit shall run above ceiling as much as possible.
Contractor will provide a work site and environment that is safe for employees, for visitors to the Park, and NPS staff. If needed, the work area will be cordoned off and secured, with appropriate advance notice to NPS staff including Contracting Officer/Contracting Officer’s Representative.
All work will be performed Monday through Friday from 7:00 am until 3:30 pm. No work will be performed on weekends or federal holidays without prior written approval from the Contracting Officer.
Contractor and employee parking and equipment storage areas will be designated by the Park. No company signs shall be installed on government property. Smoking and eating will be performed in areas designated by the Park. Employees shall wear appropriate clothing at all times.
Contractors will notify NPS staff in advance of scheduled site visits to ensure access to secure areas.
The Davis-Bacon Act applies for this contract.
RADON MITIGATION IN BUILDINGS 75 AND 77
POINT REYES NATIONAL SEASHORE, CALIFORNIA
TABLE OF CONTENTS
SECTION 01110
SECTION 01310
SECTION 01330
SECTION 01360
SECTION 01420
SECTION 01430
SECTION 01600
SECTION 01770
SUMMARY OF WORK
PROJECT MEETINGS
SUBMITTALS
ACCIDENT PREVENTION
REFERENCE STANDARDS
CONTRACTOR QUALITY CONTROL
MATERIAL AND EQUIPMENT
PROJECT CLOSEOUT
SECTION 01110 - SUMMARY OF WORK
01110-5
PART 1 GENERAL
1.1 DESCRIPTION
A. The work of this contract consists of providing all labor, equipment, supervision and materials to accomplish the installation of radon mitigation measures for Point Reyes National Seashore buildings 75 and 77, including but not limited to (1) Perform sub-slab diagnostic testing of both structures to obtain data that will inform design of system that will reduce radon levels to EPA’s radon mitigation post remediation level of 4.0 pCi/L radon; (2) Provide a plan for each building for the proposed radon mitigation system that can be reviewed by park staff to evaluate impacts to the historic fabric of the structures; (3) Install radon mitigation systems; and (4) Provide third party verification that system is achieving reduction of Radon levels to EPA’s radon mitigation post remediation level of 4.0 pCi/L radon.
B. All work will be performed under a single contract.
1.2 LOCATION
A. Both buildings are located within the vicinity of the Headquarters Building at Point Reyes National Seashore: 1 Bear Valley Road, Point Reyes Station, CA 94956-9703.
1.3 CONTRACTOR’S USE OF PREMISES
A. Construction Camp: Establishment of a camp within the park will not be permitted.
B. Contractor shall at all times conduct his operations to ensure the least inconvenience to the public, staff and occupants, no closures will be permitted without specific approval of Contracting Officer.
C. Confine storage of materials to areas approved by the Contracting
Officer.
D. Preservation of Natural Features: Confine all operations to work limits of the project. Prevent damage to natural surroundings.
Restore damaged areas, repairing or replacing damaged trees and plants, at no additional expense to the Government.
E. Provide temporary barriers to protect existing trees and plants and root zones.
F. Do not remove, injure, or destroy trees or other plants without prior approval. Consult with Contracting Officer and remove agreed-on roots and branches that interfere with construction.
G. Do not fasten ropes, cables, or guys to existing trees.
SECTION 01110 - SUMMARY OF WORK
01110-6
H. Carefully supervise excavating, wading, filling, and other construction operations near trees to prevent damage.
I. Hauling Restrictions: Comply with all legal load restrictions in the hauling of materials. Load restrictions on park roads are identical to the state load restrictions with such additional regulations as may be imposed by the Park Superintendent. Information regarding rules and regulations for vehicular traffic on park roads may be obtained from the Office of the Park Superintendent. A special permit will not relieve Contractor of liability for damage that may result from moving of equipment.
1 .4 SPECIAL CONSTRUCTION REQUIREMENTS
A. The Contractor shall perform all work between the daylight hours of 7:00
AM to 3:30 PM Monday through Friday. Any variation of this work schedule must be requested in writing and approved in advance by the Contracting Officer.
B. If scheduled work cannot be performed for any reason, the Contractor shall notify the Contracting Officer’s Representative (COR) by 7:00 AM on the intended work day to inform the COR why services cannot be performed that day, including any intention to cancel work for the day due to weather.
C. Holiday Work Restrictions: No on-site work shall be performed on weekends or federal holidays unless otherwise directed by the Contracting Officer.
1 .5 FIELD VERIFICATION
A. Field verify all new and existing dimensions affecting the work of this contract before ordering products.
1.6 CONSTRUCTION MATERIALS
A. The Government will furnish both water and electricity.
B. All other materials shall be Contractor-furnished from outside the park.
C. SOILS INVESTIGATION REPORT: NOT USED.
D. If conflicts occur between the report and drawings or specifications, the drawings and specifications govern.
PART 2 PRODUCTS : NOT USED.
PART 3 EXECUTION: NOT USED.
END OF SECTION
12/97 01310-2
PROJECT MEETINGS
SECTION 01310
1 .1 PRECONSTRUCTION CONFERENCE
A. Before start of construction, Contracting Officer will arrange an on-site meeting with Contractor.
The meeting agenda will include the following as a minimum:
1. Correspondence procedures
2. Designation of responsible personnel
3. Labor standards provisions
4. Payroll reports
5. Changes
6. Payments to Contractor
7. Subcontractors
8. National Park Service regulations
9. Accident prevention program (including name of responsible supervisor)
10. Accident reporting
11. Documents required under the contract
12. Park rules and regulations
13. Recycling Program
14. Saturday, Sunday, holiday and night work
15. Tentative construction schedule
16. Submittal of shop drawings, project data, samples, and approved equals
17. Project closeout requirements
1 .2 PROGRESS MEETINGS
A. The Contracting Officer will schedule weekly meetings with the Contractor and subcontractors.
B. Subcontractors will not be allowed to work until they have attended a meeting.
C. Additional meetings will be held as needed or for new subcontractors.
12/97 01310-3
D. The meeting agenda will include the following as a minimum:
1. Approval of minutes of previous meetings
2. Review of work progress
3. Field observations, problems, and decisions
4. Identification of problems which impede planned progress
5. Review of submittals schedule and status of submittals
6. Review of off-site fabrication and delivery schedules
7. Status of project record drawings (monthly)
8. Status of operation and maintenance data manuals (monthly)
9. Maintenance of progress schedule
10. Corrective measures to regain projected schedules
11. Planned progress during succeeding work period
12. Coordination of projected progress
13. Maintenance of quality and work standards
14. Effect of proposed changes on progress schedule and coordination
15. Other business relating to work
PART 2 PRODUCTS NOT USED.
PART 4 MEASUREMENT AND PAYMENT
4 .1 PROJECT MEETINGS
A. Payment will be included in the bid item to which this work relates.
SECTION 01330 - SUBMITTALS
01330-4
1.1 DESCRIPTION
A. The work of this section consists of submittal requirements before and during construction.
1.2 RELATED REQUIREMENTS
A. Project closeout - Section 01770.
1.3 SUBMITTAL AND APPROVAL PROCEDURES
A. All submittals shall be transmitted using National Park Service form DSC-l(CS), dated 11/95. (A copy of the form is included at the end of this section.)
No action will be taken on a submittal item unless accompanied by the transmittal form.
B. As specified in the individual sections, forward submittals to Contracting Officer at least 10 days before need for approval. Unless a different number is specified, submit one reproducible original and two copies of each shop drawing, three copies of manufacturer’s catalog sheets (cut sheets), three specimens of each sample, and three copies of all other submittals requested.
1. Basic plan outlining proposed construction methods.
2. Basic floor plan identifying proposed installation of equipment.
3. Final Report.
4. Operations, maintenance and warranty information on installed systems.
5. Post Test results.
C. Contracting Officer reserves the right to require submittals in addition to those called in individual sections.
D. Approved Equals:
I. For each item proposed as an “approved equal,” submit supporting data including:
a. Drawings and samples as appropriate.
b. Comparison of the characteristics of the proposed item with that specified.
c. Changes required in other elements of the work because of the substitution.
01330-5
d. Name, address, and telephone number of vendor.
e. Manufacturer’s literature regarding installation, operation, and maintenance, including schematics for electrical and hydraulic systems, lubrication requirements, and parts lists. Describe availability of maintenance service, and state source of replacement materials.
2. A request for approval constitutes a representation that Contractor:
a. Has investigated the proposed item and determined that it is equal or superior in all respects to that specified.
b. Will provide the same warranties for the proposed item as for the item specified.
c. Has determined that the proposed item is compatible with interfacing items.
d. Will coordinate the installation of an approved item and make all changes required in other elements of the work because of the substitution.
e. Waives all claims for additional expenses that may be incurred as a result of the substitution.
3. Construction Materials: The Contractor is encouraged to submit for approval products made out of recycled or environmentally responsible material. Every effort will be made by the National Park Service to approve these materials.
E. Coordinate all submittals and review them for legibility, accuracy, completeness, and compliance with contract requirements. Forward submittals that are related to or affect one another as a package to facilitate coordinated review. Each transmittal shall contain only data specific to that individual submittal.
F. Submittal Identification:
1. Identification shall include the park name-package number, project title, contract number, and transmittal number.
2. All sets of shop drawings, manufacturer’s catalog sheets, samples, and other documents submitted to the Contracting Officer must have the identification information stamped on the submittal.
3. Identification information shall be applied to the bottom right margin on each page. Identification information on samples shall be applied to the most readily visible area on the sample or on tags attached to sample.
G. Submittal Numbering:
1. Number each submittal consecutively.
2. For re-submittals use the original submittal number, plus a letter suffix
01330-6 beginning with A.
3. Additional re-submittals of the same item shall contain the original number with the next consecutive letter.
H. Contracting Officer’s Review:
1. Submittals will be returned disapproved without technical review if identification information is missing, not filled in, or if placed on the back of the submittal; an incorrect number or format of submittals is provided; the transmittal form is incorrectly filled out; submittals are not coordinated; or submittals do not show evidence of Contractor’s approval.
2. Any work done or orders for materials or services placed before approval shall be at the Contractor’s own risk.
3. After reviewing submittal. the Contracting Officer will return one copy of form DSC-1 (CS) and one copy of applicable (marked up) submittal sheets to the Contractor. Shop drawing review notations will be returned on the reproducible original shop drawing. All other submitted items will be retained. The Contractor is responsible for producing additional copies for his/her own use.
4. The returned submittal will be marked in one of three ways as defined below:
a. APPROVED: Acceptable with no corrections.
b. APPROVED WITH NOTATIONS: Minor corrections or clarifications required. All comments are clear and no further review is required. The Contractor shall address all review comments when proceeding with the work.
c. DISAPPROVED - RESUBMIT: Rejected as not in accordance with the contract or as requiring major corrections or clarifications. The Contracting Officer will identify the reasons for disapproval. The Contractor shall revise and resubmit with changes clearly identified.
Sheet: 1 of: TRANSMITTAL - NATIONAL PARK SERVICE Transmittal No.:
Park: Project: Contract No.: Pkg. No.: Date:
Contractor: Subcontractor/Supplier:
NPS ACTION
Specification Section No.
Description of Item (Size, Type, Name, Manufacturer, Use, Etc.)
Contractor Signature Recommended by
Title, Date Title Date I hereby certify that this submittal has been reviewed for accuracy, completeness, and compliance with contract requirements (FAR 52.236-21)
Review Comments Action By Date Contracting Officer’s Representative
Approval of this submittal is subject to the provisions of the contract drawings and specifications. This action is for general concurrence only and the Government is not responsible for errors or omission.
SUBMITTAL LOG DATES: From contractor [ ], To reviewer [ ], From reviewer [ ], To Contractor [ ] Distribution: ( ) Contractor ( ) DSC File ( ) COR ( ) A/E ( ) DSC Interim ( ) COR Interim ( ) Contractor Interim CM-16Rev. 4/00 (Formerly DSC-1(CS)
TRANSMITTAL CONTINUATION - NATIONAL PARK SERVICE Transmittal No.:
Sheet: 1 of:
Park: Project: Contract No.: Pkg. No.: Date:
Contractor: Subcontractor/Supplier:
NPS ACTION
Specification Section No.
Description of Item (Size, Type, Name, Manufacturer, Use, Etc.)
Review Comments
CM-16 Rev. 4/00 (Formerly DSC-1(CS)
08/00 01360-3
ACCIDENT PREVENTION
SECTION 01360
1 .1 DESCRIPTION
A. The work of this section consists of establishing an effective accident prevention program and providing a safe environment for all personnel and visitors.
1 .2 SUBMITTALS
A. Accident Prevention Program: Before on-site work begins, submit for approval an accident prevention program. The Contracting Officer will review the proposed program for compliance with OSHA and project requirements. If the program requires any revisions or corrections, the Contractor shall resubmit the program within 10 days. No progress payments will be made until the program is approved. The program shall include:
1. Name of responsible supervisor to carry out the program.
2. Weekly and monthly safety meetings.
3. First aid procedures.
4. Outline of each phase of the work, the hazards associated with each major phase, and the methods proposed to ensure property protection and safety of the public, National Park Service personnel, and Contractor's employees. Identify the work included under each phase by reference to specification section or division numbers. Specifically identify the methods of protecting workers and visitors from exposure to radon.
5. Training, both initial and continuing.
6. OSHA DART rate. Include OSHA 300A Summary for last three years.
7. Personal protective equipment to be used.
8. Hazardous materials (HAZMAT) to be used. Include copies of Safety Data Sheets (SDS) must be provided to the Park and plan for storage of HAZMAT.
9. Planning for possible emergency situations, such as floods, fires, cave-ins, slides, explosions, power outages, and wind storms. Such planning shall take into consideration the nature of construction, site conditions, and degree of exposure of persons and property.
10. Housekeeping: Section 01570.
B. Certificates: Provide certificates from a mechanic that all mechanical equipment has been inspected and meets OSHA requirements.
C. Submit a copy of test reports, as required by OSHA, for personnel working with hazardous materials, specifically radon.
D. Submit a report of safety meetings and of inspections.
08/00 01360-4
E. Upon request, submit proof of employees' qualifications to perform assigned duties in a safe manner.
1 .3 QUALITY ASSURANCE
A. Clauses entitled "Accident Prevention" and "Permits and Responsibilities" of the contract. In case of conflicts between Federal, state, and local safety and health requirements, the most stringent shall apply. Equipment or tools not meeting OSHA requirements will not be allowed on the project sites. Failure to comply with the requirements of this section and related sections may result in suspension of work.
B. Qualifications of Employees:
1. Ensure that employees are physically qualified to perform their assigned duties in a safe manner.
2. Do not allow employees to work whose ability or alertness is impaired because of drugs, fatigue, illness, intoxication, or other conditions that may expose themselves or others to injury.
3. Operators of vehicles, mobile equipment, hoisting equipment, and hazardous plant equipment shall be able to understand signs, signals, and operating instructions, and be capable of operating such equipment. Provide operating instructions for all equipment.
Newly hired operators shall be individually tested by an experienced operator or supervisor to determine if they are capable of safely operating equipment.
1 .4 ACCIDENT REPORTING
A. Reportable Accidents: A reportable accident is defined as death, occupational disease, traumatic injury to employees or the public, property damage by accident in excess of $100, and fires.
Notify Contracting Officer immediately in the event of a reportable accident. Within 7 days of a reportable accident, fill out and forward to Contracting Officer an Accident/Property Damage Report (Form CM-22). Form may be obtained from the Contracting Officer.
B. All Other Accidents: The Contractor shall report all other accidents to the Contracting Officer as soon as possible and assist the Contracting Officer and other officials as required in the investigation of the accident.
PART 2 PRODUCTS
2 .1 FIRST AID FACILITIES
A. Provide adequate facilities for the number of employees and the type of construction at the site.
2 .2 PERSONNEL PROTECTIVE EQUIPMENT
A. Meet requirements of NIOSH and MSHA.
PART 3 EXECUTION
3 .1 EMERGENCY INSTRUCTIONS
A. Post telephone numbers and reporting instructions for ambulance, physician, hospital, fire
08/00 01360-5 department, and police in conspicuous locations at the work site.
3 .2 EGRESS
A. Provide and maintain adequate egress at all times in accordance with the Life Safety Code (NFPA 101). No corridor, aisle, stairway, door, or exit shall be obstructed or used in a manner that interferes with egress.
3 .3 PROTECTIVE EQUIPMENT
A. Inspect personal protective equipment daily and maintain in a serviceable condition. Clean, sanitize, and repair, as appropriate, personal items before issuing them to another individual.
B. Inspect and maintain other protective equipment and devices before use and on a periodic basis to ensure safe operation.
3 .4 SAFETY MEETINGS
A. As a minimum, conduct weekly "toolbox" safety meetings. These meetings shall be conducted by a foreman and attended by all construction personnel at the worksite.
B. Conduct monthly safety meetings for all levels of supervision. Notify the Contracting Officer of meeting dates and times. These meetings shall be used to review the effectiveness of the Contractor's safety effort, to resolve current health and safety problems, to provide a forum for planning safe construction activities, and for updating the accident prevention program. The Contracting Officer will attend the meeting and enter the results of the meetings into the daily log.
3 .5 HARD HATS AND PROTECTIVE EQUIPMENT AREAS
A. A hard hat area will be designated by the Contracting Officer. The hard hat area shall be posted by the Contractor in a manner satisfactory to the Contracting Officer.
B. It is the Contractor's responsibility to require all those working on or visiting the site to wear hard hats and other necessary protective equipment at all times. As a minimum, provide six hard hats for use by visitors. Change liners before reissuing hats.
3 .6 TRAINING
A. First Aid: Provide adequate training to ensure prompt and efficient first aid.
B. Hazardous Material: Train and instruct each employee exposed to hazardous material in safe and approved methods of handling and storage. Hazardous materials are defined as explosive, flammable, poisonous, corrosive, oxidizing, irritating, or otherwise harmful substances that could cause death or injury. In this particular case the potetial hazard is lead based paint.
4 .1 ACCIDENT PREVENTION
12/97 01420-1
REFERENCE STANDARDS
SECTION 01420
1 .1 The following abbreviations, which may be used in the construction specifications, refer to the organizations and specifications of the organizations listed below:
AA Aluminum Association
900 19th Street, NW, Suite 300 Washington, D.C. 20006-2168
AABC Associated Air Balance Council 1518 K Street, NW, Suite 503 Washington, D.C. 20005
AAMA American Architectural Manufacturers Association 1827 Walden Office Square, Suite 104 Schaumberg, Illinois 60173
AAN American Association of Nurserymen 1250 I Street, NW, Suite 500 Washington, D.C. 20005
AASHTO American Association of State Highway and Transportation Officials 444 North Capitol Street, NW, Suite 249 Washington, D.C. 20001
ABMA American Boiler Manufacturers Association 950 N. Glebe Road, Suite 160 Arlington, Virginia 22203-1824
ACI American Concrete Institute P.O. Box 9094 Farmington Hills, Michigan 48333
ACPA American Concrete Pipe Association 222 West Colinas Boulevard, Suite 641 Irving, Texas 75039-5423
ADC Air Diffusion Council 11 South LaSalle Street, Suite 1400 Chicago, Illinois 60603
AFPA American Forest and Paper Association 1111 19th Street, NW, Suite 800 Washington, D.C. 20036
AGA American Gas Association 1515 Wilson Boulevard Arlington, Virginia 22209
AHA American Hardboard Association 1210 W. Northwest Highway Palatine, Illinois 60067-1897
AHAM Association of Home Appliance Manufacturers 20 N. Wacker Drive, Suite 1500 Chicago, Illinois 60606
12/97 01420-2
AI Asphalt Institute Research Park Drive P.O. Box 14052 Lexington, Kentucky 40512-4052
AISC American Institute of Steel Construction, Inc.
1 East Wacker Drive, Suite 3100 Chicago, Illinois 60601-2001
AISI American Iron and Steel Institute 1101 17th Street, NW, Suite 1300 Washington, D.C. 20036-4700
AITC American Institute of Timber Construction 7012 S. Revere Parkway, Suite 140 Englewood, Colorado 80112
ALSC American Lumber Standards Committee P.O. Box 210 Germantown, Maryland 20875
AMCA Air Movement and Control Association 30 W. University Drive Arlington Heights, Illinois 60004-1893
ANSI American National Standards Institute 11 West 42nd Street, 13th Floor New York, New York 10036
APA American Plywood Association (See EWA)
APWA American Public Works Association 106 West 11th Street, Suite 1800 Kansas City, Missouri 64105-1806
ARI Air-Conditioning and Refrigeration Institute 4301 Fairfax Drive, Suite 425 Arlington, Virginia 22203
ARM Asphalt Roofing Manufacturers Association 6001 Executive Boulevard, Suite 201 Rockville, Maryland 20852
ASC Adhesive and Sealant Council 1627 K Street, NW, Suite 1000 Washington, D.C. 20006-1707
ASHRAE American Society of Heating, Refrigerating, and Air-Conditioning Engineers 1791 Tullie Circle, NE Atlanta, Georgia 30329-2305
ASLA American Society of Landscape Architects 4401 Connecticut Avenue, NW Fifth Floor Washington, D.C. 20008-2302
ASME American Society of Mechanical Engineers 345 East 47th Street New York, New York 10017
12/97 01420-3
ASPE American Society of Plumbing Engineers 3617 Thousand Oaks Boulevard, Suite 210 Westlake, California 91362-3649
ASSE American Society of Sanitary Engineering 28901 Clemens Road, Suite 100 Westlake, Ohio 44145
ASTM American Society for Testing and Materials 100 Barr Harbor Drive West Conshohocken, Pennsylvania 19428-2959
AWI Architectural Woodwork Institute 1952 Isaac Newton Square Reston, Virginia 20190
AWPA American Wood-Preservers' Association P.O. Box 286 Woodstock, Maryland 21163-0286
AWPI American Wood Preservers Institute 1945 Old Gallows Road, Suite 550 Vienna, Virginia 22182
AWS American Welding Society, Inc.
550 NW LeJeune Road Miami, Florida 33126
AWWA American Water Works Association 6666 W. Quincy Avenue Denver, Colorado 80235
BHMA Builders Hardware Manufacturers Association, Inc.
355 Lexington Avenue, 17th Floor New York, New York 10017
BIA Brick Institute of America 11490 Commerce Park Drive, Suite 300 Reston, Virginia 22091-1506
BOCA Building Officials Code Administrators 4051 W. Flossmoor Road Country Club Hills, Illinois 60478-5795
CBM Certified Ballast Manufacturers 1422 Euclid Avenue, Suite 402 Cleveland, Ohio 44115-2851
CDA Copper Development Association, Inc.
260 Madison Avenue, 16th Floor New York, New York 10016-2401
CE Corps of Engineers (Chief of Engineers - Referral, U.S. Department of the Army) Washington, D.C. 20314
CID Commercial Item Description See General Provisions
CISPI Cast Iron Soil Pipe Institute 5959 Shallowford Road, Suite 419 Chattanooga, Tennessee 37421
12/97 01420-4
CLFMI Chain Link Fence Manufacturers Institute 9891 Broken Land Parkway, Suite 300 Columbia, Maryland 21046
CRA California Redwood Association 405 Enfrente Drive, Suite 200 Novato, California 94949
CRI Carpet and Rug Institute Box 2048 Dalton, Georgia 30722-2048
CRSI Concrete Reinforcing Steel Institute 933 N. Plum Grove Road Schaumburg, Illinois 60173-4758
CS Commercial Standard of NBS (U.S. Department of Commerce) Government Printing Office Washington, D.C. 20402
CSSB Cedar Shingle and Shake Bureau 515 116th Avenue, Suite 275 Bellevue, Washington 98004-5294
DHI Door and Hardware Institute 14170 Newbrook Drive Chantilly, Virginia 22021-2223
EPA Environmental Protection Agency 401 M Street, SW Washington, D.C. 20460
EWA Engineered Wood Association P.O. Box 11700 Tacoma, Washington 98411-0700
FHA Federal Housing Administration (U.S. Department of Housing and Urban Development) 451 7th Street, SW Washington, D.C. 20201
FHVA Fine Hardwood Veneer Association 260 S. First Street, Suite 2 Zionsville, Indiana 46077
FM Factory Mutual Engineering Corporation 1151 Boston-Providence Turnpike P.O. Box 9102 Norwood, Massachusetts 02062
FS Federal Specifications See General Provisions
GA Gypsum Association 810 First, NE, Suite 510 Washington, D.C. 20002
GANA Glass Association of North America 3310 SW Harrison Street Topeka, Kansas 66611-2279
12/97 01420-5
HI Hydronics Institute 35 Russo Place P.O. Box 218 Berkeley Heights, New Jersey 07922
HMA Hardwood Manufacturers Association (Formerly Southern Hardwood Lumber Manufacturers Association) 400 Penn Center Boulevard, Suite 531 Pittsburgh, Pennsylvania 15235
HPMA Hardwood Plywood Manufacturers Association P.O. Box 2789 Reston, Virginia 22090-2789
IA Irrigation Association 1911 N. Fort Myer Drive, Suite 1009 Arlington, Virginia 22209-1630
ICBO International Conference of Building Officials 5360 S. Workman Mill Road Whittier, California 90601
ICEA Insulated Cable Engineers Association, Inc.
P.O. Box 440 South Yarmouth, Massachusetts 02664
IEEE The Institute of Electrical and Electronics Engineers 345 E. 47th Street New York, New York 10017-2394
IES Illuminating Engineering Society of North America 120 Wall Street, FI 17 New York, New York 10005-4001
IGCC Insulating Glass Certification Council 3393 Route 11, Industrial Park P.O. Box 2040 Cortland, New York 13045-0950
ILIA Indiana Limestone Institute of America, Inc.
Suite 400, Stone City Bank Building Bedford, Indiana 47421
KCMA Kitchen Cabinet Manufacturers Association 1899 Preston White Drive Reston, Virginia 22091-4326
LIA Lead Industries Association, Inc.
295 Madison Avenue, 19th Floor New York, New York 10017
MBMA Metal Building Manufacturers Association 1300 Sumner Avenue Cleveland, Ohio 44115-2851
MFMA Maple Flooring Manufacturers Association 60 Revere Drive, Suite 500 Northbrook, Illinois 60062
MIA Marble Institute of America 30 Eden Alley, Suite 201 Columbus, Ohio 43215
12/97 01420-6
MIMA Mineral Insulation Manufacturers Association 1420 King Street Alexandria, Virginia 22314
MLSFA Metal Lath/Steel Framing Association - A Division of NAAMM 8 South Michigan Avenue, Suite 1000 Chicago, Illinois 60603
MS Military Standardization Documents See General Provisions
MSHA Mine Safety and Health Administration 4015 Wilson Boulevard, Room 601 Arlington, Virginia 22203
MSS Manufacturers Standardization Society of the Valve and Fittings Industry 127 Park Street, NE Vienna, Virginia 22180
NAAMM The National Association of Architectural Metal Manufacturers 8 South Michigan Avenue, Suite 1000 Chicago, Illinois 60603
NACE National Association of Corrosion Engineers 1440 South Creek Drive P.O. Box 218340 Houston, Texas 77218-8340
NAIMA North American Insulation Manufacturers Association 44 Canal Center Plaza, Suite 310 Alexandria, Virginia 22314
NAPA National Asphalt Pavement Association NAPA Building 5100 Forbes Boulevard Lanham, Maryland 20706-4413
NAPCA National Association of Pipe Coating Applicators 8th Floor, Commercial National Bank Building 333 Texas Street, Suite 800 Shreveport, Louisiana 71101-3673
NBS National Bureau of Standards (U.S. Department of Commerce)(See NIST)
NCMA National Concrete Masonry Association 2302 Horse Pen Road Herndon, Virginia 22071-3499
NEC National Electrical Code (by NFPA)
NECA National Electrical Contractors Association 3 Bethesda Metro Center, Suite 1100 Bethesda, Maryland 20814
NELM Northeastern Lumber Manufacturers' Association 272 Tuttle Road P.O. Box 87A Cumberland Center, Maine 04021-0687
12/97 01420-7
NEII National Elevator Industry, Inc.
185 Bridge Plaza North, Suite 310 Fort Lee, New Jersey 07024
NEMA National Electrical Manufacturers Association 2101 L Street, NW, Suite 300 Washington, D.C. 20037-1526
NFPA National Fire Protection Association 1 Batterymarch Park P.O. Box 9101 Quincy, Massachusetts 02269-9101
NHLA National Hardwood Lumber Association P.O. Box 34518 Memphis, Tennessee 38184-0518
NHPMA Northern Hardwood and Pine Manufacturers Association, Inc., c/o Northern Softwood Lumber Bureau Box 217 Dear River, Minnesota 56636
NIOSH National Institute for Occupational Safety and Health NIOSH Building 1, Room 3007 1600 Clifton Road, NE Atlanta, Georgia 30333
NIST National Institute of Standards and Technology (US Department of Commerce) Administration Building, Room E128 Gaithersburg, Maryland 20899
Send requests for publications to:
Superintendent of Documents Government Printing Office Washington, D.C. 20402
NOFMA National Oak Flooring Manufacturers Association P.O. Box 3009 Memphis, Tennessee 38173-0009
NPA National Particleboard Association 18928 Premiere Court Gaithersburg, Maryland 20879-1569
NRCA National Roofing Contractors Association O'Hare International Center 10255 W. Higgins Road, Suite 600 Rosemont, Illinois 60018-5607
NSF National Sanitation Foundation 3475 Plymouth Road P.O. Box 130140 Ann Arbor, Michigan 48113-0140
NTMA The National Terrazzo and Mosaic Association 3166 Des Plaines Avenue, Suite 132 Des Plaines, Illinois 60018
12/97 01420-8
NWWDA National Wood Window and Door Association 1400 East Touhy Avenue, Suite 470 Des Plaines, Illinois 60018
OSHA Occupational Safety and Health Administration (U.S. Department of Labor) Government Printing Office Washington, D.C. 20402
PCA Portland Cement Association 5420 Old Orchard Road Skokie, Illinois 60077-1083
PCI Precast/Prestressed Concrete Institute 175 W. Jackson Boulevard Chicago, Illinois 60604
PDI Plumbing and Drainage Institute 45 Briston Drive, Suite 101 South Euston, Massachusetts 02375
PEI Porcelain Enamel Institute, Inc.
4004 Hillsboro Pike, Suite 224-B Nashville, Tennessee 37215
PI Perlite Institute, Inc.
88 New Dorp Plaza Staten Island, New York 10306
PS Product Standard of NBS (U.S. Department of Commerce) Government Printing Office Washington, D.C. 20402
RFCI Resilient Floor Covering Institute 966 Hungerford Drive, Suite 12-B Rockville, Maryland 20850
RIS Redwood Inspection Service (Grading Rules) 405 Enfrente Drive, Suite 200 Novato, California 94949
RMMI Rocky Mountain Masonry Institute 1780 South Bellaire Street, No. 602 Denver, Colorado 80222
SCMA Southern Cypress Manufacturers Association 400 Penn Center Blvd., Suite 530 Pittsburgh, Pennsylvania 15235
SDI Steel Deck Institute P.O. Box 9506 Canton, Ohio 44711
SDI Steel Door Institute 30200 Detroit Road Cleveland, Ohio 44145-1967
SFPA Southern Forest Products Association P.O. Box 52468 New Orleans, Louisiana 70152
12/97 01420-9
SGCC Safety Glazing Certification Council ETL Testing Labs, Inc., Industrial Park 3933 U.S. Route 11 P.O. Box 2040 Cortland, New York 13045-0950
SIGMA Sealed Insulating Glass Manufacturers Association 401 N. Michigan Avenue Chicago, Illinois 60611
SJI Steel Joist Institute 3127 10th Avenue, North Ext.
Myrtle Beach, South Carolina 29577-6760
SMACN
A
Sheet Metal and Air-Conditioning Contractors' National Association 4201 Lafayette Center Drive Chantilly, Virginia 22021
SPIB Southern Pine Inspection Bureau (Grading Rules) 4709 Scenic Highway Pensacola, Florida 32504-9094
SSPC Steel Structures Painting Council 40 24th Street, 6th Floor Pittsburgh, Pennsylvania 15222-4643
SWI Steel Window Institute c/o Thomas Associates, Inc.
1300 Sumner Avenue Cleveland, Ohio 44115-2851
TCA Tile Council of America 100 Clemson Research Boulevard Anderson, South Carolina 29625
TIMA Thermal Insulation Manufacturers Association (See NAIMA)
TPI Truss Plate Institute 583 D'Onofrio Drive, Suite 200 Madison, Wisconsin 53719
UBC Uniform Building Code (by ICBO)
UL Underwriters Laboratories, Inc.
333 Pfingsten Road Northbrook, Illinois 60062
USDA U.S. Department of Agriculture Independence Avenue, between 12th and 14th Streets, SW Washington, D.C. 20250
WCLB West Coast Lumber Inspection Bureau (Grading Rules) P.O. Box 23145 Portland, Oregon 97281
WIC Woodwork Institute of California P.O. Box 980247 3164 Industrial Boulevard West Sacramento, California 95798-0247
12/97 01420-10
WMMPA Wood Moulding and Millwork Producers Association P.O. Box 25278 Portland, Oregon 97225-0278
WRI Wire Reinforcement Institute, Inc.
203 Loudoun Street, SW Leesburg, Virginia 22075
WSFI Wood and Synthetic Flooring Institute (See MFMA)
WWPA Western Wood Products Association (Grading Rules) Yeon Building 522 S.W. 5th Avenue Portland, Oregon 97204-2122
WWPA Woven Wire Products Association 2515 Nordica Avenue Chicago, Illinois 60635
PART 2 PRODUCTS Not used.
PART 3 EXECUTIONNOT USED.
PART 4 MEASUREMENT AND PAYMENT NOT USED.
12/97 01430-1
CONTRACTOR QUALITY CONTROL
SECTION 01430
A. The work of this section consists of preparing and executing a quality control program during performance of this painting contract.
1 .2 SUBMITTALS
A. Quality Control Plan: At the time of the preconstruction conference, submit for approval a written Contractor
Quality Control (CQC) plan. If the plan requires any revisions or corrections, the Contractor shall resubmit the plan within 10 days. The Government reserves the right to require changes in the plan during the contract period as necessary to obtain the quality specified. No change in the approved plan may be made without written concurrence by the Contracting Officer. The plan shall include:
1. A list of personnel responsible for quality control and assigned duties. Include each person's qualifications.
2. A copy of a letter of direction to the Contractor's quality control supervisor outlining assigned duties.
3. Names and descriptions of laboratories to perform sampling and testing, and samples of proposed report forms.
4. Methods of monitoring and controlling environmental pollution and contamination as required by regulations and laws.
5. Methods of performing, documenting, and enforcing quality control of all work.
B. Daily Submittals: Submit Daily Quality Control Report showing all inspections and tests on the first workday following the date covered by the report.
C. Tests: Submit triplicate copies of complete test results not later than three calendar days after the test was performed. Submit failing test results and proposed remedial actions within four hours of noted deficiency.
D. Off Site Inspection Reports: Submit prior to shipment.
E. Progress Payments: If the CQC plan and Daily Quality Control Reports are not submitted in a timely manner, the Contracting Officer may retain an appropriate amount of the applicable progress payment.
1 .3 QUALITY ASSURANCE
A. General: Except for tests or other items of work specified to be performed by the Government, the quality of all work shall be the responsibility of the Contractor. Inspect and test all work often enough to ensure that the quality of materials, workmanship, construction, finish, and functional performance is in compliance with applicable specifications and drawings.
B. Quality Control Staff: The Contractor's job supervisory staff may be used for quality control, supplemented as necessary by additional technicians. The Contractor's designated Quality Control Supervisor shall be employed full time at the project site whenever contract work is in progress.
12/97 01430-2
PART 2 PRODUCTS NOT USED.
3 .1 OFF-SITE CONTROL
A. Items that are fabricated or assembled off-site shall be inspected for quality control at the place of fabrication.
3 .2 ON-SITE CONTROL
A. Notify the Contracting Officer at least 24 hours in advance of the initial and follow-up phases.
B. Preparatory: Perform before beginning each feature of work.
1. Review control submittal requirements with personnel directly responsible for the quality control work.
2. Ensure that provisions have been made for field control testing.
3. Examine the work area to ensure that all preliminary work has been completed.
4. Verify all field dimensions and advise the Contracting Officer of discrepancies.
5. Ensure that necessary equipment and materials are at the project site and that they comply with approved shop drawings and submittals.
C. Initial: As soon as work begins, inspect and test a representative portion of a particular feature of work for quality of workmanship. Review control testing procedures to ensure compliance with contract requirements.
D. Follow-Up: Inspect and test as work progresses to ensure compliance with contract requirements until completion of work.
3 .3 DOCUMENTATION
A. Maintain Daily Quality Control Reports (sample attached) of quality control activities and tests. Daily Quality
Control Reports may not be substituted for other written reports required under the General Provisions, such as Disputes, Differing Site Conditions, or Changes.
3 .4 ENFORCEMENT
A. The Contractor shall stop work on any item or feature pending satisfactory correction of any deficiency noted by the quality control staff or the Contracting Officer. Construction shall not proceed on any feature of work containing uncorrected work.
4 .1 CONTRACTOR QUALITY CONTROL
12/97 01430-3
CONTRACTOR'S Q.C. DAILY REPORT
REPORT NO. SHEET 1 OF
PROJECT CONTRACT NO. DATE
PARK CONTRACTOR'S REPRESENTATIVE ON THE JOB
WEATHER (Rain, Snow, Cloudy, Windy, etc.)
RAINFALL
Inches
TEMPERATURE GROUND CONDITIONS (Dry, Damp, Wet, Frozen, etc.)
MAX. MIN.
1. PRIME CONTRACTOR
NO. EMPLOYEES BY JOB CATEGORIES Hours HEAVY EQUIPMENT ON
JOB
NO.
UNITS
HRS. WORKING
YES NO Comments
WORK PERFORMED BY PRIME CONTRACTOR:
MATERIALS DELIVERED OFFICIAL VISITORS TO SITE
2A. SUBCONTRACTOR, : (If more than one subcontractor use copies of following page.)
NO. EMPLOYEES BY JOB CATEGORIES Hours HEAVY EQUIPMENT ON
JOB
NO.
UNITS
WORK PERFORMED BY SUBCONTRACTOR:
3. SPECIFIC INSPECTIONS: (Inspections performed, results, and corrective actions)
4. TESTING: 1 Check if any testing was performed today. (Complete and attach Test Report Information Sheets.)
Type and Location of Testing:
5. VERBAL INSTRUCTION RECEIVED FROM GOVERNMENT ON CONSTRUCTION DEFICIENCIES OR RE-TESTING
REQUIRED:
6. REMARKS:
7. CERTIFICATION:
I certify that the above report is complete and correct and that I, or my authorized representative, have inspected all work performed this day by the prime contractor and each subcontractor and determined that all materials, equipment, and workmanship are in strict compliance with the plans and specifications except as may be noted above.
Contractor's Designated Quality Control Representative
12/97 01430-4
SUBCONTRACTOR WORK CONTINUED: CONTRACT NO. REPORT NO.
SHEET OF
2 SUBCONTRACTOR,
NO. EMPLOYEES BY JOB CATEGORIES Hours HEAVY EQUIPMENT ON
JOB
NO.
UNITS
2 SUBCONTRACTOR,
NO. EMPLOYEES BY JOB CATEGORIES Hours HEAVY EQUIPMENT ON
JOB
NO.
UNITS
JOB
NO.
UNITS
JOB
NO.
UNITS
YES NO COMMENTS
12/97 01430-5
TEST REPORT INFORMATION SHEET
CONTRACT NO. REPORT NO.
SHEET OF
1. Individual Making Inspection or Test:
2. Testing Laboratory; Name: Phone #:
Address:
3. Description of Work and Test Method:
4. Location of Samples and Tests or Inspections:
5. Specification Section:
6. Inspection or Test Data:
7. Test Results and Interpretations of Test Results:
8. Comments or Professional Opinion About Compliance of Inspected Work or Tested Work with contract Document Requirements:
9. Recommendations:
10. Corrective Actions Taken:
CERTIFICATION:
I certify that the above testing report is complete and correct and that all testing performed this day for this contract is in strict compliance with the plans and specifications except as noted above.
Signature of Inspector
SECTION 1600
A. The work of this section consists of the general procedures for handling, storing, and protecting material and equipment.
1 .2 TRANSPORTATION AND HANDLING
A. Arrange deliveries of materials in accordance with construction schedules; coordinate to avoid conflict with work and conditions at the site. Deliver materials in undamaged condition, in manufacturer's original containers or packaging, with identifying labels intact and legible.
Contractor is encouraged to obtain materials in biodegradable or recyclable/reusable packaging which uses the minimum amount of packaging possible.
1 .3 STORAGE AND PROTECTION
A. Store materials in accordance with manufacturer's instructions, with seals and labels accessible for inspection.
B. Interior Storage: Maintain temperature and humidity within the ranges required by manufacturer's instructions.
C. Exterior Storage:
1. Store products subject to damage by the elements in weathertight enclosures.
2. Store fabricated products above the ground, on blocking or skids; prevent soiling or staining. Cover products subject to damage or deterioration with impervious sheet coverings; provide adequate ventilation to avoid condensation.
3. Store loose granular materials in a well-drained area on solid surfaces to prevent mixing with foreign matter.
D. Protection After Installation: Provide adequate coverings as necessary to protect installed materials from damage resulting from natural elements, traffic, and subsequent construction.
Remove when no longer needed.
3 .1 MATERIAL AND EQUIPMENT
12/97 01600-1
SECTION 100
07/99 01770-1
A. The work of this section consists of final cleanup, closeout submittals, and final inspection procedures.
PART 2 PRODUCTS
2 .1 CLEANING MATERIALS
A. As recommended by the manufacturer of the surface to be cleaned.
3 .1 CLEANING
A. Before scheduling the final inspection, remove all tools, equipment, surplus materials, and rubbish. Restore or refinish surfaces that are damaged due to work of this contract to original condition. Remove grease, dirt, stains, foreign materials, and labels from finished surfaces.
Thoroughly clean building interiors. Pick up all construction debris from the site. At time of final inspection, project shall be thoroughly clean and ready for use.
3 .2 CLOSEOUT SUBMITTALS
A. Submit before final inspection request.
1. Guarantees and Bonds: As specified in individual sections.
2. Spare Parts and Materials: As specified in individual sections.
3. All product submittals are provided and accepted.
3 .3 SUBSTANTIAL COMPLETION AND FINAL INSPECTION
A. When project, or designated portion of project, is substantially complete, request in writing a final inspection. Upon receipt of written request that project is substantially complete, the Contracting Officer will proceed with inspection within 10 days of receipt of request or will advise the Contractor of items that prevent the project from being designated as substantially complete.
B. If, following final inspection, the work is determined to be substantially complete, Contracting
Officer will prepare a list of deficiencies to be corrected before final acceptance and issue a Letter of Substantial Completion. Contractor shall complete the work described on the list of deficiencies within 30 calendar days, as weather permits. If the Contractor fails to complete the work within this time frame, the Contracting Officer may either replace or correct the work with an appropriate reduction in the contract price or charge for reinspection costs in accordance with the Inspection of Construction clause of the contract..
07/99 01770-1
C. If, following final inspection, the work is not determined to be substantially complete, Contracting Officer will notify Contractor in writing. After completing work, Contractor shall request a new final inspection. All reinspection costs may be charged against the Contractor in accordance with the Inspection of Construction clause of the contract.
3 .4 FINAL ACCEPTANCE OF THE WORK
A. After all deficiencies have been corrected, a Letter of Final Acceptance will be issued.
4 .1 PROJECT CLOSEOUT