Atch. 1 531-25-102 - Expand ED - SOW.pdf
PDF 154 KB Posted
- Attached to
- Y1DA--CON NRM 531-25-102 | Expand Emergency Room
- Solicitation number
- 36C26027R0002
About this file
Statement of Work Summary: Expand Emergency Room
This is a Statement of Work (SOW) for Boise Veterans Affairs Medical Center Project Number 531-25-102, titled "Expand Emergency Room." The project involves renovating 10,700 square feet of space within Building 85, first floor, to expand the existing 5,700 square foot emergency department to 8,900 square feet, with adjacent functions (Admitting Office, corridors, and ER waiting) occupying an additional 1,800 square feet to be reconfigured and relocated. The contractor must provide all tools, equipment, materials, labor, supervision, and management to complete the work, including demolition, structural work, wall systems, flooring, painting, ceiling systems, windows, architectural finishes, millwork, mechanical systems (HVAC and hydronic), plumbing, medical gas, patient lifts, fireproofing, electrical, telecommunications, nurse call, security, fire alarm, fire protection sprinkler work, and potential asbestos/lead abatement. The work will be completed in two anticipated phases to maintain 24/7 emergency department operations and patient care continuity.
The contractor must comply with strict operational requirements specific to an active medical center environment. Construction activities shall be secondary to hospital operations, with restrictions on timing, noise, noxious fumes, and vibrations, with final authority over scheduling vested in the Contracting Officer or designated representative. The contractor is responsible for all testing and laboratory services, proper waste disposal per provided guidelines, and coordination with the Contracting Officer's Representative (COR) regarding disruptions. Security requirements mandate access only to buildings directly associated with the work, with no entry into patient care areas, and construction site security must be provided. The project follows a Class IV Infection Control Risk Assessment (ICRA) protocol requiring HVAC isolation, critical barriers with negative air pressure, anterooms with HEPA vacuuming, shoe covers, and contained waste transport. The contract length is 443 calendar days from Notice to Proceed, with a Limited Notice to Proceed issued after the preconstruction meeting for submittals and procurement, and a Construction NTP likely issued in Spring 2027. The place of performance is Boise VA Medical Center, 500 W. Fort Street, Boise, ID 83702, with the COR being Brian Blake (208-422-1061, brian.blake@va.gov).
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
STATEMENT OF WORK (SOW)
Boise VAMC Project Number: 531-25-102
1. Contracting Officer’s Representative (COR)
Name: Brian Blake
Section: FMS
Address: 500 W. Fort St., Boise, ID 83702
Phone Number: 208-422-1061
Fax Number: 208-422-1334
E-Mail Address: brian.blake@va.gov
2. Contract Title
Expand Emergency Room
3. Background
The purpose of the project is to expand the Emergency Department (ED) due to continued and rapid growth in the Boise market. The existing Purple Team clinic will be demolished and rebuilt as Phase 1 of the expanded Emergency Department while the current ED space remains active. The current ED space will then be demolished and rebuilt as Phase 2 so that the entire area becomes one larger, continuous ED.
4. Scope
This project will renovate 10,700 sf of space within Building 85, first floor. The existing 5,700 square foot emergency room will also be expanded and reconfigured to 8,900 square feet. The adjacent functions, occupying 1,800 square feet (Admitting Office, corridors, and ER waiting) will be reconfigured and relocated as part of the remodel. All necessary utilities are in the building and must be extended and connected from the surrounding areas within the building.
Renovation work includes the following work, but is not limited to: demolition, phasing, structural, creation of new wall systems, flooring, painting, ceiling systems, installation of new windows and sashes, architectural finish work, millwork, mechanical (HVAC and hydronic), mechanical systems digital control, plumbing, medical gas, patient lifts, fire proofing, electrical, telecommunications, nurse call, security, fire alarm, and fire protection sprinkler work, potential asbestos and/or lead abatement. Refer to the drawings and specifications for details on the extent of construction.
Contractor shall provide all tools, equipment, materials, labor, supervision, and management to complete the intent of project 531-25-102 in strict accordance with this SOW, contract drawings, and contract specifications. All work not specifically identified by the contract drawings and/or specifications, but necessary for a complete system, shall be included as if specifically identified in the Contract Documents.
5. Specific Tasks
The Boise Veterans Affairs Medical Center is a hospital first. Any and all construction activities shall be secondary to the mission of the Medical Center. This means: some activities shall only be performed outside of normal business hours; some activities may be curtailed if they interfere with normal activities and may be delayed for other times or conditions. Other potential issues include, but are not limited to, noise pollution; noxious fumes; and vibrations. Restrictions on activities may be imposed even if they are below OSHA allowable limits. The Contracting Officer or designated representative shall have the final authority over the needs of the Medical Center. Additionally, construction safety, infection control and site security shall be prime requirements of the Work, and as such any infraction may be considered a material breach of the Work and cause for termination for cause by the Government.
Unless otherwise specifically identified, the Contractor shall provide all tools, materials, equipment, labor, and supervision of every kind necessary to provide complete and operational systems for the
Medical Center meeting the intent of this Statement of Work, the Specifications, and Drawings. Any and all Work not specifically identified but necessary for a complete system shall be included as if specifically identified in the Contract Documents.
TESTING
The Contractor shall be responsible for all testing and laboratory services in connection with this project as stated in the contract Drawings and Specifications.
DISPOSAL OF EQUIPMENT AND MATERIALS
The Contractor is responsible for the correct disposal of all materials associated with this project. Details on documenting waste streams as well as a list of recycling/disposal facilities will be provided to the
Contractor at the start of work. Some existing materials will be retained by the VA, refer to Drawings for guidance.
COORDINATION OF WORK
If any questions or concerns arise, the Contractor shall coordinate with the Contracting Officer’s
Representative (COR) for direction. Any and all disruptions to the normal functions of the BVAMC (road closures, utility connections, etc.) shall be brought to the attention of the COR as soon as possible. Refer to the Specifications for the acceptable time frames of notification.
PHASING
Construction shall be completed in phases (anticipated to be 2) in order to maintain 24/7 operation for this active Emergency Department and provide continuity of patient care.
6. Performance Monitoring
The Government is required to monitor contractor performance and certify the work was done in accordance with the contract. This monitoring is done by the COR. At least weekly, the COR shall perform Safety and Interim Life Safety inspection and Environmental inspections. In addition, the COR shall perform periodic inspections of the Work as further detailed in the Specifications.
7. Security Requirements
The Contractor shall only access Medical Center Buildings directly associated with the Work. The
Contractor shall not enter or attempt to enter any patient care areas. Additionally, the Contractor shall provide construction site security as further identified in the Specifications or on the Drawings.
8. Government-Furnished Equipment (GFE)/Government-Furnished Information (GFI)
Reference contract Drawings, and contract Specifications.
9. Other Pertinent Information or Special Considerations
There are no special considerations necessary to accomplish the Work.
a. Identification of Possible Follow-on Work
This is the first and only phase of the construction project. No follow-on work is scheduled.
b. Identification of Potential Conflicts of Interest (COI)
There are no known Potential Conflicts of Interest.
c. Identification of Non-Disclosure Requirements
The Contractor shall not have access to sensitive and/or proprietary information.
d. Packaging, Packing and Shipping Instructions
All deliveries shall be specifically addressed to the Contractor and not the Medical Center. The
Medical Center shall make best efforts to refuse delivery of Contractor goods or materials. Any materials inadvertently received by the Medical Center will be identified to the Contractor for immediate pick-up. The Medical Center takes no responsibility in the receipt of any goods or materials that are the Contractor’s.
e. Inspection and Acceptance Criteria
The COR is responsible for certifying that the work done under the contract is performed to time and standard. The COR is also responsible to assure the inspection and acceptance of in place products provided incidental to services. A demonstration period or trial is not inspection of a product.
10. Risk Control
The Contractor shall refer to Division 01 specifications for guidelines on safety, risk, and infection control.
An Infection Control Risk Assessment (ICRA) shall be performed by BVAMC and is to be followed by the contractor. This project is to be a Class IV project with the following requirements:
1. Remove or isolate HVAC system in area where work is being done to prevent contamination of duct system.
2. Complete all critical barriers i.e. sheetrock, plywood, plastic, to seal area from non-work area or implement control cube method (cart with plastic covering and sealed connection to work site with
HEPA vacuum for vacuuming prior to exit) before construction begins.
3. Maintain negative air pressure within work site utilizing HEPA equipped air filtration units unless exhausted outside.
4. Seal holes, pipes, conduits, and punctures appropriately.
5. Construct anteroom and require all personnel to pass through this room so they can be vacuumed using a HEPA vacuum cleaner before leaving work site or they can wear cloth or paper coveralls that are removed each time they leave the work site.
6. All personnel entering work site are required to wear shoe covers that are removed each time they leave the work area.
7. Contain construction waste before transport in tightly covered containers.
8. Cover transport receptacles or carts. Tape covering unless solid lid.
11. Quality Control
The Contractor is responsible for their own quality control. Refer to specifications for expectations and reporting requirements related to quality control.
12. Place of Performance
Work shall be performed at the Boise VA Medical Center, Boise, ID, 500 W. Fort Street, Boise, ID
83702.
13. Period of Performance
The contract length shall be 443 calendar days from issuance of the Notice to Proceed (NTP). A Limited
Notice to Proceed (LNTP) will be issued after completion of the project preconstruction meeting. LNTP is for submittals and procurement. A Construction NTP is likely to be issued Spring 2027 and will allow contractor to mobilize and begin physical work on-site. All work under LNTP must be completed for contractor to be issued Construction NTP. Refer to specifications for additional information on the contract schedule.
- End of Section -