Atch4 Schedule of Material Submittals_.pdf
PDF 255 KB Posted
- Attached to
- Roads/Pavements & Misc. Civil Work Federal contract opportunity
- Solicitation number
- FA520523D0005
About this file
This is a schedule of material submittals for a federal contract to provide roads, pavements, and miscellaneous civil work at Misawa Air Base in Japan. The contract was awarded by the Department of the Air Force Pacific Air Forces with solicitation number FA520523D0005.
The schedule outlines submittal requirements for 19 sections related to earthwork, concrete, asphalt, utilities, and other site improvements. It requires the submission of items like mix designs, test results, samples, equipment lists, and manufacturing data for materials and processes. Submittals are due prior to construction or within 10 days of on-site work completion, and must be approved by the project engineer to ensure compliance with specifications. This schedule provides a comprehensive list of submittal line items and due dates to guide the contractor's compliance with reporting and documentation requirements for the contract work.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Atch3 Drawings_.pdf | ||
| Atch2 Specifications_.pdf | ||
| Atch1 Other Contract Requirements_.pdf | ||
| Atch5 Addendum No.1_.pdf | ||
| Contract_FA520523D0005.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
APPROVED DISAPPROV
ED
DIVISION 1 - GENERAL REQUIREMENTS
1. Section - 01 11 00, Special Contract Requirements
1.1.1.4 Soil sumpling and testing 3
1.1.1.4 Cementitious Materials and Bituminous 3 3 3
1.1.1.4 Field testing 3
2.15.1 As-Built Drawings (CD Auto CAD) 3 within 10 days after on-site work completion.
2. Section - 01 33 00, Submittals SD-01 a. Submittal Register 3
3. Section - 01 57 19 TEMPORARY ENVIRONMENTAL CONTROLS SD-01 a. Environmental Protection Plan 3 SD-01 b. Dirt and Dust Control Plan 3 SD-01 c. Employee Training Records 3 SD-01 d. Environmental Manager Qualifications 3 SD-06 a. Laboratory Analysis Inspection 3 SD-06 b. Solid Waste Management Report 3 SD-07 a. Employee Training Records 3 SD-07 b. EMS Certificate Of Completion 3 SD-07 c. Certificate of Competency 3 SD-07 d. Erosion and Sediment Control Inspector Qu 3 SD-11 a. Stormwater Pollution Prevention Plan Complianc 3 SD-11 b. Waste Determination Documentation 3 SD-11 c. Solid Waste Management Report 3 SD-11 d. Contractor Certification 3
DIVISION 2 - EXISTING CONDITIONS
4. Section - 02 41 00, Demolition
SD-07 a. Demolition Plan 3 3
DIVISION 3 - CONCRETE
5. Section - 03 20 00 00 10, CONCRETE REINFORCEMENT
SD-02 a. Reinforcement 3 SD-03 a. Welding 3 SD-07 a. Reinforcing Steel 3
6. Section - 03 31 01 00 10, CCAST-IN-PLACE STRUCTURAL CONCRETE FOR CIVIL WORK SD-03 a. Concrete Mix Designs 3 SD-06 a. Testing and Inspections 3 SD-07 a. Cementitious Materials 3
SU
BM
IT
TA
L N
U M
BE
R
S
DATE CONTRACTOR
NOTIFIED
C O
N
TR
AC
TO
R R
ES
U
BM
IT
TA
L
FI
N
AL
A
PP
R
O
VA
L
REMARKS
IN
ST
R U
C
TI
O N
M
SD
S H
EE
TS
R
EQ
U
IR
ED
S
U
BM
IS
SI
O N
D
AT
E
D
AT
E R
EC
EI
VE
D
IN
C
O N
TR
AC
TI
N
G
D
AT
E
TO
C
IV
IL
E
N G
IN
EE
R
IN
G
R
ET
U R
N S
U
SP
EN
SE
D
AT
E
PR
EC
O N
ST
R
U C
TI
O
N S
U
BM
IT
TA
LS
O
PE
R
AT
IN
G
IN
ST
R U
C
TI
O N
S
R
EC
O R
D S
M
AN
U
FA
C
TU
R
ER
C
AT
AL
O
G D
AT
A
O
PE
R
AT
IO
N
, M
AI
N
TE
N
AN
C E
M
AN
U
AL
S
SC
H
ED
U
LE
(To be completed by Project Engineer) (To be completed by Contract Administrator)
NUMBER OF COPIES REQUIRED
LI
N
E N
U M
BE
R
C
ER
TI
FI
C
AT
IO
N
O F
C O
M
PL
IA
N
C E
SH
O
P D
R
AW
IN
G
S
D
ES
IG
N
D
AT
A
SA
M
PL
ESITEM OR DESCRIPTION OF ITEM, CONTRACT
REFERENCE, TYPE OF SUBMITTAL
SCHEDULE OF MATERIAL SUBMITTALS
PROJECT NUMBER PROJECT TITLE
Roads/Pavements & Misc. Civil Work IDIQ contract, Misawa Aie Base Japan
TE
ST
R
EP
O R
TS
C O
LO
R
S
EL
EC
TI
O N
M
AN
U
FA
C
TU
R
ER
'S
IN
ST
R
U C
TI
O
N S
PR
O
D U
C T
D
AT
A
Schedule of Material Submittals Template, Feb 05 (SAF/AQCP) Page 1 of 4
SOLICITATION / CONTRACT NO.
FA520523D0005
Attachment 4 of Contract No. FA520523D0005
1594581730U Line
SU
BM
IT
TA
L N
U M
BE
R
S
DATE CONTRACTOR
NOTIFIED
C O
N
TR
AC
TO
R R
ES
U
BM
IT
TA
L
FI
N
AL
A
PP
R
O
VA
L
REMARKS
IN
ST
R U
C
TI
S H
EE
TS
R
EQ
U
IR
ED
S
U
BM
IS
SI
O N
D
AT
E
D
AT
E R
EC
EI
VE
D
IN
C
O N
TR
AC
TI
N
G
D
AT
E
TO
C
IV
IL
E
N G
IN
EE
R
IN
G
R
ET
U R
N S
U
SP
EN
SE
D
AT
E
PR
EC
O N
ST
R
U C
TI
O
N S
U
BM
IT
TA
LS
O
PE
R
AT
IN
G
IN
ST
R U
C
TI
O N
S
R
EC
O R
D S
M
AN
U
FA
C
TU
R
ER
C
AT
AL
O
G D
AT
A
O
PE
R
AT
IO
N
, M
AI
N
TE
N
AN
C E
M
AN
U
AL
S
SC
H
ED
U
LE
SOLICITATION / CONTRACT NO.
(To be completed by Project Engineer) (To be completed by Contract Administrator)
NUMBER OF COPIES REQUIRED
LI
N
E N
U M
BE
R
C
ER
TI
FI
C
AT
IO
N
O F
C O
M
PL
IA
N
C E
SH
O
P D
R
AW
IN
G
S
D
ES
IG
N
D
AT
A
SA
M
PL
ESITEM OR DESCRIPTION OF ITEM, CONTRACT
REFERENCE, TYPE OF SUBMITTAL
SCHEDULE OF MATERIAL SUBMITTALS
PROJECT NUMBER PROJECT TITLE
Roads/Pavements & Misc. Civil Work IDIQ contract, Misawa Aie Base Japan
TE
ST
R
EP
O R
TS
C O
LO
R
S
EL
EC
TI
O N
M
AN
U
FA
C
TU
R
ER
'S
IN
ST
R
U C
TI
O
N S
PR
O
D U
C T
D
AT
A
SD-08 a. Curing Compound 3
DIVISION 31 - EXTERIOR IMPROVEMENTS
7. Section - 31 00 00, EARTHWORK
SD-01 a. Shoring 3 SD-01 b. Dewatering Work Plan 3 SD-03 a. Utilization of Excavated materials 3 SD-06 a. Testing 3 SD-06 b. Borrow Site Testing 3 SD-07 a. Testing 3
8. Section - 31 05 19, GEOTEXTILE SD-03 a. Thread 3 SD-04 a. Quality Assurance Samples and Tests 3 SD-07 a. Geotextile 3
9. Section - 31 23 00 00 20, EXCAVATION AND FILL SD-01 a. Shoring and Sheeting Plan 3 SD-01 b. Dewatering Work Plan 3 SD-01 c. Blasting Work Plan 3 SD-06 a. Borrow Site Testing 3 SD-06 b. Fill and Backfill Test 3 SD-06 c. Select Material Test 3 SD-06 d. Porous Fill for Capillary Water Barrier 3 SD-06 e. Density Tests 3
DIVISION 32 - EXTERIOR IMPROVEMENTS
10. Section - 32 01 24 HOT IN-PLACE RECYCLING OF BITUMINOUS PAVEMENTS
SD-04 a. Samples 3 SD-06 a. Field Testing and Sampling 3
11. Section - 32 11 20 BASE COURSE FOR RIGID AND SUBBASES COURSES FOR FLEXIBLE PAVING SD-03 a. Equipment 3 SD-06 a. Sampling and Testing 3 SD-06 b. Field Density Tests 3
12. Section - 32 11 23 AGGREGATE BASE COURSE SD-03 a. Plant, Equipment, and Tools 3 SD-06 a. Sampling and Testing 3 SD-06 b. Field Density Tests 3
13. Section - 32 12 10 BITUMINOUS TACK AND PRIME COATS SD-03 a. Waybills and Delivery Tickets 3
Schedule of Material Submittals Template, Feb 05 (SAF/AQCP) Page 2 of 4
FA520523D0005
Attachment 4 of Contract No. FA520523D0005
SU
BM
IT
TA
L N
U M
BE
R
S
DATE CONTRACTOR
NOTIFIED
C O
N
TR
AC
TO
R R
ES
U
BM
IT
TA
L
FI
N
AL
A
PP
R
O
VA
L
REMARKS
IN
ST
R U
C
TI
S H
EE
TS
R
EQ
U
IR
ED
S
U
BM
IS
SI
O N
D
AT
E
D
AT
E R
EC
EI
VE
D
IN
C
O N
TR
AC
TI
N
G
D
AT
E
TO
C
IV
IL
E
N G
IN
EE
R
IN
G
R
ET
U R
N S
U
SP
EN
SE
D
AT
E
PR
EC
O N
ST
R
U C
TI
O
N S
U
BM
IT
TA
LS
O
PE
R
AT
IN
G
IN
ST
R U
C
TI
O N
S
R
EC
O R
D S
M
AN
U
FA
C
TU
R
ER
C
AT
AL
O
G D
AT
A
O
PE
R
AT
IO
N
, M
AI
N
TE
N
AN
C E
M
AN
U
AL
S
SC
H
ED
U
LE
SOLICITATION / CONTRACT NO.
(To be completed by Project Engineer) (To be completed by Contract Administrator)
NUMBER OF COPIES REQUIRED
LI
N
E N
U M
BE
R
C
ER
TI
FI
C
AT
IO
N
O F
C O
M
PL
IA
N
C E
SH
O
P D
R
AW
IN
G
S
D
ES
IG
N
D
AT
A
SA
M
PL
ESITEM OR DESCRIPTION OF ITEM, CONTRACT
REFERENCE, TYPE OF SUBMITTAL
SCHEDULE OF MATERIAL SUBMITTALS
PROJECT NUMBER PROJECT TITLE
Roads/Pavements & Misc. Civil Work IDIQ contract, Misawa Aie Base Japan
TE
ST
R
EP
O R
TS
C O
LO
R
S
EL
EC
TI
O N
M
AN
U
FA
C
TU
R
ER
'S
IN
ST
R
U C
TI
O
N S
PR
O
D U
C T
D
AT
A
SD-03 b. Local/Regional Materials 3 SD-06 a. Sampling and Testing 3
14. Section - 32 12 16 HOT-MIX ASPHALT (HMA) FOR ROADS SD-03 a. Mix Design 3 SD-03 b. Quality Control 3 SD-03 c. Material Acceptance 3 SD-04 a. Asphalt Cement Binder 3 SD-04 b. Aggregates 3 SD-06 a. Aggregates 3 SD-06 b. QC Monitoring 3 SD-07 a. Asphalt Cement Binder 3 SD-07 b. Testing Laboratory 3
15. Section - 32 16 13 CONCRETE SIDEWALKS, CURBS AND GUTTERS 1.2.1.a Construction Equipment 3 1.2.1.b Course and Fine Aggregate 3 1.2.1.c Job Mix Formula 3 1.2.1.d Expansion Joint Filler 3 1.2.1.e Joint Sealant 3 1.2.1.f Epoxy-Resin 3 1.2.2.a Precast Concrete Curb and Gutter 3 1.2.2.b Concrete Stairs with Steel Handrails 3 1.2.2.c Traffic Sign Post w/Concrete Footing 3 1.2.2.d Precast Concrete Wheel Stop 3 1.2.2.e Sidewalk Ramp Type A, B, & C 3 1.2.3.a Pavement Inspection 3 1.2.3.b Sieve Analysis of Aggregates 3 1.2.3.c Compressive Strength 3 1.2.3.d Liquid Limit of Aggregate 3 1.2.3.e Plasticity Index of Aggregates 3 1.2.3.f Sieve Analysis of Combined Material 3 1.2.3.g Portland Cement 3 1.2.4.a Location of Aggregate Source 3 1.2.5.a Construction Equipment List / Mixing Plant 3
16. Section - 32 17 23 PAVEMENT MARKINGS SD-03 a. Equipment 3 SD-03 b. Composition Requirements 3 SD-03 c. Qualifications 3 SD-06 a. Sampling and Testing 3
Schedule of Material Submittals Template, Feb 05 (SAF/AQCP) Page 3 of 4
FA520523D0005
Attachment 4 of Contract No. FA520523D0005
SU
BM
IT
TA
L N
U M
BE
R
S
DATE CONTRACTOR
NOTIFIED
C O
N
TR
AC
TO
R R
ES
U
BM
IT
TA
L
FI
N
AL
A
PP
R
O
VA
L
REMARKS
IN
ST
R U
C
TI
S H
EE
TS
R
EQ
U
IR
ED
S
U
BM
IS
SI
O N
D
AT
E
D
AT
E R
EC
EI
VE
D
IN
C
O N
TR
AC
TI
N
G
D
AT
E
TO
C
IV
IL
E
N G
IN
EE
R
IN
G
R
ET
U R
N S
U
SP
EN
SE
D
AT
E
PR
EC
O N
ST
R
U C
TI
O
N S
U
BM
IT
TA
LS
O
PE
R
AT
IN
G
IN
ST
R U
C
TI
O N
S
R
EC
O R
D S
M
AN
U
FA
C
TU
R
ER
C
AT
AL
O
G D
AT
A
O
PE
R
AT
IO
N
, M
AI
N
TE
N
AN
C E
M
AN
U
AL
S
SC
H
ED
U
LE
SOLICITATION / CONTRACT NO.
(To be completed by Project Engineer) (To be completed by Contract Administrator)
NUMBER OF COPIES REQUIRED
LI
N
E N
U M
BE
R
C
ER
TI
FI
C
AT
IO
N
O F
C O
M
PL
IA
N
C E
SH
O
P D
R
AW
IN
G
S
D
ES
IG
N
D
AT
A
SA
M
PL
ESITEM OR DESCRIPTION OF ITEM, CONTRACT
REFERENCE, TYPE OF SUBMITTAL
SCHEDULE OF MATERIAL SUBMITTALS
PROJECT NUMBER PROJECT TITLE
Roads/Pavements & Misc. Civil Work IDIQ contract, Misawa Aie Base Japan
TE
ST
R
EP
O R
TS
C O
LO
R
S
EL
EC
TI
O N
M
AN
U
FA
C
TU
R
ER
'S
IN
ST
R
U C
TI
O
N S
PR
O
D U
C T
D
AT
A
17. Section - 32 92 23 SODDING SD-03 a. Fertilizer 3 SD-06 a. Topsoil Composition Tests 3 SD-07 a. Sod farm certification for sods 3
DIVISION 33 - UTILITIES
18. Section - 33 11 00 WATER UTILITY DISTRIBUTION PIPING
SD-02 Pre-cast Valve Box (Water) 3 SD-04 Pre-cast Valve Box (Water) 3
19. Section - 33 40 00 STORM DRAINAGE UTILITIES SD-03 a. Placing Pipe 3 SD-04 a. Pipe for Culverts and Storm Drains 3 SD-07 a. Frame and Cover for Gratings 3
Schedule of Material Submittals Template, Feb 05 (SAF/AQCP) Page 4 of 4
FA520523D0005
Attachment 4 of Contract No. FA520523D0005
Title
File details come from the government source that posted it. Updated .