RFQ No. 140P8421Q0141 Replace Park Guardrails, Crater Lake National Park
CONTRACT PRICE SCHEDULE
Offerors are required to submit an offer that conforms to the Solicitation with pricing for Contract Price Schedule’s Base Line Items and all Option line items - failure to do so may render the offer non-responsive. On lump-sum price items, provide total cost only; on unit price items, provide the unit price and the extended amount of total price for the item. If no price item exists for a portion of the work, include the costs in a related price item. In case of error in extension of prices, unit price governs. In case of error in summation, the total of the corrected price amount governs. Round totals and extend prices to whole dollars. The Government reserves the right to award any or no options at the time of the award as detailed in the Solicitation. Pricing will be evaluated based on what is determined to be the best value to the Government. Options may be exercised in any combination, order, or grouping deemed in the judgement of the Contracting Officer to offer the best value to the Government.
Price award will be made based upon the following equations. The specific equation that is used will be at the Government’s discretion.
Equation 1: Base Price Equation 2: Base Price + Option A Equation 3: Base Price + Option A + Option B Equation 4: Base Price + Option A + Option B + Option C Equation 5: Base Price + Option A + Option B + Option C + Option D Equation 6: Base Price + Option A + Option B + Option C + Option D + Option E
Base Price:
Base Price: Elephant Back and Annie Falls PA
Options:
Option A: Corkscrew Lower and Upper Option B: First Guiderail Option C: Big Tree Upper & Lower Option D: Annie Falls Option E: Old South
Note: The project intent is to award as many options as possible within funding limitations.
CONTRACT CONTRACT
LINE ITEM LINE ITEM TITLE
NUMBER
(CLIN)
QUANTITY
AND UNIT
OF
MEASURE
UNIT PRICE TOTAL PRICE
BASE BID LINE ITEMS
LOCATION: Elephant Back and Annie Falls PA
012700
Mobilization& Demobilization 1 LS @$________ @$_________
Remove Guardrail & Posts 1 LS @$________ @$_________
Install Guardrail Posts 1 LS @$________ @$_________
Install Guardrail 100 LF @$________ @$_________
Install End Treatments - LST 4 EA @$________ @$_________
Traffic Control 1 LS @$________ @$_________
TOTAL BASE PRICE ------------------------------------------------------------------------------- =$___________
BID OPTION A LINE ITEMS
LOCATION: Corkscrew Lower and Upper
A001
Remove Guardrail & Select Posts 1 LS @$________ @$_________
A002
Install Select Guardrail Posts 1 LS @$________ @$_________
A003
Install Guardrail 912.5 LF @$________ @$_________
A004
Install End Treatments – Parabolic Flare 4 EA @$________ @$_________
A005
TOTAL PRICE FOR BID OPTION A---------------------------------------------------------------- =$____________
BID OPTION B LINE ITEMS
LOCATION: First Guiderail
B001
B002
B003
Install Guardrail 1037.5 LF @$________ @$_________
B004
Install End Treatments – Parabolic Flare 2 EA @$________ @$_________
B005
TOTAL PRICE FOR BID OPTION B---------------------------------------------------------------- =$____________
BID OPTION C LINE ITEMS
LOCATION: Big Tree Upper & Lower
C001
C002
C003
Install Guardrail 312.5LF @$________ @$_________
C004
Install End Treatments – Parabolic Flare 4 EA @$________ @$_________
C005
TOTAL PRICE FOR BID OPTION C----------------------------------------------------------------- =$____________
BID OPTION D LINE ITEMS
LOCATION: Annie Falls
D001
D002
D003
Install Guardrail 175 LF @$________ @$_________
D004
D005
TOTAL PRICE FOR BID OPTION D----------------------------------------------------------------- =$____________
BID OPTION E LINE ITEMS
LOCATION: Old South
E001
E002
E003
Install Guardrail 112.5 LF @$________ @$_________
E004
E005
TOTAL PRICE FOR BID OPTION E----------------------------------------------------------------- =$____________
Quantities for unit price items are estimated, but payment will be made only for actual quantities of work completed up to the Not-To-Exceed quantity.
Award will be made to one Offeror in accordance with the Solicitation.
The low offeror will be determined by taking each offeror’s Base Price, or Base Price with Option(s) at the discretion of the Government.
All measurement and payment information is included in the project specifications Section 01 27 00 Definition of Contract Price Schedule Line Items.
END OF SECTION