This is a Statement of Objectives for a solicitation issued by the USDA Agricultural Research Service for the replacement of air conditioning units at the Temperate Tree Fruit and Vegetable Research Unit in Wapato, Washington. The project, designated AH 5-6, requires contractors to submit technical and cost proposals for the complete removal and replacement of existing outdoor air conditioning units and associated cooling system components serving air handlers in rooms 48B and 51. The contracting officer is Crystal Amos (crystal.amos@usda.gov), and a mandatory site visit and inspection tour is required prior to proposal submission.
The scope of work includes: removal and disposal of existing outdoor A/C units (AH 5 Model# H1DA024S06A, Serial# EFAM239778 and AH 6 Model# H1D076S46A, Serial# ENCM613011); installation of new compatible A/C units on the roof with EPA-approved refrigerant; installation of new line sets, electrical components, and building automation system (BAS) integration to the air handlers; completion of all electrical connections; and startup and testing of all components with confirmation of operational building controls. The contractor is responsible for obtaining all necessary permits and licenses, coordinating demolition activities to avoid disruption to ongoing research, managing waste diversion to recycling where practical, and maintaining quality control throughout construction. A one-year warranty is required from the date of final acceptance, with the contractor obligated to remedy any defects or damage resulting from non-conformance to contract requirements. Final inspection requires 10 days' written notice, and payment is contingent upon completion and acceptance of work.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Breaker Pic 1.pdf | ||
| Breaker Pic 2.pdf | ||
| AH 5-6 questions_answers 24 Sep 26.pdf | ||
| Amd_0001_Air Handler Air Conditioning Units signed.pdf | ||
| AH 5-6 Questions_Answers.pdf | ||
| 1000013024.jpg | JPG image | |
| 1000013023.jpg | JPG image | |
| 1000013021.jpg | JPG image | |
| Atch_Three_WD_Yakima.pdf | ||
| C04_CSS_Commercial Construction_Repair handler.pdf | ||
| Atch_Two_Preliminary Submittal.docx | DOCX document |
Show all 11
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
AH 5-6
TTFVRU Wapato Air Handler 5-6 (Air Conditioning units) USDA Agriculture Research Service
Wapato, WA
Project Title: “Wapato AH 5 & 6”
1. Government Points of Contact
a) Contracting Officer (CO): Crystal Amos, crystal.amos@usda.gov
2. Location: The site of work is the US Agricultural Research Service location, Temperate Tree Fruit and Vegetable Research Unit 5230 Konnowac Pass RD Wapato WA 98951.
3. Site Visit: A site visit and inspection tour is required.
4. Scope of Service: The contractor shall provide all professional services necessary for the accomplishment of the contract project and such required services shall be in accordance with requirements as described herein.
a) The Contractor shall provide services for the following tasks marked by an “X”.
[X] Provide a technical and cost proposal to complete the project as per project requirements.
5. Project Requirements: Contractor shall furnish a technical and cost proposal to install the following.
I. Contractor will remove and dispose of existing Outdoor A/C unit and coils AH 5 Model# H1DA024S06A, Serial# EFAM239778 and AH 6 Model # H1D076S46A Serial #
ENCM613011.
II. Contractor will install new compatible A/C unit or units on roof and coils for existing air handlers in room 48B and 51. Using EPA approved refrigerant. (Outdoor units are located directly above air handlers)
III. Contractor will install new line sets, components all electrical, distich building controls, and integrate BAS to AHU’s 5-6.
IV. Contractor will start and test all components.
6. Documents: See attached map
7. Description of Work:
AH 5-6:
a) Remove existing Cooling system
b) Install new complete units.
c) Complete electrical hookups.
d) Start and test unit.
e) Confirm Building controls are operational.
mailto:crystal.amos@usda.gov
f) References & Standards: All construction shall comply with ARS Facilities Design Standards (ARS Manual 242.1, 5-01-12), ARS Energy, Water, and Sustainability Policy (ARS Policy & Procedures 134.2, 11-12-13), ARS Energy, Water, and Sustainability Policy Bulletin (ARS Policy & Procedures Bulletin 15-134.2), governing Building Codes, and all applicable local, regional, State, and Federal regulations. Where one or more Codes or regulations conflict, the more stringent shall apply.
g) Permits: Where governing regulations and imposed codes and standards require notices, permits, licenses, inspections, tests, and similar items or actions in order to lawfully proceed with the required work, the Contractor shall obtain items and take those actions in accordance with the regulations of the governing authority. The costs of such permits, licenses, inspections, etc., are the obligation of the Contractor.
h) Existing Installations/Demolition:
a) Contractor shall modify existing installations as needed to accommodate the new installation. Where applicable contractor shall coordinate demolition or modification of existing installations with the Owner. All disturbances of existing systems shall be thoroughly coordinated with the Owner to prevent disconnecting equipment that may potentially jeopardize in-progress research.
b) The Owner reserves the right to retain any equipment or materials removed as part of this scope of work. The Contractor shall coordinate any equipment or materials to be retained with the Owner prior to starting demolition operations. The Contractor shall legally dispose all equipment or material removed that will not be retained.
c) The contractor shall divert project waste to recycle where practical. The Contractor shall track and document the amount of waste diverted to recycle. The contractor shall submit diversion documentation as part of closeout. If no waste is diverted to recycle, the contractor shall submit a letter stating so and why diversion was not practical.
i) Quality Control: The work performed under this contract shall be subject to continuous audit by the COR. Quality control is the exclusive responsibility of the Contractor.
j) Temporary Facilities:
a) Temporary utilities (water and electricity) may be furnished to the Contractor by the Government, if so requested. The Contractor shall maintain and protect all such utilities during the course of construction and shall repair or replace any items damaged through its own negligence.
b) Should the Contractor require any power or utility shutdowns during construction, the Contractor shall obtain approval for such shutdown from the Location Monitor three working days prior to the need
k) Site Cleanup: The construction site shall be kept clean and free of debris at all times. Restore areas disturbed as nearly as possible to the original appearance and condition. Upon completion of the project, and prior to final inspection, the Contractor shall remove from the premises all unused material, trash, and debris resulting from the work to the satisfaction of the COR.
8.Submittals:
a) For all proposed material, contractor shall provide concrete mix design, relevant illustrations, standard schedules, performance charts, instructions, brochures, diagrams, manufacturer descriptive literature, or catalog data.
b) The descriptive literature shall be annotated/highlighted to show its conformance with contract requirements.
c) Submittals are required for all building materials and equipment and shall be provided to the CO and COR for review and approval.
d) Contractor is responsible for any costs incurred for equipment ordered without prior approval.
Final Inspection:
The Contractor shall notify the Contracting Officer and Owner in writing 10 days prior to the date that the project will be ready for final inspection. An inspection of the project will be made by the Contracting Officer and Contractor at a mutually agreed upon time. COR and contractor shall compile a “punch list” prior to final acceptance of the installation and submit completed warranty documentation to manufacturer.
Warranty:
In addition to any other warranties set out elsewhere in this contract, the Contractor warrants that work performed under this contract conforms to the contract requirements and is free of any defect of equipment, material or design furnished, or workmanship performed by the Contractor or any of his subcontractors or suppliers at any tier. Such warranty shall continue for a period of one year from the date of final acceptance of the project. Under this warranty, the Contractor shall remedy at his own expense any such failure to conform or any such defect. In addition, the Contractor shall remedy at his own expense any damage to Government owned or controlled real or personal property, when that damage is the result of the Contractor's failure to conform to contract requirements or any such defect of equipment, material, workmanship, or design. The Contractor shall also restore any work damaged in fulfilling the terms of this clause. The Contractor's warranty with respect to work repaired or replaced hereunder will run for one year from the date of such repair or replacement.
Notification and Compliance: The Government shall notify the Contractor in writing within a reasonable time after the discovery of any failure, defect, or damage. Should the Contractor fail to remedy any failure, defect, or damage within a reasonable time after receipt of notice thereof, the Government shall have the right to replace or repair and have the cost billed to the
Contractor.
Latent Defects:
The Warranty specified herein shall not limit the Government’s rights with respect to latent defects, gross mistake, or fraud.
Acceptance:
Upon satisfactory submittal of the above documents the Contracting Officer shall issue to the Owner a certificate recommending final acceptance of the project. Minor unfinished items of work may be listed on the certificate and accepted from final acceptance. The government will only pay for work completed and accepted.
END